CN107299620A - Sluice main structure construction scheme - Google Patents

Sluice main structure construction scheme Download PDF

Info

Publication number
CN107299620A
CN107299620A CN201710395270.0A CN201710395270A CN107299620A CN 107299620 A CN107299620 A CN 107299620A CN 201710395270 A CN201710395270 A CN 201710395270A CN 107299620 A CN107299620 A CN 107299620A
Authority
CN
China
Prior art keywords
concrete
construction
gate
rubble
sluice
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710395270.0A
Other languages
Chinese (zh)
Inventor
王婷
余潇
何良德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710395270.0A priority Critical patent/CN107299620A/en
Publication of CN107299620A publication Critical patent/CN107299620A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/20Movable barrages; Lock or dry-dock gates

Abstract

The invention discloses a kind of sluice main structure construction scheme, be related to hydraulic engineering field, the sluice main structure construction scheme employ earth excavation and fill, the process that the construction of rock excavation, projects, grouting construction, concrete and reinforced concrete engineering, stonework, metal structure and electrical equipment are installed carries out construction.The sluice main structure construction scheme fully takes into account the construction difficulty of sluice, built using optimal sequence of construction and mode, the construction quality of sluice main body can be effectively improved, and construction cost is reduced to greatest extent, the maintenance and reinforcement expense of saving, day-to-day operation maintenance cost of reduction etc., improve the benefits, increased Land Use Efficiency such as land use value.

Description

Sluice main structure construction scheme
Technical field
The present invention relates to hydraulic engineering field, more particularly to a kind of sluice main structure construction scheme.
Background technology
Sluice is to be built in the low water head hydraulic structure for controlling flow and regulation water level on river course and channel using gate. Closed shutter with flood retention, gear tide or can raise upper pond level, to meet irrigations, generating, shipping, aquatic products, environmental protection, industry and live Needed with water etc.;Starting gate, can drain off floodwater, excess water, abandon water or waste water, also can be to downstream river course or canal water supply. In hydraulic engineering, sluice is widely used as dash, the building for sluicing or fetching water.Existing sluice construction method compares biography System, causes construction speed slow, with high costs, there is day-to-day operation maintenance cost height, the problems such as land use value is low.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of sluice main structure construction scheme, can effectively improve water The construction quality of lock main body, and construction cost, the maintenance and reinforcement expense of saving, the day-to-day operation of reduction are reduced to greatest extent Maintenance cost etc., improves the benefits, increased Land Use Efficiency such as land use value.
To achieve the above object, the present invention provides following technical scheme:The sluice main structure construction scheme is included such as Lower step:
(1) earth excavation and fill:Water gate engineering earth excavation is mainly on the left of lock chamber and aileron earth excavation, and slope is opened Dig, dry work, using 1~2m3Backacter stage excavation, spoir 10t dump trucks are transported to 1km, be can be used as back The spoil banketed is deposited in the non-construction section in both sides nearby, to avoid disturbing foundation soil, 0.3m protective layers is finally reserved, in concrete Excavated again before pouring, pour the plain concrete bed courses of C20 after excavation immediately, protective layer, basic tooth pin groove and the whole slope of side slope etc. are by artificial Excavate finishing, strike off, double rubber-tired carts are transported, the backfill earthwork is largely using the earthwork excavated, and insufficient section is purchased outside the venue from fetching earth, Backfill was divided to for two phases carried out according to aileron or lock wall construction performance, and the second phase is returned after cofferdam demolition using cofferdam cubic metre of earth Fill out, the backfill earthwork is carried out after correspondent section aileron, lock wall are completed and reach the intensity of requirement, and backfill is transported by 10t dump trucks Scene is transported to, backfilling of earthwork answers placement in layers, compacting, and transport uses rubber-tired cart, and compacting is using tractor and is aided with breast-stroke ramming Machine, corner and narrow positions fill out compacting by artificial paving;;
(2) rock excavation:Local sluice basis is rock excavation, and depth capacity about 2.5m is drilled with hand air drill and excavated, built Basal plane protective layer uses hand excavation, and rock ballast is accumulated by 88kw bull-dozers, uses 1m3Excavator digs dress, is transported to by 5t dump trucks Interim stockyard is used to backfill after stacking.Part backbreak using the plain concrete backfills of C20;
(3) projects are constructed:Old gate electric equipment can be removed using original driving, and gate and headstock gear are used and hung Go out to remove, remove equipment and specified storage place is transported to automobile, because ship lock and sluice share a set of hydraulic headstock gear, sluice Ship lock hydraulic headstock gear should be first installed, it is ensured that the normal keying of ship lock before dismounting, concrete is removed by manually using pneumatic pick with the rectangular slab of stone is grouted Carry out, hand fit 1m3Excavator, dress 5t dump trucks are mucked haulage, and backfill and tile construction road for aileron;
(4) grouting construction:The consolidation by grouting of ship lock gate pier should construct in advance.Decomposed rock during consolidation grouting grout hole bottom hole enters Layer 1.5m, average hole depth 6m, are drilled using geological drilling rig, first carry out the grouting of periphery round, then in the middle part of outer and interior progress The grouting of round, constructs by II sequences;Drill as vertical hole, bore diameter is not less than 56mm;Design grouting pressure is 0.6Mpa, The average permeability rate of the dam foundation is less than 5Lu after grouting;Drill appropriate to the occasion selection carbide drill, slim-hole drilling, the diameter of inspection hole Can be bigger, the deviation of arrangement hole position should be less than 10cm when consolidation grouting drills, and deviation of the pore-forming in vertical direction should be less than 25 Interruption, grout leaking should be avoided the occurrence of during~35cm, grouting construction, grout, slurry is returned and a problem that spillage, and should be noted that and see The metabolies such as analysis rock is lifted, crack is increased are examined, grout curtain grout hole average hole depth 10m is drilled using geological drilling rig, Point sequence is gradually encrypted, and segmentation from bottom to top is in the milk;
(5) concrete and reinforced concrete engineering:Concrete structure mainly includes bottom plate, lock wall, gate pier, intake pool, disappeared The concrete at the positions such as power pond, aileron, the principle that concrete construction follows " secondary after the former head, shallow after first depth " is organized and implemented, coagulation Soil uses commerical ready-mixed concrete, is transported by concrete delivery truck to after scene, then is put in storage by concrete mixer conveying, and scene is set 0.4m3One, moving concrete mixer is as supplement, and casting concrete is vibrated using 2.2kw poker vibrators, between vibrating a little Away from 0.45m, by blossom type interlaced arrangement, side wall and the segmentation of middle pier concrete are poured to design altitude, and aileron wall body is by structure point Seam progress, which is constructed, divides a storehouse, and the mass concrete such as sluice plate, Dun Qiang is arranged in and starts construction 11~January, it is necessary to fully examines Consider the unfavorable factor during concrete works is constructed at low temperature, take the practicable technical measures such as insulation, antifreeze, it is ensured that be mixed Solidifying soil meets design requirement, and concrete curing can be used after straw bag method of curing, i.e. form removal, in time the insulation of covering straw bag, in covering Straw bag on sprinkle water maintenance, keep concrete surface moistening, curing time typically be no less than 14 days, pier wall concrete construction, Temperature control measures are carried out, to prevent concrete thermal cracking, it is ensured that the construction quality and progress of engineering;
(6) stonework:Sand material need to debark and store up to operation platform mainly by shipping from the through Project Areas in borrow-area, Bed course rubble transports to working face, Manual with 10t dumpers;Packed rubble is using artificial pack, artificial laying, packed rubble Rubble select 5~40mm of particle diameter, wherein 20~40mm of particle diameter to account for 40~50%, packed rubble laying will keep continuity, Separation is prevented, and must not have the aspect changing of the relative positions and interruption, packed rubble should be laid from bottom to top, and claps that paving is even, surface undulation is poor 50mm is cannot be greater than, Wai Jiang sides shield beach jackstone can be multiplied climax by stone dumper and rush beach jackstone, if can not reach, stone dumper is thrown on the spot Stone, is manually carried to working face, and the jackstone backfill of punching hole and anti-scour trench jackstone use dump truck or automobile by block stone before cofferdam demolition Working face jackstone is transported to, building block stone is filled and uses 2m with building stones3Loading machine entrucking, 10t dump trucks fortune is discharged to working face, using people Work is built by laying bricks or stones, and it is the graduation two concrete of C20 fine aggregates one to fill building block stone concrete, and maximum particle diameter 2cm, cement is 42.5 grades of ordinary silicons Acid salt cement, mixing water is clean fresh water.Concrete, which is mixed and stirred, uses 0.4m3Portable mixer is produced, rubber-tired cart transport, is adopted Manually spade, which is thrown, is filled, and poker vibrator is made firm by ramming, and filling concrete is finished, to ensure that concrete has suitable curing condition, And abnormal contraction is prevented, laying straw bag in masonry surface keeps wet, the concrete curing time is no less than 10 days, buries Stone concrete barricade is laying of markstone rate 20~30%, it is desirable to which building stones quality is solid, no weathering and crackle, and the building stones size mixed in concrete should be big In the 1/3 of poured position minimum thickness, and 300mm is cannot be greater than, surface is rinsed well using water if any sludge, scale, poured When building, it should successively pave rubble and pour concrete, until barricade top surface, keeps having the concrete covering thick no less than 100mm at the top of rubble Layer, 20% no more than concrete volume should be controlled by filling rubble quantity, and rubble is laid should be evenly distributed, be made greatly downwards, facet Upwards, rubble spacing is typically no less than 100mm, leaves template or cell wall distance is not less than 150mm, to guarantee to insert therebetween Vibrating head is made firm by ramming can be wrapped up with rubble by concrete;
(7) metal structure and electrical equipment are installed:The metal structure of water gate engineering be mainly main gate, bulkhead gate, Headstock gear and embedded part, gate aperture dead size are 8.0 × 6.7m, gate integral assembling on factory's platform for making, using ship Harbour nearby is transported to, then is lifted in place with LT1040 autocranes, the crane biggest lifting capacity is 40t, and contractor unit exists To check material quality certificate before metal structure making in time and sample doing the experiment of material physicochemical property, one, two classes are welded Seam carries out ultrasonic examination inspection and X-ray examination by code requirement, and profile chi is carried out to the assembled metal structure completed of welding Very little and flatness inspection, it is ensured that the making quality of metal structure, metal structure embedded part is pre-buried using second stage concrete, and embedded part is installed Quality directly influences the installation quality of gate, it is desirable to which installation dimension is accurate, fixed reliable and meets drawing and code requirement, Gu Determine winch hoist and purchase finished product from producer, installation should be on the basis of gate lifting center, and vertical, horizontal centre deviation should be less than 3mm, horizontal departure should be less than 0.5/1000, and height variation is preferably less than 5mm.
It is preferred that, earthwork construction program in the step (1):Must with architecture construction phase cooperation, as early as possible The basic engineering construction scope of operation is provided, the requirement of architecture construction plan is met, while earthwork construction must comply with a cubic metre of earth excavation and filling The principle of allotment is balanced, makes full use of the earth material for meeting design requirement to carry out backfilling of earthwork, the secondary transhipment amount of the earthwork is reduced as far as possible.
It is preferred that, stonework includes blotter, packed rubble, jackstone and fills building block stone, the cubic meter of stone in the step (6) The implementation of engineering should maintain strict control over sandstone material quality and construction quality, the level of filtering layer is matched somebody with somebody, the density of stone body, flatness should height Degree is paid attention to, and block stone should select that quality is hard, durable, texture uniform, the building stones of flawless.
Beneficial effect using above technical scheme is:The sluice main structure construction scheme employs earth excavation and filled out Build, the construction of rock excavation, projects, grouting construction, concrete and reinforced concrete engineering, stonework, metal structure and The process that electrical equipment is installed carries out construction.The construction that the sluice main structure construction scheme fully takes into account sluice is difficult Point, is built using optimal sequence of construction and mode, can effectively improve the construction quality of sluice main body, and to greatest extent Reduction construction cost, the maintenance and reinforcement expense of saving, the day-to-day operation maintenance cost of reduction etc. improve land use value etc. Benefit, increased Land Use Efficiency.
Brief description of the drawings
The embodiment to the present invention is described in further detail below in conjunction with the accompanying drawings.
Fig. 1 is the process chart of sluice main structure construction scheme of the present invention;
Fig. 2 is gate pier construction process figure.
Embodiment
Illustrate the preferred embodiment of sluice main structure construction scheme of the present invention below in conjunction with the accompanying drawings.
Fig. 1 and Fig. 2 show the embodiment of sluice main structure construction scheme of the present invention:
With reference to Fig. 1 and Fig. 2, the sluice main structure construction scheme comprises the following steps:
(1) earth excavation and fill:Water gate engineering earth excavation is mainly on the left of lock chamber and aileron earth excavation, and slope is opened Dig, dry work, using 1~2m3Backacter stage excavation, spoir 10t dump trucks are transported to 1km, be can be used as back The spoil banketed is deposited in the non-construction section in both sides nearby, to avoid disturbing foundation soil, 0.3m protective layers is finally reserved, in concrete Excavated again before pouring, pour the plain concrete bed courses of C20 after excavation immediately, protective layer, basic tooth pin groove and the whole slope of side slope etc. are by artificial Excavate finishing, strike off, double rubber-tired carts are transported, the backfill earthwork is largely using the earthwork excavated, and insufficient section is purchased outside the venue from fetching earth, Backfill was divided to for two phases carried out according to aileron or lock wall construction performance, and the second phase is returned after cofferdam demolition using cofferdam cubic metre of earth Fill out, the backfill earthwork is carried out after correspondent section aileron, lock wall are completed and reach the intensity of requirement, and backfill is transported by 10t dump trucks Scene is transported to, backfilling of earthwork answers placement in layers, compacting, and transport uses rubber-tired cart, and compacting is using tractor and is aided with breast-stroke ramming Machine, corner and narrow positions fill out compacting by artificial paving;;
(2) rock excavation:Local sluice basis is rock excavation, and depth capacity about 2.5m is drilled with hand air drill and excavated, built Basal plane protective layer uses hand excavation, and rock ballast is accumulated by 88kw bull-dozers, uses 1m3Excavator digs dress, is transported to by 5t dump trucks Interim stockyard is used to backfill after stacking.Part backbreak using the plain concrete backfills of C20;
(3) projects are constructed:Old gate electric equipment can be removed using original driving, and gate and headstock gear are used and hung Go out to remove, remove equipment and specified storage place is transported to automobile, because ship lock and sluice share a set of hydraulic headstock gear, sluice Ship lock hydraulic headstock gear should be first installed, it is ensured that the normal keying of ship lock before dismounting, concrete is removed by manually using pneumatic pick with the rectangular slab of stone is grouted Carry out, hand fit 1m3Excavator, dress 5t dump trucks are mucked haulage, and backfill and tile construction road for aileron;
(4) grouting construction:The consolidation by grouting of ship lock gate pier should construct in advance.Decomposed rock during consolidation grouting grout hole bottom hole enters Layer 1.5m, average hole depth 6m, are drilled using geological drilling rig, first carry out the grouting of periphery round, then in the middle part of outer and interior progress The grouting of round, constructs by II sequences;Drill as vertical hole, bore diameter is not less than 56mm;Design grouting pressure is 0.6Mpa, The average permeability rate of the dam foundation is less than 5Lu after grouting;Drill appropriate to the occasion selection carbide drill, slim-hole drilling, the diameter of inspection hole Can be bigger, the deviation of arrangement hole position should be less than 10cm when consolidation grouting drills, and deviation of the pore-forming in vertical direction should be less than 25 Interruption, grout leaking should be avoided the occurrence of during~35cm, grouting construction, grout, slurry is returned and a problem that spillage, and should be noted that and see The metabolies such as analysis rock is lifted, crack is increased are examined, grout curtain grout hole average hole depth 10m is drilled using geological drilling rig, Point sequence is gradually encrypted, and segmentation from bottom to top is in the milk;
(5) as shown in Fig. 2 concrete and reinforced concrete engineering:Concrete structure mainly include bottom plate, lock wall, gate pier, The concrete at the positions such as intake pool, stiling basin, aileron, concrete construction follows the principle tissue of " secondary after the former head, shallow after first depth " Implement, concrete uses commerical ready-mixed concrete, is transported by concrete delivery truck to after scene, then be conveyed into by concrete mixer Storehouse, scene sets 0.4m3One, moving concrete mixer is as supplement, and casting concrete is vibrated using 2.2kw poker vibrators, Vibrated a spacing 0.45m, by blossom type interlaced arrangement, and side wall and the segmentation of middle pier concrete are poured to design altitude, aileron wall body By a structural jointing progress construction point storehouse, the mass concrete such as sluice plate, Dun Qiang is arranged in and starts construction 11~January, must Must take into full account concrete works construct at low temperature in unfavorable factor, take the practicable technology such as insulation, antifreeze to arrange Apply, it is ensured that concrete meets design requirement, concrete curing can be used after straw bag method of curing, i.e. form removal, and covering straw bag is protected in time Temperature, maintenance of being sprinkled water on the straw bag of covering keeps concrete surface moistening, and curing time is typically no less than 14 days, pier wall coagulation Soil application work, will carry out temperature control measures, to prevent concrete thermal cracking, it is ensured that the construction quality and progress of engineering;
(6) stonework:Sand material need to debark and store up to operation platform mainly by shipping from the through Project Areas in borrow-area, Bed course rubble transports to working face, Manual with 10t dumpers;Packed rubble is using artificial pack, artificial laying, packed rubble Rubble select 5~40mm of particle diameter, wherein 20~40mm of particle diameter to account for 40~50%, packed rubble laying will keep continuity, Separation is prevented, and must not have the aspect changing of the relative positions and interruption, packed rubble should be laid from bottom to top, and claps that paving is even, surface undulation is poor 50mm is cannot be greater than, Wai Jiang sides shield beach jackstone can be multiplied climax by stone dumper and rush beach jackstone, if can not reach, stone dumper is thrown on the spot Stone, is manually carried to working face, and the jackstone backfill of punching hole and anti-scour trench jackstone use dump truck or automobile by block stone before cofferdam demolition Working face jackstone is transported to, building block stone is filled and uses 2m with building stones3Loading machine entrucking, 10t dump trucks fortune is discharged to working face, using people Work is built by laying bricks or stones, and it is the graduation two concrete of C20 fine aggregates one to fill building block stone concrete, and maximum particle diameter 2cm, cement is 42.5 grades of ordinary silicons Acid salt cement, mixing water is clean fresh water.Concrete, which is mixed and stirred, uses 0.4m3Portable mixer is produced, rubber-tired cart transport, is adopted Manually spade, which is thrown, is filled, and poker vibrator is made firm by ramming, and filling concrete is finished, to ensure that concrete has suitable curing condition, And abnormal contraction is prevented, laying straw bag in masonry surface keeps wet, the concrete curing time is no less than 10 days, buries Stone concrete barricade is laying of markstone rate 20~30%, it is desirable to which building stones quality is solid, no weathering and crackle, and the building stones size mixed in concrete should be big In the 1/3 of poured position minimum thickness, and 300mm is cannot be greater than, surface is rinsed well using water if any sludge, scale, poured When building, it should successively pave rubble and pour concrete, until barricade top surface, keeps having the concrete covering thick no less than 100mm at the top of rubble Layer, 20% no more than concrete volume should be controlled by filling rubble quantity, and rubble is laid should be evenly distributed, be made greatly downwards, facet Upwards, rubble spacing is typically no less than 100mm, leaves template or cell wall distance is not less than 150mm, to guarantee to insert therebetween Vibrating head is made firm by ramming can be wrapped up with rubble by concrete;
(7) metal structure and electrical equipment are installed:The metal structure of water gate engineering be mainly main gate, bulkhead gate, Headstock gear and embedded part, gate aperture dead size are 8.0 × 6.7m, gate integral assembling on factory's platform for making, using ship Harbour nearby is transported to, then is lifted in place with LT1040 autocranes, the crane biggest lifting capacity is 40t, and contractor unit exists To check material quality certificate before metal structure making in time and sample doing the experiment of material physicochemical property, one, two classes are welded Seam carries out ultrasonic examination inspection and X-ray examination by code requirement, and profile chi is carried out to the assembled metal structure completed of welding Very little and flatness inspection, it is ensured that the making quality of metal structure, metal structure embedded part is pre-buried using second stage concrete, and embedded part is installed Quality directly influences the installation quality of gate, it is desirable to which installation dimension is accurate, fixed reliable and meets drawing and code requirement, Gu Determine winch hoist and purchase finished product from producer, installation should be on the basis of gate lifting center, and vertical, horizontal centre deviation should be less than 3mm, horizontal departure should be less than 0.5/1000, and height variation is preferably less than 5mm.
Earthwork construction program in step (1):Foundation engineering must be provided as early as possible with architecture construction phase cooperation Operation side, meets the requirement of architecture construction plan, while earthwork construction must comply with a cubic metre of earth original for excavation and filling balance allotment Then, make full use of the earth material for meeting design requirement to carry out backfilling of earthwork, the secondary transhipment amount of the earthwork is reduced as far as possible.
Stonework includes blotter, packed rubble, jackstone and fills building block stone, the implementation of stonework in step (6) Sandstone material quality and construction quality should be maintained strict control over, the level of filtering layer is matched somebody with somebody, the density of stone body, flatness should be paid much attention to, block Stone should select that quality is hard, durable, texture uniform, the building stones of flawless.
The above is only the preferred embodiment of the present invention, it is noted that for the person of ordinary skill of the art, Without departing from the concept of the premise of the invention, various modifications and improvements can be made, these belong to the guarantor of the present invention Protect scope.

Claims (3)

1. a kind of sluice main structure construction scheme, it is characterised in that:The sluice main structure construction scheme includes following step Suddenly:
(1) earth excavation and fill:Water gate engineering earth excavation is mainly on the left of lock chamber and aileron earth excavation, and slope is excavated, Dry work, using 1~2m3Backacter stage excavation, spoir 10t dump trucks are transported to 1km, can be used as backfill Spoil be deposited in nearby in the non-construction section in both sides, to avoid disturbing foundation soil, 0.3m protective layers are finally reserved, in concrete placings It is preceding to excavate again, the plain concrete bed courses of C20 are poured after excavation immediately, protective layer, basic tooth pin groove and the whole slope of side slope etc. are by hand excavation Repair, strike off, double rubber-tired carts are transported, the backfill earthwork is largely using the earthwork excavated, and insufficient section is purchased outside the venue from fetching earth, and backfills It was divided to for two phases carried out according to aileron or lock wall construction performance, the second phase is backfilled after cofferdam demolition using cofferdam cubic metre of earth, is returned Earth fill is carried out after correspondent section aileron, lock wall are completed and reach the intensity of requirement, and backfill is transported to existing by 10t dump trucks , backfilling of earthwork answers placement in layers, compacting, and transport uses rubber-tired cart, and compacting is using tractor and is aided with frog hammer, corner Compacting is filled out by artificial paving with narrow positions;;
(2) rock excavation:Local sluice basis is rock excavation, and depth capacity about 2.5m is drilled with hand air drill and excavated, foundation plane Protective layer uses hand excavation, and rock ballast is accumulated by 88kw bull-dozers, uses 1m3Excavator digs dress, is transported to by 5t dump trucks temporarily Stockyard is used to backfill after stacking.Part backbreak using the plain concrete backfills of C20;
(3) projects are constructed:Old gate electric equipment can be removed using original driving, and gate and headstock gear are used to hang out and torn open Remove, remove equipment and specified storage place is transported to automobile, because ship lock and sluice share a set of hydraulic headstock gear, sluice is removed Before ship lock hydraulic headstock gear should be first installed, it is ensured that the normal keying of ship lock, concrete and grout the rectangular slab of stone remove by manually being carried out with pneumatic pick, Hand fit 1m3Excavator, dress 5t dump trucks are mucked haulage, and backfill and tile construction road for aileron;
(4) grouting construction:The consolidation by grouting of ship lock gate pier should construct in advance.Weathered rock formation during consolidation grouting grout hole bottom hole enters 1.5m, average hole depth 6m, is drilled using geological drilling rig, first carries out the grouting of periphery round, then by row in the middle part of outer and interior progress The grouting in hole, constructs by II sequences;Drill as vertical hole, bore diameter is not less than 56mm;Design grouting pressure is 0.6Mpa, is filled The average permeability rate of the dam foundation is less than 5Lu after slurry;Drill appropriate to the occasion selection carbide drill, slim-hole drilling, and the diameter of inspection hole can Bigger, the deviation of arrangement hole position should be less than 10cm when consolidation grouting drills, and deviation of the pore-forming in vertical direction should be less than 25~ Interruption, grout leaking should be avoided the occurrence of during 35cm, grouting construction, grout, slurry is returned and a problem that spillage, and should be noted that observation The metabolies such as analysis rock is lifted, crack increasing, grout curtain grout hole average hole depth 10m is drilled using geological drilling rig, point Sequence is gradually encrypted, and segmentation from bottom to top is in the milk;
(5) concrete and reinforced concrete engineering:Concrete structure mainly include bottom plate, lock wall, gate pier, intake pool, stiling basin, The concrete at the positions such as aileron, the principle that concrete construction follows " secondary after the former head, shallow after first depth " is organized and implemented, and concrete is adopted With commerical ready-mixed concrete, transported to after scene, then put in storage by concrete mixer conveying by concrete delivery truck, scene sets 0.4m3 One, moving concrete mixer is as supplement, and casting concrete is vibrated using 2.2kw poker vibrators, a spacing of vibrating 0.45m, by blossom type interlaced arrangement, side wall and the segmentation of middle pier concrete are poured to design altitude, and aileron wall body presses structural jointing Progress, which is constructed, divides a storehouse, and the mass concrete such as sluice plate, Dun Qiang is arranged in and starts construction 11~January, it is necessary to takes into full account Concrete works construct at low temperature in unfavorable factor, take the practicable technical measures such as insulation, antifreeze, it is ensured that coagulation Soil meets design requirement, and concrete curing can be used after straw bag method of curing, i.e. form removal, in time the insulation of covering straw bag, in covering Sprinkle water and conserve on straw bag, keep concrete surface moistening, curing time is typically no less than 14 days, and pier wall concrete construction will be done Good temperature control measures, to prevent concrete thermal cracking, it is ensured that the construction quality and progress of engineering;
(6) stonework:Sand material need to debark and store up to operation platform, bed course mainly by shipping from the through Project Areas in borrow-area Rubble transports to working face, Manual with 10t dumpers;Packed rubble is using artificial pack, artificial laying, packed rubble it is broken Stone selects 5~40mm of particle diameter, wherein 20~40mm of particle diameter to account for 40~50%, and packed rubble laying will keep continuity, prevent Separation, and must not have the aspect changing of the relative positions and interruption, and packed rubble should be laid from bottom to top, and clap that paving is even, and surface undulation difference must not More than 50mm, Wai Jiang sides shield beach jackstone can be multiplied climax by stone dumper and rush beach jackstone, if can not reach, stone dumper jackstone, people on the spot Work is carried to working face, and block stone is transported to work by the jackstone backfill of punching hole and anti-scour trench jackstone before cofferdam demolition with dump truck or automobile Make face jackstone, fill building block stone and use 2m with building stones3Loading machine entrucking, 10t dump trucks fortune is discharged to working face, using artificial block Build, it is the graduation two concrete of C20 fine aggregates one to fill building block stone concrete, and maximum particle diameter 2cm, cement is 42.5 grades of normal silicates Cement, mixing water is clean fresh water.Concrete, which is mixed and stirred, uses 0.4m3Portable mixer is produced, rubber-tired cart transport, using people Work spade, which is thrown, to be filled, and poker vibrator is made firm by ramming, and filling concrete is finished, and to ensure that concrete has suitable curing condition, and is prevented Only abnormal to shrink, laying straw bag in masonry surface keeps wet, the concrete curing time is no less than 10 days, concrete of layinging of markstone Barricade is laying of markstone rate 20~30%, it is desirable to which building stones quality is solid, no weathering and crackle, and the building stones size mixed in concrete not should be greater than institute The 1/3 of position minimum thickness is poured, and cannot be greater than 300mm, surface is rinsed well using water if any sludge, scale, poured When, it should successively pave rubble and pour concrete, until barricade top surface, keeps having the concrete coating thick no less than 100mm at the top of rubble, Filled rubble quantity should control 20% no more than concrete volume, and rubble is laid should be evenly distributed, make it is big downwards, it is small towards On, rubble spacing is typically no less than 100mm, leaves template or cell wall distance is not less than 150mm, shaken with guaranteeing to insert therebetween Dynamic rod is made firm by ramming can be wrapped up with rubble by concrete;
(7) metal structure and electrical equipment are installed:The metal structure of water gate engineering is mainly main gate, bulkhead gate, keying Machine and embedded part, gate aperture dead size is 8.0 × 6.7m, gate integral assembling on factory's platform for making, using shipping extremely Neighbouring harbour, then lifted in place with LT1040 autocranes, the crane biggest lifting capacity is 40t, and contractor unit is being carried out Metal structure will check material quality certificate in time and sample before making does the experiment of material physicochemical property, and one, two class weld seams are pressed Code requirement carries out ultrasonic examination inspection and X-ray examination, to it is assembled weld the metal structure completed carry out appearance and size and Flatness is checked, it is ensured that the making quality of metal structure, and metal structure embedded part is pre-buried using second stage concrete, embedded part installation quality Directly influence the installation quality of gate, it is desirable to which installation dimension is accurate, fixed reliable and meets drawing and code requirement, fixed volume Raise formula headstock gear and purchase finished product from producer, installation should be on the basis of gate lifting center, and vertical, horizontal centre deviation should be less than 3mm, Horizontal departure should be less than 0.5/1000, and height variation is preferably less than 5mm.
2. sluice main structure construction scheme according to claim 1, it is characterised in that:Earthwork work in the step (1) Journey operational procedure:The basic engineering construction scope of operation must be as early as possible provided, building is met and apply with architecture construction phase cooperation The requirement of work plan, while earthwork construction must comply with a cubic metre of earth principle for excavation and filling balance allotment, makes full use of and meets design requirement Earth material carry out backfilling of earthwork, as far as possible reduce the secondary transhipment amount of the earthwork.
3. sluice main structure construction scheme according to claim 1, it is characterised in that:Cubic meter of stone work in the step (6) Journey includes blotter, packed rubble, jackstone and fills building block stone, and the implementation of stonework should maintain strict control over sandstone material quality and construction Gate of the quality monitoring, matches somebody with somebody, the density of stone body, flatness should be paid much attention to the level of filtering layer, and block stone should select that quality is hard, durable, line Reason is uniform, the building stones of flawless.
CN201710395270.0A 2017-05-22 2017-05-22 Sluice main structure construction scheme Pending CN107299620A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710395270.0A CN107299620A (en) 2017-05-22 2017-05-22 Sluice main structure construction scheme

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710395270.0A CN107299620A (en) 2017-05-22 2017-05-22 Sluice main structure construction scheme

Publications (1)

Publication Number Publication Date
CN107299620A true CN107299620A (en) 2017-10-27

Family

ID=60137358

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710395270.0A Pending CN107299620A (en) 2017-05-22 2017-05-22 Sluice main structure construction scheme

Country Status (1)

Country Link
CN (1) CN107299620A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108532562A (en) * 2018-04-23 2018-09-14 中国水利水电第九工程局有限公司 A kind of concrete for sluice of tumbling automatically is from inclining door manufacture method
CN110700207A (en) * 2019-10-16 2020-01-17 中交第三航务工程勘察设计院有限公司 Fabricated sluice stilling basin structure on soft soil foundation and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108532562A (en) * 2018-04-23 2018-09-14 中国水利水电第九工程局有限公司 A kind of concrete for sluice of tumbling automatically is from inclining door manufacture method
CN110700207A (en) * 2019-10-16 2020-01-17 中交第三航务工程勘察设计院有限公司 Fabricated sluice stilling basin structure on soft soil foundation and construction method thereof

Similar Documents

Publication Publication Date Title
CN102146679A (en) Construction method for complex geological section earth pressure balance shield passing middle air shaft
CN104131575A (en) Plugging and drainage method for dam foundation on karst highly developed stratum
CN113699971A (en) Soft soil stratum in-situ curing agent preparation feeding equipment and curing process thereof
CN104153371A (en) Grouting-to-stop-water construction method of underwater rubble bed
CN106812149A (en) A kind of construction method of pile foundation
CN109706952A (en) Large-scale well-sinking construction method
CN109812271B (en) Construction method for shield-crossing limited box culvert
CN111778941A (en) High-standard farmland channel construction method and structure
CN102182866A (en) Backfilling process for large ultra-deep circulating water pipe
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN201598610U (en) Face plate rock-fill dam structure reasonably utilizing gravel sand
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN107299620A (en) Sluice main structure construction scheme
CN110080232A (en) A kind of deep basal pit earth-filling method of underground high water level
CN112144514A (en) Simple method for forming hole and pile in sand and pebble stratum easy to collapse during rotary drilling machine
CN107142902A (en) High head and large flow tunneling boring damming method
CN100523394C (en) Construction method for concrete shaft wall module masonry
CN112813756A (en) Roadbed based on municipal soft soil and construction method
CN103061352A (en) Salt lake region bridge foundation concrete anticorrosion structure and construction method
CN206189430U (en) A escape canal for deep overburden ground
CN108316237A (en) Revetment barricade
CN213143069U (en) Pouring type impervious core earth-rock dam structure
CN212272234U (en) High-strength combined template for open groove section of large-section inclined shaft
CN112575794A (en) Deep silt geological foundation pit support structure and construction method thereof
CN111577330A (en) Construction method for open channel section of large-section inclined shaft and high-strength combined template thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171027

WD01 Invention patent application deemed withdrawn after publication