CN205526359U CN201620096795.5U CN201620096795U CN205526359U CN 205526359 U CN205526359 U CN 205526359U CN 201620096795 U CN201620096795 U CN 201620096795U CN 205526359 U CN205526359 U CN 205526359U
Authority
CN
China
Prior art keywords
prefabricated component
lifting
walking
component conveying
track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620096795.5U
Other languages
Chinese (zh)
Inventor
俞大有
彭海辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan people's Republic of China build friends Mdt InfoTech Ltd
Original Assignee
China Minsheng Zhuyou Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Minsheng Zhuyou Co Ltd filed Critical China Minsheng Zhuyou Co Ltd
Priority to CN201620096795.5U priority Critical patent/CN205526359U/en
Application granted granted Critical
Publication of CN205526359U publication Critical patent/CN205526359U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)

Abstract

The utility model provides a prefab conveyer, including prefab travelling bogie, prefab hoisting trolley and walking track, prefab travelling bogie and prefab hoisting trolley are in move on the walking track, prefab hoisting trolley walking platform and hoist device, the setting of walking platform is in hoist device's bottom, the walking platform includes two vertical walking bracket, the 2nd drive arrangement and at least two sets of hoist and mount walking wheel, wherein at least a set of hoist and mount walking wheel motion of the 2nd drive arrangement drive, hoist and mount walking wheel sets up vertical walking bracket's bottom, hoist device is including the hoist and mount frame and hang hook component, it sets up to hang hook component the top of hoist and mount frame, the lower part of hoist and mount frame is provided with lifts by crane running gear, it can be relative to lift by crane running gear walking platform movement. Like this, reduced the hoist and mount transportation time, practiced thrift production line place area occupied.

Description

A kind of prefabricated component conveying arrangement
Technical field
This utility model relates to construction engineering technical field, particularly to a kind of prefabricated component conveying arrangement.
Background technology
Along with the development of building trade, current various precast concretes have been widely used in various building In.Producing of precast concrete typically uses production line and the mode of supply line combination.In preform production During, due to prefabricated component quality weight, volume greatly, transport process is wasted time and energy, it is often necessary to use driving Or the crane lifting such as crane, then it is transported through by prefabricated component transport vehicle.But, use driving or lifting The hoisting prefabricated part of machine, not only occupied ground, lifting efficiency is relatively low, and existing prefabricated component transport vehicle is also required to Designing special transport channel, it is also desirable to occupied ground, therefore, design one lifting efficiency is high, place accounts for With the low prefabricated component conveying arrangement of rate, become those skilled in the art and be badly in need of solving the technical problem that.
Summary of the invention
This utility model solves the technical problem that and is: providing a kind of prefabricated component conveying arrangement, it can improve prefabricated The lifting efficiency of part, saves place area occupied.
Solution of the present utility model is achieved in that a kind of prefabricated component conveying arrangement, including prefabricated component Travelling bogie, prefabricated component lifting trolley and walking track, described prefabricated component travelling bogie and prefabricated component lifting are little Car runs on described walking track, and described prefabricated component travelling bogie is for the transport of prefabricated component, described prefabricated Part lifting trolley is used for prefabricated component handling to described prefabricated component travelling bogie;Described prefabricated component lifting trolley, Including travelling platform and hanging apparatus, described travelling platform is arranged on the bottom of hanging apparatus, and described walking is put down Platform includes two longitudinal mobile roof supports, the second driving means and at least two groups lifting road wheel, and described second drives Dynamic device drives at least a part of which one group lifting road wheel motion, and described lifting road wheel is arranged on described lengthwise rows Walk the bottom of support;Described hanging apparatus includes that mast-up and hook assembly, described hook assembly are arranged on institute Stating the top of mast-up, the bottom of described mast-up is provided with lifting walking mechanism, described lifting walking mechanism Can the motion of the most described travelling platform.So, described prefabricated component travelling bogie and prefabricated component lifting trolley are in institute Stating and run on walking track, prefabricated component lifting trolley is used for prefabricated component handling to described prefabricated component travelling bogie On, prefabricated component travelling bogie and prefabricated component lifting trolley run on same track, decrease lifting the transhipment time, Save production line place area occupied, production line has been integrated conllinear with material flow line simultaneously, not only solve material Line floor space problem, and can also avoid occur material report to the leadship after accomplishing a task blocking problem.It addition, use above-mentioned Prefabricated component lifting trolley come hoisting prefabricated part, have following excellent compared with traditional driving or crane loading Gesture, sling height is low, range ability is little, simple to operate flexible and low power consumption and other advantages, uses meanwhile Self-propelled wheel-type is across the mode operation of production line both sides, and its work flow is short, and particularly it is along production line direction Lifting and the operating type of movement so that it is in operation process, prefabricated component will not produce and significantly swing, can Prevent lifting trolley from toppling, drastically increase the security performance of operation.And, lifting walking mechanism can phase Moving described travelling platform, hanging apparatus is not take up bogey surrounding space, improves the utilization in place Rate, beneficially prefabricated component are lifted on bogey, and, the prefabricated component being lifted on bogey also may be used To play the effect of counterweight so that it is will not rock swing in lifting, transportation, stability is more preferable.
Another technical scheme of the present utility model is on above-mentioned basis, described mast-up be door type or Triangular structure.So, when mast-up is door type or triangular structure, triangular structure has very Excellent stability so that it is be unlikely to deform in hoisting process.
Another technical scheme of the present utility model is on above-mentioned basis, bottom described hanging apparatus End is provided with built-in fitting placement mechanism, and described built-in fitting placement mechanism is for placing produce needed for prefabricated component pre- Embedded part;And/or, at least side bottom described hanging apparatus is provided with limit mould fixed mechanism, and described limit mould is solid Determine mechanism's transhipment for limit mould.So, during preform production, can by lifting trolley by reinforcing bar, Reinforced mesh, reinforcing bar, steel skeleton or limit mould transport to production line precalculated position, and are put down one by one, So, advantageously reduce hand labor intensity, improve production efficiency, reduce preform production cost.
Another technical scheme of the present utility model is on above-mentioned basis, two described longitudinal mobile roof supports Being connected by least one vertical door-shaped frame, described door-shaped frame is higher than mast-up.So, door shape is used Framework connects as mobile roof support, can improve the stability in the large of prefabricated component lifting trolley, prevents it in lifting During deformed damaged.
Another technical scheme of the present utility model is on above-mentioned basis, described longitudinally walking frame upper Being provided with boom hoisting track, described lifting walking mechanism moves along described upper boom hoisting track.So, When longitudinally walking frame upper is provided with upper boom hoisting track, and described lifting walking mechanism is along described upper lifting Device track moves, during hoisting prefabricated part, after prefabricated component is lifted by boom hoisting, and Ke Yitong Crossing track to move to carrying platform, particularly it is along the lifting of production line direction and the operating type of movement, makes It is in operation process, and prefabricated component does not have and significantly swings, and can prevent lifting trolley from toppling, greatly carry The high security performance of operation.
Another technical scheme of the present utility model is on above-mentioned basis, and described lifting walking mechanism is rail Road formula scroll wheel.So, lifting walking mechanism is track rolling wheel, and reducible doing up hangs walking mechanism in-orbit Move forward and backward on road, it is not necessary to consider that the situation of direction skew occurs, reduce operation easier, improve peace Quan Xing.
Another technical scheme of the present utility model is on above-mentioned basis, described hook assembly include suspension hook, Lifting rope and motor, described motor drives suspension hook to move up and down by lifting rope.So, use motor as lifting During actuating unit, hoisting prefabricated part controls simple, and it is relatively low that technology realizes difficulty, it is simple to operative.
Another technical scheme of the present utility model is that, on above-mentioned basis, described hook assembly includes two Suspension hook and two motors, said two suspension hook interval layout, two motors individually drive on two suspension hooks Lower movement;Or described hook assembly includes that two suspension hooks and a motor, said two suspension hook interval are arranged, Described motor drives two suspension hooks to move up and down.So, suspension hook interval is used to arrange, when hoisting prefabricated part, Can lift by flat condition, improve the translation stability of lifting trolley, be particularly prone to flat board and pile up, make plate body It is not easily susceptible to damage, and so that the relatively low height i.e. Liftable that lifts by crane of prefabricated component completes.
Another technical scheme of the present utility model is that, on above-mentioned basis, the bottom of described mast-up is extremely Few one end is provided with alignment pin or hole, location.So, at least one end in the bottom of mast-up is provided with location Pin or location hole after, prefabricated component lifting trolley can easily with other traction apparatuss or multiple travelling bogie Connect traction, facilitate that production line is longer, prefabricated component more in the case of use, particularly prefabricated component lifting is little Car and the docking of prefabricated component travelling bogie are fixed and are accurately positioned, can be accurate by orbital docking easily so that it is Successfully can be smoothly transitted on boom hoisting platform and bogey walking.
Another technical scheme of the present utility model is on above-mentioned basis, and described second driving means is for driving Dynamic motor or driving motor;Or described lifting road wheel is track rolling wheel or pneumatic tire.So, When two driving means are for driving motor or driving motor, prefabricated component lifting trolley controls simple, and technology is real Existing difficulty is relatively low, it is simple to operative;Described lifting road wheel is track rolling wheel or pneumatic tire, then Road wheel can be selected, it is possible to relatively easily meet the application in various different place according to practical situation.
Another technical scheme of the present utility model is on above-mentioned basis, described prefabricated component travelling bogie, Including bogey and the first walking mechanism, described first walking mechanism is arranged on the bottom of bogey, institute Stating the first walking mechanism, including the first driving means and at least two group road wheels, described first driving means is driven The one group of road wheel motion of dynamic at least a part of which.So, prefabricated component travelling bogie can by the first walking mechanism certainly Every trade is walked, independent operating.
Another technical scheme of the present utility model is that, on above-mentioned basis, described bogey includes two Longitudinal bracing frame and at least two cross-brace framves, the two ends of described cross-brace frame are indulged with described two respectively Connecting to bracing frame, described cross-brace frame forms carrying platform with longitudinal bracing frame.So, when carrying dress Putting and include at least two longitudinal bracing framves and at least two cross-brace framves, the two ends of described cross-brace frame are divided When not being connected with described two longitudinal bracing framves, at boom hoisting prefabricated component lifted and be placed to bogey After on, contacting between prefabricated component with bogey is linear contact lay, not only saved bogey weight and Material, also can lay according to its force way, effectively prevents prefabricated component from fractureing damage.
Another technical scheme of the present utility model is on above-mentioned basis, and described road wheel is arranged on described The bottom of longitudinal bracing frame.So, when road wheel is arranged on the bottom of described longitudinal bracing frame, carrying dress Put and the load of prefabricated component can be handed on road wheel by straight-line transmitting, decrease the moment of torsion of road wheel wheel shaft, can Prevent its deformed damaged under big load effect.
Another technical scheme of the present utility model is on above-mentioned basis, and described cross-brace frame is arch Or it is trapezoidal.So, when cross-brace frame be arch or trapezoidal time, its arch or trapezoidal bottom are reserved with one Fixed space, such prefabricated component travelling bogie, in running, can directly stride across from prefabricated component.
Another technical scheme of the present utility model is on above-mentioned basis, the top of described longitudinal bracing frame Being provided with lower boom hoisting track, the mast-up bottom of described hanging apparatus is provided with lifting walking mechanism, when After described prefabricated component travelling bogie and the docking of prefabricated component lifting trolley are fixed, described lifting walking mechanism can be along institute State lower boom hoisting track to move.So, it is provided with lower boom hoisting track on the top of longitudinal bracing frame, After the mast-up bottom of described hanging apparatus is provided with lifting walking mechanism, when described prefabricated component travelling bogie and After the docking of prefabricated component lifting trolley is fixing, described lifting walking mechanism can move along described lower boom hoisting track, Boom hoisting is not take up bogey surrounding space, improves the utilization rate in place, beneficially prefabricated component lifting On bogey, and, the prefabricated component being lifted on bogey may also operate as the effect of counterweight, makes It will not rock swing in lifting, transportation, and stability is more preferable.
Another technical scheme of the present utility model is on above-mentioned basis, and described bogey also includes adjusting Regulating device, described adjusting means is for regulating the length of carrying platform, and described adjusting means is described for being arranged on Sliding rail on longitudinal bracing frame, described cross-brace frame is sliding with described longitudinal bracing frame by sliding rail It is dynamically connected.So, when being provided with adjusting means on bogey, described adjusting means is used for regulating carrying dress During the length put, for the different length size of prefabricated component, can by the length adjusting bogey come with Adapt, facilitate application.Further, regulated by sliding rail, easy to operate simple, The amplitude of accommodation is easily controlled, and is conducive to improving the security reliability of prefabricated component travelling bogie.
Another technical scheme of the present utility model is on above-mentioned basis, and described bogey also includes adjusting Regulating device, described adjusting means is for regulating the length of carrying platform, and described adjusting means is described for being arranged on Multiple locating grooves on longitudinal bracing frame, described cross-brace frame is by locating groove and described longitudinal bracing Frame connects.So, when being provided with adjusting means on bogey, described adjusting means is used for regulating carrying dress During the length put, for the different length size of prefabricated component, can by the length adjusting bogey come with Adapt, facilitate application.Further, when regulating device be arranged on described longitudinal bracing frame many Individual locating groove, when described cross-brace frame is connected with described longitudinal bracing frame by locating groove, by fixed Position draw-in groove fixes with cross-brace frame location, easy to operate simple, is conducive to improving prefabricated component transport little The security reliability of car.
Another technical scheme of the present utility model is on above-mentioned basis, and described longitudinal bracing frame is at least One end is provided with alignment pin or hole, location.So, at least one end at longitudinal bracing frame be provided with alignment pin or Behind hole, location, prefabricated component travelling bogie can connect with other traction apparatuss or multiple travelling bogie easily Traction, facilitate that production line is longer, prefabricated component more in the case of use, particularly prefabricated component travelling bogie and The docking of boom hoisting platform is fixing and is accurately positioned, can be accurate by orbital docking easily so that it is can be smooth Ground smoothly transits walking on boom hoisting platform and bogey.
Another technical scheme of the present utility model is on above-mentioned basis, and described first driving means is for driving Dynamic motor or driving motor;Or described road wheel is track rolling wheel or pneumatic tire.So, first drive When dynamic device is for driving motor or driving motor, prefabricated component travelling bogie controls simple, and technology realizes difficulty Spend relatively low, it is simple to operative;Described road wheel is track rolling wheel or pneumatic tire, then can basis Practical situation selects road wheel, it is possible to relatively easily meet the application in various different place.
Another technical scheme of the present utility model is that, on above-mentioned basis, the end of described carrying platform is also Being provided with partition deployment mechanism, described partition deployment mechanism is used for depositing preform production line and cuts off.So, After the end of bogey is additionally provided with partition deployment mechanism, during preform production, can be by fortune The transport of reinforcing bar, reinforced mesh, reinforcing bar or steel skeleton is made a reservation for by defeated dolly and partition deployment mechanism to production line Position, and put down one by one, so, advantageously reduce hand labor intensity, improve production efficiency, fall Low preform production cost.
Accompanying drawing explanation
The accompanying drawing constituting a part of the present utility model is further appreciated by of the present utility model for providing, this The schematic description and description of utility model is used for explaining this utility model, is not intended that this practicality new The improper restriction of type.
Fig. 1 is the structure chart of the prefabricated component conveying arrangement involved by a kind of embodiment of this technology;
Fig. 2 is the structure chart of the prefabricated component conveying arrangement involved by this technology another embodiment;
Fig. 3 is a kind of embodiment of the prefabricated component lifting trolley shown in Fig. 1 in prefabricated component conveying arrangement Front view;
Fig. 4 is a kind of embodiment of the prefabricated component lifting trolley shown in Fig. 1 in prefabricated component conveying arrangement Side view;
Fig. 5 is partial enlarged drawing at the B of prefabricated component lifting trolley shown in Fig. 4;
Fig. 6 is the another embodiment of the prefabricated component lifting trolley shown in Fig. 2 in prefabricated component conveying arrangement Front view;
Fig. 7 is the another embodiment of the prefabricated component lifting trolley shown in Fig. 2 in prefabricated component conveying arrangement Side view;
Fig. 8 is another embodiment of the prefabricated component lifting trolley shown in Fig. 2 in prefabricated component conveying arrangement Front view;
Fig. 9 is a kind of embodiment of the prefabricated component travelling bogie shown in Fig. 1 in prefabricated component conveying arrangement Structure chart;
Figure 10 is the another embodiment of the prefabricated component travelling bogie shown in Fig. 1 in prefabricated component conveying arrangement Local structural graph.
In figure:
1 hanging apparatus 11 mast-up 12 hook assembly
14 ceiling mounted tracks 2 travelling platforms
21 second driving means 22 lift the longitudinal mobile roof support of road wheel 23
Boom hoisting track 3 door-shaped frame in 24 lifting walking mechanisms 221
101 cross-brace frame 102 longitudinal bracing frame 103 first driving means
104 road wheel 105 times boom hoisting track 106 sliding rails
107 cut off deployment mechanism
Detailed description of the invention
Being described in detail this utility model below in conjunction with the accompanying drawings, the description of this part is only exemplary reconciliation The property released, should not have any restriction effect to protection domain of the present utility model.Additionally, people in the art Feature in embodiment in presents and in different embodiment, according to the description of presents, can be carried out by member Respective combination.
This utility model embodiment is as follows, refers to Fig. 1 to Figure 10, a kind of prefabricated component conveying arrangement, especially Can be used for the transport of prestressed slab, it includes prefabricated component travelling bogie, prefabricated component lifting trolley and walking track, Described prefabricated component travelling bogie and prefabricated component lifting trolley run on described walking track, and described prefabricated component is transported Defeated dolly is used for prefabricated component handling to described prefabricated for the transport of prefabricated component, described prefabricated component lifting trolley On part travelling bogie;Described prefabricated component lifting trolley, including travelling platform 2 and hanging apparatus 1, described row Walk platform 2 and be arranged on the bottom of hanging apparatus 1, described travelling platform 2 include two longitudinal mobile roof supports 23, Second driving means 21 and at least two groups lifting road wheel 22, described second driving means 21 drives the most extremely Few one group of lifting road wheel 22 moves, and described lifting road wheel 22 is arranged on described longitudinal mobile roof support 23 Bottom;Described hanging apparatus 1 includes that mast-up 11 and hook assembly 12, described hook assembly 12 are arranged At the top of described mast-up 11, the top of described mast-up can be provided with ceiling mounted tracks 14, described in hang Hook assembly runs on ceiling mounted tracks 14, and the bottom of described mast-up 11 is provided with lifting walking mechanism 24, Described lifting walking mechanism 24 can be moved by the most described travelling platform 2.So, described prefabricated component travelling bogie Running on described walking track with prefabricated component lifting trolley, prefabricated component lifting trolley is for by prefabricated component handling On described prefabricated component travelling bogie, prefabricated component travelling bogie and prefabricated component lifting trolley run on same track, Decrease the lifting transhipment time, save production line place area occupied, simultaneously that production line is whole with material flow line Amount to line, not only solve material line floor space problem, and can also avoid occur material report to the leadship after accomplishing a task blocking Problem.It addition, use above-mentioned prefabricated component lifting trolley to carry out hoisting prefabricated part, with traditional driving or lifting Machine lifting is compared and is had the advantage that, sling height is low, range ability is little, simple to operate flexible and energy consumption The advantage such as low, meanwhile, uses the self-propelled wheel-type mode operation across production line both sides, and its work flow is short, Particularly it is along the lifting of production line direction and the operating type of movement so that it is in operation process, prefabricated component is not Can produce and significantly swing, can prevent lifting trolley from toppling, drastically increase the security performance of operation.And And, lifting walking mechanism 24 can be moved by the most described travelling platform 2, and hanging apparatus 1 is not take up bogey Surrounding space, improves the utilization rate in place, beneficially prefabricated component and is lifted on bogey, and, hang Install to the prefabricated component on bogey and may also operate as the effect of counterweight so that it is in lifting, transportation not Can rock swing, stability is more preferable.
On the basis of above-described embodiment, in another embodiment of this utility model, as depicted in figs. 1 and 2, Described mast-up 11 can be door type or triangular structure.So, it is door type or three when mast-up 11 During angular structure, triangular structure has the most excellent stability so that it is be unlikely to deform in hoisting process.
On the basis of above-described embodiment, in another embodiment of this utility model, bottom described hanging apparatus 1 One end be provided with built-in fitting placement mechanism, needed for described built-in fitting placement mechanism is used for placing production prefabricated component Built-in fitting;And/or, at least side bottom described hanging apparatus 1 is provided with limit mould fixed mechanism, described Limit mould fixed mechanism is for the transhipment of limit mould.So, during preform production, lifting trolley can be passed through Reinforcing bar, reinforced mesh, reinforcing bar, steel skeleton or limit mould are transported to production line precalculated position, and one by one will It puts down, and so, advantageously reduces hand labor intensity, improves production efficiency, reduces preform production and becomes This.
On the basis of above-described embodiment, in another embodiment of this utility model, as in figure 2 it is shown, two institutes State longitudinal mobile roof support 23 to be connected by least one vertical door-shaped frame 3, described door-shaped frame 3 Higher than mast-up 11.So, use door-shaped frame 3 to connect as mobile roof support, prefabricated component lifting can be improved The stability in the large of dolly, prevents its deformed damaged in hoisting process.
On the basis of above-described embodiment, in another embodiment of this utility model, as shown in Figures 1 to 8, Described longitudinal mobile roof support 23 top is also provided with boom hoisting track 221, described lifting vehicle with walking machine Structure 24 moves along described upper boom hoisting track 221.So, it is provided with when longitudinal mobile roof support 23 top Upper boom hoisting track 221, described lifting walking mechanism 24 moves along described upper boom hoisting track 221, During hoisting prefabricated part, after prefabricated component is lifted by boom hoisting, can be moved to holding by track On carrying platform, particularly it is along the lifting of production line direction and the operating type of movement so that it is in operation process, Prefabricated component does not have and significantly swings, and can prevent lifting trolley from toppling, drastically increase the safety of operation Energy.
On the basis of above-described embodiment, in another embodiment of this utility model, described lifting walking mechanism 24 Take turns for track rolling.So, lifting walking mechanism is track rolling wheel, and reducible doing up hangs walking mechanism 24 move forward and backward in orbit, it is not necessary to consider that the situation of direction skew occurs, reduce operation easier, carry High safety.
On the basis of above-described embodiment, in another embodiment of this utility model, described hook assembly 12 is permissible Including suspension hook, lifting rope and motor, described motor drives suspension hook to move up and down by lifting rope.So, electricity is used When machine is as lifting power machine structure, hoisting prefabricated part controls simple, and it is relatively low that technology realizes difficulty, it is simple to Operative.
On the basis of above-described embodiment, in another embodiment of this utility model, described hook assembly 12 is permissible Including two suspension hooks and two motors, said two suspension hook interval is arranged, two motors individually drive two Individual suspension hook moves up and down;Or described hook assembly 12 includes two suspension hooks and a motor, said two suspension hook Interval is arranged, described motor drives two suspension hooks to move up and down.So, use suspension hook interval to arrange, hanging During dress prefabricated component, can lift by flat condition, improve the translation stability of lifting trolley, be particularly prone to flat board Pile up, make plate body be not easily susceptible to damage, and so that the height i.e. Liftable that the lifting of prefabricated component is relatively low is complete Become.
On the basis of above-described embodiment, in another embodiment of this utility model, the bottom of described mast-up 11 At least one end can be provided with alignment pin or location hole.So, at least one end of the bottom of mast-up 11 After being provided with alignment pin or hole, location, prefabricated component lifting trolley can easily with other traction apparatuss or many Individual travelling bogie connects traction, facilitate that production line is longer, prefabricated component more in the case of use, the most in advance Product lifting trolley and the docking of prefabricated component travelling bogie are fixed and are accurately positioned, can be easily by orbital docking Accurately so that it is can successfully smoothly transit on boom hoisting platform and bogey walking.
On the basis of above-described embodiment, in another embodiment of this utility model, described second driving means 21 Can be to drive motor or drive motor;Or described lifting road wheel 22 is track rolling wheel or inflated wheel Tire.So, when the second driving means 21 is for driving motor or driving motor, prefabricated component lifting trolley controls letter Single easy, it is relatively low that technology realizes difficulty, it is simple to operative;Described lifting road wheel 22 is track rolling Wheel or pneumatic tire, then can select lifting road wheel according to practical situation, it is possible to relatively easily meet The application in various different places.
On the basis of above-described embodiment, in another embodiment of this utility model, as shown in Figure 9 and Figure 10, Described prefabricated component travelling bogie, can include bogey and the first walking mechanism, described first walking mechanism Being arranged on the bottom of bogey, described first walking mechanism, including the first driving means 103 and at least two Group road wheel 104, described first driving means 103 drives one group of road wheel 104 of at least a part of which to move.This Sample, prefabricated component travelling bogie can pass through the first walking mechanism and walk voluntarily, independent operating.
On the basis of above-described embodiment, in another embodiment of this utility model, as shown in Figure 9 and Figure 10, Described bogey can include two longitudinal bracing framves 102 and at least two cross-brace framves 101, described The two ends of cross-brace frame 101 are connected with described two longitudinal bracing framves 102 respectively, described cross-brace frame 101 form carrying platform with longitudinal bracing frame 102.So, include that at least two longitudinal directions are propped up when bogey Support 102 and at least two cross-brace framves 101, the two ends of described cross-brace frame 101 are respectively with described Article two, when longitudinal bracing frame 102 connects, after prefabricated component is lifted and is placed on bogey by boom hoisting, Contacting between prefabricated component with bogey is linear contact lay, has not only saved weight and the material of bogey, Also can lay according to its force way, effectively prevent prefabricated component from fractureing damage.
On the basis of above-described embodiment, in another embodiment of this utility model, as shown in Figure 9 and Figure 10, Described road wheel 104 can be arranged on the bottom of described longitudinal bracing frame 102.So, when road wheel 104 When being arranged on the bottom of described longitudinal bracing frame 102, the load of bogey and prefabricated component can pass through straight-line transmitting It is handed on road wheel, decreases the moment of torsion of road wheel wheel shaft, its deformed damaged under big load effect can be prevented.
On the basis of above-described embodiment, in another embodiment of this utility model, described cross-brace frame 101 For arch or trapezoidal.So, when cross-brace frame 101 be arch or trapezoidal time, its arch or trapezoidal under Portion is reserved with certain space, and such prefabricated component travelling bogie, can be directly from prefabricated component in running On stride across.
On the basis of above-described embodiment, in another embodiment of this utility model, as it is shown in figure 9, described vertical Lower boom hoisting track 105, the lifting of described hanging apparatus 1 can be provided with to the top of bracing frame 102 Frame 11 bottom is provided with lifting walking mechanism 24, when described prefabricated component travelling bogie and prefabricated component lifting trolley After docking is fixing, described lifting walking mechanism 24 can move along described lower boom hoisting track 105.So, Lower boom hoisting track 105, the lifting of described hanging apparatus 1 it is provided with on the top of longitudinal bracing frame 102 After frame 11 bottom is provided with lifting walking mechanism 24, when described prefabricated component travelling bogie and prefabricated component lift little After car docking is fixing, described lifting walking mechanism 24 can move along described lower boom hoisting track 105, lifting Device is not take up bogey surrounding space, improves the utilization rate in place, beneficially prefabricated component and is lifted into and holds Carry and put, and, the prefabricated component being lifted on bogey may also operate as the effect of counterweight so that it is Will not rock swing in lifting, transportation, stability is more preferable.
On the basis of above-described embodiment, in another embodiment of this utility model, as it is shown in figure 9, described in hold Carrying to put and can also include adjusting means, described adjusting means is for regulating the length of carrying platform, described tune Regulating device is the sliding rail 106 being arranged on described longitudinal bracing frame 102, described cross-brace frame 101 It is slidably connected with described longitudinal bracing frame 102 by sliding rail 106.So, when arranging on bogey There is adjusting means, when described adjusting means is for regulating the length of bogey, for the different length of prefabricated component Degree size, can be adapted therewith by the length adjusting bogey, facilitate application.Further, Being regulated by sliding rail 106, easy to operate simple, the amplitude of accommodation is easily controlled, and is conducive to carrying The security reliability of high prefabricated component travelling bogie.
On the basis of above-described embodiment, in another embodiment of this utility model, described bogey is all right Including adjusting means, described adjusting means is for regulating the length of carrying platform, and described adjusting means is for arranging Multiple locating grooves on described longitudinal bracing frame 102, described cross-brace frame 101 passes through locating groove It is connected with described longitudinal bracing frame 102.So, when being provided with adjusting means on bogey, described regulation When device is for regulating the length of bogey, for the different length size of prefabricated component, can be by adjusting The length of bogey adapts therewith, facilitates application.Further, when regulating device is for being arranged on Stating the multiple locating grooves on longitudinal bracing frame 102, described cross-brace frame 101 is by locating groove and institute State longitudinal bracing frame 102 when connecting, fixed with cross-brace frame 101 location by locating groove, operation side The most simple, be conducive to improving the security reliability of prefabricated component travelling bogie.
On the basis of above-described embodiment, in another embodiment of this utility model, described longitudinal bracing frame 102 At least one end can be provided with alignment pin or location hole.So, at least one end of longitudinal bracing frame 102 After being provided with alignment pin or hole, location, prefabricated component travelling bogie can easily with other traction apparatuss or many Individual travelling bogie connects traction, facilitate that production line is longer, prefabricated component more in the case of use, the most in advance Product travelling bogie and the docking of boom hoisting platform are fixed and are accurately positioned, can be accurate by orbital docking easily Really so that it is can successfully smoothly transit on boom hoisting platform and bogey walking.
On the basis of above-described embodiment, in another embodiment of this utility model, described first driving means 103 Can be to drive motor or drive motor;Or described road wheel 104 can be track rolling wheel or inflated wheel Tire.So, when the first driving means 103 is for driving motor or driving motor, prefabricated component travelling bogie controls Simple, it is relatively low that technology realizes difficulty, it is simple to operative;Described road wheel 104 is track rolling Wheel or pneumatic tire, then can select road wheel according to practical situation, it is possible to relatively easily meet various The application in different places.
On the basis of above-described embodiment, in another embodiment of this utility model, as shown in Figure 10, hold described in The end of carrying platform is also provided with cutting off deployment mechanism 107, and described partition deployment mechanism 107 is used for depositing Put preform production line to cut off.So, after the end of bogey is additionally provided with partition deployment mechanism 107, During preform production, can by travelling bogie and cut off deployment mechanism 107 by reinforcing bar, reinforced mesh, Reinforcing bar or steel skeleton transport to production line precalculated position, and are put down one by one, so, advantageously reduce Hand labor intensity, improves production efficiency, reduces preform production cost.
The above is only preferred implementation of the present utility model, it is noted that for the art For those of ordinary skill, on the premise of without departing from this utility model principle, it is also possible to make some improvement And retouching, these improvements and modifications also should be regarded as protection domain of the present utility model.

Claims (20)

1. a prefabricated component conveying arrangement, it is characterized in that: include prefabricated component travelling bogie, prefabricated component lifting trolley and walking track, described prefabricated component travelling bogie and prefabricated component lifting trolley run on described walking track, described prefabricated component travelling bogie is used for prefabricated component handling to described prefabricated component travelling bogie for the transport of prefabricated component, described prefabricated component lifting trolley;
Described prefabricated component lifting trolley, including travelling platform and hanging apparatus, described travelling platform is arranged on the bottom of hanging apparatus, described travelling platform includes two longitudinal mobile roof supports, the second driving means and at least two groups lifting road wheel, described second driving means drives at least a part of which one group lifting road wheel motion, and described lifting road wheel is arranged on the bottom of described longitudinal mobile roof support;Described hanging apparatus includes that mast-up and hook assembly, described hook assembly are arranged on the top of described mast-up, and the bottom of described mast-up is provided with lifting walking mechanism, and described lifting walking mechanism can the motion of the most described travelling platform.
Prefabricated component conveying arrangement the most according to claim 1, it is characterised in that described mast-up is door type or triangular structure.
Prefabricated component conveying arrangement the most according to claim 1, it is characterised in that the one end bottom described hanging apparatus is provided with built-in fitting placement mechanism, described built-in fitting placement mechanism is for placing the built-in fitting produced needed for prefabricated component;And/or, at least side bottom described hanging apparatus is provided with limit mould fixed mechanism, and described limit mould fixed mechanism is for the transhipment of limit mould.
Prefabricated component conveying arrangement the most according to claim 1, it is characterised in that two described longitudinal mobile roof supports are connected by least one vertical door-shaped frame, and described door-shaped frame is higher than mast-up.
Prefabricated component conveying arrangement the most according to claim 1, it is characterised in that described longitudinally walking frame upper is provided with boom hoisting track, and described lifting walking mechanism moves along described upper boom hoisting track.
Prefabricated component conveying arrangement the most according to claim 5, it is characterised in that described lifting walking mechanism is track rolling wheel.
Prefabricated component conveying arrangement the most according to claim 1, it is characterised in that described hook assembly includes suspension hook, lifting rope and motor, described motor drives suspension hook to move up and down by lifting rope.
Prefabricated component conveying arrangement the most according to claim 7, it is characterised in that described hook assembly includes that two suspension hooks and two motors, said two suspension hook interval are arranged, two motors individually drive two suspension hooks to move up and down;Or described hook assembly includes that two suspension hooks and a motor, said two suspension hook interval are arranged, described motor drives two suspension hooks to move up and down.
Prefabricated component conveying arrangement the most according to claim 1, it is characterised in that at least one end of the bottom of described mast-up is provided with alignment pin or hole, location.
Prefabricated component conveying arrangement the most according to any one of claim 1 to 9, it is characterised in that described second driving means is for driving motor or driving motor;Or described lifting road wheel is track rolling wheel or pneumatic tire.
11. prefabricated component conveying arrangements according to any one of claim 1 to 9, it is characterized in that, described prefabricated component travelling bogie, including bogey and the first walking mechanism, described first walking mechanism is arranged on the bottom of bogey, described first walking mechanism, including the first driving means and at least two group road wheels, described first driving means drives one group of road wheel motion of at least a part of which.
12. prefabricated component conveying arrangements according to claim 11, it is characterized in that, described bogey includes two longitudinal bracing framves and at least two cross-brace framves, the two ends of described cross-brace frame are connected with described two longitudinal bracing framves respectively, and described cross-brace frame forms carrying platform with longitudinal bracing frame.
13. prefabricated component conveying arrangements according to claim 12, it is characterised in that described road wheel is arranged on the bottom of described longitudinal bracing frame.
14. prefabricated component conveying arrangements according to claim 12, it is characterised in that described cross-brace frame is arch or trapezoidal.
15. prefabricated component conveying arrangements according to claim 12, it is characterized in that, the top of described longitudinal bracing frame is provided with lower boom hoisting track, the mast-up bottom of described hanging apparatus is provided with lifting walking mechanism, after described prefabricated component travelling bogie and prefabricated component lifting trolley dock and fix, described lifting walking mechanism can move along described lower boom hoisting track.
16. prefabricated component conveying arrangements according to claim 12, it is characterized in that, described bogey also includes adjusting means, described adjusting means is for regulating the length of carrying platform, described adjusting means is the sliding rail being arranged on described longitudinal bracing frame, and described cross-brace frame is slidably connected with described longitudinal bracing frame by sliding rail.
17. prefabricated component conveying arrangements according to claim 12, it is characterized in that, described bogey also includes adjusting means, described adjusting means is for regulating the length of carrying platform, described adjusting means is the multiple locating grooves being arranged on described longitudinal bracing frame, and described cross-brace frame is connected with described longitudinal bracing frame by locating groove.
18. prefabricated component conveying arrangements according to claim 12, it is characterised in that at least one end of described longitudinal bracing frame is provided with alignment pin or hole, location.
19. prefabricated component conveying arrangements according to claim 12, it is characterised in that described first driving means is for driving motor or driving motor;Or described road wheel is track rolling wheel or pneumatic tire.
20. prefabricated component conveying arrangements according to claim 11, it is characterised in that the end of described carrying platform is additionally provided with partition deployment mechanism, described partition deployment mechanism is used for depositing preform production line and cuts off.
CN201620096795.5U 2016-01-29 2016-01-29 Prefab conveyer Active CN205526359U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620096795.5U CN205526359U (en) 2016-01-29 2016-01-29 Prefab conveyer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620096795.5U CN205526359U (en) 2016-01-29 2016-01-29 Prefab conveyer

Publications (1)

Publication Number Publication Date
CN205526359U true CN205526359U (en) 2016-08-31

Family

ID=56774543

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620096795.5U Active CN205526359U (en) 2016-01-29 2016-01-29 Prefab conveyer

Country Status (1)

Country Link
CN (1) CN205526359U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107587413A (en) * 2017-11-01 2018-01-16 中冶建工集团有限公司 A kind of kerbstone installation auxiliary chassis
CN109573850A (en) * 2018-10-31 2019-04-05 中民筑友智能装备科技有限公司 A kind of prefabricated component boom hoisting
CN111038940A (en) * 2019-12-02 2020-04-21 上海市政工程设计研究总院(集团)有限公司 Rail mounted is used for hoist and mount traction system of transportation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107587413A (en) * 2017-11-01 2018-01-16 中冶建工集团有限公司 A kind of kerbstone installation auxiliary chassis
CN109573850A (en) * 2018-10-31 2019-04-05 中民筑友智能装备科技有限公司 A kind of prefabricated component boom hoisting
CN109573850B (en) * 2018-10-31 2023-12-22 中民筑友智能装备科技有限公司 Prefabricated member lifting device
CN111038940A (en) * 2019-12-02 2020-04-21 上海市政工程设计研究总院(集团)有限公司 Rail mounted is used for hoist and mount traction system of transportation

Similar Documents

Publication Publication Date Title
US20210332533A1 (en) Novel track layer for urban track traffic engineering and its construction method
CN207498755U (en) A kind of traveling trolley adjusted with horizontal extension and vertical supporting
CN105668163A (en) Prefabricated part production and transportation system
CN105645057A (en) Prefabricated part production and transportation system
CN205526359U (en) Prefab conveyer
CN111502293B (en) Method and system for hoisting single peripheral component of assembly type building
CN207498754U (en) A kind of novel track-laying machine of city track traffic engineering
CN105501872A (en) Prefabricated part production and conveying system
CN205739198U (en) A kind of preform production transportation system
KR20150070578A (en) Construction Method
CN205526360U (en) Prefab conveyer
CN108130862B (en) Tunnel passing beam vehicle
CN205418901U (en) Prefab conveyer
CN205574940U (en) Prefab conveyer
CN205574936U (en) Prefab conveyer
CN105480662A (en) Fabricated part production and transport system
KR101373098B1 (en) Construction appratus for composit truss free cantilever bridge and construction method of composit truss free cantilever bridge using the same
CN110065783B (en) Track crossing type transport vehicle
CN205471273U (en) Prefab production conveyor system
CN205526358U (en) Prefab production conveyor system
CN205526362U (en) Prefab travelling bogie
CN205574939U (en) Prefab conveyer
CN205574937U (en) Prefab production conveyor system
CN205574938U (en) Prefab production conveyor system
CN205346714U (en) Prefab hoisting trolley

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170816

Address after: 410205 comprehensive building in Hunan province Changsha Kaifu District, No. 30 Xingang Road, Changsha Jinxia bonded logistics center room 3005

Patentee after: Hunan people's Republic of China build friends Mdt InfoTech Ltd

Address before: 410205 comprehensive building in Hunan province Changsha Kaifu District, No. 30 Xingang Road, Changsha Jinxia bonded logistics center room 3005

Patentee before: Zhong Minzhuyou Co., Ltd

TR01 Transfer of patent right