CN205444902U - Prepared hole die of concrete - Google Patents

Prepared hole die of concrete Download PDF

Info

Publication number
CN205444902U
CN205444902U CN201620155988.3U CN201620155988U CN205444902U CN 205444902 U CN205444902 U CN 205444902U CN 201620155988 U CN201620155988 U CN 201620155988U CN 205444902 U CN205444902 U CN 205444902U
Authority
CN
China
Prior art keywords
roof
screw rod
top board
concrete
roof plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620155988.3U
Other languages
Chinese (zh)
Inventor
陈迪雍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201620155988.3U priority Critical patent/CN205444902U/en
Application granted granted Critical
Publication of CN205444902U publication Critical patent/CN205444902U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses prepared hole die of concrete, include the circular cone stage body with concrete preformed hole assorted big -end -up, fix the roof at circular cone stage body top, there is the roof centre bore on the corresponding position of roof and circular cone stage body bottom respectively, the area is the bottom centre bore of roof mounting groove down, the roof is equipped with down in the roof mounting groove, the screw rod of top area handle passes the roof centre bore in proper order, the bottom centre bore, down the roof and stretch out down the roof outer and down the roof fix on the screw rod, screw rod bottom end is the toper, the top board is equipped with to the position that lies in the roof on the screw rod outer. The utility model discloses simple structure, construction, installation, fixed convenient, the suitability is strong, saves time, laborsaving, durable.

Description

Prepared hole die of concrete
Technical field:
This utility model building engineering construction field, particularly to be a kind of coagulation prepared hole die.
Background technology:
Modern architecture building mainly use and first do chassis body, carry out the assembling of second phase inner facility after chassis body binds again.Indoor are given, the pipeline of draining is all to assemble with the main body construction reserving hole later stage again.Former concrete floor flat board reserving hole mainly uses the pvc pipe of appropriate length or conduit peschel to make provided pipe, then pvc pipe or conduit peschel iron wire, iron nail are fixed on the position of needs, after concrete initial set, further take out pvc pipe or conduit peschel, complete the construction of preformed hole.This method needs workmen's accurate assurance of operation to take the pipe time, has taken early concrete slump, can not form required hole, the most then can not take provided pipe, waste, and when pouring into a mould concrete, due to the side pressure of concrete, the provided pipe using iron wire fixing the most all can produce displacement.
Utility model content:
The purpose of this utility model is to overcome above deficiency, it is provided that a kind of simple in construction, constructs, installs, convenient fixing, and the suitability is strong, saves time, laborsaving, long-lived prepared hole die of concrete.
The purpose of this utility model is achieved like this:
This utility model prepared hole die of concrete, including the up big and down small circular cone stage body matched with concrete preformed hole, the top board that is fixed on circular cone stage body top, top board centre bore, the bottom centre hole of leukorrhagia mounting of roof plate groove is had on opposite position respectively bottom top board and circular cone stage body, equipped with lower roof plate in lower roof plate mounting groove, the screw rod of top tape handle sequentially pass through top board centre bore, bottom centre hole, lower roof plate and stretch out outside lower roof plate and lower roof plate is fixed on screw rod, screw rod bottom is taper, and position screw rod being positioned at outside top board is equipped with top board.
Having the tubular being positioned at outside top board centre bore, bottom mesopore to support in above-mentioned frustum of a cone body, intensity is high.
This utility model have employed up big and down small circular cone stage body, and the outlet aperture of the reserved hole shaped of construction is in magnifying state, so after concrete completes solidification, delivery is very easy to.This utility model have employed when the screw rod that bottom is the top tape handle of taper is installed and is prone to fixing, and accurate positioning, location can be as accurate as millimeter;During taking-up light, quick, time saving and energy saving.Screw rod uses coarse groove screw rod, durable in use during construction at the scene, is hardly damaged.
This utility model simple in construction, constructs, installs, convenient fixing, and the suitability is strong, saves time, laborsaving, durable in use.
Accompanying drawing illustrates:
Fig. 1 is this utility model structural representation.
Fig. 2 is this utility model schematic perspective view.
Fig. 3 is utility model works schematic diagram.
Detailed description of the invention:
Seeing Fig. 1, Fig. 2, this utility model prepared hole die of concrete, including the up big and down small circular cone stage body 1 matched with concrete preformed hole, the top board 2 that is fixed on circular cone stage body top.Top board centre bore 3, the bottom centre hole 5 of leukorrhagia mounting of roof plate groove 4 is had on opposite position respectively bottom top board and circular cone stage body.Equipped with lower roof plate 6 in lower roof plate mounting groove.The screw rod 8 of top tape handle 7 sequentially pass through top board centre bore, bottom centre hole, lower roof plate and stretch out outside lower roof plate and lower roof plate is fixed on screw rod.Screw rod bottom is cone.The position being positioned at outside top board on screw rod is fixed with top board 9.
Seeing Fig. 3, during utility model works, screw rod with handles sequentially passes through top board centre bore, circular cone stage body bottom centre hole and lower roof plate and stretches out outside lower roof plate and be integrally fixed in rear thread precession template 10 with lower roof plate, then carries out concrete 11 and pours into a mould.After the solidification of concrete casting complete, reversely rotating handle, screw rod drives lower roof plate upwards, and this utility model is taken out of the concrete of casting solidification.

Claims (2)

1. prepared hole die of concrete, it is characterized in that including the up big and down small circular cone stage body matched with concrete preformed hole, the top board being fixed on circular cone stage body top, top board centre bore, the bottom centre hole of leukorrhagia mounting of roof plate groove is had on opposite position respectively bottom top board and circular cone stage body, equipped with lower roof plate in lower roof plate mounting groove, the screw rod of top tape handle sequentially pass through top board centre bore, bottom centre hole, lower roof plate and stretch out outside lower roof plate and lower roof plate is fixed on screw rod, screw rod bottom is taper, and position screw rod being positioned at outside top board is equipped with top board.
2. prepared hole die of concrete as claimed in claim 1, it is characterised in that be positioned in frustum of a cone body outside top board centre bore, bottom centre hole and have tubular to support.
CN201620155988.3U 2016-03-02 2016-03-02 Prepared hole die of concrete Expired - Fee Related CN205444902U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620155988.3U CN205444902U (en) 2016-03-02 2016-03-02 Prepared hole die of concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620155988.3U CN205444902U (en) 2016-03-02 2016-03-02 Prepared hole die of concrete

Publications (1)

Publication Number Publication Date
CN205444902U true CN205444902U (en) 2016-08-10

Family

ID=56604576

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620155988.3U Expired - Fee Related CN205444902U (en) 2016-03-02 2016-03-02 Prepared hole die of concrete

Country Status (1)

Country Link
CN (1) CN205444902U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108265976A (en) * 2017-12-05 2018-07-10 徐硕 A kind of pipe hole preformed device and operating method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108265976A (en) * 2017-12-05 2018-07-10 徐硕 A kind of pipe hole preformed device and operating method

Similar Documents

Publication Publication Date Title
CN103061504B (en) Concrete slab Pipe installing hole to be provided construction mould and construction method
CN205444902U (en) Prepared hole die of concrete
CN201574507U (en) Soft film ceiling mounting structure
CN204754216U (en) But telescopic tube
CN207569004U (en) A kind of hanger fixing device of a Preembedded
CN203867588U (en) Pre-buried channel fixing component
CN206667787U (en) A kind of civilian steel house assembles positioning clamping fixture with square tube post
CN203878756U (en) Embedded connecting device
CN205296617U (en) Warmhouse booth is with snow removing device
CN205591549U (en) Building structure floor plate preformed hole mould
CN203430034U (en) Fixing tool for locating pre-buried sleeve of cast-in-place slab
CN202391114U (en) Pipe passing floorslab sleeve pail
CN207892233U (en) Structure and decoration integrated cast-in-place concrete elastic decorative mould system
CN205712954U (en) Joint structure is installed in EPS finished product moulding bar planting
CN207487649U (en) A kind of total station prism reflection unit
CN202689554U (en) Concrete wall form positioning and supporting device
CN208363616U (en) A kind of locating sleeve buried beforehand device
CN206091340U (en) Adjustable datum line fixing device
CN205688736U (en) A kind of many curved surfaces concavo-convex moulding GRG mounting structure
CN106437144B (en) Turn over beam die plate reinforcing device
CN105317444A (en) Fixing assembly for pre-buried channel
CN203795856U (en) Installation structure of shaping combination formwork
CN203066413U (en) Reinforced connecting device for stone material
CN205504221U (en) A fixed component for inciting somebody to action air conditioner pipeline is fixed on building ceiling
CN201535062U (en) Movable scaffold

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160810

Termination date: 20170302

CF01 Termination of patent right due to non-payment of annual fee