CN205444201U CN201620200886.9U CN201620200886U CN205444201U CN 205444201 U CN205444201 U CN 205444201U CN 201620200886 U CN201620200886 U CN 201620200886U CN 205444201 U CN205444201 U CN 205444201U
Authority
CN
China
Prior art keywords
reinforcement cage
cage skeleton
reinforcement
steel reinforcement
waist rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620200886.9U
Other languages
Chinese (zh)
Inventor
王巧南
张立国
段仕伟
杨宝军
陈洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201620200886.9U priority Critical patent/CN205444201U/en
Application granted granted Critical
Publication of CN205444201U publication Critical patent/CN205444201U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The utility model relates to a building trade, in particular to underground structure. A reinforced concrete waist rail structure is proposed, including the steel reinforcement cage skeleton and pour the concrete structure layer inside and outside the steel reinforcement cage skeleton, the steel reinforcement cage skeleton is become by longitudinal reinforcement and stirrup ligature, is provided with fore -and -aft anti splitting reinforcing bar net in the steel reinforcement cage skeleton, and anti splitting reinforcing bar net and steel reinforcement cage skeleton bound connection are provided with the lacing wire in the steel reinforcement cage skeleton, the lacing wire is horizontal set up and with longitudinal reinforcement and stirrup bound connection, interval distribution has the reinforcement reinforcing bar on the steel reinforcement cage skeleton, consolidates the one end and steel reinforcement cage skeleton bound connection of reinforcing bar, and the other end stretches out the steel reinforcement cage skeleton. The utility model has the advantages of simple structure, underground structure's is stable good, improves construction speed, reduces construction cost, can be extensive be applied to in the building trade.

Description

A kind of reinforced concrete waist rail structure
Technical field
This utility model relates to building trade, particularly to foundation pit supporting construction.
Background technology
At present, the commonly used steel wale of deep foundation pit supporting structure waist rail, but being in the architectural engineering of northern area in engineering, winter temperature is relatively low, and the deep 22m of this Deep Foundation Pit, geological conditions contains a large amount of clay parting, owing to the clay property of water-bearing and water-retaining property are relatively big, temperature is the most too low, frost heave easily occurs, produce soil expansion, easily affect the stability of foundation pit supporting construction according to steel wale.
Summary of the invention
The utility model proposes reinforced concrete waist rail structure, this utility model simple in construction, improve the construction quality of reinforced concrete waist rail, the good stability of foundation pit supporting construction, improves construction speed, reduces construction cost.
For achieving the above object, the technical solution adopted in the utility model is: a kind of reinforced concrete waist rail structure, including reinforcement cage skeleton and pour the concrete inside and outside reinforcement cage skeleton, described reinforcement cage skeleton is become with stirrup colligation by longitudinal reinforcement, longitudinal anti-splitting bar-mat reinforcement it is provided with in reinforcement cage skeleton, anti-splitting bar-mat reinforcement is connected with reinforcement cage skeleton colligation, lacing wire it is provided with in reinforcement cage skeleton, lacing wire horizontally set and being connected with longitudinal reinforcement and stirrup colligation, it is intervally distributed with reinforced steel on described reinforcement cage skeleton, one end of reinforced steel is connected with reinforcement cage skeleton colligation, the other end stretches out reinforcement cage skeleton.
Described stirrup is stirrup of remaining silent, and stirrup is longitudinally spaced distribution on reinforcement cage skeleton.
Described anti-splitting bar-mat reinforcement is through to be arranged in reinforcement cage skeleton.
Described anti-splitting bar-mat reinforcement has two-layer, and two-layer anti-splitting bar-mat reinforcement is spaced apart.
The layout pitch of described reinforced steel is 500mm-1000mm.
This utility model, by using reinforced concrete waist rail, increases the contact surface of waist rail and supporting construction, it is possible to preferably transmission supporting construction and anchor pole fulcrum power, thus increases the stability of supporting construction.Compared with prior art, there is simple in construction, the good stability of foundation pit supporting construction, improves construction speed, reduces the advantages such as construction cost, can be widely used in building trade.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Fig. 2 is use view of the present utility model.
In figure: 1-longitudinal reinforcement, 2-stirrup, 3-lacing wire, 4-ground floor anti-splitting bar-mat reinforcement, the 5-second layer anti-splitting bar-mat reinforcement, 6-concrete, 7-reinforced steel.
Detailed description of the invention
Below in conjunction with the accompanying drawings this utility model is described in detail.
Reinforced concrete waist rail structure as shown in Figure 1, including reinforcement cage skeleton and be cast in the concrete 6 inside and outside reinforcement cage skeleton, reinforcement cage skeleton is the steel reinforcement cage become with stirrup 2 colligation by longitudinal reinforcement 1, being provided with the anti-splitting bar-mat reinforcement that two-layer is longitudinal in reinforcement cage skeleton, two-layer anti-splitting bar-mat reinforcement is through to be arranged in reinforcement cage skeleton.Ground floor anti-splitting bar-mat reinforcement 4 and the second layer anti-splitting bar-mat reinforcement 5 are spaced apart, anti-splitting bar-mat reinforcement is connected with reinforcement cage skeleton colligation, lacing wire 3 it is provided with in reinforcement cage skeleton, lacing wire 3 horizontally set and being connected with longitudinal reinforcement 1 and stirrup 2 colligation, being intervally distributed with reinforced steel 7 on reinforcement cage skeleton, the reinforced steel 7 layout pitch on waist rail is 1000mm-3000mm.One end of reinforced steel 7 is connected with reinforcement cage skeleton colligation, and the other end stretches out reinforcement cage skeleton muscle main with support pile and is welded to connect, as shown in Figure 2.
Reinforced concrete waist rail construction method comprises the steps:
1. preparation: mechanical engagement labor cleaning ground before reinforced concrete waist rail construction, leveling.Cleaning support pile face simultaneously, carries out picking chisel with electric pick docking contacting surface concrete, gently pick out pile concrete fresh.
2. anchor cable construction: manually adjust anchor cable steel strand wires elevation angle, it is ensured that make it in same level.
3. anchor cable protection set construction: complete anchor cable steel strand wires are each passed through 6 points of PVC plastic pipes by constructing; pvc pipe is buried in the earth not less than 100mm near inter-pile soil side; in hole, side exposes outside template not less than 50mm; select pvc pipe neither to affect anchorage cable stretching, again anchor cable steel strand wires are served protective effect simultaneously.
4. reinforcement cage skeleton is installed: reinforcement cage skeleton uses in-situ precast steel reinforcement cage, and after reinforcement yard is by steel reinforcement cage colligation, direct integral installation, manually adjusts reinforcement location, makes the reinforcing bar up and down crossing steel strand wires draw close to centre.
5. waist rail is reinforced: for preventing steel reinforcement cage from shifting, arranges waist rail reinforced steel, arranges reinforced steel in support pile interplanar distance 2.6m, when installing precast reinforced cage, by the most firm with steel reinforcement cage longitudinal reinforcement colligation for reinforced steel.
6. waist rail mould construction: lay the layer of non-woven fabric bed die as waist rail under steel reinforcement cage.
7. waist rail side form construction: waist rail side template uses single side formwork, selects the plank sheathing that surfacing is smooth, bores aperture in the anchor cable steel strand wires position of plank sheathing, and quantity is identical with corresponding anchor cable steel strand wires quantity, and PVC sleeve pipe and anchor cable steel strand wires are through boring.
8. waist rail formwork reinforcement: waist rail side template longitudinal rib uses 50mm steel pipe, top, bottom respectively arrange a sleeper and support, wood supports through layout, during steel pipe oblique cutting buries, angle is consistent with waist rail side template angle is 15 °, steel pipe level interval 1m, it may be necessary to utilize steel strand wires colligation iron wire reinforcing template.
9. concreting.

Claims (5)

1. a reinforced concrete waist rail structure, it is characterized in that: include reinforcement cage skeleton and pour the concrete inside and outside reinforcement cage skeleton, described reinforcement cage skeleton is become with stirrup colligation by longitudinal reinforcement, longitudinal anti-splitting bar-mat reinforcement it is provided with in reinforcement cage skeleton, anti-splitting bar-mat reinforcement is connected with reinforcement cage skeleton colligation, lacing wire it is provided with in reinforcement cage skeleton, lacing wire horizontally set and being connected with longitudinal reinforcement and stirrup colligation, it is intervally distributed with reinforced steel on described reinforcement cage skeleton, one end of reinforced steel is connected with reinforcement cage skeleton colligation, the other end stretches out reinforcement cage skeleton.
Reinforced concrete waist rail structure the most according to claim 1, it is characterised in that: described stirrup is stirrup of remaining silent, and stirrup is longitudinally spaced distribution on reinforcement cage skeleton.
Reinforced concrete waist rail structure the most according to claim 1, it is characterised in that: described anti-splitting bar-mat reinforcement is through to be arranged in reinforcement cage skeleton.
4. according to the arbitrary described reinforced concrete waist rail structure of claim 1-3, it is characterised in that: described anti-splitting bar-mat reinforcement has two-layer, and two-layer anti-splitting bar-mat reinforcement is spaced apart.
5. according to the arbitrary described reinforced concrete waist rail structure of claim 1-3, it is characterised in that: the layout pitch of described reinforced steel is 500mm-1000mm.
CN201620200886.9U 2016-03-16 2016-03-16 Reinforced concrete waist rail structure Expired - Fee Related CN205444201U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620200886.9U CN205444201U (en) 2016-03-16 2016-03-16 Reinforced concrete waist rail structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620200886.9U CN205444201U (en) 2016-03-16 2016-03-16 Reinforced concrete waist rail structure

Publications (1)

Publication Number Publication Date
CN205444201U true CN205444201U (en) 2016-08-10

Family

ID=56603007

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620200886.9U Expired - Fee Related CN205444201U (en) 2016-03-16 2016-03-16 Reinforced concrete waist rail structure

Country Status (1)

Country Link
CN (1) CN205444201U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106854872A (en) * 2017-01-18 2017-06-16 中国建筑第八工程局有限公司 Dell cylinder mould anti-floating hardened system and its construction method
CN106894426A (en) * 2017-04-24 2017-06-27 青岛建集团有限公司 A kind of combined bolting and shotcrete breast beam structure
CN107268634A (en) * 2017-06-27 2017-10-20 湖南省第六工程有限公司 Deep basal pit waist rail construction typified form system
CN114934517A (en) * 2022-05-18 2022-08-23 中建八局第一建设有限公司 Foundation pit special-shaped continuous waist beam and construction method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106854872A (en) * 2017-01-18 2017-06-16 中国建筑第八工程局有限公司 Dell cylinder mould anti-floating hardened system and its construction method
CN106894426A (en) * 2017-04-24 2017-06-27 青岛建集团有限公司 A kind of combined bolting and shotcrete breast beam structure
CN106894426B (en) * 2017-04-24 2024-06-18 青岛一建集团有限公司 Waist beam structure for shotcrete support
CN107268634A (en) * 2017-06-27 2017-10-20 湖南省第六工程有限公司 Deep basal pit waist rail construction typified form system
CN114934517A (en) * 2022-05-18 2022-08-23 中建八局第一建设有限公司 Foundation pit special-shaped continuous waist beam and construction method thereof
CN114934517B (en) * 2022-05-18 2023-07-25 中建八局第一建设有限公司 Special-shaped continuous waist beam for foundation pit and construction method thereof

Similar Documents

Publication Publication Date Title
CN102031784B (en) Slope protection pile pouring and cable bolting construction method for deep foundation pit
CN101985882B (en) Construction method of rigid primary support of mould-building concrete of plateau permafrost tunnel
CN205444201U (en) Reinforced concrete waist rail structure
CN106120801B (en) Pipeline crosses the construction method at foundation ditch in water-rich sand layer
CN206376276U (en) A kind of prefabricated pipe gallery
CN105951848A (en) Non-intermittent composite transfer structure for super-deep foundation pit support and construction method
CN106988343A (en) A kind of town road pipeline protection structure and its construction method
CN105625298B (en) Using the continuous underground wall structure and its construction method of glass fiber-reinforced polymer lap joint sleeve milling
CN104060781A (en) Cast-in-situ cranked slab stair without seams at stair sections and construction method
CN205100225U (en) Assembled stake - board - anchor - roof beam combination formula batholith supporting construction
CN105201012A (en) Casting cable trench after assembly of L-shaped precast concrete and construction method of casting cable trench
CN106013171A (en) Semi-rigid and semi-flexible support structure and method for deep foundation pit side wall
CN103161176B (en) Tower crane foundation construction method in main building disjunctor garage
CN106436732A (en) Reinforcing method and reinforcing structure for replacing strip foundations by raft foundations
CN104631674A (en) Composite floor slab and construction method thereof
CN105089023A (en) Hydropower house concrete bottom plate improvement method and structure thereof
CN204825928U (en) Excavation supporting
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN205296209U (en) Prestressed anchorage cable assembled stake siding wall protective structure
CN110761795B (en) Construction method of shallow tunnel in loess gully
CN210263075U (en) Arrange bars formula tubular pile post back slip casting internal anchor outer stagnant water support system
CN205116220U (en) Pour cable pit after assembly of L type precast concrete spare
CN204238264U (en) A kind of sole plate post-poured strip structure
CN203905331U (en) Cast-in-place plate-type staircase with seamless steps
CN102877413B (en) Construction technology for large-size cableway bridge engineering

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160810

CF01 Termination of patent right due to non-payment of annual fee