CN205382551U - Glass fiber reinforced plastic inspection well - Google Patents

Glass fiber reinforced plastic inspection well Download PDF

Info

Publication number
CN205382551U
CN205382551U CN201620200660.9U CN201620200660U CN205382551U CN 205382551 U CN205382551 U CN 205382551U CN 201620200660 U CN201620200660 U CN 201620200660U CN 205382551 U CN205382551 U CN 205382551U
Authority
CN
China
Prior art keywords
well body
well
chamber
inspection
pipe network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620200660.9U
Other languages
Chinese (zh)
Inventor
蒋涛
洪涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Yangxin Equipment Engineering Co Ltd
Original Assignee
Shanghai Yangxin Equipment Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Yangxin Equipment Engineering Co Ltd filed Critical Shanghai Yangxin Equipment Engineering Co Ltd
Priority to CN201620200660.9U priority Critical patent/CN205382551U/en
Application granted granted Critical
Publication of CN205382551U publication Critical patent/CN205382551U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model discloses a glass fiber reinforced plastic inspection well relates to secret pipeline technology field, personally experience sth. Part of the body including last well, go up the supporting well lid of installing in well body upper end, upward be provided with the bearing pad circle around the well body upper end, go up the well body bottom zonulae occludens reducing well body, reducing well body bottom zonulae occludens examination room, examination room bottom zonulae occludens sink the mud room, be provided with the connecting hole on the examination room lateral wall, heavy mud room both sides set up to sludge bucket, and the mud room internally mounted that sinks there is the aeration pipe network, and aeration equipment is installed to heavy mud room bottom, the aeration pipe network be formed by connecting on many root canals ways, be provided with a plurality of ventholes on the pipeline, aeration pipe network and aeration equipment pass through the tube coupling intake pipe, and the intake pipe extends to the well lid bottom. The utility model discloses a components of a whole that can function independently package assembly can realize quick installation, has reduced workman's construction intensity simultaneously, has improved maintenance efficiency to can relieve workman's potential safety hazard with the flammable or last well of the toxic gas follow body discharge inside the examination room.

Description

A kind of fiber glass reinforced plastics inspection well
Technical field
This utility model relates to underground piping technical field, is specifically related to a kind of fiber glass reinforced plastics inspection well.
Background technology
Inspection chamber is commonly called as " inspection shaft ", and it is generally located in drainage pipeline intersection, turning, caliber or gradient change place, drop place and rectilinear tubes section to locate at a certain distance, is for making regular check on, clean and the draining auxiliary construction of dredging pipeline.Wherein, inspection chamber is broadly divided into dirt (giving up) water inspection chamber and rainwater inspection chamber.Owing to the pipeline section between adjacent two wells should be point-blank, therefore, all need to arrange inspection chamber in conduit section change place, gradient change place, intersection, elevation change place, long straight line pipeline section also needs subsection setup inspection chamber (carrying out regulation sublevel interval according to pipe diameter and rain, sewage type).
There are the following problems in the process used for existing inspection chamber: inspection chamber adopt build by laying bricks or stones, cast-in-place, add a cover the construction technology of concrete cover, such construction technology earthwork excavated volume is big, building construction amount is big, and long construction period, material roping amount is big;Owing to will do waterproof, preservative treatment inside inspection chamber, engineering difficulty is big, and the technology of staff is required height;Concrete cover needs can complete with hanging device when installing, it is necessary to more human and material resources, machinery, place can complete, and construction costs is high.
Simultaneously, owing to being chronically at closed environment, cannot circulate between gas and the external world in pipeline, if having humus to distribute methane or other sources leaking flammable or toxic gas, when workman enters tubular service, serious consequence will be caused, media in recent years often report workman enter that underground suffocates, inspection well cover flies out suddenly, kindling material falls into inspection chamber and causes the events such as blast, it is simply that flammable or what toxic gas caused in pipeline inner accumulated.
Again, mud is easily piled up in inspection chamber bottom, and it is hardening that mud does not clear up soil property for a long time, it is necessary to manually manually loosen the soil to shaft bottom, then manually little by little carries out by mud, so not only wastes time and energy, and cleaning efficiency is low, there is also potential safety hazard.
Utility model content
nullIn order to overcome existing inspection chamber machinery cost high,Internal flammable or toxic gas easily causes potential safety hazard during workman is to the maintenance of maintenance room,And pile real mud bottom inspection chamber and can not adopt the deficiency taking out slag car extraction,This utility model provides a kind of fiber glass reinforced plastics inspection well,This inspection shaft adopts separable assembled structure,All-weather construction can be met,Well body adopts glass-reinforced plastic material,Mud sinking chamber bottom well body is connected and installed with aeration pipe network and aerator by pipeline,Gases at high pressure are provided by outside air compressor,Gases at high pressure are aeration from aeration pipe network and aerator,Impact the earth within mud sinking chamber,Earth and gases at high pressure collide mutually,In this process, mud particles diminishes,Formation dirty solution blended with sewage,Ensure that taking out the slag car can extract out dirty solution,Simultaneously under the drive of air-flow flammable or toxic gas inspection chamber within from upper well body discharge,Release the potential safety hazard of workman.
This utility model solves its technical problem and be the technical scheme is that
A kind of fiber glass reinforced plastics inspection well, including upper well body, the supporting well lid that is provided with in upper well body upper end, upper well body upper end is provided around pressure-bearing packing ring;Upper well body bottom compact siro spinning technology diameter variable well body, diameter variable well body bottom compact siro spinning technology inspection chamber, inspection chamber bottom compact siro spinning technology mud sinking chamber;Inspection chamber sidewall is provided with connecting hole;Mud sinking chamber both sides are set to sludge bucket, and mud sinking chamber is internally installed aeration pipe network, is provided with aerator bottom mud sinking chamber;Described aeration pipe network is formed by connecting by many pipelines, and pipeline is provided with multiple venthole;Aeration pipe network and aerator connect air inlet pipe by pipeline, and air inlet pipe extends to well lid bottom.By arranging diameter variable well body, upper well body and inspection chamber are connected, be possible not only to reduce the cross-sectional area of upper well body, improve its ability keeping out extraneous stress, eliminate safe hidden trouble, but also the volume of inspection chamber can be expanded, be conducive to workman in inspection chamber interior construction.Connecting hole is connected with arm, and the diverse location on inspection chamber sidewall arranges multiple connecting hole according to actual needs, it is ensured that it is general.Sludge bucket collects mud, gases at high pressure are inputted by extraneous air compression plant by air inlet pipe, gases at high pressure enter into sewer catch basin from the online venthole of aeration tube and aerator, impact the earth that the heap within mud sinking chamber is real, earth and gases at high pressure collide mutually, in this process, mud particles diminishes, formation dirty solution blended with sewage, extract out by taking out the slag car with pipeline after dirty solution, change traditional workman to loosen the soil in mud room the working method then little by little carrying out by soil, alleviate the working strength of workman greatly, simultaneously under the drive of air-flow flammable or toxic gas inspection chamber within from upper well body discharge, release the potential safety hazard of workman.
Preferably, the described upper well body borehole wall being provided with cat ladder, cat ladder extends to inspection chamber bottom, facilitates workman to enter inspection chamber and carries out checking work.
Preferably, the gap of described pressure-bearing packing ring and upper well body fills up filler, further by pressure-bearing packing ring and upper well body compact siro spinning technology, improves the comprcssive strength of upper well body.
Preferably, described upper well body, diameter variable well body, inspection chamber and mud sinking chamber adopt glass-reinforced plastic material to make, and improve the corrosion resistance of this inspection shaft, increase the service life and be greatly improved its intensity.
The utility model has the advantages that:
(1) this utility model adopts separable assembled structure, can realize Fast Installation, short construction period, instant effect, can realize all-weather construction;
(2) mud room is carried out aeration by aerator and aeration pipe network by this utility model, the mud particles of compacting is diminished, become dirty solution blended with sewage, uses and takes out slag car extraction, convenient and swift, greatly reduces the construction intensity of workman, improves overhaul efficiency;
(3) mud room is carried out aeration by aerator and aeration pipe network by this utility model, and under the drive of air-flow, the flammable or toxic gas within inspection chamber is discharged from upper well body, releases the potential safety hazard of workman;
(4) this utility model can arrange connecting hole according to practical situation at the diverse location of inspection chamber sidewall, and the position of connecting hole, shape and size can realize manual adjustment, it is ensured that general.
Accompanying drawing explanation
Fig. 1 is sectional view of the present utility model;
Fig. 2 is the structural representation of aeration pipe network of the present utility model.
Symbol description in figure: 1, upper well body;11, well lid;12, pressure-bearing packing ring;13, filler;14, cat ladder;2, diameter variable well body;3, inspection chamber;31, connecting hole;4, mud room;41, aeration pipe network;411, venthole;42, aerator;43, air inlet pipe;44, sludge bucket.
Detailed description of the invention
Below in conjunction with accompanying drawing, this utility model is further described:
Embodiment 1:
A kind of fiber glass reinforced plastics inspection well, including upper well body 1, the supporting well lid 11 that is provided with in upper well body 1 upper end, upper well body 1 upper end is provided around pressure-bearing packing ring 12;Upper well body 1 bottom compact siro spinning technology diameter variable well body 2, diameter variable well body 2 bottom compact siro spinning technology inspection chamber 3, inspection chamber 3 bottom compact siro spinning technology mud sinking chamber 4;Inspection chamber 3 sidewall is provided with connecting hole 31;Mud sinking chamber 4 both sides are set to sludge bucket 44, and mud sinking chamber 4 is internally installed aeration pipe network 41, is provided with aerator 42 bottom mud sinking chamber 4;Described aeration pipe network 41 is formed by connecting by many pipelines, and pipeline is provided with multiple venthole 411;Aeration pipe network 41 and aerator 42 connect air inlet pipe 43 by pipeline, and air inlet pipe 43 extends to well lid 11 bottom.
Embodiment 2:
On the basis of embodiment 1, this utility model carries out checking work to facilitate workman to enter inspection chamber 3, preferred embodiment also has: being provided with cat ladder 14 on described upper well body 1 borehole wall, cat ladder 14 extends to inspection chamber 3 bottom, and other parts are identical with embodiment 1.
Embodiment 3:
On the basis of embodiment 2, this utility model is in order to further by pressure-bearing packing ring 12 and upper well body 1 compact siro spinning technology, improve the comprcssive strength of upper well body 1, it is advantageous to embodiment also have: the gap of described pressure-bearing packing ring 12 and upper well body 1 fills up filler 13, and other parts are identical with embodiment 1.
Embodiment 4:
On the basis of embodiment 3, this utility model is in order to improve the corrosion resistance of this inspection shaft, increase the service life and improve its intensity, it is advantageous to embodiment also have: described upper well body 1, diameter variable well body 2, inspection chamber 3 and mud sinking chamber 4 adopt glass-reinforced plastic material to make.
Last it is noted that obvious, above-described embodiment is only for clearly demonstrating this utility model example, and is not the restriction to embodiment.For those of ordinary skill in the field, can also make other changes in different forms on the basis of the above description.Here without also cannot all of embodiment be given exhaustive.And the apparent change thus amplified out or variation are still among protection domain of the present utility model.

Claims (4)

1. a fiber glass reinforced plastics inspection well, including upper well body, the supporting well lid that is provided with in upper well body upper end, upper well body upper end is provided around pressure-bearing packing ring;It is characterized in that, upper well body bottom compact siro spinning technology diameter variable well body, diameter variable well body bottom compact siro spinning technology inspection chamber, inspection chamber bottom compact siro spinning technology mud sinking chamber;Inspection chamber sidewall is provided with connecting hole;Mud sinking chamber both sides are set to sludge bucket, and mud sinking chamber is internally installed aeration pipe network, is provided with aerator bottom mud sinking chamber;Described aeration pipe network is formed by connecting by many pipelines, and pipeline is provided with multiple venthole;Aeration pipe network and aerator connect air inlet pipe by pipeline, and air inlet pipe extends to well lid bottom.
2. a kind of fiber glass reinforced plastics inspection well as claimed in claim 1, it is characterised in that being provided with cat ladder on the described upper well body borehole wall, cat ladder extends to inspection chamber bottom.
3. a kind of fiber glass reinforced plastics inspection well as claimed in claim 2, it is characterised in that the gap of described pressure-bearing packing ring and upper well body fills up filler.
4. fiber glass reinforced plastics inspection well as claimed in claim 3 a kind of, it is characterised in that described upper well body, diameter variable well body, inspection chamber and mud sinking chamber all adopt glass-reinforced plastic material to make.
CN201620200660.9U 2016-03-16 2016-03-16 Glass fiber reinforced plastic inspection well Active CN205382551U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620200660.9U CN205382551U (en) 2016-03-16 2016-03-16 Glass fiber reinforced plastic inspection well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620200660.9U CN205382551U (en) 2016-03-16 2016-03-16 Glass fiber reinforced plastic inspection well

Publications (1)

Publication Number Publication Date
CN205382551U true CN205382551U (en) 2016-07-13

Family

ID=56352071

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620200660.9U Active CN205382551U (en) 2016-03-16 2016-03-16 Glass fiber reinforced plastic inspection well

Country Status (1)

Country Link
CN (1) CN205382551U (en)

Similar Documents

Publication Publication Date Title
CN111335344A (en) Super pressure suction combined well point dewatering construction method for subway deep foundation pit
CN103374965B (en) Venturi self-circulation negative-pressure drainage system of refuse landfill
CN105625445A (en) Foundation pit dewatering method in coastal sandy soil region
JP3213600U (en) Washed vent siphon structure of sewer installation pipe
CN212104426U (en) Miniature piping lane drainage system
CN206438526U (en) Deep basal pit tube well dewatering equipment
CN209443555U (en) A kind of Leachate site winding shaft applied to refuse landfill
CN205382551U (en) Glass fiber reinforced plastic inspection well
CN205035816U (en) Simple and easy heterogeneous extraction device based on light well point precipitation technology
CN202122876U (en) Rainwater recycling system
CN210066996U (en) Underground pipe network water jet dredging construction device
CN201762716U (en) Novel light densely-distributed well point rainfall system
CN206956917U (en) A kind of automatically cleaning pumping plant base for collecting sludge certainly
CN208152233U (en) A kind of horizontal underground sewage disposal system Boosting pumping station
CN205663006U (en) Sewage sewage pipes is used in municipal administration
CN202509613U (en) Launder
CN205556273U (en) Special liquid solid separation ware of oil field liquid water disposal
CN205296343U (en) Be applied to waste fitting discharging in workshop
CN104963383B (en) A kind of pressure conduit inverted siphon hydraulic automatism erosion and deposition device
CN207295964U (en) A kind of horizontal prefabricated pumping plant of integration
CN201158823Y (en) Recoverable impact drill steel pipe downcast well
CN202148537U (en) Fire-fighting integral valve shaft
CN208395840U (en) Basement sump pit preventive drainage device
CN204543668U (en) One under water gas rushes soil discharging facility
CN205935150U (en) Rain water pipe assembly

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant