CN210066996U - Underground pipe network water jet dredging construction device - Google Patents
Underground pipe network water jet dredging construction device Download PDFInfo
- Publication number
- CN210066996U CN210066996U CN201920104287.0U CN201920104287U CN210066996U CN 210066996 U CN210066996 U CN 210066996U CN 201920104287 U CN201920104287 U CN 201920104287U CN 210066996 U CN210066996 U CN 210066996U
- Authority
- CN
- China
- Prior art keywords
- pipeline
- plugging portion
- cleaning
- bricking
- air bag
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Sewage (AREA)
Abstract
The utility model relates to a desilting field of water environment underground pipe network, concretely relates to underground pipe network water jet desilting construction equipment, first inspection shaft and upper portion of upper reaches pipeline are linked together, second junction well and the upper portion of one side end of clearance pipeline are linked together, third junction well and the upper portion of the other side end of clearance pipeline are linked together, fourth inspection shaft and lower reaches pipeline upper portion are linked together, be provided with first pipeline isolation plug between upper reaches pipeline and clearance pipeline one end, be provided with second pipeline isolation plug between lower reaches pipeline and the clearance pipeline other end; the utility model discloses penetrate water desilting and can make pipeline blockage along with the rivers, pollution-free basically, be applicable to the pipeline of different pipe diameters (35-3000 mm), traffic is dredged pressure little, and the time limit for a project is short, effective reduce cost.
Description
Technical Field
The utility model relates to a desilting field of water environment underground pipe network, concretely relates to underground pipe network water jet desilting construction equipment.
Background
The traditional manual dredging process flow comprises the following steps: on-site drainage → temporary road construction → sludge removal → earthwork transportation → sludge drying (earthwork cofferdam) → earthwork transportation outside.
The defects of traditional manual dredging are as follows: the agricultural workers are mostly used, the safety measures of the agricultural workers on the underground limited space operation are nearly unknown, toxic casualty accidents often occur, and great loss is caused to the lives and properties of people; in the manual dredging operation process, the physical strength is heavy, and the efficiency is low; the operation environment of underground rain and sewage pipelines is severe, and part of the underground rain and sewage pipelines are seriously silted and damaged; the manual dredging is basically applied without time to the small-caliber pipeline, the application range is small, the workload is large, the construction period is long, the cost is high, the traffic occupied area is large, coordination is not facilitated, the traffic pressure is relieved, secondary pollution is easy to generate in the construction process, the construction applicable pipe diameter is more than 800mm, the construction progress is slow, and the cost is high.
Based on the above prior art, the applicant has made a long-lasting and useful search and trial and error, and has conducted a non-limited number of experiments, and finally found a solution to the above technical problem and formed a solution as will be described below.
Disclosure of Invention
For solving the problems of the prior art, the utility model provides a.
In order to achieve the above purpose, the utility model adopts the following technical scheme: a water jetting and dredging construction device for an underground pipe network comprises a cleaning vehicle, a high-pressure pipeline, a high-pressure spray head, a first inspection well, a second connection well, a third connection well, a fourth inspection well, an upstream pipeline, a cleaning pipeline, a downstream pipeline, a sewage discharge pump and a sewage discharge pipe;
the first inspection well is communicated with the upper part of an upstream pipeline, the second connecting well is communicated with the upper part of one side end of the cleaning pipeline, the third connecting well is communicated with the upper part of the other side end of the cleaning pipeline, the fourth inspection well is communicated with the upper part of a downstream pipeline, a first pipeline isolating plug is arranged between the upstream pipeline and one end of the cleaning pipeline, and a second pipeline isolating plug is arranged between the downstream pipeline and the other end of the cleaning pipeline;
and a sewage pump is arranged on the upstream pipeline at the lower part corresponding to the first inspection well, the sewage pump is connected with a sewage discharge pipe, and the sewage discharge pipe protrudes out of the first inspection well and extends upwards.
The first pipeline isolation plug comprises a first bricking plugging portion and a first air bag plugging portion, the first bricking plugging portion and the first air bag plugging portion are arranged in an upstream pipeline, the first bricking plugging portion is arranged on one side of the first air bag plugging portion, the first bricking plugging portion is close to one end of a cleaning pipeline and is arranged in a downstream pipeline, the first bricking plugging portion is of a bricking structure, the first air bag plugging portion is of an air bag structure, the first pipeline isolation plug comprises a second bricking plugging portion and a second air bag plugging portion, the second bricking plugging portion and the second air bag plugging portion are fixedly arranged in the downstream pipeline, the second bricking plugging portion is arranged on one side of the second air bag plugging portion, the second bricking plugging portion is close to the other end of the cleaning pipeline and is arranged in a bricking structure, and the second air bag plugging portion is of an air bag structure.
The cleaning vehicle is arranged on one side of the second connecting well, the cleaning vehicle is connected with a high-pressure pipeline, one end of the high-pressure pipeline is connected with a high-pressure nozzle, the high-pressure pipeline penetrates through the second connecting well and extends into the cleaning pipeline, dirt portions to be cleaned are arranged in the cleaning pipeline, and the end portion of the high-pressure nozzle is arranged at one end of each dirt portion to be cleaned.
The sewage collecting pit is arranged at the end part of the cleaning pipeline and correspondingly arranged at the lower part of the third junction well, the upper end face of the sewage collecting pit is flush with the lower end face of the cleaning pipeline, a sewage discharging pump is arranged in the sewage collecting pit and connected with a sewage discharging pipe, and the sewage discharging pipe protrudes out of the upper end face of the third junction well.
Compared with the prior art, the invention has the beneficial effects that: the utility model discloses penetrate water desilting can make pipeline plug along with water free flow, and is pollution-free basically, is applicable to the pipeline of different pipe diameters (35-3000 mm), and the traffic is dredged pressure and is little, the time limit for a project short, effective reduce cost.
Drawings
Other features, objects and advantages of the invention will become more apparent from a reading of the following detailed description of non-limiting embodiments thereof, with reference to the accompanying drawings.
Fig. 1 is a schematic structural diagram of the present invention.
In the figures, the names corresponding to the reference numerals are a cleaning vehicle 1, a high-pressure pipeline 11, a high-pressure spray head 12, a first inspection well 21, a second connection well 22, a third connection well 23, a fourth inspection well 24, an upstream pipeline 31, a cleaning pipeline 32, a downstream pipeline 33, a first pipeline isolation plug 41, a first bricklaying plugging part 411, a first air bag plugging part 412, a second pipeline isolation plug 42, a second bricklaying plugging part 421, a second air bag plugging part 422, a sewage collection pit 5, a sewage discharge pump 6 and a sewage discharge pipe 61.
Detailed Description
The present invention will be described in further detail with reference to the following examples, which are provided only for illustrating the present invention and do not limit the scope of the present invention.
Referring to fig. 1, a water jet dredging device for underground pipe network, comprising a cleaning vehicle 1, a high-pressure pipeline 11, a high-pressure spray head 12, a first inspection well 21, a second connection well 22, a third connection well 23, a fourth inspection well 24, an upstream pipeline 31, a cleaning pipeline 32, a downstream pipeline 33, a first pipeline isolation plug 41, a second pipeline isolation plug 42, a dirt collecting pit 5, a sewage discharge pump 6 and a sewage discharge pipe 61, wherein the first inspection well 21 is communicated with the upper part of the upstream pipeline 31, the second connection well 22 is communicated with the upper part of one side end of the cleaning pipeline 32, the third connection well 23 is communicated with the upper part of the other side end of the cleaning pipeline 32, the fourth inspection well 24 is communicated with the upper part of the downstream pipeline 33, the first pipeline isolation plug 41 is arranged between the upstream pipeline 31 and one end of the cleaning pipeline 32, the second pipeline isolation plug 42 is arranged between the downstream pipeline 33 and the other end of the cleaning pipeline 32, the first inspection well 21 is provided with a sewage pump 211 corresponding to the lower part of the upstream pipeline 31, the sewage pump 211 is connected with the sewage discharge pipe 212, the sewage discharge pipe 212 protrudes from the first inspection well 21 and extends upwards, and particularly, the upper portion of the sewage discharge pipe can extend directly to the inlet of the fourth inspection well 24, so as to discharge the upstream sewage into the downstream pipeline 33, the first pipeline isolation plug 41 comprises a first bricklaying plug portion 411 and a first air bag plug portion 412, the first bricklaying plug portion 411 and the first air bag plug portion 412 are both arranged in the upstream pipeline 31, the first bricklaying plug portion 411 is arranged at one side of the first air bag plug portion 412, the first bricklaying plug portion 411 is arranged near one end of the cleaning pipeline 32, the first bricklaying plug portion 411 is of bricklaying structure, the first air bag plug portion 412 is of air bag structure, the first pipeline isolation plug 42 comprises a second bricklaying plug portion 421 and a second air bag plug portion 422, both the second bricklaying plug portion 421 and the second air bag plug portion 422 are fixedly arranged in the downstream pipeline 33, the second bricklaying plugging portion 421 is arranged on one side of the second air bag plugging portion 422, the second bricklaying plugging portion 421 is arranged close to the other end of the cleaning pipeline 32, the second bricklaying plugging portion 421 is of a bricklaying structure, the second air bag plugging portion 422 is of an air bag structure, the cleaning vehicle 1 is arranged on one side of the second connecting well 22, the cleaning vehicle 1 adopts a high-pressure waterwheel, the cleaning vehicle 1 is connected with the high-pressure pipeline 11, one end of the high-pressure pipeline 11 is connected with the high-pressure nozzle 12, the high-pressure pipeline 11 penetrates through the second connecting well 22 and extends into the cleaning pipeline 32, a dirt portion 321 to be cleaned in the cleaning pipeline 32 is arranged at one end of the dirt portion 321 to be cleaned, the end of the high-pressure nozzle 12 is arranged at one end of the dirt portion 321 to be cleaned, a dirt collecting pit 5 is arranged at the end of the cleaning pipeline 32, the dirt collecting pit 5 is correspondingly arranged at the lower portion of the third connecting well 23, the dirt collecting pit 5 is circular and, a sewage discharge pump 6 is arranged in the sewage collection pit 5, the sewage discharge pump 6 is connected with a sewage discharge pipe 61, and the sewage discharge pipe 61 protrudes out of the upper end face of the third junction well 23. The specific sewage discharge pipe 61 is connected with a sewage suction truck, and the sewage suction truck adopts Dongfeng 145 (10 square).
(1) Process flow
The method comprises the following steps of early investigation → traffic relief → operation in limited space for crossing the bottom → forced ventilation → gas detection → examination and approval of well descending operation → pipeline plugging → closure and drainage guide → pipeline dredging → acceptance and transfer.
Early-stage investigation: the method mainly aims to determine the pipeline dredging range, judge the pipeline clogging condition and determine the technical scheme.
Traffic fluffing: mainly aims at ensuring the safety of normal dredging construction and traffic operation.
Forced ventilation: the natural ventilation is kept, and the harm of toxic gas to operators is reduced.
And (4) gas detection, namely monitoring the content of toxic gas in the underground pipeline at regular time and ensuring construction in safety.
And (3) examining and approving the well descending operation: the strict approval system of the downhole operation is the premise of ensuring the smooth operation of the project.
Pipeline plugging: when the upstream water flow is large, brick laying and air bag double-layer plugging are needed, and the upstream and downstream of the pipe section needing dredging are plugged so as to facilitate detection.
Temporary guide and drainage: and pumping the sewage at the upstream of the construction section out of the inspection well by using a sewage pump, and discharging the sewage into a downstream pipe to ensure that the pipeline normally completes dredging.
Dredging a pipeline: the high-pressure pump that utilizes washing car 1 beats out the water under high pressure, through high-pressure hose, utilizes the nozzle to spout high-pressure water flow, and foraminiferous and can shoot a aperture that is greater than the shower nozzle diameter forward directly in this nozzle front, then utilize the water impact to impel the principle and go forward, lean on simultaneously to enlarge the drilling to the efflux of spouting to one side, the shower nozzle impels forward, silt flows out to the contact well backward with the inclined hole rivers, and the soil pick-up car carries out the soil pick-up operation simultaneously. When solid blockage exists in the pipe, the pressure of the jet flow vehicle needs to be adjusted, when continuous water jet flow continuously impacts the blockage, stable impact force is formed, and the water jet pressure for cleaning the impurities in the common pipeline is shown as the following table I (pressure for cleaning the impurities in the common pipeline).
Acceptance and transfer: and (3) adopting a CCTV (closed-circuit television) endoscopic system for detecting the interior of the pipeline without structural defects, and shooting image data of the inner wall of the lining pipe to form a report. The pipe wall should not have the functional defects of tree roots, dam roots, residual walls and the like.
Watch 1
(2) Effects of the implementation
The construction method is applied to the engineering construction for the third standard-section sand well street sewage pipe network connection perfection of the comprehensive water environment improvement project in the maozhou river basin (Baoan district), the pipeline dredging progress is effectively improved, better quality and economic benefits are obtained, meanwhile, the high-pressure jet flow vehicle of the sewage circulating device is selected, the sewage can be recycled, the sewage in the pipeline is used as jet flow, the cost is effectively reduced, and the method is environment-friendly and pollution-free. The main advantages compared with the traditional manual dredging are as follows:
(1) no pollution: the cleaning agent is washed and cleaned by common tap water or rain water at high speed, does not pollute the environment, and can also remove special dirt which is difficult to dissolve or not difficult to dissolve in chemical cleaning.
(2) The power is high: the cleaning quality is good. The pipe network water jetting dredging belongs to physical cleaning, no chemical reaction exists in the cleaning process, the water jet pressure can be adjusted, and the original pipeline is not corroded or damaged.
(3) The cost is low: the resources are rich. The jet flow dredging uses water as a resource, simultaneously, the water consumption is less, the water consumption is low and the power is low under the continuous condition, and the water resource can be recycled, thereby belonging to the energy-saving and environment-friendly technology.
While the invention has been described with reference to a preferred embodiment, it will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention. However, any simple modification, equivalent change and modification made to the above embodiments according to the technical substance of the present invention still belong to the protection scope of the technical solution of the present invention.
Claims (4)
1. The utility model provides an underground pipe network jetting desilting construction equipment which characterized in that: the device comprises a cleaning vehicle, a high-pressure pipeline, a high-pressure spray head, a first inspection well, a second connection well, a third connection well, a fourth inspection well, an upstream pipeline, a cleaning pipeline, a downstream pipeline, a sewage discharge pump and a sewage discharge pipe;
the first inspection well is communicated with the upper part of an upstream pipeline, the second connecting well is communicated with the upper part of one side end of the cleaning pipeline, the third connecting well is communicated with the upper part of the other side end of the cleaning pipeline, the fourth inspection well is communicated with the upper part of a downstream pipeline, a first pipeline isolating plug is arranged between the upstream pipeline and one end of the cleaning pipeline, and a second pipeline isolating plug is arranged between the downstream pipeline and the other end of the cleaning pipeline;
and a sewage pump is arranged on the upstream pipeline at the lower part corresponding to the first inspection well, the sewage pump is connected with a sewage discharge pipe, and the sewage discharge pipe protrudes out of the first inspection well and extends upwards.
2. The underground pipe network water jet dredging construction device according to claim 1, characterized in that: the first pipeline isolation plug comprises a first bricking plugging portion and a first air bag plugging portion, the first bricking plugging portion and the first air bag plugging portion are arranged in an upstream pipeline, the first bricking plugging portion is arranged on one side of the first air bag plugging portion, the first bricking plugging portion is close to one end of a cleaning pipeline and is arranged in a downstream pipeline, the first bricking plugging portion is of a bricking structure, the first air bag plugging portion is of an air bag structure, the first pipeline isolation plug comprises a second bricking plugging portion and a second air bag plugging portion, the second bricking plugging portion and the second air bag plugging portion are fixedly arranged in the downstream pipeline, the second bricking plugging portion is arranged on one side of the second air bag plugging portion, the second bricking plugging portion is close to the other end of the cleaning pipeline and is arranged in a bricking structure, and the second air bag plugging portion is of an air bag structure.
3. The underground pipe network water jet dredging construction device according to claim 1 or 2, characterized in that: the cleaning vehicle is arranged on one side of the second connecting well, the cleaning vehicle is connected with a high-pressure pipeline, one end of the high-pressure pipeline is connected with a high-pressure nozzle, the high-pressure pipeline penetrates through the second connecting well and extends into the cleaning pipeline, dirt portions to be cleaned are arranged in the cleaning pipeline, and the end portion of the high-pressure nozzle is arranged at one end of each dirt portion to be cleaned.
4. The underground pipe network water jet dredging construction device according to claim 3, characterized in that: the sewage collecting pit is arranged at the end part of the cleaning pipeline and correspondingly arranged at the lower part of the third junction well, the upper end face of the sewage collecting pit is flush with the lower end face of the cleaning pipeline, a sewage discharging pump is arranged in the sewage collecting pit and connected with a sewage discharging pipe, and the sewage discharging pipe protrudes out of the upper end face of the third junction well.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920104287.0U CN210066996U (en) | 2019-01-22 | 2019-01-22 | Underground pipe network water jet dredging construction device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920104287.0U CN210066996U (en) | 2019-01-22 | 2019-01-22 | Underground pipe network water jet dredging construction device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210066996U true CN210066996U (en) | 2020-02-14 |
Family
ID=69426708
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920104287.0U Active CN210066996U (en) | 2019-01-22 | 2019-01-22 | Underground pipe network water jet dredging construction device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210066996U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113062235A (en) * | 2021-03-23 | 2021-07-02 | 中冶南方城市建设工程技术有限公司 | Flushing device for drainage box culvert |
CN117569440A (en) * | 2024-01-02 | 2024-02-20 | 北京住总集团有限责任公司 | Drainage pipeline cleaning device and cleaning method thereof |
-
2019
- 2019-01-22 CN CN201920104287.0U patent/CN210066996U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113062235A (en) * | 2021-03-23 | 2021-07-02 | 中冶南方城市建设工程技术有限公司 | Flushing device for drainage box culvert |
CN117569440A (en) * | 2024-01-02 | 2024-02-20 | 北京住总集团有限责任公司 | Drainage pipeline cleaning device and cleaning method thereof |
CN117569440B (en) * | 2024-01-02 | 2024-06-07 | 北京住总集团有限责任公司 | Drainage pipeline cleaning device and cleaning method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101736804B (en) | Refuse landfill percolate pump drainage minor-caliber shaft structure and silt prevention method | |
CN103669557B (en) | Underground conduit dredging engineering method | |
CN109707444B (en) | Automatic start-up formula tunnel drainage system | |
CN210066996U (en) | Underground pipe network water jet dredging construction device | |
CN214034031U (en) | Municipal administration pipeline mediation structure | |
CN109826163A (en) | A kind of device and its silt-proof method that the underwater sand surfing of gate is anti-silting | |
CN103374965A (en) | Venturi self-circulation negative-pressure drainage system of refuse landfill | |
CN201137152Y (en) | Sealed multi-tube strata precipitation device | |
CN201850643U (en) | Closure deep well self-siphon hydraulic dredging device | |
CN205935164U (en) | A hydrocone type drainage filter equipment for urban road | |
CN215630060U (en) | Reusable precipitation well casing | |
CN212452854U (en) | Underwater dredging system for hydropower station tail canal | |
CN108583530A (en) | Utilize the vehicle washing system of base pit dewatering well cycling use of water | |
CN211057991U (en) | Prefabricated pump station with self-cleaning function | |
CN211646321U (en) | Self-elevating platform pile-punching monitoring device | |
CN204543668U (en) | One under water gas rushes soil discharging facility | |
CN206512818U (en) | A kind of plastic stone rockery construction waste water drainage system device | |
CN210013303U (en) | Connecting structure for new and old sewage pipelines | |
CN209451626U (en) | Refuse landfill gas barrier arragement construction | |
CN101892705B (en) | Intercepting deep well self-siphoning hydraulic desilting device | |
CN202913497U (en) | Planomural winding pipeline plate-strip used for repairing rainy sewer pipeline | |
CN203487619U (en) | Water resource recycling system for city underground engineering construction | |
CN209179133U (en) | A kind of municipal underground blowdown pipelines of silting blocking | |
CN209741881U (en) | Pneumatic precipitation device | |
CN111809677A (en) | Underwater dredging system and method for hydropower station tail canal |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |