CN205314552U - External corner for mould is found to building - Google Patents

External corner for mould is found to building Download PDF

Info

Publication number
CN205314552U
CN205314552U CN201620000710.9U CN201620000710U CN205314552U CN 205314552 U CN205314552 U CN 205314552U CN 201620000710 U CN201620000710 U CN 201620000710U CN 205314552 U CN205314552 U CN 205314552U
Authority
CN
China
Prior art keywords
external corner
building
concrete column
model
formwork erection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620000710.9U
Other languages
Chinese (zh)
Inventor
李东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yancheng Xindongfang Plastic Building Template Co Ltd
Original Assignee
Yancheng Xindongfang Plastic Building Template Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yancheng Xindongfang Plastic Building Template Co Ltd filed Critical Yancheng Xindongfang Plastic Building Template Co Ltd
Priority to CN201620000710.9U priority Critical patent/CN205314552U/en
Application granted granted Critical
Publication of CN205314552U publication Critical patent/CN205314552U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model provides an external corner for mould is found to building, external corner for mould is found to building wherein connects through three " L " shape step between two adjacent faces in order, " the L " of both sides shape step respectively with the edges and corners phase coupling of two piece adjacent plank sheathings, the edges and corners phase coupling of the concrete column that middle " L " shape step and watering take shape. When buildding concrete column watering model, set up an external corner for mould is found to building on four edges and corners of concrete column watering model respectively, " L " shape step of external corner for mould is found to building's both sides respectively with the edges and corners phase coupling of two piece adjacent plank sheathings, the edges and corners phase coupling of the concrete column that middle " L " shape step and watering take shape, therefore use the utility model discloses a when external corner for mould is found to building builds concrete column watering model, can lack than traditional concrete column watering model and use 4 external corner for mould is found to building to reduce external corner for mould is found to building's use amount, reduce the consumptive material, and because the external corner for mould is found to building quantity of using reduction, thereby reduce the work load of buildding concrete column watering model, improve work efficiency.

Description

Building formwork erection external corner
Technical field
This utility model relates to building implement technical field, in particular to a kind of external corner building formwork erection external corner.
Background technology
Major part building in life is all xoncrete structure now, first will carry out the formwork erection work of concrete column when carrying out construction, namely builds concrete column pouring model by plank sheathing 10 ' and building formwork erection external corner.
Traditional concrete column pouring model is as shown in Figure 1, the profile of concrete column 20 ' is built by plank sheathing 10 ', then (Fig. 1 show the both sides of each plank sheathing 10 ' and is respectively arranged with building formwork erection external corner to add at least two building formwork erection external corner on every block of plank sheathing 10 ', when concrete column 20 ' is bigger, also need to arrange many building formwork erection external corners in each plank sheathing 10 ' Intermediate View situation) strengthen the intensity of plank sheathing 10 ', after putting up concrete column pouring model, placing concrete is starched inward again, concrete column 20 ' is formed after concrete grout solidifies, last concrete column pouring model of dismantling again.
Traditional concrete column pouring model there is problems in that
(1) each concrete column pouring model at least needs to arrange 8 building formwork erection external corners, and consumptive material is big, and arranges the length consuming time of 8 building formwork erection external corners, affects formwork erection efficiency;
(2) the easy percolating water mud in junction of adjacent two plank sheathings 10 ' of concrete column pouring model, causes cement mortar to waste, and after form removal, it is exposed that four corner angle of concrete column 20 ' have stone, affects the quality of concrete column and attractive in appearance.
Summary of the invention
Main purpose of the present utility model is in that to provide a kind of building formwork erection external corner, the problem big to solve concrete column of the prior art pouring model consumptive material.
To achieve these goals, this utility model provides a kind of building formwork erection external corner, it is sequentially connected with by three " L " shape steps between wherein adjacent two faces of building formwork erection external corner, " L " shape step of both sides is coupled with the corner angle of adjacent two blocks of plank sheathings respectively, and middle " L " shape step and the corner angle watering the concrete column shaped are coupled.
Further, the centre building formwork erection external corner is provided through the elongated hole of building formwork erection external corner.
Further, elongated hole is spaced multiple.
Further, the material building formwork erection external corner is plastics.
Application the technical solution of the utility model, it is sequentially connected with by three " L " shape steps between wherein adjacent two faces of building formwork erection external corner, when building concrete column pouring model, four corner angle of concrete column pouring model are respectively provided with a building formwork erection external corner, " L " shape step of the both sides of building formwork erection external corner is coupled with the corner angle of adjacent two blocks of plank sheathings respectively, middle " L " shape step and the corner angle watering the concrete column shaped are coupled, thus apply building formwork erection external corner of the present utility model build concrete column pouring model time, can be fewer with 4 building formwork erection external corners than traditional concrete column pouring model, thus reduce building formwork erection external corner make consumption, reduce consumptive material, and the building formwork erection external corner quantity owing to using reduces, thus reducing the workload building concrete column pouring model, improve work efficiency. simultaneously, " L " shape step owing to building the both sides of formwork erection external corner is coupled with the corner angle of adjacent two blocks of plank sheathings respectively, namely it is coupled between two faces that two faces of " L " shape step are corresponding with the corner angle of plank sheathing respectively, thus improving the sealing of building formwork erection external corner and plank sheathing, prevent the seepage of cement mortar, reduce waste, and the stone that can be prevented effectively from four corner angle of concrete column is exposed, be conducive to the forming quality of four corner angle of solidifying earth pillar and attractive in appearance.
Accompanying drawing explanation
The Figure of description constituting the part of the application is used for providing being further appreciated by of the present utility model, and schematic description and description of the present utility model is used for explaining this utility model, is not intended that improper restriction of the present utility model. In the accompanying drawings:
Fig. 1 illustrates the structural representation of traditional concrete column pouring model;
Fig. 2 illustrates the structural representation of the building formwork erection external corner of the first embodiment of the present utility model;
Fig. 3 illustrates that the building formwork erection external corner of the first embodiment of the present utility model is for building structural representation during concrete column pouring model;
Fig. 4 illustrates the structural representation of the second embodiment of building formwork erection external corner of the present utility model.
Wherein, above-mentioned accompanying drawing includes the following drawings labelling:
10 ', plank sheathing; 20 ', concrete column; 10, plank sheathing; 20, concrete column; 30, " L " shape step; 40, elongated hole.
Detailed description of the invention
It should be noted that when not conflicting, the embodiment in the application and the feature in embodiment can be mutually combined. Describe this utility model below with reference to the accompanying drawings and in conjunction with the embodiments in detail.
It it is noted that described further below is all exemplary, it is intended to provide further instruction to the application. Unless otherwise, all technology used herein and scientific terminology have the identical meanings being generally understood that with the application person of an ordinary skill in the technical field.
The problem big for solving concrete column of the prior art pouring model consumptive material, this utility model provides a kind of building formwork erection external corner.
As shown in Figures 2 to 4, it is sequentially connected with by three " L " shape steps 30 between wherein adjacent two faces of building formwork erection external corner, " L " shape step 30 of both sides is coupled with the corner angle of adjacent two blocks of plank sheathings 10 respectively, and the corner angle of the concrete column 20 that middle " L " shape step 30 shapes with pouring are coupled.
As shown in Figure 2, when building concrete column pouring model, four corner angle of concrete column pouring model are respectively provided with a building formwork erection external corner, " L " shape step 30 of the both sides of building formwork erection external corner is coupled with the corner angle of adjacent two blocks of plank sheathings 10 respectively, the corner angle of the concrete column 20 that middle " L " shape step 30 shapes with pouring are coupled, thus apply building formwork erection external corner of the present utility model build concrete column pouring model time, can be fewer with 4 building formwork erection external corners than traditional concrete column pouring model, thus reduce building formwork erection external corner make consumption, reduce consumptive material, and the building formwork erection external corner quantity owing to using reduces, thus reducing the workload building concrete column pouring model, improve work efficiency. simultaneously, " L " shape step owing to building the both sides of formwork erection external corner is coupled with the corner angle of adjacent two blocks of plank sheathings 10 respectively, namely it is coupled between two faces that two faces of " L " shape step 30 are corresponding with the corner angle of plank sheathing 10 respectively, thus improving the sealing of building formwork erection external corner of the present utility model and plank sheathing 10, prevent the seepage of cement mortar, reduce waste, and the stone that can be prevented effectively from four corner angle of concrete column 20 is exposed, be conducive to the forming quality of four corner angle of concrete column 20 and attractive in appearance.
As shown in Figure 3, when concrete column 20 is square, apply building formwork erection external corner of the present utility model build concrete column pouring model time, four blocks of plank sheathings 10 are of a size of unanimously, thus be easy to get the raw materials ready, and the mutual replaceability between plank sheathing can be increased, also be able to reduce the size of plank sheathing 10 simultaneously, reduce consumptive material.
Embodiment as shown in Figure 4, the centre of building formwork erection external corner is provided through the elongated hole 40 of building formwork erection external corner. Centre owing to building formwork erection external corner is provided through the elongated hole 40 of building formwork erection external corner, it is thus able to effectively reduce the materials'use amount of building formwork erection external corner, save the cost making building formwork erection external corner, and effectively alleviate the weight of building formwork erection external corner.
Preferably, elongated hole 40 is spaced multiple, and the elongated hole 40 of the building formwork erection external corner shown in Fig. 4 is spaced two. Owing to elongated hole 40 is spaced multiple, it is thus possible to while reducing the materials'use amount of building formwork erection external corner, it is effectively ensured the structural strength of this utility model building formwork erection external corner.
Preferably, the material building formwork erection external corner is plastics. Owing to plastics have lightweight and easily shape, thus it is easy to make building formwork erection external corner of the present utility model.
Preferably, the material building formwork erection external corner can also be metal, timber etc.
As can be seen from the above description, this utility model the above embodiments achieve following technique effect;
1. reduce building formwork erection external corner and make consumption, save cost, improve efficiency of construction;
2. sealing is better, reduces the leakage of cement mortar, increases the shaping aesthetic property of concrete column 20;
3. the size of plank sheathing 10 is unified, it is simple to gets the raw materials ready and exchanges.
It should be noted that term used herein above merely to describe detailed description of the invention, and be not intended to the restricted root illustrative embodiments according to the application. As used herein, unless the context clearly indicates otherwise, otherwise singulative is also intended to include plural form, in addition, it is to be further understood that, when using term " comprising " and/or " including " in this manual, it indicates existing characteristics, step, work, device, assembly and/or their combination.
It should be noted that, term " including " in the description and claims of this application and above-mentioned accompanying drawing and " having " and their any deformation, it is intended to cover non-exclusive comprising, such as, contain series of steps or the process of unit, method, system, product or equipment be not necessarily limited to those steps or the unit clearly listed, but can include clearly not listing or for intrinsic other step of these processes, method, product or equipment or unit.
The foregoing is only preferred embodiment of the present utility model, be not limited to this utility model, for a person skilled in the art, this utility model can have various modifications and variations. All within spirit of the present utility model and principle, any amendment of making, equivalent replacement, improvement etc., should be included within protection domain of the present utility model.

Claims (4)

1. a building formwork erection external corner, it is characterized in that, it is sequentially connected with by three " L " shape steps (30) between wherein adjacent two faces of described building formwork erection external corner, described " L " shape step (30) of both sides are coupled with the corner angle of adjacent two pieces of plank sheathings (10) respectively, and middle described " L " shape step (30) and the corner angle watering the concrete column (20) shaped are coupled.
2. building formwork erection external corner according to claim 1, it is characterised in that the centre of described building formwork erection external corner is provided through the elongated hole (40) of described building formwork erection external corner.
3. building formwork erection external corner according to claim 2, it is characterised in that described elongated hole (40) is for spaced multiple.
4. building formwork erection external corner according to any one of claim 1 to 3, it is characterised in that the material of described building formwork erection external corner is plastics.
CN201620000710.9U 2016-01-05 2016-01-05 External corner for mould is found to building Expired - Fee Related CN205314552U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620000710.9U CN205314552U (en) 2016-01-05 2016-01-05 External corner for mould is found to building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620000710.9U CN205314552U (en) 2016-01-05 2016-01-05 External corner for mould is found to building

Publications (1)

Publication Number Publication Date
CN205314552U true CN205314552U (en) 2016-06-15

Family

ID=56200550

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620000710.9U Expired - Fee Related CN205314552U (en) 2016-01-05 2016-01-05 External corner for mould is found to building

Country Status (1)

Country Link
CN (1) CN205314552U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110388054A (en) * 2018-04-17 2019-10-29 江苏南通二建集团有限公司 One kind exempting from aperture building engineering structure template system and construction technology

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110388054A (en) * 2018-04-17 2019-10-29 江苏南通二建集团有限公司 One kind exempting from aperture building engineering structure template system and construction technology

Similar Documents

Publication Publication Date Title
CN107143034A (en) A kind of assembly concrete frame structure beam column rigid connection node
CN204435542U (en) Integration bean column node formwork structure
CN105971160A (en) Method for preventing 3D printing reinforced masonry shear wall being unshelled
CN204531382U (en) Umbrella shape space curved surface clear water concrete template structure
CN105908965A (en) Assembly type concrete wall board, assembly type building and assembly method
CN201730325U (en) Formwork for concrete column
CN203049846U (en) Permanent compound heat preservation external framework cast-in-situ lightweight concrete wall structure
CN104805960A (en) Mould-stripping-free concrete beam and construction method thereof
CN205314552U (en) External corner for mould is found to building
CN201250465Y (en) Prefabricated exterior wall panel
CN202658765U (en) Keel framework concrete anti-crack filling wall
CN206201157U (en) A kind of prefab-form
CN203808291U (en) Prefabricated lattice shear wallboard
CN206467828U (en) A kind of fabricated construction insulation and decoration integrated plate wall
CN210421512U (en) Positioning, mounting and connecting structure of PC prefabricated wall board
CN203129572U (en) Prefabricated concrete formwork and prefabricated building formed by same
CN106968366B (en) Construction method for pouring constructional column without dismantling formwork
CN206016002U (en) Assembly concrete beam
CN205012499U (en) Equipment antidetonation wall brick
CN206016048U (en) Assemble type concrete slab
CN205637305U (en) Building block material unit and butt -joint structural thereof
CN204781581U (en) Prefabricated wallboard of foam concrete is strengthened to fibre
CN210507501U (en) Novel finished product prefabricated brick fetal membrane assembly structure
CN203499246U (en) Tool type constructional column mould
CN207003720U (en) A kind of assembled integral concrete shear force wall attachment structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160615

Termination date: 20170105