CN205279540U - Construction ventilation of tunnel refrigerating system - Google Patents
Construction ventilation of tunnel refrigerating system Download PDFInfo
- Publication number
- CN205279540U CN205279540U CN201520940738.6U CN201520940738U CN205279540U CN 205279540 U CN205279540 U CN 205279540U CN 201520940738 U CN201520940738 U CN 201520940738U CN 205279540 U CN205279540 U CN 205279540U
- Authority
- CN
- China
- Prior art keywords
- water
- tunnel
- construction
- refrigeration
- vent line
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model relates to a construction system, in particular to construction ventilation of tunnel refrigerating system. To refrigeration among the present tunnel construction be increase many air -blower relays carry from the holes outside fresh air in order to mediate in the hole measure such as sultry air the inefficiency of bringing, problem with high costs, the utility model discloses a construction ventilation of tunnel refrigerating system, this refrigerating system set up in tunnel construction, its characterized in that, refrigerating system include condensing system and circulation system, condensing system still include the refrigerating plant of condenser, choke valve, evaporimeter and compressor unit one -tenth including the water cooler that is used for storage water, the water -cooled tube of being connected with the water cooler, the first water pump of setting on the water -cooled tube, this condensing system, this condensing system and circulation system are connected, circulation system include circulation pipeline, the air pipeline in be provided with this circulation pipeline. This refrigerating system sets up on the air pipeline, carry, convenient operation, simple structure.
Description
Technical field
The utility model relates to construction system, in particular to constructing tunnel ventilation refrigeration system.
Background technology
There are Climatic regionalization tunnel and low warm harmful tunnel two class in heat evil tunnel, Climatic regionalization tunnel is owing in construction, too high or that various thermal source discharges in the construction process heat of country rock temperature causes construction environment temperature too high, low warm harmful tunnel refers to that country rock original temperature is too low or too low in extremely frigid zones tunnel environment temperature, when inlet temperature is lower than 20 DEG C, it is necessary to carrying out preheating in hole. In these two kinds of tunnel environment situations so that difficulty of construction is bigger than normal, and security risk is big.
For Climatic regionalization tunnel, the method that present unit in charge of construction takes is freezing ice cube outside tunnel, the ice cube made is transported in tunnel, or increase multiple stage gas blower relay carries fresh air to mediate in hole the measures such as sultry air from hole, reach the object that cooling is ventilated, guarantee that the healthy of workmen and construction carry out smoothly with this. But such mode, inefficiency, brings inconvenience to construction side.
Practical novel content
For current above-mentioned technology Problems existing, the utility model provides simple, the easy to operate constructing tunnel ventilation refrigeration system of a kind of structure.
The technical solution adopted in the utility model is, constructing tunnel ventilation refrigeration system, this refrigeration system is arranged in construction tunnel, described refrigeration system comprises condenser system and the recycle system, described condenser system comprises the water cooler for storage of water, the water cooling tube being connected with water cooler, the first water pump being arranged on water cooling tube, this condenser system also comprises condenser, throttling valve, the refrigeration plant of vaporizer and compressor composition, this condenser system is connected with the recycle system, water in this refrigeration system flows to the recycle system through refrigeration plant, water refluxes into condenser system through the recycle system, the described recycle system comprises circulation line, this circulation line it is provided with in described vent line.
By arranging refrigeration system in vent line, vent line in construction tunnel is carried out refrigeration process, this refrigeration system is arranged on described vent line, carry, easy to operate, structure simple, carrying out smoothly of the healthy of workmen and construction can be guaranteed preferably.
Further, the described recycle system also comprises water tank and the 2nd water pump, and described water tank and the 2nd water pump are arranged on described circulation line.
Water tank is used for supplementing heat-eliminating medium-water, by the 2nd water pump, water is transported to condenser system.
Further, the described recycle system also comprises the 2nd water pump, and the 2nd water pump is connected by circulation line with river or reservoir.
When water source resources such as Pang You rivers, tunnel, just can utilize water source resource, it is necessary to time with supplementary heat-eliminating medium-water.
Further, the part that described circulation line is arranged in vent line be that spatial grid structure is distributed in vent line and prolongs vent line and extend layout.
After circulation line in vent line is set to spatial grid structure, forming refrigeration area in described vent line, this region is more long, and refrigeration is more good, and refrigeration area is arranged with length and the actual needs of vent line.
Further, it is provided with air cooler in described vent line.
Further, the circulation line being arranged at vent line described in is arranged in air cooler.
Here arranging air cooler is lowered the temperature further by the air-flow in vent line, the minimum temperature that setting air cooler degree of being lowered the temperature here can freeze lower than refrigeration system certainly.
The beneficial effects of the utility model are:
By arranging refrigeration system in vent line, vent line in construction tunnel is carried out refrigeration process, this refrigeration system is arranged on described vent line, carry, easy to operate, structure simple, carrying out smoothly of the healthy of workmen and construction can be guaranteed preferably.
Accompanying drawing explanation
Fig. 1 is the structural representation of constructing tunnel ventilation refrigeration system.
Embodiment
Describe embodiment below in conjunction with accompanying drawing and the utility model done concrete elaboration.
Such as Fig. 1, constructing tunnel ventilation refrigeration system, this refrigeration system is arranged in construction tunnel, described refrigeration system comprises condenser system and the recycle system, described condenser system comprises the water cooler 2 for storage of water, the water cooling tube 3 being connected with water cooler 2, the first water pump 4 being arranged on water cooling tube 3, this condenser system also comprises condenser 5, throttling valve 6, the refrigeration plant that vaporizer 7 and compressor 8 form, this condenser system is connected with the recycle system, water in this refrigeration system flows to the recycle system through refrigeration plant, water refluxes into condenser system through the recycle system, the described recycle system comprises circulation line 9, this circulation line 9 it is provided with in described vent line 1. the described recycle system also comprises water tank 10 and the 2nd water pump 11, described water tank 10 and the 2nd water pump 9 are arranged on described circulation line 9, certain water tank 10 here can also be replaced by resources such as the rivers near tunnel, the part that described circulation line 9 is arranged in vent line 1 is that spatial grid structure is distributed in vent line 1 and prolongs vent line and extend and arrange, being provided with air cooler 12 in described vent line 1, the part that circulation line 9 is arranged in described vent line 1 is arranged in air cooler 12.
Vent line in construction tunnel 1 can be carried out refrigeration process by the constructing tunnel ventilation refrigeration system described in the present embodiment, carry, easy to operate, structure simple, carrying out smoothly of the healthy of workmen and construction can be guaranteed preferably.
Claims (6)
1. constructing tunnel ventilation refrigeration system, this refrigeration system is arranged in construction tunnel, it is characterized in that, described refrigeration system comprises condenser system and the recycle system, described condenser system comprises the water cooler for storage of water (2), the water cooling tube (3) being connected with water cooler (2), the first water pump (4) being arranged on water cooling tube (3), this condenser system also comprises condenser (5), throttling valve (6), the refrigeration plant that vaporizer (7) and compressor (8) form, this condenser system is connected with the recycle system, water in this refrigeration system flows to the recycle system through refrigeration plant, water refluxes into condenser system through the recycle system, the described recycle system comprises circulation line (9), it is provided with this circulation line (9) in described vent line (1).
2. constructing tunnel ventilation refrigeration system according to claim 1, it is characterized in that, the described recycle system also comprises water tank (10) and the 2nd water pump (11), and described water storage device and the 2nd water pump (11) are arranged on described circulation line (9).
3. constructing tunnel ventilation refrigeration system according to claim 1, it is characterised in that, the described recycle system also comprises the 2nd water pump (11), and the 2nd water pump is connected by circulation line (9) with river or reservoir.
4. constructing tunnel ventilation refrigeration system according to claim 1, it is characterized in that, the part that described circulation line (9) is arranged in vent line (1) is that spatial grid structure is distributed in vent line (1) and prolongs vent line (1) and extend and arrange.
5. constructing tunnel ventilation refrigeration system according to claim 1, it is characterised in that, it is provided with air cooler (12) in described vent line (1).
6. constructing tunnel ventilation refrigeration system according to claim 5, it is characterised in that, described in be arranged at vent line (1) circulation line be arranged in air cooler (12).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520940738.6U CN205279540U (en) | 2015-11-23 | 2015-11-23 | Construction ventilation of tunnel refrigerating system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520940738.6U CN205279540U (en) | 2015-11-23 | 2015-11-23 | Construction ventilation of tunnel refrigerating system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205279540U true CN205279540U (en) | 2016-06-01 |
Family
ID=56064116
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520940738.6U Expired - Fee Related CN205279540U (en) | 2015-11-23 | 2015-11-23 | Construction ventilation of tunnel refrigerating system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205279540U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114109467A (en) * | 2021-12-06 | 2022-03-01 | 中铁隧道集团一处有限公司 | Tunnel construction comprehensive ventilation system and control method |
-
2015
- 2015-11-23 CN CN201520940738.6U patent/CN205279540U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114109467A (en) * | 2021-12-06 | 2022-03-01 | 中铁隧道集团一处有限公司 | Tunnel construction comprehensive ventilation system and control method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8567482B2 (en) | Heat tube device utilizing cold energy and application thereof | |
KR100904981B1 (en) | Earth heat cooling and heating system connected to stable ventilation and control method | |
CN206369389U (en) | A kind of ice cold-storage storage tank based on heat transfer technology of heat pipe | |
CN205154226U (en) | Construction ventilation of tunnel system | |
CN102589195A (en) | Heat supply and refrigeration system combining spatial energy with ground source energy | |
CN106482265A (en) | A kind of ground energy pipe laying constant temperature system of efficient energy-saving and emission-reducing | |
CN103636549B (en) | A kind of can the culturing pool of oxygenation temperature control | |
CN204963052U (en) | Open heat sink for station | |
CN102798185B (en) | Natural ice cold-storage and water-storage system and circulation method | |
CN205279540U (en) | Construction ventilation of tunnel refrigerating system | |
CN203869370U (en) | Heating and fresh-keeping water source heat pump device | |
CN204827510U (en) | Mine local ventilation heat sink | |
CN106482266A (en) | A kind of ground source constant temperature system of efficient energy-saving and emission-reducing | |
CN204084707U (en) | A kind of temperature-humidity of natural gas cold energy cascade utilization controls cold air conditioning system | |
CN203608716U (en) | Culture pond capable of oxygenating and controlling temperature | |
CN205357202U (en) | Low temperature storage grain bin refrigerating system | |
CN105532202A (en) | Refrigerating system of low-temperature grain storage bin | |
CN105386785B (en) | High-temperature mine tunnel wall attaches moisture film plate heat exchanger cooling system | |
CN110080817B (en) | Tunnel aeration cooling system based on phase change cold storage | |
CN106679016A (en) | Efficient, energy-saving and emission-reducing ground source constant-temperature device | |
CN107166599A (en) | A kind of ground source heating networked in length and breadth, adopt cooling system | |
CN202149555U (en) | Computer room air-conditioning system adopting double cold sources (air and soil) and fixed-point air supply mode | |
CN203785137U (en) | Low-energy-consumption temperature and humidity regulator | |
CN105241123A (en) | Heat pump well | |
CN101825316A (en) | Snowcover refrigerated energy-saving central air-conditioning system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |