CN205134337U - High slope supporting construction - Google Patents

High slope supporting construction Download PDF

Info

Publication number
CN205134337U
CN205134337U CN201520884199.9U CN201520884199U CN205134337U CN 205134337 U CN205134337 U CN 205134337U CN 201520884199 U CN201520884199 U CN 201520884199U CN 205134337 U CN205134337 U CN 205134337U
Authority
CN
China
Prior art keywords
slope
rank
order
prime
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520884199.9U
Other languages
Chinese (zh)
Inventor
滕云
刘林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Baosight cloud building integrated service platform of Limited by Share Ltd
Original Assignee
Hunan Bothink Design Platform Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Bothink Design Platform Co Ltd filed Critical Hunan Bothink Design Platform Co Ltd
Priority to CN201520884199.9U priority Critical patent/CN205134337U/en
Application granted granted Critical
Publication of CN205134337U publication Critical patent/CN205134337U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model relates to a building technical field discloses a high slope supporting construction, including the side slope drainage system, by supreme prime slope, second rank slope and the third rank that set gradually are sloping down, the slope on prime slope, second rank slope and third rank slope is 1 in proper order: 0.5, 1: 0.75 with 1: 1, the domatic shotcrete layer on prime slope, second rank slope and third rank slope, the supporting construction of prestressed anchorage pole frame and rhombus skeleton is all adopted on prime slope, second rank slope and third rank slope, and at sloping, the sloping outside adoption flexible protection net front cover in second rank slope and third rank of prime. The utility model has the advantages of economy, construction convenience and easy implementation.

Description

High slope rockmass structure
Technical field
The utility model relates to technical field of buildings, more particularly, and particularly a kind of high slope rockmass structure.
Background technology
Along with the development of national economy, various building occurs like the mushrooms after rain, and wherein, Mountainous Building just can run into the problem of high slope rockmass, and nowadays a lot of slope retaining is all within five meters, and does not have the slope retaining scheme of about 20 meters.For this reason, be necessary to redesign.
Utility model content
The purpose of this utility model is the high slope rockmass structure providing a kind of about 20 meters.
In order to solve problem set forth above, the technical solution adopted in the utility model is: high slope rockmass structure, comprise slope drainage system, the first slope, rank set gradually from the bottom to top, second-order slope and the 3rd slope, rank, described first slope, rank, the gradient on second-order slope and the 3rd slope, rank is followed successively by 1:0.5, 1:0.75 and 1:1, described first slope, rank, the domatic shotcrete layer on second-order slope and the 3rd slope, rank, described first slope, rank, second-order slope and the 3rd slope, rank all adopt the supporting and protection structure of prestressed anchor framework and rhombus skeleton, and on the first slope, rank, the outside on second-order slope and the 3rd slope, rank adopts soft protecting net front cover.
According to a preferred embodiment of the present utility model: adopt greening soil blocking bag bank protection or grass planting bank protection in described prestressed anchor framework.
According to a preferred embodiment of the present utility model: described slope drainage system comprises the gutter being arranged on top, slope, is arranged on the gutter of toe.
According to a preferred embodiment of the present utility model: described slope drainage system also comprises the water-permeable pipe in the slope body being arranged on described first slope, rank, second-order slope and the 3rd slope, rank, and the camber rate of this water-permeable pipe is 10%.
Compared with prior art, the beneficial effects of the utility model are: the advantage that the utility model has economy, easy construction and easily implements.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model embodiment or technical scheme of the prior art, be briefly described to the accompanying drawing used required in embodiment or description of the prior art below, apparently, accompanying drawing in the following describes is only embodiments more of the present utility model, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of high slope rockmass structure of the present utility model.
Description of reference numerals: 1, the first slope, rank, 2, second-order slope, the 3, the 3rd slope, rank, 4, prestressed anchor framework, 5, rhombus skeleton, 6, soft protecting net.
Detailed description of the invention
Below in conjunction with accompanying drawing, preferred embodiment of the present utility model is described in detail, to make advantage of the present utility model and feature can be easier to be readily appreciated by one skilled in the art, thus more explicit defining is made to protection domain of the present utility model.
Consult shown in Fig. 1, the utility model provides a kind of high slope rockmass structure, side slope mainly adopts three rank to put slope, each step is high 8 meters, platform is wide 2 meters, namely comprise set gradually from the bottom to top the first slope, rank 1, second-order slope 2 and the 3rd slope, rank 3, the gradient on the first slope, rank 1, second-order slope 2 and the 3rd slope, rank 3 is followed successively by 1:0.5,1:0.75 and 1:1, the domatic shotcrete layer on the first slope, rank 1, second-order slope 2 and the 3rd slope, rank 3, the first slope, rank 1, second-order slope 2 and the 3rd slope, rank 3 all adopt the supporting and protection structure of prestressed anchor framework 4 and rhombus skeleton 5.
Slope drainage system comprises the gutter being arranged on top, slope, and toe arranges gutter in conjunction with road drainage system, and slope body (the first slope, rank 1, second-order slope 2 and the 3rd slope, rank 3) arranges water-permeable pipe by 3500x3500 spacing, flare 10%.
The scheme of slope greening is: in prestressed anchor framework 4, adopt greening soil blocking bag bank protection or grass planting, adopts soft protecting net 6 front cover simultaneously.
The order of the utility model when Specific construction is, slope excavation → side slope cleaning → erection construction platform → anchor bolt construction → drain hole construction → side slope pipe laying ejectment water → m esh-hanging sprayed concrete → prestress anchorage cable.Do concrete introduction below:
1, slope excavation: adopt reverse construction.The sequence of construction of slope excavation is: during excavation from top to bottom, longitudinal kerve, horizontal partition, stage excavation.Each lift height is 3-4M.
2, side slope cleaning: adopt after marching into the arena and manually know side slope amount and loosening rock from top to bottom.Chisel out fritter loosen, suspension rock, reach construction smooth.
3, erection construction platform: engineering scaffold adopts steel pipe scaffold to set up.This engineering belongs to high slope engineering, and erection construction platform adopts bamboo springboard to set up.Setting up berm width is 2 meters, and every layer height is 2 meters, peripheral hardware guard rail.Scaffold and putting up platform want firm, have anti-impact force, anti-vibration ability.
4, vertically to drain off floodwaters pipe construction method: pipe junction of drainning off floodwaters on vertically drain off floodwaters pipe and ground adopts to refute with C25 steel concrete and connects well and be connected, refuting and connecing well head footpath is 1000 ㎜, refute to connect after well construction when concrete and just connect aboveground mouth φ 1000C60 concrete pipe is installed refuting, to carry out filling ensureing drainning off floodwaters at surrounding installation form pouring C15 concrete after two joint concrete pipes are often installed the stability of pipe, after top layer concrete pipe and packed layer pouring, blockage drains off floodwaters pipe draining in case the foreign material weeds flowing water at massif upper reaches drains off floodwaters to require to install cast iron grate at top layer concrete pipe well mouth.
5, the construction of anchor pole, drain hole: the construction of anchor pole, drain hole: this engineering grouting rock bolt is divided into Φ 28mm, Φ 32mm by bar footpath, length is 6m, 9m respectively.Anchor pole press between array pitch 1.5m × 1.5m staggered, alternately arrange.
6, mixed earth construction is sprayed: engineering sprayed mortar is mainly the spray of Polypropylene Fibre Concrete net, and injection method selects dampen shotcreting method.Before ejecting jet face is checked, and ready work, when spraying operation starts, feeding after should first feeding water; At the end of, after becalming, water should be closed again.
7, anchor cable construction: engineering adopts construction prestressed cable method, operation platform: requirement of engineering arranges the anchor cable of two T=1000KN, L=30m/35m.Boring 1000kN prestress anchorage cable boring aperture is 115mm, and this anchorage cable anchoring angle is 15 degree, the angle of depression.Anchor cable hole perforate Deviation Control is within 10cm.
8, road consolidation grouting process: duct consolidation grouting adopts single hole list to fill with, slurries adopt NJ-400 type homogenizer mixing, and Fahrenheit HS-B2 type grouting machine coordinates the grouting of JW180 agitator.Cement grout is not more than 0.5:1 (weight ratio).
9, anchorage cable stretching: after the cement calculus of anchor cable hole slurry reaches design strength, carry out anchorage cable stretching.
10, outer anchor head protection: the steel skein outside ground tackle, except retention 15cm, excises remainder.Outer anchor head is by designing requirement concrete protective, and the thickness of outer anchor head (containing exposing steel strand) topping is not less than 10cm.The outer anchor head different colours coating of different anchoring type is whitewashed and identifies, reach eye-catching and good discrimination effect.
11, quality examination: in construction prestressed cable process, carries out quality examination and the inspection of projects together with supervisor.
12, acceptance test: pre-stressed anchor rods acceptance test: in pre-stressed anchor rods construction, indicate random sampling to carry out by design and supervisor, number of sampling should not be less than 3 bundles.
13, completion acceptance: after submitting the data such as every quality examination record, test result, pre-stressed anchor rods record of acceptance and sampling check record to supervisor examination, as the completion acceptance data of prestress anchorage cable engineering.
Above-described embodiment is the utility model preferably embodiment; but embodiment of the present utility model is not restricted to the described embodiments; change, the modification done under other any does not deviate from Spirit Essence of the present utility model and principle, substitute, combine, simplify; all should be the substitute mode of equivalence, be included within protection domain of the present utility model.

Claims (4)

1. high slope rockmass structure, it is characterized in that: comprise slope drainage system, the first slope, rank (1) set gradually from the bottom to top, second-order slope (2) and the 3rd slope, rank (3), described first slope, rank (1), the gradient on second-order slope (2) and the 3rd slope, rank (3) is followed successively by 1:0.5, 1:0.75 and 1:1, described first slope, rank (1), the domatic shotcrete layer on second-order slope (2) and the 3rd slope, rank (3), described first slope, rank (1), second-order slope (2) and the 3rd slope, rank (3) all adopt the supporting and protection structure of prestressed anchor framework (4) and rhombus skeleton (5), and on the first slope, rank (1), the outside on second-order slope (2) and the 3rd slope, rank (3) adopts soft protecting net (6) front cover.
2. high slope rockmass structure according to claim 1, is characterized in that: in described prestressed anchor framework (4), adopt greening soil blocking bag bank protection or grass planting bank protection.
3. high slope rockmass structure according to claim 1, is characterized in that: described slope drainage system comprises the gutter being arranged on top, slope, is arranged on the gutter of toe.
4. high slope rockmass structure according to claim 1, it is characterized in that: described slope drainage system also comprises the water-permeable pipe in the slope body being arranged on described first slope, rank (1), second-order slope (2) and the 3rd slope, rank (3), and the camber rate of this water-permeable pipe is 10%.
CN201520884199.9U 2015-11-07 2015-11-07 High slope supporting construction Active CN205134337U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520884199.9U CN205134337U (en) 2015-11-07 2015-11-07 High slope supporting construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520884199.9U CN205134337U (en) 2015-11-07 2015-11-07 High slope supporting construction

Publications (1)

Publication Number Publication Date
CN205134337U true CN205134337U (en) 2016-04-06

Family

ID=55620144

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520884199.9U Active CN205134337U (en) 2015-11-07 2015-11-07 High slope supporting construction

Country Status (1)

Country Link
CN (1) CN205134337U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105821891A (en) * 2016-05-12 2016-08-03 大连交通大学 Construction method for reinforced concrete panel for prestress anchoring of slope and formwork forming structure of concrete panel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105821891A (en) * 2016-05-12 2016-08-03 大连交通大学 Construction method for reinforced concrete panel for prestress anchoring of slope and formwork forming structure of concrete panel
CN105821891B (en) * 2016-05-12 2018-05-01 大连交通大学 For the construction method of prestress anchoraging side slope armored concrete panel and the template molding structure of concrete slab

Similar Documents

Publication Publication Date Title
CN106013191B (en) Environment-friendly type grass planting Concrete Highway protective slope structure and construction method
CN102021911B (en) Side slope reinforcing method and structure
CN105544460B (en) Cast-in-place plant growing type eco-concrete slope protection construction method
CN102031784B (en) Slope protection pile pouring and cable bolting construction method for deep foundation pit
CN102296961B (en) Karst tunnel large-scale cavern processing method
CN109209389B (en) Construction method for entering semi-open and semi-closed tunnel
CN205999903U (en) Environment-friendly type grass planting Concrete Highway protective slope structure
CN104500077A (en) Construction method for enabling shallowly buried and darkly excavated tunnel to pass through cottage area
CN109594568B (en) Rock slope ecological protection structure and method thereof
CN205314115U (en) High steep side slope combined supporting greening structure of highway
CN110080254A (en) Draining friction pile-water guide culvert structure and construction method for oblique slope reinforcement
CN108716219A (en) side slope ecological protection structure and its construction method
CN113236259A (en) Special construction process for excavation and supporting of combined tunnel
CN112144552A (en) Damaged mountain ecological vegetation restoration structure, implementation method and application thereof
CN111676989A (en) Expansive soil cutting slope reinforcing structure and construction method
CN103334450B (en) Construction method of pile precast slab retaining wall with drainage ditch
CN110777802A (en) Deep foundation pit high-low span supporting structure and construction method thereof
CN203334301U (en) Cave slope strengthening protection structure
CN212077981U (en) Combined slope supporting structure
CN202989868U (en) Earthquake region high earth and rockfill dam earthquake resistance structure
CN205134337U (en) High slope supporting construction
CN106567365B (en) Earth and rockfill dam longitudinal reinforcement construction method
CN112854260A (en) Ecological concrete rock-soil slope protection structure and construction method
CN210827555U (en) Ecological reinforced earth retaining wall slope protection that red mudstone packed
CN108222030A (en) The lattice safeguard structure and construction method of a kind of not equidistant dregs side slope of transverse direction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: Yuelu District City, Hunan province 410205 Changsha Lu Valley Road No. 199 Lulong Lugu coordinates 1302 A room

Patentee after: Hunan Baosight cloud building integrated service platform of Limited by Share Ltd

Address before: Yuelu District City, Hunan province 410205 Changsha Lu Valley Road No. 199 Lulong Lugu coordinates 1302 A room

Patentee before: HUNAN BOTHINK DESIGN PLATFORM CO., LTD.