CN205047225U - A facility that is used for pipeline below to press coal exploitation - Google Patents

A facility that is used for pipeline below to press coal exploitation Download PDF

Info

Publication number
CN205047225U
CN205047225U CN201520746141.8U CN201520746141U CN205047225U CN 205047225 U CN205047225 U CN 205047225U CN 201520746141 U CN201520746141 U CN 201520746141U CN 205047225 U CN205047225 U CN 205047225U
Authority
CN
China
Prior art keywords
pipeline
facility
midair
main rope
mound
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520746141.8U
Other languages
Chinese (zh)
Inventor
李佳伟
张华�
周跃进
李宁
张奇
曹正正
汪尔乾
徐平
李永峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201520746141.8U priority Critical patent/CN205047225U/en
Application granted granted Critical
Publication of CN205047225U publication Critical patent/CN205047225U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a facility that is used for pipeline below to press coal exploitation, including supporting mound basis (1), supporting mound (2), suspending main rope (3) and hoist cable (4) in midair, support mound basis (1) and set up at the both ends of pipeline (5), support mound (2) and set up on supporting mound basis (1), set up between two support mound (2) and suspend main rope (3) in midair, suspend in midair and suspend a plurality of hoist cables (4) on main rope (3) in midair, still set up and be used for firm the drawing cable wire (6) and anchorage (7) to one side and being used for suspending in midair supporting seat (10) of pipeline (5) of mound (2) of supporting. The utility model discloses a pipeline (5) is suspended in midair in hoist cable (4), and the destruction of the earth's surface deformation of mining subsidence district settlement initiation is avoided to protection pipeline (5), adopts normal exploitation mode can exploit out the pipeline and push down the coal. The cost of the whole coal mining process protection pipeline of this method does not arrive prior art's 10%, has practiced thrift a large amount of coal resources, has high economic benefits.

Description

For the facility of mining pressed coal below pipeline
Technical field
The utility model relates to a kind of coal mining facility, specifically a kind of facility for mining pressed coal below pipeline.
Background technology
" three times " pressure coal exploitation be the major issue merited attention always, according to incompletely statistics, current China only coal mine under the unified-allocation system mine main " three times " pressure coal just reach 137.9 hundred million t, wherein build down 94.68 hundred million t, account for 69% of stagnation pressure coal amount.Along with carrying out of national West-East National Gas Transmission Project, inevitably produce the situation that coal field crossed by a lot of oil and gas pipeline, and along with the exploitation of mining area underground coal resource, will there is serious potential safety hazard in these pipelines.Once the surface subsidence caused due to coal mining causes serious destruction to pipeline, very large impact will be caused on the environment etc. of the energy of country and locality.Press the exploitation of coal below pipeline, current mainly taking implements resettlement to pipeline, and cost is high, and the cycle is long how simply, fast, effectively, complete below pipeline and press the exploitation of coal to be a great problem.
Summary of the invention
The utility model object is to provide a kind of facility for mining pressed coal below pipeline, and this facility is with low cost, can complete the exploitation of pressing coal below pipeline when guaranteeing pipeline safety.
To achieve these goals, a kind of facility for mining pressed coal below pipeline, comprises support pier basis, support pier, suspention main rope and hoist cable; Described support pier basis instrument is needing the two ends of the pipeline protected; two, one end; arrange in pipeline bilateral symmetry; support pier is arranged on two support pier bases; support pier is arranged on support pier basis; arrange suspention main rope between two support piers, suspention main rope suspends some hoist cables in midair, pipeline is suspended on suspention main rope by hoist cable.
The utility model can affect the dynamic deformation that shallow embedding gas transmission ground pipeline produces according to during exploitation of coal resources; suspension bridge overhead pipe is adopted to protect shallow embedding ground gas transmission line, thus the coal resources held up under adopting conventional mining type can exploit out pipeline.Suspension bridge erection is simple, and critical piece can reuse; After subsidence is stable, suspension bridge removes, because pipeline self has certain tensile properties, there will be no burst distortion, generally without the need to support of banketing, operation is comparatively simple; The cost of the whole coal mining process protection pipeline of the method, less than 10% of prior art, has been saved a large amount of coal resources, has been had high economic benefit.
Accompanying drawing explanation
Fig. 1 is the utility model structural representation;
Fig. 2 is the A-A partial sectional view of Fig. 1.
In figure: 1, support pier basis, 2, support pier, 3, suspention main rope, 4, hoist cable, 5, pipeline, 6, oblique pull cable wire, 7, anchorage, 8, pipeline extended line, 10, base for supporting pipeline, 12, ground tackle, 13, cord clip, 14, high-strength bolt, 101, collet, 102, upper cover, 103, groove, 104, bolt, 105, hanger, 106, cushion course.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is described further.
As depicted in figs. 1 and 2, a kind of facility for mining pressed coal below pipeline of the utility model, comprises support pier basis 1, support pier 2, suspention main rope 3 and hoist cable 4; Described support pier basis 1 is arranged on the two ends of the pipeline 5 needing protection; two, one end; arrange in pipeline 5 bilateral symmetry; support pier 2 is arranged on two support pier bases 1; support pier 2 is arranged on support pier basis 1; arrange suspention main rope 3 between two support piers 2, suspention main rope 3 suspends some hoist cables 4 in midair, pipeline 5 is suspended on suspention main rope 3 by hoist cable 4.
The utility model can affect the dynamic deformation that shallow embedding gas transmission ground pipeline produces according to during exploitation of coal resources; suspension bridge overhead pipe is adopted to protect shallow embedding ground gas transmission line, thus the coal resources held up under adopting conventional mining type can exploit out pipeline.Suspension bridge erection is simple, and critical piece can reuse; After subsidence is stable, suspension bridge removes, because pipeline self has certain tensile properties, there will be no burst distortion, generally without the need to support of banketing, operation is comparatively simple; The cost of the whole coal mining process protection pipeline of the method, less than 10% of prior art, has been saved a large amount of coal resources, has been had high economic benefit.
Further, for strengthening the steadiness of support pier 2, the utility model also comprises oblique pull cable wire 6 and anchorage 7, and anchorage 7 is arranged on two side positions of pipeline 5 two ends pipeline extended line 8, and oblique pull cable wire 6 one end connects anchorage 7, and the other end is connected with the top of support pier 2.
Further again, regulate for convenience of oblique pull cable wire 6, tensioning apparatus 9 is also set in the above.
Further, be protection pipeline 5, avoid it to be lifted rear local location pressurized excessive and damage, the utility model also comprises base for supporting pipeline 10, and base for supporting pipeline 10 is connected with hoist cable 4 lower end.Sling pipeline 5 time, because itself and base for supporting pipeline 10 contact area are comparatively large, local is born pressure and is diminished, so not easily suffer damage.
Further again, described base for supporting pipeline 10 comprises collet 101 and upper cover 102, and described collet 101 and upper cover 102 are arranged respectively the groove 103 for settling pipeline, collet 101 is connected by bolt 104 with upper cover 102, upper cover 102 arranges hanger 105, and pipeline 5 of slinging like this is not only convenient but also firm.
Further again, described groove 103 arranges cushion course 106, avoids pipeline 5 firmly contact with base for supporting pipeline 10 and damage pipeline.
Further, regulate for convenience of hoist cable 4, tensioning apparatus is set thereon.
Further, described hoist cable 4 and oblique pull cable wire 6 arrange stretching force detecting apparatus, can pulling force situation suffered by Real-Time Monitoring hoist cable 4 and oblique pull cable wire 6, judge that whether whole facility accepts even, adjusts in time.
Further, described hoist cable 4 is suspended on suspention main rope 3 by ground tackle 12, cord clip 13 and high-strength bolt 14, more firmly.

Claims (5)

1. for a facility for mining pressed coal below pipeline, it is characterized in that, comprise support pier basis (1), support pier (2), suspention main rope (3) and hoist cable (4); Described support pier basis (1) is arranged on the two ends of the pipeline (5) needing protection; two, one end; arrange in pipeline (5) bilateral symmetry; support pier (2) is arranged on two support pier bases (1); suspention main rope (3) is set between two support piers (2); suspention main rope (3) the some hoist cables of upper suspention (4), pipeline (5) is suspended in suspention main rope (3) by hoist cable (4).
2. the facility for mining pressed coal below pipeline according to claim 1, it is characterized in that, also comprise oblique pull cable wire (6) and anchorage (7), anchorage (7) is arranged on two side positions at pipeline (5) two ends extended line (8), oblique pull cable wire (6) one end connects anchorage (7), and the other end is connected with the top of support pier (2).
3. the facility for mining pressed coal below pipeline according to claim 2, is characterized in that, also comprises base for supporting pipeline (10), and base for supporting pipeline (10) is connected with hoist cable (4) lower end.
4. the facility for mining pressed coal below pipeline according to claim 3, it is characterized in that, described base for supporting pipeline (10) comprises collet (101) and upper cover (102), described collet (101) and upper cover (102) are arranged respectively the groove (103) for settling pipeline, collet (101) is connected by bolt (104) with upper cover (102), and upper cover (102) arranges hanger (105).
5. the facility for mining pressed coal below pipeline according to claim 4, is characterized in that, described groove (103) is arranged cushion course (106).
CN201520746141.8U 2015-09-24 2015-09-24 A facility that is used for pipeline below to press coal exploitation Expired - Fee Related CN205047225U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520746141.8U CN205047225U (en) 2015-09-24 2015-09-24 A facility that is used for pipeline below to press coal exploitation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520746141.8U CN205047225U (en) 2015-09-24 2015-09-24 A facility that is used for pipeline below to press coal exploitation

Publications (1)

Publication Number Publication Date
CN205047225U true CN205047225U (en) 2016-02-24

Family

ID=55340817

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520746141.8U Expired - Fee Related CN205047225U (en) 2015-09-24 2015-09-24 A facility that is used for pipeline below to press coal exploitation

Country Status (1)

Country Link
CN (1) CN205047225U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109000037A (en) * 2018-08-22 2018-12-14 北京城建集团有限责任公司 The suspension protective device and its construction method of pipeline in a kind of pit slot digging process

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109000037A (en) * 2018-08-22 2018-12-14 北京城建集团有限责任公司 The suspension protective device and its construction method of pipeline in a kind of pit slot digging process
CN109000037B (en) * 2018-08-22 2023-08-11 北京城建集团有限责任公司 Suspension protection device for pipeline in pit excavation process and construction method thereof

Similar Documents

Publication Publication Date Title
CN206842830U (en) Bushing lifting auxiliary boatswain chair
CN109973130B (en) Construction system and method for realizing one-time traction of extra-long tunnel anchor narrow space by main cable strand
CN205047225U (en) A facility that is used for pipeline below to press coal exploitation
CN202488055U (en) Cable protection device
CN203758760U (en) Loading test apparatus for petroleum drilling machine
CN203451055U (en) Lifting device for large-diameter reinforced concrete pipelines
CN204752046U (en) On --spot hoist and mount are with two steps of towers
CN201801295U (en) Wire rope totally-closed suspender
CN203998596U (en) Be easy to the vertical lifting structure coordinating with major diameter pipe
CN201605579U (en) Tubular pile industrial steel cage suspending device
CN204992433U (en) Cable carrier
CN204927955U (en) Support of using when overhead transmission line let -down ground wire, optical cable
CN204370397U (en) The wind resistance cable device of adjustable length
CN205152792U (en) A anchor for wire rope holds tightly
CN202561404U (en) Hoisting device
CN214298913U (en) Swift lifting device who does not destroy tubular product
CN103640964A (en) Wind power flange supporting-expanding-type lifting appliance
CN203269338U (en) Motor lifting device
CN204493902U (en) A kind of knot for lifting pipeline
CN203699681U (en) Remote-control hydraulic type scrap iron gripper
CN204986006U (en) Aerial cableway of big pipe diameter piping erection of complicated topography in mountain area is exclusively used in
CN204079250U (en) There is the lifting hook special for steel tube of adsorption plant
CN204042181U (en) Large-diameter steel pipe range distance through bridge constructing device
CN202296821U (en) Installation structure for lifting appliance
CN102022020B (en) A kind of tower lifting tackles connector and hoisting method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160224

Termination date: 20160924