CN204876526U - Instrument formula girder steel of encorbelmenting - Google Patents

Instrument formula girder steel of encorbelmenting Download PDF

Info

Publication number
CN204876526U
CN204876526U CN201520656334.4U CN201520656334U CN204876526U CN 204876526 U CN204876526 U CN 204876526U CN 201520656334 U CN201520656334 U CN 201520656334U CN 204876526 U CN204876526 U CN 204876526U
Authority
CN
China
Prior art keywords
steel
iron
utility
model
connecting rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520656334.4U
Other languages
Chinese (zh)
Inventor
万黔云
银克俭
张璞红
杨俊涛
吴德远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau Third Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau Third Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau Third Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau Third Construction Engineering Co Ltd
Priority to CN201520656334.4U priority Critical patent/CN204876526U/en
Application granted granted Critical
Publication of CN204876526U publication Critical patent/CN204876526U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses an instrument formula girder steel of encorbelmenting, set up backup pad and this backup pad perpendicular to I -steel in I -steel one end, set up in the backup pad with construct the outer wall on pre -buried hole site put the connecting hole that corresponds, connect pre -buried hole and connecting hole realization I -steel vertical fixation on building the outer wall through bolt no. 1, set up the locating lever on the I -steel upper surface, set up the connecting rod at the I -steel lower surface, set up rings directly over the backup pad, connect through wire rope between rings and connecting rod, the utility model provides an it is alternately many to run into negative and positive bight bit -type steel among the prior art in the builder's jack I -steel installation, girder steel, the difficult location of embedded ring, problem that I -shaped steel beam mounting is difficult, the utility model discloses effectively solve this type of problem, enable the girder steel and can all install in any position, can also practice thrift simultaneously the installation cost of the girder steel of encorbelmenting, reduce NULL, the installation rate also improves greatly, ensures do not encorbelmented steel beam mounting's influence of duration of a project.

Description

A kind of tool-type cantilever steel girder
Technical field
The utility model relates to a kind of tool-type cantilever steel girder, belongs to building scaffold set-up technology field.
Background technology
Along with the development in epoch, the progress of society, and the enforcement of new technology, new diseases and new criteria in construction, construction installation and safety protection facility progressively advance to " tool, regularization, standardization ".And erection of encorbelmenting belongs to safety protection facility indispensable in building construction process, i iron is again one of necessary component of outrigger of encorbelmenting.
Overwhelming majority project perimeter defense all adopts the shaped steel suspension scaffolding, adopts traditional mode of setting up can form interior of building shaped steel in negative and positive angular position and intersects more, and girder steel, pre-buried ring difficulty location, causes shaped steel to install complicated, constructional difficulties; Jog bit-type steel need different in size, the constructor in such project will carry out shaped steel to cut (normal section steel length is all 6m or 9m).This way not only increases constructing operation difficulty and operating time, and the shaped steel after being simultaneously cut can not use at other positions or sundry item, cause larger waste of material.
Utility model content
The purpose of this utility model is: for the defect of prior art, and provide a kind of tool-type cantilever steel girder, it is easy for installation, and structure is simple, firmly, is easy to construction, to overcome the deficiencies in the prior art.
The technical solution of the utility model
A kind of tool-type cantilever steel girder, comprise i iron, in i iron one end, gripper shoe is set and this gripper shoe perpendicular to i iron, the connecting hole corresponding with embedded hole position on external wall is set on the supporting plate, connect embedded hole and connecting hole by bolt one to realize i iron and be vertically fixed on external wall, i iron upper surface arranges backstay.
In aforesaid a kind of tool-type cantilever steel girder, arrange connecting rod at i iron soffit, directly over gripper shoe, arrange suspension ring, suspension ring are fixed in embedded hole by bolt two and backing plate, are connected between suspension ring with connecting rod by wire rope.
In aforesaid a kind of tool-type cantilever steel girder, the distance of described connecting rod and gripper shoe is the 2/3-3/4 of i iron total length.
Owing to have employed technique scheme, compared with prior art, run into negative and positive angular position shaped steel and intersect many in the utility model solution prior art in builder's jack i iron installation process, girder steel, pre-buried ring difficulty location, difficult problem installed by steel I-beam; The utility model effectively solves problems, and girder steel can be made can to install in any position; Can also save the installation cost of cantilever steel girder, decrease material usage, installation rate also improves greatly simultaneously, and guarantee the duration of a project not by the impact that cantilever steel girder is installed, the utility model structure is simple, easy to make, practical.
Accompanying drawing explanation
Accompanying drawing 1 is structural representation of the present utility model;
Accompanying drawing 2 is the connection diagram of embedded hole in connecting hole and building structure in the utility model;
Accompanying drawing 3 is the connection diagram of embedded hole in suspension ring and building structure in the utility model;
Accompanying drawing 4 is construction plan of the present utility model.
Detailed description of the invention
Below in conjunction with accompanying drawing to the utility model with being described in further detail, but not as to any restriction of the present utility model.
Embodiment of the present utility model: a kind of construction method of tool-type cantilever steel girder, when building structure need install lifting false work, the exterior wall place corresponding at each floor of building structure arranges embedded hole side by side, adopt i iron as the main body of tool-type Cantilever Beams, in one end of i iron, gripper shoe is set, at the connecting hole that gripper shoe setting position is corresponding with embedded hole position, employing bolt penetrates connecting hole and embedded hole implementation tool formula Cantilever Beams is vertically fixed on the exterior wall of the corresponding floor of building structure, at the upper surface of tool-type Cantilever Beams, the backstay be connected and fixed with lifting false work is set, at tool-type Cantilever Beams soffit, connecting rod is set, the embedded hole being positioned at a upper floor place of tool-type Cantilever Beams arranges suspension ring, suspension ring are fixed on the embedded hole place at a upper floor place by bolt and pad, employing wire rope connects suspension ring and connecting rod implementation tool formula Cantilever Beams two ends are simultaneously stressed, substantially improve the stressing conditions of tool-type Cantilever Beams, then lifting false work be arranged on tool-type Cantilever Beams and be connected and fixed by backstay and lifting false work, then complete the construction and installation to tool-type Cantilever Beams, when after the external wall construction completing lifting false work correspondence building, remove lifting false work and backstay connection and by tower crane by self-lifting scaffold frame integral hoisting, unclamp bolt by suspension ring and tool-type Cantilever Beams and take out, just suspension ring and tool-type Cantilever Beams are fixed in the embedded hole needing construction floor place in the same way, carry out the installation of lifting false work.
A kind of tool-type cantilever steel girder constructed by said method, as shown in drawings, comprise i iron 1, in i iron 1 one end, gripper shoe 2 is set and this gripper shoe 2 perpendicular to i iron 1, gripper shoe 2 arranges the connecting hole 3 corresponding with embedded hole position on external wall, realizing i iron 1 by bolt 1 connection embedded hole and connecting hole 3 is vertically fixed on external wall, i iron 1 upper surface arranges backstay 5, at i iron 1 soffit, connecting rod 6 is set, suspension ring 7 are set directly over gripper shoe 2, suspension ring 7 are fixed in embedded hole by bolt 28 and backing plate 9, be connected by wire rope 10 between suspension ring 7 with connecting rod 6, this connecting rod 6 and the distance of gripper shoe 2 are the 2/3-3/4 of i iron 1 total length.
During concrete making application
Select the long 16# i iron of 6m to carry out cutting and be divided into 4 sections, each segment length 1.5m, (connecting hole center is: with the steel plate upper left corner for reference point to select steel plate 200*200*10 also to make a call to two connecting holes mated with bolt one M32 thereon as gripper shoe, offset 50mm and 150mm respectively to the right, offset downward 70mm), one end of every section of i iron is welded (weld bead height 10mm) with a block plate (gripper shoe), the upper surface of the other end arranges the anchor point that scaffold upright rod can be made reliably to fix, anchor point adopts reinforcing bar and the steel I-beam firm welding (weld bead height 5mm) of long 100mm Ф 25, integrated structure working drawing and outrigger layout plan of encorbelmenting, reserved two embedded holes matched with bolt M32 on the wall at steel girder erection position, instrument is that cantilever steel girder is connected firmly the above-mentioned steel I-beam that processes and building pre-buried hole position wall or beam with two M32 bolts one when installing, and the length that screw rod exposes nut end should not be less than 3 buttons, and must not be greater than 10mm, each i iron Cantilever Beams outer end should arrange Ф 20mm connecting rod and last layer building structure drawknot, at the embedded hole place of one deck building structure, suspension ring are set, suspension ring adopt the reinforcing bar of Ф 20mm to make, the backing plate of steel plate as bolt adopting a block-type number to be 100*100*10, and be connected firmly with two bolts two, the connection of the suspension ring of connecting rod and building drawknot adopts Ф 20 wire rope, suspension ring way: one end adopts straight spiral grains mantle silk, and the other end is bent into ring-type and welds (weld length is not less than 100mm, weld bead height 5mm) finally installs scaffold upright rod, carry out the installation of superstructure structure updating scaffold after completing construction, final dismounting maintenance after total body construction completes, warehouse-in is preserved, and treats that next time, turnover used.

Claims (3)

1. a tool-type cantilever steel girder, comprise i iron (1), it is characterized in that: in i iron (1) one end, gripper shoe (2) is set and this gripper shoe (2) perpendicular to i iron (1), at the connecting hole (3) that the upper setting of gripper shoe (2) is corresponding with embedded hole position on external wall, realizing i iron (1) by bolt one (4) connection embedded hole and connecting hole (3) is vertically fixed on external wall, and i iron (1) upper surface arranges backstay (5).
2. a kind of tool-type cantilever steel girder according to claim 1, it is characterized in that: at i iron (1) soffit, connecting rod (6) is set, suspension ring (7) are set directly over gripper shoe (2), suspension ring (7) are fixed in embedded hole by bolt two (8) and backing plate (9), are connected between suspension ring (7) with connecting rod (6) by wire rope (10).
3. a kind of tool-type cantilever steel girder according to claim 2, is characterized in that: described connecting rod (6) and the distance of gripper shoe (2) are the 2/3-3/4 of i iron (1) total length.
CN201520656334.4U 2015-08-28 2015-08-28 Instrument formula girder steel of encorbelmenting Expired - Fee Related CN204876526U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520656334.4U CN204876526U (en) 2015-08-28 2015-08-28 Instrument formula girder steel of encorbelmenting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520656334.4U CN204876526U (en) 2015-08-28 2015-08-28 Instrument formula girder steel of encorbelmenting

Publications (1)

Publication Number Publication Date
CN204876526U true CN204876526U (en) 2015-12-16

Family

ID=54820917

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520656334.4U Expired - Fee Related CN204876526U (en) 2015-08-28 2015-08-28 Instrument formula girder steel of encorbelmenting

Country Status (1)

Country Link
CN (1) CN204876526U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105201198A (en) * 2015-08-28 2015-12-30 中建四局第三建筑工程有限公司 Tool-type cantilever beam and construction method thereof
CN117702981A (en) * 2024-02-05 2024-03-15 湖南恒之宇建筑安装工程有限公司 Steel construction roofing and installation reinforced structure of roofing purlin thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105201198A (en) * 2015-08-28 2015-12-30 中建四局第三建筑工程有限公司 Tool-type cantilever beam and construction method thereof
CN117702981A (en) * 2024-02-05 2024-03-15 湖南恒之宇建筑安装工程有限公司 Steel construction roofing and installation reinforced structure of roofing purlin thereof
CN117702981B (en) * 2024-02-05 2024-04-19 湖南恒之宇建筑安装工程有限公司 Steel construction roofing and installation reinforced structure of roofing purlin thereof

Similar Documents

Publication Publication Date Title
CN105201198A (en) Tool-type cantilever beam and construction method thereof
CN103195256B (en) Hanging column type steel structure jig frame construction method
CN202139833U (en) Cantilever scaffold for building construction
CN104975719A (en) Novel material distribution device and floor concrete casting construction method of novel material distribution device
CN104929364B (en) Auxiliary construction method for longspan cantilever entire laminated Vierendeel truss structure
CN103938875A (en) Ground single body tensioning lifting construction method of single layer suspendome
CN208965714U (en) A kind of prefabricated piping lane main frame structure of assembly concrete
CN105804400A (en) Hoisting construction method of curved truss
CN204876526U (en) Instrument formula girder steel of encorbelmenting
CN103206075B (en) Suspension platform for construction of steel reinforced concrete cantilever structure
CN104989111A (en) Construction method for steel structure high-rise hoisting
CN110725324A (en) Shear wall high-limb guide wall conversion supporting structure and construction method thereof
CN103993739B (en) The construction method of granulation tower spraying layer stiff beam
CN112360469A (en) Super-deep shaft sequential-lining single-side formwork-erecting lifting formwork and construction method
CN113338333A (en) Quick mounting method for steel beam plate under cover-excavation top-down condition
CN106592446A (en) Assembling construction method of precast segmental balanced cantilever with side-span wet joints
CN204225503U (en) Large span steel truss high altitude bulk conversion beam moulding bed
CN209874434U (en) Simple and easy scaffold frame of encorbelmenting of building high latitude
CN203222981U (en) Suspended platform for steel reinforced concrete cantilever structure construction
CN203924484U (en) A kind of precast beam and there is the reinforced concrete structure of tenon anchor system
CN103938877B (en) The installation method of crab-bolt stock
CN206846097U (en) A kind of Men Gangyu frameworks separately-loaded pipeline support structure
CN209322324U (en) A kind of large form handling apparatus
CN205294678U (en) Hoist and mount of instrument formula and uninstallation device of large -scale truss structure
CN105569327B (en) A kind of concrete filled steel tube height throws construction frame body and its application method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151216

Termination date: 20210828