CN204783112U - Mining novel air door wall body - Google Patents

Mining novel air door wall body Download PDF

Info

Publication number
CN204783112U
CN204783112U CN201520484420.1U CN201520484420U CN204783112U CN 204783112 U CN204783112 U CN 204783112U CN 201520484420 U CN201520484420 U CN 201520484420U CN 204783112 U CN204783112 U CN 204783112U
Authority
CN
China
Prior art keywords
air door
reinforcement cage
cage skeleton
support post
stent strut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520484420.1U
Other languages
Chinese (zh)
Inventor
张景钢
于强
王世贤
穆春明
孙春峰
谢宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China Institute of Science and Technology
Original Assignee
North China Institute of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China Institute of Science and Technology filed Critical North China Institute of Science and Technology
Priority to CN201520484420.1U priority Critical patent/CN204783112U/en
Application granted granted Critical
Publication of CN204783112U publication Critical patent/CN204783112U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a mining novel air door wall body, is applicable to the great mine of ore deposit pressure ratio in the pit. Including I -steel lintel, door frame, air door, upper beam, the symmetry sets up support post leg in the roadway wall face, and the lower part of support post leg is equipped with and is used for spacing card cable, and upper portion is connected with arched upper beam, and the lower part is equipped with the floorbar, and the floorbar becomes the arc structure of encircleing at the anti - end, the arc opening up, it is fixed mutually with support post leg that the floorbar both ends of arc structure are encircleed at the anti - end, through the welding point welding together, the floorbar that encircles the arc structure of the anti - end is reduced expenditure two and is put up three card cables and be formed by connecting, by being equipped with the steel reinforcement cage skeleton in support post leg and the arc -shaped rack that encloses that puts the beams in place the air door establish at the middle part of both sides support post leg through the door frame, the air door top is equipped with the I -steel lintel, the top of I -steel lintel is equipped with the wind window, the steel reinforcement cage skeleton pass through reinforcing bar net interconnect, the outside of steel reinforcement cage skeleton is equipped with the concrete back up coat. Its simple structure, anti deformability strengthen, long service life.

Description

A kind of new mine product air door body of wall
Technical field
The utility model relates to a kind of air door body of wall, especially a kind of new mine product air door body of wall being selected to underground coal mine.
Background technology
Air door is the important ventilation equipment of underground coal mine, be arranged on do not allow distinguished and admirable or part distinguished and admirable by but need pedestrian or cross in the tunnel of car, stable and excessively car, pedestrian the safe ready of quality to mine ventilation system of its quality and performance plays an important role, and the stable of air door body of wall normally uses most important for air door.If down-hole complex geologic conditions is changeable, ore deposit pressure manifests obviously, mining influence in addition, tunnel compressive deformation causes the damage of air door body of wall, door frame distortions, facilities services cycle short, air door does not reach protrusion-dispelling requirement, and ventilation equipment is constructed, increasing difficult in maintenance, brings potential safety hazard to shaft production.Tradition underground coal mine is commonly used air door body of wall and is usually made up of brick, sand, cement, permanent air throttle thickness of wall body is between 500mm ~ 800mm, doorframe generally adopts iron structure, air door top added wood, in the tunnel that ore deposit pressure is larger, because the husky elastic properties of materials of wall body brick is very little, the phenomenons such as body of wall is very easily peeled, fall to be cut, ftracture, crush, distortion, affect air door and normally use.
Summary of the invention
The purpose of this utility model will overcome weak point of the prior art, provides that a kind of structure is simple, non-deformability is strengthened, the new mine product air door body of wall of long service life.
For achieving the above object, new mine product air door body of wall of the present utility model, comprise i iron lintel, doorframe, air door, upper beam, stent strut leg is symmetrical arranged in the wall of tunnel, the bottom of stent strut leg is provided with for spacing card cable, top is connected with the upper beam of arch, bottom is provided with bottom girder, the arcuate structure that described bottom girder becomes the anti-end to encircle, arc opening upward, bottom girder two ends and the stent strut leg of curved arch structure of the anti-end fix, and are welded together by pad, and the bottom girder of curved arch structure of the anti-end is formed by connecting by two joint support three road card cables; The air door be provided with in the arched frame surrounded by stent strut leg and upper beam described in reinforcement cage skeleton is located at the middle part of both sides stent strut leg 1 through doorframe, air door top is provided with i iron lintel, the top of i iron lintel is provided with air regulator, described reinforcement cage skeleton is interconnected by steel mesh reinforcement, and the outside of reinforcement cage skeleton is provided with concrete strengthening layer.
Described reinforcement cage skeleton is connected with stull.
Bottom curved arch structure bottom girder of the described anti-end and doorframe, formed angle is 50 ~ 120 °.
Beneficial effect: owing to have employed technique scheme, support bottom air door by air door anti-end arch skeleton, utilize reinforcement cage framework structure body of wall, earth reinforcing is mixed its outside employing, thus air door is reinforced, arch structure of the anti-end can be prevented and treated air door press the deformation of bottom caused with being subject to, thus ensure that the normal use of air door.Be specially adapted to tunnel and be arranged in the situation that coal seam easily deforms, or the ore deposit pressure at place, tunnel is obvious, air door body of wall needs reinforcement the place of process, is also applicable to the air door wall reinforcement of other non-coal mine down-holes.Its structure is simple, non-deformability is strengthened, long service life.Compared with prior art, tool has the following advantages:
1. adopted metal cage cage construction supports air door body of wall, makes air door resistance to compression, non-deformability reinforcement.After adopting the anti-end to encircle disjunctor reinforcing, ore deposit presses remarkable location ventilation equipment anti-pressure ability significantly to strengthen, and stability improves greatly, for the safety in production of mine is laid a good foundation;
2, use waste anchor rods to make reinforcement cage skeleton, waste steel bar net connecting framework, reduce construction cost, and good consolidation effect can be played;
3, originally permanent air throttle, the ventilation equipments such as air damper just need after building up 3 ~ 6 months to carry out repairing or rebuilding, after employing new technology, service life was more than 1 year, namely air door builds up in latter 1 year does not need to keep in repair again, rebuild, standard is constructed according to ventilation equipment on current ore deposit, a cost of materials rebuild by one group of forward and reverse air door and labour cost needs 1.5 ten thousand yuan, Underground presses remarkable place air door to rebuild 3 times by the every annual mean of original technique, pressure larger area, ore deposit has 10 groups of air doors, after adopting this technology, annual minimizing air door rebuilds number of times 30 times, annual accumulative can cost saving 450,000 yuan, therefore apply this technology and there is good economic benefit and social benefit.
Accompanying drawing explanation
Fig. 1 is the utility model air door wall body structure schematic diagram;
In figure: 1-stent strut leg, 2-bottom girder, 3-pad, 4-reinforcement cage skeleton, 5-i iron lintel, 6-doorframe, 7-air door, 8-upper beam, 9-air regulator.
Detailed description of the invention
Below in conjunction with accompanying drawing, an embodiment of the present utility model is further described:
New mine product air door body of wall of the present utility model, is formed primarily of stent strut leg 1, bottom girder 2, reinforcement cage skeleton 4, i iron lintel 5, doorframe 6, air door 7, upper beam 8 and air regulator 9, described stent strut leg 1 symmetry is located in the wall of tunnel, air door 7 is located at the middle part of both sides stent strut leg 1 through doorframe 6, air door 7 top is provided with i iron lintel 5, the top of i iron lintel 5 is provided with air regulator 9, the bottom of stent strut leg 1 is provided with for spacing card cable, top is connected with the upper beam 8 of arch, reinforcement cage skeleton 4 is provided with in the arched frame surrounded by stent strut leg 1 and upper beam 8, the arcuate structure of arch of the described bottom girder 2 one-tenth anti-end, bottom girder 2 two ends and the stent strut leg 1 of curved arch structure of the anti-end fix, welded together by pad 3, the bottom girder 2 of curved arch structure of the anti-end is formed by connecting by two joint support three road card cables, described reinforcement cage skeleton 4 is interconnected by steel mesh reinforcement, the outside of reinforcement cage skeleton 4 is provided with concrete strengthening layer, reinforcement cage skeleton 4 is connected with stull, bottom curved arch structure bottom girder of the anti-end 2 and doorframe, formed angle is 50 ~ 120 °.
The course of work: according to field condition, U-shaped steel bottom girder is transformed into arch structure of the anti-end, then, dark 500mm base is dug in advance at roadway floor, pre-processed curved arch structure bottom girder of the anti-end 2 is embedded, then the shutoff of casting cement mortar is closely knit, with the waste anchor rods of many diameter of phi 18mm as root reinforcement cage skeleton 4 material, be made into anchor pole 45 that weld length is 2.4m, 2.2m length anchor pole 24 as rigid backbone; Waste steel bar net 23.5kg is utilized to cut off the anchor pole connected as skeleton; Waste and old mine timber 3m 3, manufacturing specification be 40 pieces of long 2.4m × wide 0.25m × thick 0.05m as main wooden model version; Utilize waste and old mine timber, the stull 48 of the long 0.5m of manufacturing specification × wide 0.08m × thick 0.08m makes back up, after being interconnected, uses mixed earth to carry out pouring shaping.

Claims (3)

1. a new mine product air door body of wall, comprise i iron lintel, doorframe, air door, upper beam, it is characterized in that: in the wall of tunnel, be symmetrical arranged stent strut leg, the bottom of stent strut leg is provided with for spacing card cable, top is connected with the upper beam of arch, bottom is provided with bottom girder, the arcuate structure that described bottom girder becomes the anti-end to encircle, arc opening upward, bottom girder two ends and the stent strut leg of curved arch structure of the anti-end fix, welded together by pad, the bottom girder of curved arch structure of the anti-end is formed by connecting by two joint support three road card cables; The air door be provided with in the arched frame surrounded by stent strut leg and upper beam described in reinforcement cage skeleton is located at the middle part of both sides stent strut leg 1 through doorframe, air door top is provided with i iron lintel, the top of i iron lintel is provided with air regulator, described reinforcement cage skeleton is interconnected by steel mesh reinforcement, and the outside of reinforcement cage skeleton is provided with concrete strengthening layer.
2. a kind of new mine product air door body of wall according to claim 1, is characterized in that: described reinforcement cage skeleton is connected with stull.
3. a kind of new mine product air door body of wall according to claim 1, is characterized in that: bottom curved arch structure bottom girder of the described anti-end and doorframe, formed angle is 50 ~ 120 °.
CN201520484420.1U 2015-07-07 2015-07-07 Mining novel air door wall body Expired - Fee Related CN204783112U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520484420.1U CN204783112U (en) 2015-07-07 2015-07-07 Mining novel air door wall body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520484420.1U CN204783112U (en) 2015-07-07 2015-07-07 Mining novel air door wall body

Publications (1)

Publication Number Publication Date
CN204783112U true CN204783112U (en) 2015-11-18

Family

ID=54523180

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520484420.1U Expired - Fee Related CN204783112U (en) 2015-07-07 2015-07-07 Mining novel air door wall body

Country Status (1)

Country Link
CN (1) CN204783112U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185486A (en) * 2018-08-28 2019-08-30 郑州煤炭工业(集团)杨河煤业有限公司 A kind of permanent protrusion-dispelling air door wall of concrete filled steel tube and its construction method
CN110925010A (en) * 2019-11-19 2020-03-27 煤炭科学技术研究院有限公司 Anti-deformation system for air door and air window of underground coal mine and installation method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185486A (en) * 2018-08-28 2019-08-30 郑州煤炭工业(集团)杨河煤业有限公司 A kind of permanent protrusion-dispelling air door wall of concrete filled steel tube and its construction method
CN110925010A (en) * 2019-11-19 2020-03-27 煤炭科学技术研究院有限公司 Anti-deformation system for air door and air window of underground coal mine and installation method
CN110925010B (en) * 2019-11-19 2021-06-01 煤炭科学技术研究院有限公司 Anti-deformation system for air door and air window of underground coal mine and installation method

Similar Documents

Publication Publication Date Title
CN102839675B (en) Method of long-span pre-stress fish belly sill for foundation pit support
CN102140924B (en) Double-shell coupling supporting method of deep soft rock tunnel
CN102493602B (en) Ductile concrete column capable of delaying local buckling of steel bars and manufacturing method thereof
Ning et al. Soft–strong supporting mechanism of gob-side entry retaining in deep coal seams threatened by rockburst
CN105972313B (en) One kind is across base pit engineering conduit wiring suspension method and overhung construction
CN208934197U (en) The plug-in filling wall construction system of steel frame and assembled filled-in panel
CN103711329B (en) The method of outer subsides steel reinforced concrete framework method ruggedized construction
CN106523003A (en) Rigid-flexible coupling energy absorbing support technology suitable for deep mining roadway
CN105178206B (en) Spliced-type shed tunnel
CN205806684U (en) A kind of across base pit engineering conduit wiring suspension structure
WO2023134375A1 (en) Large-span false roof structure using downward horizontal approach filling method, and construction method
CN104847381A (en) Buffer-energy absorption high resistance coupling support method of deep roadway
CN105781593A (en) Steel grating assisted diversion tunnel preliminary bracing structure and method
CN204783112U (en) Mining novel air door wall body
CN105134214A (en) Method for ventilation-assisting roadway arrangement and surrounding rock stability control in later period of coal mining
CN104563578A (en) Combined framework pillar for 500kV transformer substation and mounting method of combined framework pillar
Yu et al. Mechanism and technology study of collaborative support with long and short bolts in large-deformation roadways
CN102061742A (en) Shockproof reinforced concrete pseudo-classic building structural system
CN102477799B (en) Masonry structure integrity reinforcing method
CN204386242U (en) For the combined type truss column of 500kV transformer station
CN201908665U (en) Movable variable-cross section lining trolley
CN204754945U (en) Mine method tunnel preliminary bracing lining cutting grid steel support make
CN207620820U (en) A kind of breaking surrounding rock and soft-rock tunnel U-shaped steel cover canopy supporting construction
CN103046789B (en) Wrapping refuge cabin of existing masonry structure and construction method thereof
CN202755368U (en) Long span pre-stressing force fish-belly beam used for retaining and protecting foundation pit

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151118

Termination date: 20160707

CF01 Termination of patent right due to non-payment of annual fee