CN106523003A - Rigid-flexible coupling energy absorbing support technology suitable for deep mining roadway - Google Patents

Rigid-flexible coupling energy absorbing support technology suitable for deep mining roadway Download PDF

Info

Publication number
CN106523003A
CN106523003A CN201610854612.6A CN201610854612A CN106523003A CN 106523003 A CN106523003 A CN 106523003A CN 201610854612 A CN201610854612 A CN 201610854612A CN 106523003 A CN106523003 A CN 106523003A
Authority
CN
China
Prior art keywords
anchor
deep mining
absorbing support
support technology
roadway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610854612.6A
Other languages
Chinese (zh)
Inventor
苗胜军
梁明纯
王浩
郝欣
郭向阳
孔长青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
University of Science and Technology Beijing USTB
Original Assignee
University of Science and Technology Beijing USTB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by University of Science and Technology Beijing USTB filed Critical University of Science and Technology Beijing USTB
Priority to CN201610854612.6A priority Critical patent/CN106523003A/en
Publication of CN106523003A publication Critical patent/CN106523003A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/008Anchoring or tensioning means

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Inorganic Chemistry (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The invention provides a rigid-flexible coupling energy absorbing support technology suitable for a deep mining roadway and belongs to the technical field of mine supports. The technology comprises the specific steps that in the roadway excavation advancement process, an anchor net and anchor rods (anchor cables) are installed at the top and the two sides of the roadway, wherein the portions, at the top of the roadway, of the anchor net and the anchor rods are connected through prestressing plates; and then high pretightening force is applied to the energy absorbing threaded anchor rods and the grouting anchor cables, then plain (or steel fiber) concrete is sprayed, and the energy absorbing threaded anchor rods are fixed to the vertex and the two sides through M-shaped steel bands. According to the rigid-flexible coupling energy absorbing support technology suitable for the deep mining roadway, the tensile strength, the bending resistance and the rigidity of the top and the two sides of the roadway are improved, larger surrounding rock deformation can be borne, and the impact load effect of rock mass internal burst, rock explosion and the like can be resisted.

Description

A kind of Coupled Rigid-flexible energy-absorbing support technology for being suitable to deep mining tunnel
Technical field
The present invention relates to technical field of mine support, particularly relates to a kind of Coupled Rigid-flexible energy-absorbing for being suitable to deep mining tunnel Support technology.
Background technology
Economic high speed sustainable development and National Security Strategy be unable to do without the exploitation of mineral resources, continuous with superficial part resource Consume, underground mine proceeds to deep mining successively.Deep mining engineering rock mass is in heavily stressed, Gao Yanwen, Thief zone water pressure Under the complicated geological and mechanical environment of exploitation disturbance (i.e. " three high disturbances "), its tunnel presents obvious area with surrounding rock of chamber Not in superficial part elastic deformation, the crisp-ductility large deformation of brittle break and ductile spall, absciss layer splitting, brittle flaking off, sillar bullet New dynamic disaster phenomenons a series of with section rock burst etc. are penetrated, causes calamity complicated mechanism, stability to be difficult to control to.Coupled Rigid-flexible energy-absorbing Support technology can effectively buffer and absorb the huge energy discharged when roadway surrounding rock body is destroyed, and improve tunnel monolithic stability Property, to protecting the life security of personnel and the production safety tool of job facilities to be of great significance.
At present, China's underground mining drift support type mainly has anchor pole (rope) supporting, bolting with wire mesh, grouting cable anchor and anchor Bar combined supporting, shed ding support etc..Wherein, suspension roof support mainly prevents wall-rock crack to expand by applying pretightning force to reach Exhibition, improves the purpose of Surrounding Rock Strength and Drift stability;Because the features such as its easy construction, cheap, applied range compared with It is conventional.
However, deep rock mass has put aside substantial amounts of energy in long-term tectonic movement, and the engineering such as explosion, excavation It is movable then regional area Large strain can be caused to gather suddenly, and at the top of tunnel, shoulder and bottom etc. form high stress concentrations Region, so that cause the unstable failure in tunnel;Using Coupled Rigid-flexible energy-absorbing support technology, effectively can shift and diffusion-induced stress Concentrated area it is heavily stressed, be evenly distributed tunnel plastic zone stress field of the surrounding rock and displacement field, so as to improve country rock body Tunnel safety performance under the Impact Load such as internal rupture and rock burst.
The content of the invention
The present invention for tunnel deep rock mass rupture and the Impact Load such as rock burst under energy and stress concentration and A kind of the problems such as displacement deformation, there is provided Coupled Rigid-flexible energy-absorbing support technology for being suitable to deep mining tunnel.
The technology is specially:In roadway excavation tunneling process, anchor net and anchor pole, anchor cable are arranged at the top of tunnel and two Side, is connected by prestressed slab between the anchor net and anchor pole, anchor cable wherein at the top of tunnel;Then anchor pole and anchor cable are applied High pretightening force, prestressed slab make high pretightening force distribution tend to uniform, improve the globality of support system;Subsequently injection element or steel are fine Dimension concrete, in tunnel, drift angle and two is helped to use M steel band of model fixing anchor bars respectively.By high intensity anchor net, prestressed slab, anchor pole, The comprehensive reinforced concrete structure that anchor cable, concrete and M steel band of model are formed collectively as energy-absorbing support system is improving tunnel top Portion and two tensile strength helped, bending strength and rigidity, and bigger surrouding rock deformation is born, resist rock mass internal rupture and rock burst Deng Impact Load.
Wherein, anchor cable is grouting cable anchor, and anchor net is diamond mesh, and anchor pole is screw thread energy-absorption anchor rod, squeezes into when anchor pole and encloses After rock, anchor pole forms a common bearing structure with country rock, and its Design of Screw Thread can be such that rock mass leads to when by the impact load The stretcher strain for crossing screw thread itself absorbs part energy.
Prestressed slab replaces connection by three sections of arcs and level board and constitutes, and is provided with anchor pole and anchor cable is logical in the middle of level board Hole, prestressed slab two ends are end panel, are central flat in the middle of prestressed slab, length of the end panel length more than central flat Degree.
Prestressed slab is hot rolled steel plate, the arc length of three sections of arc two ends circular arcs may be designed as 350 according to field condition~ 450mm, the arc length of middle circular arc may be designed as 700~1000mm;Prestressed slab width may be designed as 200~300mm, and end is put down Plate is respectively 250mm and 200mm with the length of central flat.The arc length of three sections of arc two ends circular arcs is shorter and radius is larger, The arc length of middle circular arc is larger and radius is less.
Anchor net is formed by the rolling of 8# iron wires, and mesh is 35 × 35mm, with good elastic tension performance, when tunnel occurs Collapse, the rock mass unstable phenomenon such as inbreak or wall caving when, certain pressure release buffering and string bag energy-absorbing can be played a part of.
M steel band of model itself has certain rigidity and good flexibility, can impact lotus in rock mass internal rupture and rock burst etc. Load effect is lower to absorb a part of impact energy, so as to play certain buffering energy-absorbing function.
The above-mentioned technical proposal of the present invention has the beneficial effect that:
The present invention first passes through energy-absorption anchor rod and grouting cable anchor and injects cement mortar at rock mass internal voids, so as to by anchor pole Around (anchor cable) drilling, fragmentation rock mass is cemented together;Then laying high-strength degree diamond mesh is adjacent to along inwall, spray afterwards Plain (steel fibre) concrete, stops injection when concrete layer covers diamond mesh just.Press-in is helped with two at the top of tunnel Three sections of pre-stressed steel plates, then apply pretightning force to the threaded anchor rod in three sections of prestress steel plate holes and grouting cable anchor, so as to change The stress distribution of country rock has been apt to it, has improve the globality of country rock, plays good energy-absorbing supporting effect.With common coagulation Native spray-up is compared, and the program substantially increases tensile strength, bending strength and the rigidity of structure, can bear bigger surrouding rock deformation With cracking, and certain impact energy and load can be absorbed.At the drift angle of roadway's sides be often stress concentration region and split The multiple area in line crack, herein, first squeezes into screw thread energy-absorption anchor rod, then re-lays pre-stressed steel plate, then with horizontal, longitudinal direction M Steel band of model carries out drift angle reinforcement, as steel band itself also has certain rigidity and appropriate flexibility, so that screw thread energy-absorbing Anchor pole, pre-stressed steel plate and M steel band of model define a more preferable endergonic structure.When back and two helps by the impact load When, country rock absorbs part energy in itself, while being tied by the Coupled Rigid-flexible that energy-absorption anchor rod, prestressed slab and M steel band of model are constituted Structure absorbs part energy, finally absorbs dump energy by diamond mesh, to play a part of energy-absorbing buffering.The present invention can be with The stability of country rock is improved to a greater degree, is absorbed the Impact Load such as rock mass internal rupture and rock burst, is played security protection Effect.
Description of the drawings
Fig. 1 is the dimensional structure diagram of the present invention;
Fig. 2 is the cross-sectional structure schematic diagram of the present invention;
Fig. 3 is the prestressed slab top view of the present invention;
Fig. 4 is the prestressed slab profile of the present invention.
Wherein:1 anchor cable;2 anchor nets;3 anchor poles;4 M steel band of model;5 prestressed slabs;6 end panels;In 7 Between flat board;8 three sections of arcs;9 anchor poles and anchor cable through hole.
Specific embodiment
For making the technical problem to be solved in the present invention, technical scheme and advantage clearer, below in conjunction with accompanying drawing and tool Body embodiment is described in detail.
Energy and stress of the present invention for existing tunnel under the Impact Load such as deep rock mass rupture and rock burst A kind of the problems such as concentration and displacement deformation, there is provided Coupled Rigid-flexible energy-absorbing support technology for being suitable to deep mining tunnel.
As shown in Figure 1 to 4, prestressed slab of the present invention 5 is by the three sections of arcs 8 and level for being spaced connection successively Plate is constituted, and number can be adjusted according to tunnel or chamber size;The two ends of the prestressed slab 5 are provided with end panel 6, in advance should It is central flat 7 in the middle of power plate 5, end panel 6 and central flat 7 are provided with anchor cable and anchor pole through hole 9.
The width B of heretofore described prestressed slab 5 is 200~300mm, is chosen according to heading sizes, central flat 7 Length L4 is 200mm, and length L1 of end panel 6 is 250mm.
As shown in figure 4, according to field condition, heretofore described three sections of arcs, 8 concrete size may be designed as:Arc Arc length L2 of two ends circular arc is 350~450mm, and arc radius R1 is 2200~2900mm, and correspondence arc angle θ 1 is 8~10 °; Arc length L3 of middle circular arc is 700~1000mm, and arc radius R2 is 1300~1900mm, and arc angle θ 2 is 25~35 °;And And 1/2≤R2/R1≤2/3.Anchor pole and anchor cable through hole 9 are located at the middle position of end panel 6 and central flat 7, diameter root Factually border anchor pole, anchor cable are chosen.
Anchor cable 1 is grouting cable anchor, and anchor net 2 is diamond mesh, is formed by the rolling of 8# iron wires, and mesh is 35 × 35mm.Anchor Bar 3 is screw thread energy-absorption anchor rod.
Three sections of arcs 8 of the present invention and level board are pressed into by five sections of hot rolled steel plate point is curved, using hot rolled steel plate just In the support strength for improving prestressed slab.
Cement mortar is prepared:By water and 425# Portland cements according to weight 0.3:1~0.7:1 ratio is mixed Proportioning is closed, high efficiency water reducing agent is subsequently adding, weight is about the 1.2%~2.4% of cement consumption.
Install:By taking certain the gold ore in deep exploitation of Sanmenxia City Lingbao City of Henan Province area as an example, tunnel width 4m, prestressed slab 5 Width B is chosen for 250mm, and arc length L2 of three sections of arc two ends circular arcs is 400mm, and arc radius R1 is 2600mm, corresponding to justify Arc angle θ 1 is 9 °;Arc length L3 of middle circular arc is 840mm, and R2 is 1600mm, and correspondence arc angle θ 2 is 30 °.First, according to Tunnel lithology and supporting are required, it is determined that appropriate roadway layout position.Drilling construction is carried out to roadway surrounding rock with post drill, And grouting cable anchor 1 is squeezed into along drilling, position is squeezed into at the top of tunnel, bore diameter 32mm, hole depth 5600mm, exposure length 180mm.Anchor pole 3 is then mostly installed at the top board in tunnel, two helps with footing, and bore diameter 32mm wherein top and two helps hole Deep 2000mm, footing hole depth 2400mm, exposure length 120mm.There is rupture spillage phenomenon to prevent anchor shaft anchor cable, installing During, anchor pole 3 and anchor cable 1 should be noted that guarantee anchor shaft anchor cable is squeezed into straight along drilling, and substantially bending should not occur.During slip casting From bottom to top, symmetrical slip casting;Wherein help, with the slip casting of base plate boundary, the groove of 250mm need to be excavated two, by unnecessary slurry Draw;During using bolt grouting, grouting pressure is not more than 3MPa, is not more than 5MPa using grouting pressure during grouting cable anchor.Slip casting After the completion of, diamond mesh (anchor net 2) is adjacent to into arrangement along tunnel inwall, then the diamond-type metal mesh portions under roadway surrounding rock are sprayed Penetrate plain (or steel fibre) concrete tentatively to be strengthened, jet thickness is with closing metal net layer.Treat that concrete coagulation is dried Afterwards, in its underpart prestressed plate 5, horizontal, longitudinal direction M steel band of model 4 is installed and nut is tightened on anchor shaft anchor cable in drift angle and compress Prestressed slab 5, forms " prestressing force mechanism " (see Fig. 1).
At the construction field (site), what tunnel plastic zone country rock was carried out is the active support of anchor net to the present invention.Diamond mesh elder generation Be close to roadway surrounding rock, one layer concrete layer of fill-before-fire, this scheme substantially increase the tensile strength of superstructure, bending strength and Rigidity.Diamond mesh is to be rolled to form by iron wire, not only there is to roadway surrounding rock after paving tensioning good shield table to support and make With, and generation can be bloated with country rock in the dynamic impact load action such as rock mass internal rupture and rock burst and " take advantage of a situation " displacement, rise Buffer and string bag energy-absorbing function to certain pressure that allows.Simultaneously totally enclosed shield table wire netting be also prevented from country rock roof fall, wall caving, During avalanche, sillar launches the generation of casualty accident.While energy-absorption anchor rod (rope) is squeezed in hole, prestressed slab is applied to country rock Higher squeezing action is added so as to bigger surrouding rock deformation and cracking can be born, with higher deformation adaptability.In advance Stress plate provides the constraint being more uniformly distributed to anchor net jointly with M steel band of model, greatly enhances the stability of structure, rises To the effect of security protection.
The above is the preferred embodiment of the present invention, it is noted that for those skilled in the art For, on the premise of without departing from principle of the present invention, some improvements and modifications can also be made, these improvements and modifications Should be regarded as protection scope of the present invention.

Claims (6)

1. a kind of Coupled Rigid-flexible energy-absorbing support technology for being suitable to deep mining tunnel, it is characterised in that:Tunneled in roadway excavation Anchor net (2) and anchor pole (3), anchor cable (1) are arranged at the top of tunnel and two are helped by Cheng Zhong, the anchor net (2) and anchor wherein at the top of tunnel Connected by prestressed slab (5) between bar (3), anchor cable (1);Then high pretightening force is applied to anchor pole (3) and anchor cable (1), Prestressed slab (5) makes high pretightening force distribution tend to uniform, improves the globality of support system;Element or steel fibre coagulation are sprayed subsequently Soil, in tunnel, drift angle and two is helped to use M steel band of model (4) fixing anchor bar (3) respectively.
2. the Coupled Rigid-flexible energy-absorbing support technology for being suitable to deep mining tunnel according to claim 1, it is characterised in that:Institute It is grouting cable anchor to state anchor cable (1), and anchor net (2) is diamond mesh, and anchor pole (3) is screw thread energy-absorption anchor rod.
3. the Coupled Rigid-flexible energy-absorbing support technology for being suitable to deep mining tunnel according to claim 1, it is characterised in that:Institute Alternately connection is constituted by three sections of arcs (8) and level board to state prestressed slab (5), is provided with anchor pole and anchor cable through hole in the middle of level board (9), prestressed slab (5) two ends are for central flat (7), end panel (6) length in the middle of end panel (6), prestressed slab (5) More than the length of central flat (7).
4. the Coupled Rigid-flexible energy-absorbing support technology for being suitable to deep mining tunnel according to claim 1 or 3, its feature exist In:Described prestressed slab (5) are hot rolled steel plate, and the arc length of three sections of arc (8) two ends circular arcs is designed as 350 according to field condition ~450mm, the arc length of middle circular arc are designed as 700~1000mm.
5. the Coupled Rigid-flexible energy-absorbing support technology for being suitable to deep mining tunnel according to claim 1 or 3, its feature exist In:Prestressed slab (5) width is that the length of 200~300mm, end panel (6) and central flat (7) is respectively 250mm And 200mm.
6. the Coupled Rigid-flexible energy-absorbing support technology for being suitable to deep mining tunnel according to claim 1, it is characterised in that:Institute State anchor net (2) to be formed by the rolling of 8# iron wires, mesh is 35 × 35mm.
CN201610854612.6A 2016-09-27 2016-09-27 Rigid-flexible coupling energy absorbing support technology suitable for deep mining roadway Pending CN106523003A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610854612.6A CN106523003A (en) 2016-09-27 2016-09-27 Rigid-flexible coupling energy absorbing support technology suitable for deep mining roadway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610854612.6A CN106523003A (en) 2016-09-27 2016-09-27 Rigid-flexible coupling energy absorbing support technology suitable for deep mining roadway

Publications (1)

Publication Number Publication Date
CN106523003A true CN106523003A (en) 2017-03-22

Family

ID=58344496

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610854612.6A Pending CN106523003A (en) 2016-09-27 2016-09-27 Rigid-flexible coupling energy absorbing support technology suitable for deep mining roadway

Country Status (1)

Country Link
CN (1) CN106523003A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107795322A (en) * 2017-11-06 2018-03-13 山东建筑大学 A kind of assembly concrete arc plate and checkerboard type prestress anchorage cable composite supporting construction and its construction method
CN108571336A (en) * 2018-06-08 2018-09-25 北京科技大学 A kind of energy-absorbing backing plate suitable for deep mining tunnel
CN109488353A (en) * 2018-10-23 2019-03-19 新汶矿业集团有限责任公司 A kind of stope advance support system and method
CN110344854A (en) * 2019-07-24 2019-10-18 辽宁工程技术大学 Press laneway support method to a kind of thump
CN110344841A (en) * 2019-07-22 2019-10-18 周俊满 A kind of anchor rete cord shape steel bracket coupling supporting structure
CN110513129A (en) * 2019-09-26 2019-11-29 黄祖军 A kind of loose thick coal layer roadway workface fore-support supporting construction and method for protecting support
CN112444207A (en) * 2020-11-19 2021-03-05 北京科技大学 Roadway surface displacement monitoring device and method for area multipoint continuous measurement
CN113704861A (en) * 2021-10-22 2021-11-26 中国矿业大学(北京) Deep roadway energy-absorbing support design method and system
CN114483086A (en) * 2022-04-01 2022-05-13 中国矿业大学(北京) Energy-absorbing composite supporting system for protective tunnel
CN116499879A (en) * 2023-06-26 2023-07-28 中国矿业大学(北京) Underground engineering surrounding rock energy test and rock burst energy absorption control method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01295998A (en) * 1988-05-24 1989-11-29 Asahi Chem Ind Co Ltd Female screw anchoring work
CN101943013A (en) * 2010-09-09 2011-01-12 中南大学 Dynamic/static combined support method for rock burst of roadway
CN202064979U (en) * 2011-04-26 2011-12-07 山东大学 Semi-rigidity heterotypical girder anchor cable truss support system in roadway
CN102704965A (en) * 2012-05-21 2012-10-03 严红 Method for preventing tunnel top plate collapse risk caused by severe mining
CN102937030A (en) * 2012-11-26 2013-02-20 山东大学 Bolting-grouting integrated support method for zonal disintegration of deep roadway surrounding rock
CN102996149A (en) * 2012-11-21 2013-03-27 山东科技大学 Support method for bolt-grouting composite crushing dynamic-pressure roadway soft rock roof by high-pre-stressed anchor cable
CN203145954U (en) * 2013-02-05 2013-08-21 神华集团有限责任公司 Bolt support system
CN203783610U (en) * 2014-03-25 2014-08-20 山东科技大学 High-strength anchor-net-supported prestressed supporting plate beam
CN105781572A (en) * 2016-03-11 2016-07-20 中南大学 Deep mine hard rock roadway stress adsorption layer structured support method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01295998A (en) * 1988-05-24 1989-11-29 Asahi Chem Ind Co Ltd Female screw anchoring work
CN101943013A (en) * 2010-09-09 2011-01-12 中南大学 Dynamic/static combined support method for rock burst of roadway
CN202064979U (en) * 2011-04-26 2011-12-07 山东大学 Semi-rigidity heterotypical girder anchor cable truss support system in roadway
CN102704965A (en) * 2012-05-21 2012-10-03 严红 Method for preventing tunnel top plate collapse risk caused by severe mining
CN102996149A (en) * 2012-11-21 2013-03-27 山东科技大学 Support method for bolt-grouting composite crushing dynamic-pressure roadway soft rock roof by high-pre-stressed anchor cable
CN102937030A (en) * 2012-11-26 2013-02-20 山东大学 Bolting-grouting integrated support method for zonal disintegration of deep roadway surrounding rock
CN203145954U (en) * 2013-02-05 2013-08-21 神华集团有限责任公司 Bolt support system
CN203783610U (en) * 2014-03-25 2014-08-20 山东科技大学 High-strength anchor-net-supported prestressed supporting plate beam
CN105781572A (en) * 2016-03-11 2016-07-20 中南大学 Deep mine hard rock roadway stress adsorption layer structured support method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
经来旺 等: "《超深矿井岩石巷道及井筒快速施工综合技术研究》", 31 January 2014, 武汉理工大学出版社 *
齐干等: "深部大断面软岩巷道变形力学机制及耦合支护设计", 《采矿与安全工程学报》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107795322A (en) * 2017-11-06 2018-03-13 山东建筑大学 A kind of assembly concrete arc plate and checkerboard type prestress anchorage cable composite supporting construction and its construction method
CN107795322B (en) * 2017-11-06 2023-10-24 山东建筑大学 Assembled concrete arc plate and chessboard type prestressed anchor cable composite supporting structure and construction method thereof
CN108571336B (en) * 2018-06-08 2023-07-25 北京科技大学 Energy-absorbing backing plate suitable for deep mining roadway
CN108571336A (en) * 2018-06-08 2018-09-25 北京科技大学 A kind of energy-absorbing backing plate suitable for deep mining tunnel
CN109488353A (en) * 2018-10-23 2019-03-19 新汶矿业集团有限责任公司 A kind of stope advance support system and method
CN110344841A (en) * 2019-07-22 2019-10-18 周俊满 A kind of anchor rete cord shape steel bracket coupling supporting structure
CN110344854A (en) * 2019-07-24 2019-10-18 辽宁工程技术大学 Press laneway support method to a kind of thump
CN110513129A (en) * 2019-09-26 2019-11-29 黄祖军 A kind of loose thick coal layer roadway workface fore-support supporting construction and method for protecting support
CN110513129B (en) * 2019-09-26 2024-04-02 黄祖军 Advanced roof-protecting supporting structure and method for roadway of soft and thick coal seam working face
CN112444207A (en) * 2020-11-19 2021-03-05 北京科技大学 Roadway surface displacement monitoring device and method for area multipoint continuous measurement
CN113704861A (en) * 2021-10-22 2021-11-26 中国矿业大学(北京) Deep roadway energy-absorbing support design method and system
CN114483086A (en) * 2022-04-01 2022-05-13 中国矿业大学(北京) Energy-absorbing composite supporting system for protective tunnel
CN116499879A (en) * 2023-06-26 2023-07-28 中国矿业大学(北京) Underground engineering surrounding rock energy test and rock burst energy absorption control method
CN116499879B (en) * 2023-06-26 2023-09-05 中国矿业大学(北京) Underground engineering surrounding rock energy test and rock burst energy absorption control method

Similar Documents

Publication Publication Date Title
CN106523003A (en) Rigid-flexible coupling energy absorbing support technology suitable for deep mining roadway
CN105178981B (en) The closed depth coupling of broken soft rock roadway full-fracture-surfacanchoring-rod, which allows, presses bolt-grouting support method
CN102937030B (en) Bolting-grouting integrated support method for zonal disintegration of deep roadway surrounding rock
CN101967984B (en) Deep well tunnel cable anchor rigid-flexible coupling support and surrounding rock overall reinforced support method
CN102296976B (en) Asymmetrical bolt-net-cable combined supporting method for special-shaped recovery tunnel of large inclination angle coal bed
CN102140924B (en) Double-shell coupling supporting method of deep soft rock tunnel
CN108087008B (en) A kind of three-soft seam gob side entry method for protecting support
CN205117366U (en) Supporting device is encircleed to two pressure -bearings of big soft broken coal road of section
CN103244122B (en) Trinity coupling support stability control method for gob-side entry-driving coal pillar
CN102562093B (en) Full-length anchoring supporting method with intensive resin anchor rod and anchor-shotcrete net
CN106321119A (en) Double-layer anchor net cable supporting structure for controlling mining roadway surrounding rock deformation and method thereof
CN108316941A (en) A kind of breaking surrounding rock and soft-rock tunnel U-shaped steel cover canopy method for protecting support
CN113090284B (en) Roadway support method for soft and broken rock mass of underground mine
CN106194203A (en) A kind of coal-mine soft-rock method for protecting support
CN101509383A (en) Tunnel footing anchor pouring reinforcement anti bottom expanding method and construction technique
CN103075170A (en) Method for controlling surrounding rock deformation of gateway subjected to repeated overhead mining by using hollow grouting anchor cable
CN104533483A (en) Roadway total-space prestress truss, anchor cable and anchor rod coordinated supporting method
CN110645018B (en) Mine underground strong dynamic pressure roadway prestress anchor-charging integrated supporting structure and method
CN110985079A (en) Energy-absorbing impact-resistant roadway support method
CN210977516U (en) A scour protection energy release composite support structure for rock burst mine tunnel
CN101082281A (en) Method for controlling deformation of surrounding rocks of gallery influenced by overhead mining
CN107939419A (en) A kind of tunnel U-shaped steel covers canopy supporting construction
CN207620820U (en) A kind of breaking surrounding rock and soft-rock tunnel U-shaped steel cover canopy supporting construction
CN114087016B (en) Caving-to-filling mining isolation top column pre-control supporting method
CN113073991B (en) Roadway support method for extremely loose and broken rock mass of underground mine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170322