CN204736301U - Prefabricated staircase mould - Google Patents

Prefabricated staircase mould Download PDF

Info

Publication number
CN204736301U
CN204736301U CN201520273433.4U CN201520273433U CN204736301U CN 204736301 U CN204736301 U CN 204736301U CN 201520273433 U CN201520273433 U CN 201520273433U CN 204736301 U CN204736301 U CN 204736301U
Authority
CN
China
Prior art keywords
side form
die station
precast stair
plate
holder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520273433.4U
Other languages
Chinese (zh)
Inventor
孔曦
刘光辉
刘强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201520273433.4U priority Critical patent/CN204736301U/en
Application granted granted Critical
Publication of CN204736301U publication Critical patent/CN204736301U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Moulds, Cores, Or Mandrels (AREA)

Abstract

The utility model provides a prefabricated staircase mould, stable in structure, the drawing of patterns saves time, the convenience of wiping one's face. A prefabricated staircase mould, includes: the mould platform sets up on the guide rail of prefabricated staircase production line to can walk along the guide rail, two side forms set up in mould platform both sides respectively to be formed with the pouring die cavity between side form and the mould platform, with the closed guider of side form, guiding mechanism, positioning mechanism and coupling mechanism have, and wherein guiding mechanism sets up mould platform bottom, and positioning mechanism can follow guiding mechanism and slide, and the side form is fixed through coupling mechanism and positioning mechanism.

Description

Precast stair mould
Technical field
The utility model relates to a kind of construction apparatus, is specially a kind of precast stair mould.
Background technology
Existing stairway die has the following disadvantages: the stair demould time of cast is long, structural instability; Early strength is lower, easily causes the concrete poured into a mould to come off, and has increased the weight of the patch work amount in later stage; To wipe one's face inconvenience.
Utility model content
In order to solve above-mentioned prior art Problems existing, the utility model provides a kind of precast stair mould, Stability Analysis of Structures, and the demoulding saves time, and wipes one's face conveniently.
The utility model is by the following technical solutions:
A kind of precast stair mould, comprising:
Die station, is arranged on the guide rail of precast stair production line, and can walk along guide rail;
Two side forms, are separately positioned on die station both sides, and are formed with cast die cavity between side form and die station; With
Side form closes guider, has guiding mechanism, detent mechanism and bindiny mechanism, and wherein guiding mechanism arranges bottom die station, and detent mechanism can slide along guiding mechanism, and side form is fixed through bindiny mechanism and detent mechanism.
Above-mentioned precast stair mould preferred version, guiding mechanism comprises holder and the axis of guide, and wherein holder and die station removably connect, and the axis of guide laterally runs through holder; Detent mechanism comprises push-pull shaft, location pin block and alignment pin, and location pin block slides on the axis of guide, and push-pull shaft is threaded with holder and is connected with location pin block; Bindiny mechanism is alignment pin, and alignment pin one end is fixedly connected with location pin block, and the other end and side form connect as one.
Above-mentioned precast stair mould preferred version, side form comprises side form base plate, side form upper plate, two cant boards and multiple step plate, it is upper and lower that side form upper plate is set in parallel in side form base plate, two cant boards are separately positioned on side form base plate two ends, cant board is connected with side form upper plate, and multiple step plate head and the tail connect and compose multi-stage stairs successively.
Above-mentioned precast stair mould preferred version, is provided with multiple vertical stiffener between side form base plate and side form upper plate, be provided with multiple horizontal stiffener between two cant boards.
Above-mentioned precast stair mould preferred version, it also comprises caster device, and caster device comprises the road wheel being arranged on the live axle bottom die station by road wheel baffle plate and being arranged on live axle.
Above-mentioned precast stair mould preferred version, side form is connected by active grab with die station.
The beneficial effects of the utility model:
Side form closes guider and side form accurately can be located, and ensure that the precision of stair size; Side form is separately positioned on die station both sides, ensure that the rigidity of die station and the uniformity of part, reduces interchangeability and operability that difficulty of processing improves parts; Assembling adopts active grab to connect, and reduces operation easier, improves operating efficiency.
Accompanying drawing explanation
Fig. 1 is the schematic front view of precast stair mould;
Fig. 2 is the schematic top plan view of precast stair mould;
Fig. 3 is the schematic side view of precast stair mould;
Fig. 4 is the schematic front view of side form;
Fig. 5 is the schematic top plan view of side form;
Fig. 6 is the structural representation of caster device;
Fig. 7 is that side form closes guider and die station and side form connection diagram;
Fig. 8 is guiding mechanism structural representation.
Wherein, 1-active grab; 2-die station; 3-side form; 301-hanger; 302-cant board; 303-side form base plate; 304-cant board; 305-tread plate; 306-step plate; 307-step plate; The horizontal stiffener of 308-; 309-side form upper plate; The vertical stiffener of 310-; 4-caster device; 401-road wheel; 402-live axle; 403-road wheel baffle plate; 5-side form closes guider; 501-alignment pin; 502-locates pin block; 503-push-pull shaft; 504-holder, the 505-axis of guide.
Detailed description of the invention
In conjunction with the accompanying drawing in the utility model embodiment, do describe clearly and completely further the utility model, described embodiment is only the utility model part embodiment, instead of whole embodiments.
A kind of precast stair mould, comprises die station 2, two side forms 3, four side forms and closes guider 5 and four caster devices 4; Wherein die station 2 is arranged on the guide rail of precast stair production line, and can walk along guide rail; Two side forms 3 are separately positioned on die station 2 both sides, and are formed with cast die cavity between side form 3 and die station 2; Side form closes guider 5 and is distributed in side form 3 two ends, has guiding mechanism, detent mechanism and bindiny mechanism, and wherein guiding mechanism arranges bottom die station 2, and detent mechanism can slide along guiding mechanism, and side form 3 is fixed through bindiny mechanism and detent mechanism; Caster device 4 is arranged on bottom die station 2, and caster device 4 comprises the road wheel 401 being arranged on the live axle 402 bottom die station 2 by road wheel baffle plate 403 and being arranged on live axle 402.
In the present embodiment, guiding mechanism comprises holder 504 and the axis of guide 505, and wherein holder 504 and die station 2 removably connect, and the axis of guide 505 laterally runs through holder 504; Detent mechanism comprises push-pull shaft 503, location pin block 502 and alignment pin 501, and location pin block 502 slides on the axis of guide 505, push-pull shaft 503 be arranged on holder 504 being threaded and with locate pin block 502 and be connected; Bindiny mechanism is alignment pin 501, and alignment pin 501 one end is fixedly connected with location pin block 502, and the other end and side form 3 connect as one.
In the present embodiment, side form 3 comprises side form base plate 303, side form upper plate 309, two cant boards 302,304 and multiple step plate 306,307, side form upper plate 309 is set in parallel in side form base plate about 303, two cant boards 302,304 are separately positioned on side form base plate 303 two ends, cant board is connected with side form upper plate 309, multiple step plate head and the tail connect and compose multi-stage stairs successively, and step plate is provided with tread plate 305.
In the present embodiment, be provided with between side form base plate 303 and side form upper plate 309 between multiple vertical stiffener 310, two cant boards and be provided with multiple horizontal stiffener 308; Consider easy to operate, side form 3 is provided with hanger 301, hanger 301 and vertical stiffener 310 are welded as a whole.
In the present embodiment, side form 3 is connected by active grab 1 with die station 2, reduces operation easier, improves operating efficiency.
The course of work of the present utility model is as follows: be positioned over by the bar frame in stair in stair die station 2 fixing during use, side form 3 lifting is put in die station 2, be provided with alignment pin 501 that locating hole and side form close guider 5 bottom side form 3 to coordinate and locate, rotating sliding axle 503, side form 3 is formed casting moulds chamber with die station 2 is closed, then utilizes active grab 1 side form 3 and die station 2 to be fixed.Then to casting concrete in cast die cavity, by floating for upper plane, after maintenance completes, form removal.Unclamped by active grab 1 when form removal, the cooperation of reverse rotation push-pull shaft 503 turns die sinking bolt and side form 3 and die station 2 is opened, and realizes die sinking; Then capable for precast stair hanging is hung away, complete stair prefabricated.
Above only describes general principle of the present utility model and preferred embodiment, those skilled in the art can make many changes and improvements according to foregoing description, and these changes and improvements should belong to protection domain of the present utility model.

Claims (6)

1. a precast stair mould, is characterized in that comprising:
Die station, is arranged on the guide rail of precast stair production line, and can walk along guide rail;
Two side forms, are separately positioned on die station both sides, and are formed with cast die cavity between side form and die station; With
Side form closes guider, has guiding mechanism, detent mechanism and bindiny mechanism, and wherein guiding mechanism arranges bottom die station, and detent mechanism can slide along guiding mechanism, and side form is fixed through bindiny mechanism and detent mechanism.
2. precast stair mould according to claim 1, it is characterized in that: guiding mechanism comprises holder and the axis of guide, wherein holder and die station removably connect, and the axis of guide laterally runs through holder; Detent mechanism comprises push-pull shaft, location pin block and alignment pin, and location pin block slides on the axis of guide, and push-pull shaft is threaded with holder and is connected with location pin block; Bindiny mechanism is alignment pin, and alignment pin one end is fixedly connected with location pin block, and the other end and side form connect as one.
3. precast stair mould according to claim 1, it is characterized in that: side form comprises side form base plate, side form upper plate, two cant boards and multiple step plate, it is upper and lower that side form upper plate is set in parallel in side form base plate, two cant boards are separately positioned on side form base plate two ends, cant board is connected with side form upper plate, and multiple step plate head and the tail connect and compose multi-stage stairs successively.
4. precast stair mould according to claim 3, is characterized in that: be provided with multiple vertical stiffener between side form base plate and side form upper plate, is provided with multiple horizontal stiffener between two cant boards.
5. precast stair mould according to claim 1, is characterized in that: it also comprises caster device, and caster device comprises the road wheel being arranged on the live axle bottom die station by road wheel baffle plate and being arranged on live axle.
6. precast stair mould according to any one of claim 1 to 5, is characterized in that: side form is connected by active grab with die station.
CN201520273433.4U 2015-04-30 2015-04-30 Prefabricated staircase mould Expired - Fee Related CN204736301U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520273433.4U CN204736301U (en) 2015-04-30 2015-04-30 Prefabricated staircase mould

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520273433.4U CN204736301U (en) 2015-04-30 2015-04-30 Prefabricated staircase mould

Publications (1)

Publication Number Publication Date
CN204736301U true CN204736301U (en) 2015-11-04

Family

ID=54418057

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520273433.4U Expired - Fee Related CN204736301U (en) 2015-04-30 2015-04-30 Prefabricated staircase mould

Country Status (1)

Country Link
CN (1) CN204736301U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106914973A (en) * 2017-03-16 2017-07-04 中国五冶集团有限公司 Based on mold system for improving precast stair production efficiency and preparation method thereof
CN108068202A (en) * 2016-11-16 2018-05-25 任丘市永基建筑安装工程有限公司 Vertical Combination stair board mold
CN112252713A (en) * 2020-11-04 2021-01-22 四川周兴和实业有限公司 Adjustable assembled house stair assembling die

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108068202A (en) * 2016-11-16 2018-05-25 任丘市永基建筑安装工程有限公司 Vertical Combination stair board mold
CN106914973A (en) * 2017-03-16 2017-07-04 中国五冶集团有限公司 Based on mold system for improving precast stair production efficiency and preparation method thereof
CN112252713A (en) * 2020-11-04 2021-01-22 四川周兴和实业有限公司 Adjustable assembled house stair assembling die
CN112252713B (en) * 2020-11-04 2021-11-09 四川周兴和实业有限公司 Adjustable assembled house stair assembling die

Similar Documents

Publication Publication Date Title
CN204736301U (en) Prefabricated staircase mould
CN111438811A (en) Concrete prefabricated section upset shedder
CN201669783U (en) Bedplate basin type sanitary ceramics stripping equipment
CN102416663B (en) Micro-pressure ceramic forming machine
CN202946193U (en) Tunnel center gutterway formwork
CN201864500U (en) Chain sling hoister for closestool vertical casting line
CN203076538U (en) Core shooter
CN208668945U (en) A kind of stair template for building construction
CN201482976U (en) Sand mould demoulding device used for casting
CN208748533U (en) A kind of T shape Continuous Rigid Girder Bridge pours external mold mobile device
CN207564681U (en) A kind of prefabricated three-dimensional mobile formwork of cantilever beam section long line method
CN109605550A (en) Building gypsum diaphragm capsule molding machine
CN202606812U (en) Leaky-mode machine taking crank connecting rod as lifting mechanism
CN202073045U (en) Hanging basket inner mould sliding apparatus
CN212602527U (en) Concrete prefabricated section upset shedder
CN107060044B (en) One-step forming die for pouring groove and using method thereof
CN207348880U (en) A kind of tunnel center gutter formed molding board
CN220226901U (en) Main drainage ditch box die capable of achieving narrow and demoulding movement of tunnel inverted arch
CN215208062U (en) Core setting lifting appliance for cylinder block horizontal pouring gate core
CN201313178Y (en) Pouring operation platform for castings
CN210460692U (en) Platform is pour in tunnel
CN218138856U (en) Irregular stiff column cross construction device
CN212716660U (en) Shrinkage type tunnel center ditch secondary forming template with slide block
CN220226900U (en) Tunnel inverted arch main drainage ditch box die
CN209466406U (en) A kind of prefabricated carrying bogie beam mould

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151104

Termination date: 20160430