CN204680051U - A kind of project of transmitting and converting electricity is constructed intelligent auxiliary tube Ore-controlling Role - Google Patents

A kind of project of transmitting and converting electricity is constructed intelligent auxiliary tube Ore-controlling Role Download PDF

Info

Publication number
CN204680051U
CN204680051U CN201420645454.XU CN201420645454U CN204680051U CN 204680051 U CN204680051 U CN 204680051U CN 201420645454 U CN201420645454 U CN 201420645454U CN 204680051 U CN204680051 U CN 204680051U
Authority
CN
China
Prior art keywords
project
construction
main frame
mobile platform
transmitting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420645454.XU
Other languages
Chinese (zh)
Inventor
李元锋
宋惠忠
莫加杰
魏敏
沈红峰
夏强峰
周咏槟
袁均祥
屠晔炜
吴伟江
蒋晓波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIAXING HENGGUANG ELECTRIC POWER CONSTRUCTION CO Ltd
Jiaxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
JIAXING HENGGUANG ELECTRIC POWER CONSTRUCTION CO Ltd
Jiaxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIAXING HENGGUANG ELECTRIC POWER CONSTRUCTION CO Ltd, Jiaxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical JIAXING HENGGUANG ELECTRIC POWER CONSTRUCTION CO Ltd
Priority to CN201420645454.XU priority Critical patent/CN204680051U/en
Application granted granted Critical
Publication of CN204680051U publication Critical patent/CN204680051U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Abstract

A kind of project of transmitting and converting electricity is constructed intelligent auxiliary tube Ore-controlling Role, described system forms primarily of main frame, mobile platform terminal and utility appliance, described main frame as creating newly built construction, managing existing engineering, and is integrated the master data that each mobile platform terminal returns and is stored; Described main frame is configured with multiple mobile platform terminal connected by local area network wireless communication system, and described mobile platform terminal is an operation project of transmitting and converting electricity construction intelligence-aided project manage-ment system client-side program; Described management-control method is the Organization And Management's requirement according to Transmission Projects, project is divided into project's earlier stage, project construction, the project acceptance inspection three aspects; It has can improve construction technology standard level, lifting construction person works efficiency, can realize the management in all directions of project of transmitting and converting electricity construction and perform examination, the features such as the construction quality of General Promotion project of transmitting and converting electricity and safety management level.

Description

A kind of project of transmitting and converting electricity is constructed intelligent auxiliary tube Ore-controlling Role
Technical field
The utility model relates to a kind of project of transmitting and converting electricity to construct intelligent auxiliary tube Ore-controlling Role, belong to the intelligent management and control technical field of engineering construction.
Background technology
At present, project of transmitting and converting electricity construction working is wide, point is many, it is numerous to measure, proficiency is uneven, all kinds of technological standardss, the rules and regulations of required execution in construction are various, as technological standards, common quality defect, compulsive clause, safety management system etc., often can not be exhaustive in construction task implementation process, construction quality problem in the acceptance of work is frequently occurred; Construction operation risk pressure is large, and dangerous operation occurs often, can not effectively effect a radical cure, and there is certain construction safety hidden danger.
Summary of the invention
The purpose of this utility model is the deficiency overcoming prior art existence, and provide one mainly to improve construction technology standard level, lifting construction person works efficiency, promote safety management in construction site level, thus the management in all directions of engineering construction can be realized and perform examination, the project of transmitting and converting electricity of General Promotion engineering construction quality, safety management level is constructed intelligent auxiliary tube Ore-controlling Role and management-control method thereof.
Object described in the utility model has been come by following technical solution, described project of transmitting and converting electricity is constructed intelligent auxiliary tube Ore-controlling Role, it is primarily of main frame, mobile platform terminal and utility appliance composition, it is characterized in that described main frame is as creating newly built construction, managing existing engineering; To each mobile platform terminal distribution task, and the master data that each mobile platform terminal returns is integrated and stored; Described main frame is configured with multiple mobile platform terminal connected by local area network wireless communication system, described mobile platform terminal is an operation project of transmitting and converting electricity construction intelligence-aided project manage-ment system client, and after completing item by item the task of main frame distribution, return data is to main frame.
Described utility appliance at least comprises a bluetooth scanning and robs and a bar code printer, mobile platform terminal and bluetooth scan to rob corresponding configuration and can accept bluetooth and scan the input of robbing, and automatically identify numbering equipment, check equipment installation progress, installation quality, safety work situation; Working-yard Preventive Control of Dangerous Spot measure, installation procedure quality, construction operation safety, acceptance of work situation are taken pictures and touched input record, and can send short messages and inform and specify responsible official current project progress.
Described bar code printer corresponding configuration is in described main frame, and equipment bar code is being robbed input mobile platform terminal by bluetooth scanning and after being uploaded to main frame, printing relevant device bar code by described bar code printer; Described main frame is server end.
One utilizes described project of transmitting and converting electricity intelligent auxiliary tube Ore-controlling Role of constructing to carry out management-control method, described management-control method is the Organization And Management's requirement according to construction of power transmission and transformation engineering project, project is divided into project's earlier stage, project construction, the project acceptance inspection three aspects, specifically:
(1) project's earlier stage, described project's earlier stage comprises two parts, and one is that engineering establishment and system each module primary data are set up and each management clause, special construction plan, the arrangement of the files such as job instruction and formulation; Two is engineering site security civilization standardized construction and Preventive Control of Dangerous Spot carrying out measures.
(2) project construction, described project construction comprises three parts, one be equipment march into the arena in place unpack, bar code make; Two is the Installation and Debugging of equipment standard equalization; Three is site safety task managements.
(3) acceptance of work, after all standard equalization task completes, enter acceptance stage, regulation is checked and accepted according to Guo Wang company and three grades, company of province, inspector, according to the final acceptance of construction flow process pointed out in mobile platform terminal, carries out standardization examination to installation work quality, defect of checking on the quality, propose reform advice, and assign to each person liable by management system; Person liable rectifies and improves according to suggestion, and by rectification situation input system, after to be confirmed, this grade of checking and accepting can complete, and then starts next stage checking and accepting; After checking and accepting terminates, submit completion report of construction work to.
The utility model is preferably: in described (1) project's earlier stage, specifically comprise:
1. engineering duty creates, after construction task is assigned, the file such as project profile, special construction plan, all kinds of job instruction, all kinds of construction management systems carries out arranging, collecting, and the document management module provided based on system is deleted, increase, upgrade certain engineering management fileinfo;
By the inspection of the scene of a crime, incorporation engineering work on the spot actual conditions, the security civilization standardized construction module provided based on system is formulated certain engineering safety civilization markization and is required provision; Certain engineering Preventive Control of Dangerous Spot measure requirement provision is formulated based on duration Preventive Control of Dangerous Spot measure in early stage module; Certain Engineering Standardization job requirements provision is formulated based on standardized work flows control module and engineering site equipment situation;
According to project management needs, set up construction project department, identify project management, workmen; According to the engineering management functional distribution system account authority of everyone; The personnel's file store provided according to system is deleted, increase, upgrade management, workmen's archives of certain engineering project of establishment; According to Engineering Project Construction character, project security management requirement, based on the engineering risk management and control requirement that system provides, delete, increase, upgrade certain engineering risk management and control measure of formation requirement provision.
2. project's earlier stage task closed loop is implemented, the engineering safety standard of civilization construction requirement provided according to system and engineering site Preventive Control of Dangerous Spot measure provision, site layout project construction is carried out in contrast one by one, employing digital photograph is the implementation of conditions of means record every requirement and measure provision, and forms closed loop management.Lead back to server after prerequisite task completes, and it is qualified to carry out onsite acceptance by project manager.After only completing above-mentioned steps, just carry out the task of project construction phase, therefore ensured that the construction of engineering safety standard of civilization and Preventive Control of Dangerous Spot carrying out measures are to crucial point;
In described (2) project construction, specifically comprise:
1. equipment bar code makes, electrical equipment march into the arena in place after, generated corresponding equipment installation management by work responsible official hand-held intelligent terminal encode based on each equipment factory number, the date of production, and uploaded onto the server by WLAN (wireless local area network), print corresponding equipment bar code by bar-code printer, be affixed on each equipment fixed position.Rely on bluetooth scanning technique, work responsible official or project manager can be inquired about by handheld terminal at any time and supervise per unit installation progress and quality, constructability Liability Retroact;
2. equipment standard operation Installation and Debugging, in construction process, the construction task that work responsible official arranges according to hand-held intelligent terminal system, the requirement contrasting corresponding operation and standard, rulyly carry out standardized work, by each stage duty of the form record of digital photograph.After per stage end-of-job, confirmation must be checked and accepted through operation responsible official, and acceptance information is inputted handheld terminal and next step operation can be proceeded to after uploading onto the server, guarantee engineering construction quality controlled, can control, in control.Meanwhile, in work progress, work responsible official can the job instruction of reference device Installation and Debugging at any time, special construction plan, and the files such as all kinds of construction operation handbooks, can make construction procedure normative and reasonable more, evidence-based;
3. site safety task management, in construction task implementation process, determines every work responsible official by project administrator based on personnel's archive database that system provides.In work progress, work responsible official fills in by hand-held intelligent terminal that construction station class meeting is parallel tells somebody what one's real intentions are.Construction task is issued by project of transmitting and converting electricity construction intelligence-aided project manage-ment system, work responsible official fills in construction operation ticket on hand-held intelligent terminal, select there are the personnel of respective attributes as construction working class member (if the current attribute of workmen does not meet construction operation requirement based on workmen's archive database, then cannot be added to construction operation class member), and carry out safely, confide a technological secret, and there are personnel that construction operation signs and issues attribute carry out the identification of construction operation ticket and sign and issue;
Need after a certain construction task completes to submit complete report or termination construction operation ticket to by handheld terminal, and system that information is uploaded onto the server, just can leave construction area after device system feedback corresponding information to be serviced.
The utility model has can improve construction technology standard level, lifting construction person works efficiency, promote safety management in construction site level, the management in all directions of engineering construction can be realized and perform examination, the features such as the construction quality of General Promotion project of transmitting and converting electricity and safety management level.
Accompanying drawing explanation
Fig. 1 is intelligent auxiliary tube Ore-controlling Role composition frame chart described in the utility model.
Fig. 2 is that intelligent auxiliary tube Ore-controlling Role described in the utility model uses process flow diagram at the scene.
Embodiment
Below in conjunction with accompanying drawing, the utility model is described in detail: shown in Fig. 1, project of transmitting and converting electricity described in the utility model is constructed intelligent auxiliary tube Ore-controlling Role, it is primarily of main frame, mobile platform terminal and utility appliance composition, it is characterized in that described main frame is as creating newly built construction, managing existing engineering; To each mobile platform terminal distribution task, and the master data that each mobile platform terminal returns is integrated and stored; Described main frame is configured with multiple mobile platform terminal connected by local area network wireless communication system, described mobile platform terminal is an operation project of transmitting and converting electricity construction intelligence-aided project manage-ment system client, and after completing item by item the task of main frame distribution, return data is to main frame.
Described utility appliance at least comprises a bluetooth scanning and robs and a bar code printer, mobile platform terminal and bluetooth scan to rob corresponding configuration and can accept bluetooth and scan the input of robbing, and automatically identify numbering equipment, check equipment installation progress, installation quality, safety work situation; Working-yard Preventive Control of Dangerous Spot measure, installation procedure quality, construction operation safety, acceptance of work situation are taken pictures and touched input record, and can send short messages and inform and specify responsible official current project progress.
Described bar code printer corresponding configuration is in described main frame, and equipment bar code is being robbed input mobile platform terminal by bluetooth scanning and after being uploaded to main frame, printing relevant device bar code by described bar code printer; Described main frame is server end.
Number in the figure has: project of transmitting and converting electricity construction intelligence-aided project manage-ment system 1; Hardware system 2; Software systems 3; Main frame (server)+mobile platform (handheld terminal)+utility appliance is adopted to form 4; Adopt C/S model and client and server structure, the two exchanges data 5 by LAN (Local Area Network).
Shown in Fig. 2, one utilizes described project of transmitting and converting electricity intelligent auxiliary tube Ore-controlling Role of constructing to carry out management-control method, described management-control method is the Organization And Management's requirement according to construction of power transmission and transformation engineering project, project is divided into project's earlier stage, project construction, the project acceptance inspection three aspects, specifically:
(1) project's earlier stage, described project's earlier stage comprises two parts, and one is that engineering establishment and system each module primary data are set up and each management clause, special construction plan, the arrangement of the files such as job instruction and formulation; Two is engineering site security civilization standardized construction and Preventive Control of Dangerous Spot carrying out measures.
(2) project construction, described project construction comprises three parts, one be equipment march into the arena in place unpack, bar code make; Two is the Installation and Debugging of equipment standard equalization; Three is site safety task managements.
(3) acceptance of work, after all standard equalization task completes, enter acceptance stage, regulation is checked and accepted according to Guo Wang company and three grades, company of province, inspector, according to the final acceptance of construction flow process pointed out in mobile platform terminal, carries out standardization examination to installation work quality, defect of checking on the quality, propose reform advice, and assign to each person liable by management system; Person liable rectifies and improves according to suggestion, and by rectification situation input system, after to be confirmed, this grade of checking and accepting can complete, and then starts next stage checking and accepting; After checking and accepting terminates, submit completion report of construction work to.
The utility model is preferably: in described (1) project's earlier stage, specifically comprise:
1. engineering duty creates, after construction task is assigned, the file such as project profile, special construction plan, all kinds of job instruction, all kinds of construction management systems carries out arranging, collecting, and the document management module provided based on system is deleted, increase, upgrade certain engineering management fileinfo;
By the inspection of the scene of a crime, incorporation engineering work on the spot actual conditions, the security civilization standardized construction module provided based on system is formulated certain engineering safety civilization markization and is required provision; Certain engineering Preventive Control of Dangerous Spot measure requirement provision is formulated based on duration Preventive Control of Dangerous Spot measure in early stage module; Certain Engineering Standardization job requirements provision is formulated based on standardized work flows control module and engineering site equipment situation;
According to project management needs, set up construction project department, identify project management, workmen; According to the engineering management functional distribution system account authority of everyone; The personnel's file store provided according to system is deleted, increase, upgrade management, workmen's archives of certain engineering project of establishment; According to Engineering Project Construction character, project security management requirement, based on the engineering risk management and control requirement that system provides, delete, increase, upgrade certain engineering risk management and control measure of formation requirement provision.
2. project's earlier stage task closed loop is implemented, the engineering safety standard of civilization construction requirement provided according to system and engineering site Preventive Control of Dangerous Spot measure provision, site layout project construction is carried out in contrast one by one, employing digital photograph is the implementation of conditions of means record every requirement and measure provision, and forms closed loop management.Lead back to server after prerequisite task completes, and it is qualified to carry out onsite acceptance by project manager.After only completing above-mentioned steps, just carry out the task of project construction phase, therefore ensured that the construction of engineering safety standard of civilization and Preventive Control of Dangerous Spot carrying out measures are to crucial point;
In described (2) project construction, specifically comprise:
1. equipment bar code makes, electrical equipment march into the arena in place after, generated corresponding equipment installation management by work responsible official hand-held intelligent terminal encode based on each equipment factory number, the date of production, and uploaded onto the server by WLAN (wireless local area network), print corresponding equipment bar code by bar-code printer, be affixed on each equipment fixed position.Rely on bluetooth scanning technique, work responsible official or project manager can be inquired about by handheld terminal at any time and supervise per unit installation progress and quality, constructability Liability Retroact;
2. equipment standard operation Installation and Debugging, in construction process, the construction task that work responsible official arranges according to hand-held intelligent terminal system, the requirement contrasting corresponding operation and standard, rulyly carry out standardized work, by each stage duty of the form record of digital photograph.After per stage end-of-job, confirmation must be checked and accepted through operation responsible official, and acceptance information is inputted handheld terminal and next step operation can be proceeded to after uploading onto the server, guarantee engineering construction quality controlled, can control, in control.Meanwhile, in work progress, work responsible official can the job instruction of reference device Installation and Debugging at any time, special construction plan, and the files such as all kinds of construction operation handbooks, can make construction procedure normative and reasonable more, evidence-based;
3. site safety task management, in construction task implementation process, determines every work responsible official by project administrator based on personnel's archive database that system provides.In work progress, work responsible official fills in by hand-held intelligent terminal that construction station class meeting is parallel tells somebody what one's real intentions are.Construction task is issued by project of transmitting and converting electricity construction intelligence-aided project manage-ment system, work responsible official fills in construction operation ticket on hand-held intelligent terminal, select there are the personnel of respective attributes as construction working class member (if the current attribute of workmen does not meet construction operation requirement based on workmen's archive database, then cannot be added to construction operation class member), and carry out safely, confide a technological secret, and there are personnel that construction operation signs and issues attribute carry out the identification of construction operation ticket and sign and issue;
Need after a certain construction task completes to submit complete report or termination construction operation ticket to by handheld terminal, and system that information is uploaded onto the server, just can leave construction area after device system feedback corresponding information to be serviced.
Word content shown in Fig. 2 is the content of the utility model embodiment.
The utility model has can improve construction technology standard level, lifting construction person works efficiency, promote safety management in construction site level, the management in all directions of engineering construction can be realized and perform examination, the features such as the construction quality of General Promotion project of transmitting and converting electricity and safety management level.

Claims (3)

1. project of transmitting and converting electricity is constructed an intelligent auxiliary tube Ore-controlling Role, and it is primarily of main frame, mobile platform terminal and utility appliance composition, it is characterized in that described main frame is as establishment newly built construction, manage existing engineering; To each mobile platform terminal distribution task, and the master data that each mobile platform terminal returns is integrated and stored; Described main frame is configured with multiple mobile platform terminal connected by local area network wireless communication system, described mobile platform terminal is an operation project of transmitting and converting electricity construction intelligence-aided project manage-ment system client, and after completing item by item the task of main frame distribution, return data is to main frame.
2. project of transmitting and converting electricity according to claim 1 is constructed intelligent auxiliary tube Ore-controlling Role, it is characterized in that described utility appliance at least comprises a bluetooth scanning and robs and a bar code printer, mobile platform terminal and bluetooth scan to rob corresponding configuration and can accept bluetooth and scan the input of robbing, and automatically identify numbering equipment, check equipment installation progress, installation quality, safety work situation; Working-yard Preventive Control of Dangerous Spot measure, installation procedure quality, construction operation safety, acceptance of work situation are taken pictures and touched input record, and can send short messages and inform and specify responsible official current project progress.
3. project of transmitting and converting electricity according to claim 2 is constructed intelligent auxiliary tube Ore-controlling Role, it is characterized in that described bar code printer corresponding configuration is in described main frame, equipment bar code is being robbed input mobile platform terminal by bluetooth scanning and after being uploaded to main frame, is printing relevant device bar code by described bar code printer; Described main frame is server end.
CN201420645454.XU 2014-11-03 2014-11-03 A kind of project of transmitting and converting electricity is constructed intelligent auxiliary tube Ore-controlling Role Expired - Fee Related CN204680051U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420645454.XU CN204680051U (en) 2014-11-03 2014-11-03 A kind of project of transmitting and converting electricity is constructed intelligent auxiliary tube Ore-controlling Role

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420645454.XU CN204680051U (en) 2014-11-03 2014-11-03 A kind of project of transmitting and converting electricity is constructed intelligent auxiliary tube Ore-controlling Role

Publications (1)

Publication Number Publication Date
CN204680051U true CN204680051U (en) 2015-09-30

Family

ID=54179726

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420645454.XU Expired - Fee Related CN204680051U (en) 2014-11-03 2014-11-03 A kind of project of transmitting and converting electricity is constructed intelligent auxiliary tube Ore-controlling Role

Country Status (1)

Country Link
CN (1) CN204680051U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107622546A (en) * 2017-08-29 2018-01-23 石河子开发区天业化工有限责任公司 A kind of method that intelligent technical precaution management and control electric control chamber is screened based on Quick Response Code identity
CN111105217A (en) * 2019-12-31 2020-05-05 孙杰 Power transmission line corridor safety construction operation management and control system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107622546A (en) * 2017-08-29 2018-01-23 石河子开发区天业化工有限责任公司 A kind of method that intelligent technical precaution management and control electric control chamber is screened based on Quick Response Code identity
CN111105217A (en) * 2019-12-31 2020-05-05 孙杰 Power transmission line corridor safety construction operation management and control system

Similar Documents

Publication Publication Date Title
CN104700192A (en) Aided intelligent management and control system for power transmission and transformation project and management and control method thereof
CN106815681B (en) Transformer substation secondary equipment closed-loop management platform based on two-dimensional code and management system thereof
CN105449867A (en) Visual operation process monitoring mistake precaution system and control method
CN106485298A (en) A kind of equipment routing inspection maintaining method based on Quick Response Code
CN103035041A (en) Novel field device inspection system and inspection method thereof
CN102968748A (en) Field comprehensive maintenance system for power distribution network electrical equipment
CN203217621U (en) On-site comprehensive maintenance system of electrical equipment for distribution network
CN104573971A (en) Metal mine underground safety digital management system based on radio frequency and WIFI technology
CN104978696A (en) Electronic acceptance and handover method based on BIM technology
CN104076767B (en) Railway signal equipment overhauling control system and method
CN104902011A (en) Overhauling operation control method based on mobile terminal
CN105243440A (en) Marketing mobile working platform based paperless office on-site working method
CN104463297A (en) Asset two-dimensional code identification application method and device structure
CN103177327A (en) Comprehensive management system for low-voltage power operations based on B/S (browser/server) and C/S (client/server) architectures
CN104732345A (en) Supervision and management information system used for field management in power transmission and transformation engineering
CN102938101A (en) Method for implementing mobile operation of low-voltage distribution region based on intelligent mobile terminal
CN102594604A (en) Operation and maintenance management system and method
CN105098982A (en) On-pole switch control system and method
CN106845834A (en) Transmission line of electricity hidden danger management method and system based on mobile phone A PP
CN204680051U (en) A kind of project of transmitting and converting electricity is constructed intelligent auxiliary tube Ore-controlling Role
CN105184519A (en) Standardized safety operation tracing management system
CN113191591A (en) On-site monitoring method for electric power operating personnel
CN110751454A (en) Cable accessory installation process control system and method
CN105576832A (en) Sub-station simulation and transmission system and method of substation automation system
CN106779100A (en) A kind of elevator repair and maintenance handheld terminal and its application method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150930

Termination date: 20201103