CN204558683U - A kind of parallel groove clamp - Google Patents

A kind of parallel groove clamp Download PDF

Info

Publication number
CN204558683U
CN204558683U CN201520258253.9U CN201520258253U CN204558683U CN 204558683 U CN204558683 U CN 204558683U CN 201520258253 U CN201520258253 U CN 201520258253U CN 204558683 U CN204558683 U CN 204558683U
Authority
CN
China
Prior art keywords
splint
groove
hole
screw rod
lower plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520258253.9U
Other languages
Chinese (zh)
Inventor
赵臣
仵宗生
高勇
方晋东
陈硕
李国昌
刘宗杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201520258253.9U priority Critical patent/CN204558683U/en
Application granted granted Critical
Publication of CN204558683U publication Critical patent/CN204558683U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型公开了一种并沟线夹,包括上夹板、至少一个下夹板、至少一个加长螺丝杆至少一个固定螺母和至少一个特制插板,上夹板和下夹板对应卡住作业导线处分别有凹槽,中间分别开有上中部卡槽和下中部卡槽,并利用特制插板穿过加长螺丝杆固定上夹板和下夹板。本实用新型工作时,加长螺丝杆的采用扩大了作业导线的适用范围,根据需要可以具体确定下夹板的数量;同时实现预装并沟夹与作业导线便捷、稳妥的固装和匹配,节省了高空作业时间,提高了高空作业的安全度。

The utility model discloses a parallel ditch line clamp, which comprises an upper splint, at least one lower splint, at least one elongated screw rod, at least one fixing nut and at least one special inserting plate. There are grooves in the middle of which there are upper and middle card slots and lower middle card slots respectively, and the upper and lower splints are fixed by using a special insert plate through the lengthened screw rod. When the utility model works, the use of the extended screw rod expands the scope of application of the working wire, and the number of the lower splints can be specifically determined according to the needs; at the same time, the pre-installed groove clamp and the working wire are conveniently and securely fixed and matched, saving High-altitude operation time improves the safety of high-altitude operations.

Description

一种并沟线夹A parallel ditch clamp

技术领域technical field

本实用新型涉及电力器材技术领域,尤其是一种并沟线夹。The utility model relates to the technical field of electric equipment, in particular to a ditch parallel clip.

背景技术Background technique

目前,现有技术中采用的并沟线夹包括的零件多、组件分散,在实际的安装过程中,当需要安装的数量较多时,由于并沟线夹的组件分散,造成安装过程非常繁琐,同时由于分流导线采用钢芯铝绞线硬度大、不易弯曲,引流线的长短不一,即分流导线与引流线的弧度不一致等一系列弊端的存在,造成施工工人往往会在高空风力较大的情况下进行高空作业时,线路会左右摆动,安装时间长,从而使架空导线上的工作效率非常低,甚至发生高空安全生产问题。At present, the parallel groove clamps used in the prior art include many parts and scattered components. In the actual installation process, when the number of installations is large, the installation process is very cumbersome due to the scattered components of the parallel groove clamps. At the same time, due to the existence of a series of disadvantages such as the diversion wire adopting steel-cored aluminum stranded wire, which is hard and not easy to bend, and the length of the drainage wire is different, that is, the radians of the shunt wire and the drainage wire are inconsistent, construction workers often work at high altitudes where the wind is strong. When working at heights, the line will swing left and right, and the installation time will be long, so that the work efficiency on the overhead wires will be very low, and even high-altitude safety production problems will occur.

实用新型内容Utility model content

本实用新型的目的是为了克服上述现有技术的不足,提供一种并沟线夹,实现对分流线和导线的便捷、稳妥的固定,提高高空作业的安全性和操作效率。The purpose of this utility model is to overcome the shortcomings of the above-mentioned prior art, and provide a parallel ditch wire clamp to realize convenient and secure fixing of shunt wires and wires, and improve the safety and operating efficiency of high-altitude operations.

为实现上述目的,本实用新型采用下述技术方案:In order to achieve the above object, the utility model adopts the following technical solutions:

一种并沟线夹,包括上夹板、至少一个下夹板、至少一个加长螺丝杆至少一个固定螺母和至少一个特制插板;所述上夹板上开有至少一个孔、下表面上每一个孔两侧都分别开有凹槽,所述下夹板中心开一个孔、上表面的两侧分别开有凹槽,所述加长螺丝杆依次穿过所述上夹板和所述下夹板的孔,所述固定螺母固定在所述加长螺丝杆的另一端;所述特制插板中间弯曲成350°-360°,所述特制插板的中间穿过所述加长螺丝杆来支撑在所述上夹板和所述下夹板之间。A parallel groove clamp, including an upper splint, at least one lower splint, at least one elongated screw rod, at least one fixing nut and at least one special inserting plate; at least one hole is opened on the upper splint, and each hole on the lower surface is two The sides are respectively provided with grooves, a hole is opened in the center of the lower splint, and grooves are respectively opened on both sides of the upper surface, and the elongated screw rod passes through the holes of the upper splint and the lower splint in sequence. The fixing nut is fixed on the other end of the lengthened screw rod; the middle of the special board is bent to 350°-360°, and the middle of the special board passes through the lengthened screw rod to support the upper splint and the Between the lower splints.

在上夹板的下表面在其孔的两侧均有凸起,两个凸起与其之间的面形成一个上中部卡槽;所述下夹板的上表面在其孔的两侧均有凸起,两个凸起与其之间的面形成下中部卡槽,所述特制插板的中间穿过所述加长螺丝杆通过所述上中部卡槽和所述下中部卡槽来固定所述的上夹板和所述的下夹板。There are protrusions on both sides of the hole on the lower surface of the upper splint, and the two protrusions and the surface between them form an upper middle part slot; the upper surface of the lower splint has protrusions on both sides of the hole , the two protrusions and the surface between them form a lower middle card slot, and the middle of the special board passes through the elongated screw rod to fix the upper middle card slot and the lower middle card slot. splint and said lower splint.

进一步地,上夹板的孔与所述下夹板的数量、所述加长螺丝杆的数量和所述固定螺母的数量相同。Further, the number of holes of the upper splint is the same as that of the lower splint, the number of the elongated screw rods and the number of the fixing nuts.

进一步地,加长螺丝杆的螺帽与所述的上夹板之间设有弹簧垫圈。Further, a spring washer is provided between the nut of the elongated screw rod and the upper splint.

进一步地,固定螺母与所述的下夹板之间设有平垫片。Further, a flat washer is provided between the fixing nut and the lower splint.

进一步地,凹槽的内表面呈锯齿状。Further, the inner surface of the groove is serrated.

进一步地,下夹板的数量为1个。Further, the number of the lower splint is one.

进一步地,下夹板的数量为4个。Further, there are four lower splints.

本实用新型的有益效果:The beneficial effects of the utility model:

1.预装好的并沟夹能够与作业导线便捷、稳妥的固装,同时预装好的并沟夹能够与作业导线完全匹配,节省了高空作业时间,提高了安装工人的高空作业的安全度。1. The pre-installed paralleling clamp can be conveniently and securely fixed with the working wire, and at the same time, the pre-installed paralleling clamp can completely match the working wire, which saves the time of high-altitude work and improves the safety of the installation workers for high-altitude work Spend.

2.加长螺丝杆的采用适用于更大线径的压紧作业导线,增加了并沟夹的适用范围。2. The use of the extended screw rod is suitable for the compression work wire with a larger wire diameter, which increases the scope of application of the groove clamp.

3.特制插板的固定,有利于上夹板和下夹板的预先固定,为安装提供便利。3. The fixing of the special inserting plate is conducive to the pre-fixing of the upper splint and the lower splint, and provides convenience for installation.

附图说明Description of drawings

图1为本实用新型采用一个下夹板时的结构图;Fig. 1 is the structural diagram when the utility model adopts a lower splint;

图2为本实用新型特制插板的侧视图;Fig. 2 is the side view of the utility model special board;

图3为本实用新型采用四个下夹板时的结构图;Fig. 3 is the structural diagram when the utility model adopts four lower splints;

其中1.弹簧垫圈,2.加长螺丝杆,3.上夹板,4.凹槽,5.下中部卡槽,6.下夹板,7.固定螺母,8.平垫片,9.特制插板,10.上中部卡槽。1. Spring washer, 2. Extended screw rod, 3. Upper splint, 4. Groove, 5. Lower middle card slot, 6. Lower splint, 7. Fixing nut, 8. Flat washer, 9. Special insert plate , 10. Upper middle card slot.

具体实施方式Detailed ways

下面结合附图和实施例对本实用新型进一步说明。Below in conjunction with accompanying drawing and embodiment the utility model is further described.

实施例1Example 1

如图1所示,一种并沟线夹,包括上夹板3、至少一个下夹板6、至少一个加长螺丝杆2、至少一个固定螺母7和至少一个特制插板9;所述上夹板3上开有至少一个孔、下表面上每一个孔两侧都分别开有凹槽4,所述下夹板6中心开一个孔、上表面的两侧分别开有凹槽,所述加长螺丝杆2依次穿过所述上夹板3和所述下夹板6的孔,所述固定螺母7固定在所述加长螺丝杆2的另一端;所述特制插板9中间弯曲成350°-360°,所述下夹板6的上表面在其孔的两侧有凸起形成下中部卡槽5,特制插板9的中间穿过所述加长螺丝杆通过所述上中部卡槽10和所述下中部卡槽5来固定所述的上夹板3和所述的下夹板6;As shown in Figure 1, a parallel groove clamp includes an upper clamping plate 3, at least one lower clamping plate 6, at least one elongated screw rod 2, at least one fixing nut 7 and at least one special inserting plate 9; on the upper clamping plate 3 There is at least one hole, grooves 4 are respectively opened on both sides of each hole on the lower surface, a hole is opened in the center of the lower splint 6, grooves are respectively opened on both sides of the upper surface, and the lengthened screw rod 2 is in turn Through the holes of the upper splint 3 and the lower splint 6, the fixing nut 7 is fixed on the other end of the elongated screw rod 2; The upper surface of the lower splint 6 has protrusions on both sides of the hole to form the lower middle draw-in groove 5, and the middle of the special inserting plate 9 passes through the elongated screw rod and passes through the upper middle draw-in groove 10 and the lower middle draw-in groove. 5 to fix the upper splint 3 and the lower splint 6;

进一步地,上夹板3的孔与所述下夹板6的数量、所述加长螺丝杆2的数量和所述固定螺母7的数量相同。Further, the number of holes of the upper splint 3 is the same as that of the lower splint 6 , the number of the elongated screw rods 2 and the number of the fixing nuts 7 .

进一步地,加长螺丝杆2的螺帽与所述的上夹板3之间设有弹簧垫圈。Further, a spring washer is provided between the nut of the elongated screw rod 2 and the upper splint 3 .

进一步地,固定螺母7与所述的下夹板6之间设有平垫片8。Further, a flat washer 8 is provided between the fixing nut 7 and the lower clamping plate 6 .

进一步地,凹槽4的内表面呈锯齿状。Further, the inner surface of the groove 4 is serrated.

进一步地,下夹板6的数量为1个。Further, the number of the lower splint 6 is one.

特制插板9是一个较长的板,沿其长度方向中间对折、弯曲成350°-360°,上夹板的下表面在其孔的两侧有凸起形成一个上中部卡槽,下夹板的上表面在其孔的两侧有凸起形成下中部卡槽,特制插板9利用中部卡槽固定上夹板和下夹板。The special board 9 is a longer board, which is folded in half along its length and bent to 350°-360°. The lower surface of the upper splint has protrusions on both sides of the hole to form an upper middle card slot, and the lower splint The upper surface has protrusions on both sides of its hole to form the lower middle part of the draw-in groove, and the special inserting plate 9 utilizes the middle part of the draw-in groove to fix the upper splint and the lower splint.

本实施例中下夹板的数量有1个,通常将上夹板3和下夹板6设置成上下对应的、大小相等的,二者相对应的凹槽部分用于卡住作业导线;在地面完成并沟夹的预装,即通过将加长螺丝杆2的螺帽下方放上弹簧垫圈1,然后将加长螺丝杆2依次穿过上、下夹板的孔,在螺杆的最下端放上平垫片8,并拧入固定螺母7,从而实现并沟夹的安装,并将特制插板9穿过加长螺丝杆2固定上夹板3和下夹板6。In this embodiment, there is one lower splint. Usually, the upper splint 3 and the lower splint 6 are set to correspond up and down and are equal in size. The pre-installation of the groove clamp is to put the spring washer 1 under the nut of the extended screw rod 2, then pass the extended screw rod 2 through the holes of the upper and lower splints in turn, and put a flat washer 8 at the bottom end of the screw rod , and screw in the fixing nut 7, so as to realize the installation of the groove clamp, and pass the special insert plate 9 through the lengthened screw rod 2 to fix the upper splint 3 and the lower splint 6.

实施例2Example 2

如图2所示,一种并沟线夹,包括上夹板3、至少一个下夹板6、至少一个加长螺丝杆2、至少一个固定螺母7和至少一个特制插板9;所述上夹板3上开有至少一个孔、下表面上每一个孔两侧都分别开有凹槽4,所述下夹板6中心开一个孔、上表面的两侧分别开有凹槽,所述加长螺丝杆2依次穿过所述上夹板3和所述下夹板6的孔,所述固定螺母7固定在所述加长螺丝杆2的另一端;所述特制插板9中间弯曲成350°-360°,所述下夹板6的上表面在其孔的两侧有凸起形成下中部卡槽5,特制插板9的中间穿过所述加长螺丝杆通过所述上中部卡槽10和所述下中部卡槽5来固定所述的上夹板3和所述的下夹板6。As shown in Figure 2, a parallel groove clamp includes an upper clamping plate 3, at least one lower clamping plate 6, at least one elongated screw rod 2, at least one fixing nut 7 and at least one special inserting plate 9; on the upper clamping plate 3 There is at least one hole, grooves 4 are respectively opened on both sides of each hole on the lower surface, a hole is opened in the center of the lower splint 6, grooves are respectively opened on both sides of the upper surface, and the lengthened screw rod 2 is in turn Through the holes of the upper splint 3 and the lower splint 6, the fixing nut 7 is fixed on the other end of the elongated screw rod 2; The upper surface of the lower splint 6 has protrusions on both sides of the hole to form the lower middle draw-in groove 5, and the middle of the special inserting plate 9 passes through the elongated screw rod and passes through the upper middle draw-in groove 10 and the lower middle draw-in groove. 5 to fix the upper splint 3 and the lower splint 6.

进一步地,上夹板3的孔与所述下夹板6的数量、所述加长螺丝杆2的数量和所述固定螺母7的数量相同。Further, the number of holes of the upper splint 3 is the same as that of the lower splint 6 , the number of the elongated screw rods 2 and the number of the fixing nuts 7 .

进一步地,加长螺丝杆2的螺帽与所述的上夹板3之间设有弹簧垫圈。Further, a spring washer is provided between the nut of the elongated screw rod 2 and the upper splint 3 .

进一步地,固定螺母7与所述的下夹板6之间设有平垫片8。Further, a flat washer 8 is provided between the fixing nut 7 and the lower clamping plate 6 .

进一步地,凹槽4的内表面呈锯齿状,可以增大凹槽4与作业导线之间的摩擦力。Furthermore, the inner surface of the groove 4 is serrated, which can increase the friction between the groove 4 and the working wire.

进一步地,下夹板6的数量为4个。Further, the number of lower splints 6 is four.

本实施例中下夹板的数量为4个,相应地,加长螺丝杆、固定螺母和上表面孔的数量都为4个,这样在固定的高空作业导线长度较长,不易脱落;这样的话,上夹板的凹槽与下夹板上的凹槽上下对应,用于固定作业导线;在地面完成并沟夹的预装,即通过将加长螺丝杆2的螺帽下方放上弹簧垫圈1,然后将加长螺丝杆2依次穿过上、下夹板的孔,在螺杆的最下端放上平垫片8,并拧入固定螺母7,从而实现并沟夹的安装,并将特制插板9穿过加长螺丝杆2固定上夹板3和下夹板6。In this embodiment, the number of lower splints is 4, and correspondingly, the number of lengthened screw rods, fixing nuts and upper surface holes is 4, so that the length of the fixed high-altitude operation wire is longer and it is not easy to fall off; in this case, the upper The groove of the splint corresponds to the groove of the lower splint up and down, and is used to fix the working wire; the pre-installation of the parallel groove clamp is completed on the ground, that is, the spring washer 1 is placed under the nut of the extension screw rod 2, and then the extension The screw rod 2 passes through the holes of the upper and lower splints in turn, put a flat washer 8 on the bottom end of the screw rod, and screw in the fixing nut 7, so as to realize the installation of the parallel groove clamp, and pass the special insert plate 9 through the extension screw The rod 2 fixes the upper splint 3 and the lower splint 6 .

本实用新型工作前,上夹板和下夹板的安装距离可根据固定作业导线的线径预先确定,用来保证预装完成后的并沟夹能够与作业导线完全匹配。Before the utility model works, the installation distance between the upper splint and the lower splint can be determined in advance according to the wire diameter of the fixed working wire, which is used to ensure that the doubling clamp after pre-installation can completely match the working wire.

以上所述仅是本实用新型的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本实用新型原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本实用新型的保护范围。The above is only a preferred embodiment of the utility model, it should be pointed out that for those of ordinary skill in the art, without departing from the principle of the utility model, some improvements and modifications can also be made, these improvements and Retouching should also be regarded as the scope of protection of the present utility model.

Claims (8)

1. a parallel groove clamp, is characterized in that, comprises train wheel bridge, at least one lower plate, at least one lengthening at least one hold-down nut of lead screw and at least one special plate; Described train wheel bridge has each both sides, hole at least one hole, lower surface and have groove, a hole is opened at described lower plate center, the both sides of upper surface have groove, described lengthening lead screw passes the hole of described train wheel bridge and described lower plate successively, and described hold-down nut is fixed on the other end of described lengthening lead screw; Described special plate bent intermediate becomes 350 °-360 °, and the centre of described special plate is supported on described train wheel bridge and described lower plate through described lengthening lead screw.
2. parallel groove clamp as claimed in claim 1, it is characterized in that, the lower surface of described train wheel bridge all has projection in the both sides in its hole, and two projections and the face between it form a upper middle part draw-in groove; The upper surface of described lower plate all has projection in the both sides in its hole, two projections and the face between it form lower middle part draw-in groove, and the centre of described special plate fixes described train wheel bridge and described lower plate through described lengthening lead screw by described upper middle part draw-in groove and described lower middle part draw-in groove.
3. parallel groove clamp as claimed in claim 1, it is characterized in that, the hole of described train wheel bridge is identical with the quantity of described hold-down nut with the quantity of the quantity of described lower plate, described lengthening lead screw.
4. parallel groove clamp as claimed in claim 1, is characterized in that, be provided with spring washer between the nut of described lengthening lead screw and described train wheel bridge.
5. parallel groove clamp as claimed in claim 1, is characterized in that, be provided with flat shim between described hold-down nut and described lower plate.
6. parallel groove clamp as claimed in claim 1, is characterized in that, the inner surface indentation of described groove.
7. parallel groove clamp as claimed in claim 1, it is characterized in that, the quantity of described lower plate is 1.
8. parallel groove clamp as claimed in claim 1, it is characterized in that, the quantity of described lower plate is 4.
CN201520258253.9U 2015-04-24 2015-04-24 A kind of parallel groove clamp Expired - Fee Related CN204558683U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520258253.9U CN204558683U (en) 2015-04-24 2015-04-24 A kind of parallel groove clamp

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520258253.9U CN204558683U (en) 2015-04-24 2015-04-24 A kind of parallel groove clamp

Publications (1)

Publication Number Publication Date
CN204558683U true CN204558683U (en) 2015-08-12

Family

ID=53833761

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520258253.9U Expired - Fee Related CN204558683U (en) 2015-04-24 2015-04-24 A kind of parallel groove clamp

Country Status (1)

Country Link
CN (1) CN204558683U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106099805A (en) * 2016-08-05 2016-11-09 苏州华安普电力科技股份有限公司 A kind of overhead transmission line lightning conducter clamping plate
CN110842641A (en) * 2019-10-12 2020-02-28 温州辰星自动化系统有限公司 Intelligent sawing system
CN112310675A (en) * 2020-10-12 2021-02-02 亿嘉和科技股份有限公司 Live lap joint compatible wire clamp

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106099805A (en) * 2016-08-05 2016-11-09 苏州华安普电力科技股份有限公司 A kind of overhead transmission line lightning conducter clamping plate
CN106099805B (en) * 2016-08-05 2019-02-05 苏州华安普电力科技股份有限公司 A kind of lightning-arrest wireplint of overhead transmission line
CN110842641A (en) * 2019-10-12 2020-02-28 温州辰星自动化系统有限公司 Intelligent sawing system
CN110842641B (en) * 2019-10-12 2021-07-23 温州辰星自动化系统有限公司 Intelligent sawing system
CN112310675A (en) * 2020-10-12 2021-02-02 亿嘉和科技股份有限公司 Live lap joint compatible wire clamp
CN112310675B (en) * 2020-10-12 2022-05-20 亿嘉和科技股份有限公司 Live lap joint compatible wire clamp

Similar Documents

Publication Publication Date Title
CN204558683U (en) A kind of parallel groove clamp
CN203949939U (en) A kind of clamp-type insulating support
CN204144837U (en) Ready-package spool fixture
CN203589239U (en) Wiring terminal fixing device
CN203729574U (en) Horizontal truss of scaffold
CN205839682U (en) A kind of drainage system of hydraulic engineering
CN203800252U (en) Wire terminal sleeve
CN203351131U (en) Overlying type phase brand fastening hardware
CN204062171U (en) A kind of feeder clip
CN203481695U (en) Safe and drop-proof grounding wire clamp convenient to maintain
CN204130507U (en) A kind of diode twines payment to a porter fixture
CN203352093U (en) Plug-in type phase board fastening fitting
CN203374582U (en) Connecting piece of aluminum angle dry hanging system
CN204123303U (en) A kind of clamping device of optical relay manufacturing equipment
CN206494967U (en) A vacuum coating screw fixture
CN203437939U (en) Clamp for punching square aluminum pipe
CN209175610U (en) A kind of Circular tube fixer
CN203271154U (en) Self-fixing type steel strand binding device
CN201837664U (en) Lug plate for electric energy meter
CN204651809U (en) Tube type bus fixed contact guide ring Rapid manufacturing device of high
CN206689955U (en) A kind of blade positioning tooling fixture
CN204076080U (en) A kind of terminal plate fixture
CN204008718U (en) A kind of clamp-type insulating support
CN207896904U (en) Auxiliary installation device and steam-electric power plant
CN204771037U (en) Automatic device is changed to welding machine interconnection strip

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150812

Termination date: 20160424