CN206020766U CN201621059486.7U CN201621059486U CN206020766U CN 206020766 U CN206020766 U CN 206020766U CN 201621059486 U CN201621059486 U CN 201621059486U CN 206020766 U CN206020766 U CN 206020766U
Authority
CN
China
Prior art keywords
insulation
opgw
transmission line
power transmission
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621059486.7U
Other languages
Chinese (zh)
Inventor
魏素芬
张悦
刘汉枝
王晓霞
赵沁
徐可
谭晓平
张晓华
王拥军
张文争
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Xiaogan Power Supply Co of State Grid Hubei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Xiaogan Power Supply Co of State Grid Hubei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Xiaogan Power Supply Co of State Grid Hubei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201621059486.7U priority Critical patent/CN206020766U/en
Application granted granted Critical
Publication of CN206020766U publication Critical patent/CN206020766U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

一种输电线路塔用OPGW绝缘引下紧固件,包括卡槽横坦,卡槽横坦上设有多个绝缘支柱安装咀,每个绝缘支柱安装咀上对应安装有绝缘支柱,绝缘支柱上设有光缆紧固机构。本实用新型提供的一种输电线路塔用OPGW绝缘引下紧固件,通过采用一个槽形横坦与多个绝缘支柱一体化安装,保证了输电线路塔内的OPGW缆绝缘引下的缆与缆、缆与塔体的绝缘间距,降低了工程建设成本,减少了上作业现场安装时间,组装方便,杜绝了脱缆及搭杆放电断股的问题,长期使用安全可靠,提高了输电线路OPGW缆的安全运行率。

An OPGW insulation lead-down fastener for a power transmission line tower, comprising a card slot horizontal tank, a plurality of insulating support mounting nozzles are arranged on the card slot horizontal tank, each insulating support mounting nozzle is correspondingly installed with an insulating support, and the insulating support is provided with a Equipped with cable fastening mechanism. The utility model provides an OPGW insulation down-lead fastener for a power transmission line tower. By adopting a groove-shaped horizontal tank and a plurality of insulating pillars for integrated installation, it ensures that the OPGW cable in the power transmission line tower is insulated. The insulation distance between cables, cables and towers reduces the cost of engineering construction, reduces the installation time on the job site, facilitates assembly, eliminates the problems of cable detachment and pole discharge and broken strands, and is safe and reliable for long-term use, improving the OPGW of transmission lines The safe operation rate of the cable.

Description

一种输电线路塔用OPGW绝缘引下紧固件An OPGW insulation downconductor fastener for transmission line towers

技术领域technical field

本实用新型涉及输电线路塔紧固件,尤其是一种输电线路塔用OPGW绝缘引下紧固件。The utility model relates to a fastener for a power transmission line tower, in particular to an OPGW insulation downlead fastener for a power transmission line tower.

背景技术Background technique

目前,国内高压、超高压输电线路架空OPGW光缆采用直接与线路塔体连接接地,引下缆采用金属夹具安装,不能利用感应电能。随着智能电网发展,拓展OPGW的绝缘安装工艺,充分利用OPGW感应电为输电线监测设备提供电能,推动智能电网全方位的新技术应用提供条件,输电线路OPGW绝缘引下是一个趋势。At present, overhead OPGW optical cables of domestic high-voltage and ultra-high-voltage transmission lines are directly connected to the ground of the line tower body, and the down-conductor cables are installed with metal fixtures, which cannot use induction power. With the development of smart grid, expanding the insulation installation process of OPGW, making full use of OPGW induction power to provide power for transmission line monitoring equipment, and promoting the application of new technologies in all aspects of smart grid to provide conditions, OPGW insulation of transmission lines is a trend.

发明内容Contents of the invention

本实用新型所要解决的技术问题是提供一种输电线路塔用OPGW绝缘引下紧固件,保证了输电线路塔内的OPGW缆绝缘引下的缆与缆、缆与塔体的绝缘间距,降低了工程建设成本,减少了上作业现场安装时间,组装方便,杜绝了脱缆及搭杆放电断股的问题。另外,还可满足在输电线路的OPGW上提取感应电能。The technical problem to be solved by the utility model is to provide a fastener for the OPGW insulation lead of the transmission line tower, which ensures the insulation distance between the cable and the cable and the cable and the tower body under the OPGW cable insulation lead in the transmission line tower, and reduces the The cost of engineering construction is reduced, the installation time on the job site is reduced, the assembly is convenient, and the problems of cable detachment and rod discharge and broken strands are eliminated. In addition, it can also meet the requirements of extracting inductive electric energy on the OPGW of the transmission line.

一种输电线路塔用OPGW绝缘引下紧固件,包括卡槽横坦,卡槽横坦上设有多个绝缘支柱安装咀,每个绝缘支柱安装咀上对应安装有绝缘支柱,绝缘支柱上设有光缆紧固机构。An OPGW insulating down-conductor fastener for transmission line towers, including a card slot horizontal tank, a plurality of insulating support mounting nozzles are arranged on the card slot horizontal tank, each insulating support mounting nozzle is correspondingly installed with an insulating support, and the insulating support is installed on the mounting nozzle. Equipped with cable fastening mechanism.

所述卡槽横坦为U型。The horizontal tank of the draw-in slot is U-shaped.

卡槽横坦的第一安装面上设有多个紧固螺栓,紧固螺栓顶端对应安装有垫片、底端通过双螺母锁紧;所述卡槽横坦的第二安装面上设有两个并排的绝缘支柱安装咀。A plurality of fastening bolts are arranged on the first mounting surface of the horizontal tank of the card slot, gaskets are installed on the top of the fastening bolts, and the bottom ends are locked by double nuts; the second mounting surface of the horizontal tank of the card slot is provided with Two side-by-side insulating posts mount the nozzle.

所述绝缘支柱安装咀上设有螺纹孔,螺纹孔中心设有螺纹柱,所述绝缘支柱下端对应设有外螺纹和内螺纹孔,绝缘支柱安装咀与绝缘支柱通过双层螺纹连接。The mounting nozzle of the insulating pillar is provided with a threaded hole, and the center of the threaded hole is provided with a threaded column. The lower end of the insulating pillar is correspondingly provided with an external thread and an internal threaded hole. The mounting nozzle of the insulating pillar is connected with the insulating pillar through double-layer threads.

所述光缆紧固机构包括引下缆紧固卡,引下缆紧固卡通过缆卡紧固螺栓锁紧。The optical cable fastening mechanism includes a down-conductor cable fastening card, and the down-conductor cable fastening card is locked by a cable clamp fastening bolt.

本实用新型一种输电线路塔用OPGW绝缘引下紧固件,具有以下技术效果:The utility model relates to an OPGW insulation down-conductor fastener for transmission line towers, which has the following technical effects:

1)、采用一个U型卡槽横坦与多个绝缘支柱一体化安装,无需调整双引下缆安装的间距,可并行进行OPGW双光缆接续绝缘引下缆紧固,减少了工程建设成本,提高了工程建设效率。另外,通过设置绝缘支柱,为在输电线路OPGW引下缆和架空缆上提取感应电能提供了条件,为智能电网普及在线监测的设备装置提供了电能,为输电线路及杆塔上应用监测智能设备创造了条件。1) Using a U-shaped card slot horizontal tank and multiple insulating supports for integrated installation, without adjusting the installation distance of double down-conductor cables, OPGW dual optical cables can be connected and fastened in parallel to insulated down-conductor cables, reducing engineering construction costs, Improve the efficiency of engineering construction. In addition, by setting insulating pillars, it provides conditions for extracting inductive electric energy on the transmission line OPGW downcomer and overhead cable, provides electric energy for the popularization of on-line monitoring equipment in the smart grid, and creates a new environment for the application of monitoring intelligent equipment on transmission lines and towers. conditions.

2)、通过设置可拆卸的卡槽横坦、绝缘支柱,方便现场组装、运输、更换及维修,提高了现场杆上作业的工作效率,组装简捷,施工方便。2) By setting detachable card slot horizontal tanks and insulating pillars, it is convenient for on-site assembly, transportation, replacement and maintenance, and improves the work efficiency of on-site pole operations. The assembly is simple and convenient for construction.

3)、可适应于500kV、750kV、1000kV各类电压等级的输电线路杆塔的OPGW绝缘引下技术方案。3) The OPGW insulation down-leading technical scheme that can be adapted to transmission line towers of various voltage levels of 500kV, 750kV, and 1000kV.

附图说明Description of drawings

下面结合附图和实施例对本实用新型作进一步说明:Below in conjunction with accompanying drawing and embodiment the utility model is further described:

图1为本实用新型的示意图。Fig. 1 is the schematic diagram of the utility model.

图2为本实用新型的示意图。Fig. 2 is the schematic diagram of the utility model.

图3为本实用新型中垫片的示意图(第一种)。Fig. 3 is a schematic diagram of the gasket in the present utility model (the first type).

图4为本实用新型中垫片的示意图(第二种)。Fig. 4 is a schematic diagram (the second type) of the gasket in the present invention.

图中:卡槽横坦1,绝缘支柱安装咀2,绝缘支柱3,紧固螺栓4,垫片5,双螺母6,螺纹孔7,螺纹柱8,引下缆紧固卡9,缆卡紧固螺栓10。In the figure: card slot horizontal tank 1, insulating support mounting nozzle 2, insulating support 3, fastening bolt 4, gasket 5, double nut 6, threaded hole 7, threaded post 8, downcomer fastening clamp 9, cable clamp Tighten the bolt 10.

具体实施方式detailed description

如图1-2所示,一种输电线路塔用OPGW绝缘引下紧固件,包括卡槽横坦1,卡槽横坦1上设有两个并排的绝缘支柱安装咀2,每个绝缘支柱安装咀2上对应安装有绝缘支柱3,绝缘支柱3上设有光缆紧固机构。由于该装置中采用两个绝缘支柱、两个光缆紧固机构,因此无需调整双引下缆安装的间距,可并行进行OPGW双光缆接续绝缘引下缆紧固,减少了工程建设成本,提高了工程建设效率。另外,采用专用支柱绝缘工艺,保证了杆塔与缆的绝缘间距,消除了缆搭在杆塔上产生放电电蚀,进而引起断股的问题。As shown in Figure 1-2, an OPGW insulation down-conductor fastener for a power transmission line tower includes a card slot horizontal tank 1, and the card slot horizontal tank 1 is provided with two side-by-side insulating pillar installation nozzles 2, each insulation Correspondingly, an insulating pillar 3 is installed on the pillar installation nozzle 2, and an optical cable fastening mechanism is arranged on the insulating pillar 3. Since the device adopts two insulating pillars and two optical cable fastening mechanisms, there is no need to adjust the installation distance of the double downcomer, and the OPGW double optical cable joint insulation downcomer can be fastened in parallel, which reduces the construction cost and improves the efficiency of the project. Engineering construction efficiency. In addition, the use of special pillar insulation technology ensures the insulation distance between the tower and the cable, and eliminates the problem of electric corrosion caused by the discharge of the cable on the tower, which in turn causes the problem of broken strands.

所述卡槽横坦1为U型(U型结构相对于S型结构节省材料),U型结构的侧面上设有多个紧固螺栓4,紧固螺栓4顶端对应安装有垫片5、底端通过双螺母6锁紧;所述U型结构的底面上设有两个并排的绝缘支柱安装咀2。由于U型结构的卡槽横坦长度可根据实际需要进行长度设计,因此可安装多个绝缘支柱,免去杆上反复调整缆与缆之间、缆与榙体之间安装间距,使安装工序更加简单、高效。另外,垫片5可设计为凸型结构,材质为弹性金属片或橡胶,凸型结构上部设有多个分割的连续块状或连续的三角凸起。当与杆塔内的横寸角钢接触时,可增大接触面,提高最大静摩擦力,防止卡槽横坦相对角钢滑动,松脱。The card slot horizontal tank 1 is U-shaped (the U-shaped structure saves material compared to the S-shaped structure), and a plurality of fastening bolts 4 are arranged on the side of the U-shaped structure, and gaskets 5 are installed on the top of the fastening bolts 4. The bottom end is locked by double nuts 6; two parallel insulating support mounting nozzles 2 are arranged on the bottom surface of the U-shaped structure. Since the length of the horizontal tank of the U-shaped structure can be designed according to the actual needs, multiple insulating pillars can be installed, eliminating the need to repeatedly adjust the installation distance between the cables and the cable and the body on the pole, making the installation process easier. Simpler and more efficient. In addition, the gasket 5 can be designed as a convex structure made of elastic metal sheet or rubber, and the upper part of the convex structure is provided with a plurality of segmented continuous blocks or continuous triangular protrusions. When in contact with the horizontal inch angle steel in the pole tower, the contact surface can be enlarged, the maximum static friction force can be improved, and the card slot horizontal tank can be prevented from sliding and loosening relative to the angle steel.

所述绝缘支柱安装咀2上设有螺纹孔7,螺纹孔7中心设有螺纹柱8,所述绝缘支柱3下端对应设有外螺纹和内螺纹孔,绝缘支柱安装咀2与绝缘支柱3通过双层螺纹连接。由于绝缘支柱安装咀2不仅与绝缘支柱3保持连接,而且还需要为绝缘支柱提供支撑力,因此需要保证连接紧密、不松脱。在螺纹孔7内增加一个螺纹柱8,由此可形成两套螺纹锁紧,增加牢靠性。而相对与固定一体化连接而言,增加了可拆卸的灵活性,方便现场组装、运输、更换及维修,提高了现场杆上作业的工作效率,组装简捷,施工方便。The mounting nozzle 2 of the insulating pillar is provided with a threaded hole 7, and the center of the threaded hole 7 is provided with a threaded pillar 8. The lower end of the insulating pillar 3 is correspondingly provided with an external thread and an internal thread hole, and the mounting nozzle 2 of the insulating pillar and the insulating pillar 3 pass through Double threaded connection. Since the insulating post installation nozzle 2 is not only kept connected with the insulating post 3, but also needs to provide supporting force for the insulating post, it is necessary to ensure that the connection is tight and not loose. A threaded column 8 is added in the threaded hole 7, thereby forming two sets of threaded locks to increase reliability. Compared with the fixed integrated connection, it increases the flexibility of detachment, facilitates on-site assembly, transportation, replacement and maintenance, improves the work efficiency of on-site pole operations, and is simple to assemble and convenient to construct.

所述光缆紧固机构包括引下缆紧固卡9,引下缆紧固卡9通过缆卡紧固螺栓10锁紧。杜绝了OPGW光缆因紧固不牢固引起的脱缆问题,降低了运维成本。The optical cable fastening mechanism includes a down-conductor cable fastening card 9 , and the down-conductor cable fastening card 9 is locked by a cable clamp fastening bolt 10 . It eliminates the detachment problem of OPGW optical cable caused by loose fastening, and reduces the operation and maintenance cost.

工作原理及过程:由于杆塔各个支撑构件均由角钢型材连接而成,这样可将该装置水平安装于杆塔内的横寸角钢上。具体操作过程为:首先,将水平结构的角钢与U型卡槽横坦1的卡槽扣合,拧紧螺栓,使角钢与卡槽横坦1紧密连接后通过双螺母锁死;然后,将绝缘支柱与绝缘支柱安装咀2螺纹锁紧;最后将OPGW引下缆置入引下缆紧固卡9中,用缆卡紧固螺栓10锁紧。Working principle and process: Since each supporting member of the tower is connected by angle steel profiles, the device can be installed horizontally on the horizontal inch angle steel in the tower. The specific operation process is as follows: first, fasten the angle steel of the horizontal structure with the slot of the U-shaped card slot horizontal tank 1, tighten the bolts so that the angle steel and the card slot horizontal tank 1 are tightly connected and then locked by double nuts; then, the insulation The pillar and the insulating pillar installation nozzle 2 are threaded and locked; finally, put the OPGW downconductor cable into the downconductor cable fastening card 9, and lock it with the cable clamp fastening bolt 10.

Claims (5)

1. a kind of power transmission line column draws lower securing member with OPGW insulation, it is characterised in that:Smooth including draw-in groove horizontal stroke(1), draw-in groove horizontal stroke is smooth (1)It is provided with multiple insulation columns and nozzle is installed(2), each insulation column installation nozzle(2)On insulation column is correspondingly installed(3), Insulation column(3)It is provided with optical cable retention mechanism.
2. a kind of power transmission line column according to claim 1 draws lower securing member with OPGW insulation, it is characterised in that:The card Groove horizontal stroke is smooth(1)For U-shaped.
3. a kind of power transmission line column according to claim 2 draws lower securing member with OPGW insulation, it is characterised in that:Draw-in groove is horizontal Smooth(1)The first mounting surface be provided with multiple fastening bolts(4), fastening bolt(4)Top is correspondingly provided with pad(5), bottom By double nut(6)Locking;The draw-in groove horizontal stroke is smooth(1)The second mounting surface be provided with two insulation columns side by side nozzles be installed (2).
4. a kind of power transmission line column according to claim 1 draws lower securing member with OPGW insulation, it is characterised in that:Described exhausted Nozzle installed by edge pillar(2)It is provided with screwed hole(7), screwed hole(7)Center is provided with threaded post(8), the insulation column(3)Lower end External screw thread and internal thread hole is correspondingly provided with, insulation column installs nozzle(2)With insulation column(3)Connected by Double-layer threaded.
5. a kind of power transmission line column according to claim 1 draws lower securing member with OPGW insulation, it is characterised in that:The light Cable retention mechanism includes drawing lower cable fastener(9), draw lower cable fastener(9)By cable clamping fixing bolt(10)Locking.
CN201621059486.7U 2016-09-18 2016-09-18 A kind of power transmission line column draws lower securing member with OPGW insulation Active CN206020766U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621059486.7U CN206020766U (en) 2016-09-18 2016-09-18 A kind of power transmission line column draws lower securing member with OPGW insulation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621059486.7U CN206020766U (en) 2016-09-18 2016-09-18 A kind of power transmission line column draws lower securing member with OPGW insulation

Publications (1)

Publication Number Publication Date
CN206020766U true CN206020766U (en) 2017-03-15

Family

ID=58260808

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621059486.7U Active CN206020766U (en) 2016-09-18 2016-09-18 A kind of power transmission line column draws lower securing member with OPGW insulation

Country Status (1)

Country Link
CN (1) CN206020766U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111999830A (en) * 2020-07-28 2020-11-27 国网山东省电力公司滨州供电公司 A kind of substation optical cable down-and-ground fixing device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111999830A (en) * 2020-07-28 2020-11-27 国网山东省电力公司滨州供电公司 A kind of substation optical cable down-and-ground fixing device

Similar Documents

Publication Publication Date Title
CN202646935U (en) Universal rotating cable support
CN108071195A (en) A kind of color steel tile fixture
CN203872118U (en) Circular clamp
CN206020765U (en) A kind of double cables of Ultra-high Voltage Substations OPGW single poles draw lower fastener
CN206020764U (en) A kind of double cables of high voltage substation OPGW draw lower fastener
CN206020766U (en) A kind of power transmission line column draws lower securing member with OPGW insulation
CN208316656U (en) A kind of integral type tracking bracket solar cell module mounting structure
CN202280979U (en) Bellows for transformer
CN204333865U (en) A kind of high-tension cable fixture
CN208422531U (en) A kind of high-strength suspension porcelain insulator
CN207265615U (en) A kind of cable fixture for high-voltage power transmission tower
CN207459549U (en) Earth potential live job mix instrument
CN203872113U (en) Photovoltaic bracket fixing structure
CN103557422B (en) A kind of Height Adjustable stent structure for photovoltaic module
CN203571231U (en) Cable clamp capable of improving fixation effect
CN204534048U (en) Meter erection fixture
CN102881742A (en) Press fitting device for solar photovoltaic panel
CN206099244U (en) Strain clamp
CN215734108U (en) Photovoltaic panel support suitable for roof surface
KR101206495B1 (en) Connection support apparatus for changing pylon
CN205304128U (en) Tower crane cable fixed bolster
CN204651778U (en) A kind of servicing unit changing electric transmission line isolator
CN203233102U (en) Vertical bottle fastening device
CN206834677U (en) Insulating device in overhead transmission line
CN205229238U (en) Dismantle convenient power metering box

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant