CN202324775U - Fixing device used for mounting equipment on power transmission tower - Google Patents

Fixing device used for mounting equipment on power transmission tower Download PDF

Info

Publication number
CN202324775U
CN202324775U CN2011203957011U CN201120395701U CN202324775U CN 202324775 U CN202324775 U CN 202324775U CN 2011203957011 U CN2011203957011 U CN 2011203957011U CN 201120395701 U CN201120395701 U CN 201120395701U CN 202324775 U CN202324775 U CN 202324775U
Authority
CN
China
Prior art keywords
clamping plate
plate
face
iron tower
bolt hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN2011203957011U
Other languages
Chinese (zh)
Inventor
庹强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI XINYING POWERTECH CO., LTD.
Original Assignee
SHANGHAI XINYING POWER TECHNOLOGY CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI XINYING POWER TECHNOLOGY CO LTD filed Critical SHANGHAI XINYING POWER TECHNOLOGY CO LTD
Priority to CN2011203957011U priority Critical patent/CN202324775U/en
Application granted granted Critical
Publication of CN202324775U publication Critical patent/CN202324775U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Abstract

The utility model relates to a fixing device used for mounting equipment on a power transmission tower. The fixing device comprises a mounting plate, a first clamping plate and a second clamping plate, wherein the first clamping plate and the second clamping plate are respectively connected with the mounting plate; the first clamping plate, the second clamping plate and the mounting plate jointly clamp iron tower angle iron tower material; the first clamping plate is an L-shaped clamping plate, and two end faces of the first clamping plate are all provided with elongated bolt holes; a connecting end face of the mounting plate and the first clamping plate is provided with corresponding elongated bolt holes; the second clamping plate is an L-shaped clamping plate, one end face of the second clamping plate which is connected with the mounting plate is provided with bolt holes, and the other end face of the second clamping plate is provided with elongated bolt holes which are corresponding to the elongated bolt holes of the first clamping plate; and one end face of the iron tower angle iron tower material is fixed between the first clamping plate and the second clamping plate, and the other end face of the iron tower angle iron tower material is fixed between the first clamping plate and the mounting plate. Compared with the prior art, the fixing device provided by the utility model has the advantages of simple structure and convenience for installation.

Description

The fastening devices that is used for erection equipment on the electric power pylon
Technical field
The utility model relates to a kind of electric power pylon correlation technique, especially relates to a kind of fastening devices that is used for erection equipment on the electric power pylon.
Background technology
At present, the device steps on the iron tower of power transmission line increases, and the installation of when building the tower design, not considering follow-up equipment because be work high above the ground, in the installation process of follow-up equipment, considered safety, convenience that personnel and equipment are installed with fixing; Because the site plant installation position is uncertain, the tower material size of equipment installation site is uncertain, and the mounting method of equipment producer employing now is multifarious; That also have even on former tower material, change hole processing; Cause the security performance of iron tower to reduce, or sectional fixture is too heavy, operation inconvenience etc.; Prolong the time that equipment is installed, increased the danger of work high above the ground.
The utility model content
The purpose of the utility model is exactly for the defective that overcomes above-mentioned prior art existence a kind of fastening devices that is used for erection equipment on the electric power pylon simple in structure, easy for installation to be provided.
The purpose of the utility model can realize through following technical scheme:
A kind of fastening devices that is used for erection equipment on the electric power pylon is characterized in that, comprises installing plate, first clamping plate and second clamping plate; First clamping plate, second clamping plate are connected with installing plate respectively, and described first clamping plate, second clamping plate and installing plate are clamped steel tower corner iron tower material jointly.
Described first clamping plate are L shaped clamping plate; Be equipped with the strip bolt hole on the both ends of the surface; Described installing plate connects end face with first clamping plate and is provided with corresponding strip bolt hole; Described second clamping plate are L shaped clamping plate, and the end face that wherein is connected with installing plate is provided with bolt hole, and the other end is provided with the strip bolt hole corresponding with the strip bolt hole of first clamping plate; One end face of described steel tower corner iron tower material is fixed between first clamping plate and second clamping plate, and the other end is fixed between first clamping plate and the installing plate.
Be provided with the fastening bolt that can in its hole, slide in the described strip bolt hole.
Compared with prior art, the utlity model has following advantage:
1, the scope of application is wide: iron tower of power transmission line so long as angle steel tower all can conveniently use.
2, easy for installation: only need to use two clamping plates, the quadruplet screw can be fixed on the iron tower of power transmission line optional position with equipment.
Description of drawings
Fig. 1 is the structural representation of the utility model.
The specific embodiment
Below in conjunction with accompanying drawing and specific embodiment the utility model is elaborated.
As shown in Figure 1, a kind of fastening devices that is used for erection equipment on the electric power pylon comprises installing plate 1, first clamping plate 2 and second clamping plate 3; First clamping plate 2, second clamping plate 3 are connected with installing plate 1 respectively, and described first clamping plate 2, second clamping plate 3 and installing plate 1 are clamped steel tower corner iron tower material jointly.Described installing plate 1 is the parts or the separate part of erection equipment.Described first clamping plate 2 are L shaped clamping plate; Be equipped with the strip bolt hole on the both ends of the surface; Described installing plate 1 connects end face with first clamping plate 2 and is provided with corresponding strip bolt hole; Described second clamping plate 3 are L shaped clamping plate, and the end face that wherein is connected with installing plate 1 is provided with bolt hole, and the other end is provided with the strip bolt hole corresponding with the strip bolt hole of first clamping plate 2; One end face of described steel tower corner iron tower material is fixed between first clamping plate 2 and second clamping plate 3, and the other end is fixed between first clamping plate 1 and the installing plate 1.During installation, fastening bolt is installed all in the described bolt hole.Described erection equipment 4 is installed on the installing plate 1.
As shown in Figure 4, the installation process of the utility model is following:
At first will need installed device 4 to be fixed on the installing plate 1, as required the angle steel breach of installation site towards, use bolton at installing plate 1 correspondence position on second clamping plate; Use bolt to connect on first clamping plate 2; The external member that assembles is fixed on steel tower corner iron tower material correspondence position,, the fastening bolt in first clamping plate 2 and second clamping plate, the 3 strip bolts hole is adjusted near steel tower corner iron tower material according to steel tower corner iron tower material size; Then that all fastening bolts are fastening, installation.

Claims (3)

1. a fastening devices that is used for erection equipment on the electric power pylon is characterized in that, comprises installing plate, first clamping plate and second clamping plate; First clamping plate, second clamping plate are connected with installing plate respectively, and described first clamping plate, second clamping plate and installing plate are clamped steel tower corner iron tower material jointly.
2. a kind of fastening devices that is used for erection equipment on the electric power pylon according to claim 1; It is characterized in that described first clamping plate are L shaped clamping plate, are equipped with the strip bolt hole on the both ends of the surface; Described installing plate connects end face with first clamping plate and is provided with corresponding strip bolt hole; Described second clamping plate are L shaped clamping plate, and the end face that wherein is connected with installing plate is provided with bolt hole, and the other end is provided with the strip bolt hole corresponding with the strip bolt hole of first clamping plate; One end face of described steel tower corner iron tower material is fixed between first clamping plate and second clamping plate, and the other end is fixed between first clamping plate and the installing plate.
3. a kind of fastening devices that is used for erection equipment on the electric power pylon according to claim 2 is characterized in that, is provided with the fastening bolt that can in its hole, slide in the described strip bolt hole.
CN2011203957011U 2011-10-17 2011-10-17 Fixing device used for mounting equipment on power transmission tower Withdrawn - After Issue CN202324775U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011203957011U CN202324775U (en) 2011-10-17 2011-10-17 Fixing device used for mounting equipment on power transmission tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011203957011U CN202324775U (en) 2011-10-17 2011-10-17 Fixing device used for mounting equipment on power transmission tower

Publications (1)

Publication Number Publication Date
CN202324775U true CN202324775U (en) 2012-07-11

Family

ID=46436756

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011203957011U Withdrawn - After Issue CN202324775U (en) 2011-10-17 2011-10-17 Fixing device used for mounting equipment on power transmission tower

Country Status (1)

Country Link
CN (1) CN202324775U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046793A (en) * 2011-10-17 2013-04-17 上海欣影电力科技发展有限公司 Fixing device used for installing device on power transmission iron tower
CN113315063A (en) * 2021-06-08 2021-08-27 国网新疆电力有限公司喀什供电公司 Bird perching frame for bird prevention of power transmission line iron tower

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046793A (en) * 2011-10-17 2013-04-17 上海欣影电力科技发展有限公司 Fixing device used for installing device on power transmission iron tower
CN103046793B (en) * 2011-10-17 2015-06-24 上海欣影电力科技股份有限公司 Fixing device used for installing device on power transmission iron tower
CN113315063A (en) * 2021-06-08 2021-08-27 国网新疆电力有限公司喀什供电公司 Bird perching frame for bird prevention of power transmission line iron tower

Similar Documents

Publication Publication Date Title
CN204066624U (en) Vertical pivoting angle formula equipment for hydroelectric station nameplate mounting bracket
CN202324775U (en) Fixing device used for mounting equipment on power transmission tower
CN203632117U (en) A rotary type insulation lift
CN203674624U (en) Sleeve-type combination tool for live-line jumper clamp fastening
CN204517332U (en) Can vertically arranged multi-functional overcurrent fixture
CN103825222B (en) A kind of charged for replacement 220kV narrow base tower strain insulator string instrument
CN203791344U (en) Connection structure for connecting shaft bracket and rolling mill base in short stress path rolling mill
CN201774188U (en) Water-cooled cable mounting clamp
CN103046793B (en) Fixing device used for installing device on power transmission iron tower
CN203882552U (en) Electric signboard fixing device
CN203813334U (en) Right-angle yoke plate clamp for live exchange of 220 kV strain insulator string
CN204143774U (en) Electric power steel pipe tower signboard fixing device
CN203135318U (en) Clamping tool used for changing single-strand insulator
CN205005002U (en) T type tile photovoltaic adaptor
CN204733117U (en) A kind of solar panels mounting bracket for cement shaft tower
CN103825223A (en) Tool and working method for live change of 220KV narrow base tower strain insulator string
CN203813335U (en) Triangular yoke plate clamp for live exchange of 220 kV strain insulator string
CN204681049U (en) A kind of universal stand of lightning arrester monitor
CN203348725U (en) Combined type cable bridge supporting arm
CN204177472U (en) Shear beam weighing device
CN103273325B (en) A kind of steel plate shearing machine load bearing holder mounting structure
CN103331723B (en) A kind of steel plate shearing machine bearing block positioning key method for dismounting
CN206517013U (en) Cable termination tower angle steel holding clamp
CN210835018U (en) Fixing device for three-phase power meter box
CN202391882U (en) Track press block assembly

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: SHANGHAI XINYING POWERTECH CO., LTD.

Free format text: FORMER NAME: SHANGHAI XINYING POWER TECHNOLOGY DEVELOPMENT CO., LTD.

CP03 Change of name, title or address

Address after: 200436 Shanghai, Zhabei District Jiang Field Road No. 214, room 250, No. three

Patentee after: SHANGHAI XINYING POWERTECH CO., LTD.

Address before: 200070 Shanghai city Zhabei District moling Road No. 50 room 5406

Patentee before: Shanghai Xinying Power Technology Co.,Ltd.

AV01 Patent right actively abandoned

Granted publication date: 20120711

Effective date of abandoning: 20150624

RGAV Abandon patent right to avoid regrant