A kind of low discharge rock matter drainage tunnel structure Download PDFInfo
- Publication number
- CN204551367U CN204551367U CN201420840151.3U CN201420840151U CN204551367U CN 204551367 U CN204551367 U CN 204551367U CN 201420840151 U CN201420840151 U CN 201420840151U CN 204551367 U CN204551367 U CN 204551367U
- Authority
- CN
- China
- Prior art keywords
- concrete lining
- drainage tunnel
- gutter
- drainage
- lining cutting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
The utility model discloses a kind of low discharge rock matter drainage tunnel structure, comprise the internal layer concrete lining (2) being arranged on drainage tunnel (1) end arch and abutment wall, and the outer concrete lining cutting (3) be arranged in internal layer concrete lining (4), underplate concrete lining cutting (4) one end of drainage tunnel (1) bottom is provided with gutter (5).The utility model is when underplate concrete lining cutting (4) of construction drainage hole (1) bottom, only need reserve a breach in underplate concrete lining cutting (4) one end, just Quick drainage ditch (5) can be formed, not only efficiency of construction improves greatly, use manpower and material resources sparingly, and avoid gutter explosion can not to cause constructing and need the problem of hand excavation, accelerate construction speed.<b/>
Description
Technical field
The utility model relates to a kind of low discharge rock matter drainage tunnel structure, belongs to construction of hydro project technical field.
Background technology
In hydraulic engineering construction, build the important measures that drainage tunnel is some important building drainage and step-downs.In traditional water conservancy engineering, after rock matter drainage tunnel base plate of being everlasting has excavated, then carrying out base plate gutter excavation, and carrying out concrete lining.But, during this section structure excavation gutter, because gutter size is less, can not blast working, can only hand excavation be adopted, for longer rock matter drainage tunnel, then need a large amount of personnel to excavate, wasting manpower and material resources, have a strong impact on the duration of engineering.
Utility model content
The purpose of this utility model is, provides that a kind of structure is simple, easy construction, effectively can improve the low discharge rock matter drainage tunnel structure of construction speed, to overcome prior art deficiency.
The technical solution of the utility model: a kind of low discharge rock matter drainage tunnel structure, comprise the internal layer concrete lining being arranged on arch and abutment wall at the bottom of drainage tunnel, and the outer concrete lining cutting be arranged in internal layer concrete lining, the underplate concrete lining cutting one end bottom drainage tunnel is provided with gutter.
Further, bottom gutter, sand finish is provided with.
Owing to adopting technique scheme, the utility model has the advantage of: during the underplate concrete lining cutting of the utility model bottom construction drainage hole, only need reserve a breach in underplate concrete lining cutting one end, just Quick drainage ditch can be formed, not only efficiency of construction improves greatly, use manpower and material resources sparingly, and avoid gutter explosion can not to cause constructing and need the problem of hand excavation, accelerate construction speed.Therefore, the utility model can form base plate gutter, cavern fast and efficiently, a large amount of saving manpower and duration, can extensive use in other Yan Zhi caverns.
Accompanying drawing explanation
Fig. 1 is section structure schematic diagram of the present utility model.
Description of reference numerals: 1-drainage tunnel, the concrete lining of 2-internal layer, 3-rotating shaft, the lining cutting of 4-underplate concrete, 5-gutter, 6-sand finish.
Detailed description of the invention
In order to make the utility model object, technical scheme and advantage clearly, below in conjunction with drawings and Examples, the utility model is described in further detail.
Embodiment
As shown in Figure 1, a kind of low discharge rock matter drainage tunnel structure of the present utility model, comprise the internal layer concrete lining 2 being arranged on drainage tunnel 1 end arch and abutment wall, and the outer concrete lining cutting 3 be arranged in internal layer concrete lining 4, underplate concrete lining cutting 4 one end bottom drainage tunnel 1 is provided with gutter 5, and the size in described gutter 5 is arranged voluntarily according to drainage requirement.Further, bottom gutter 5, be provided with sand finish 6, make bottom gutter 5 more smooth, improve the drainage efficiency in gutter 5.
Claims (2)
1. a low discharge rock matter drainage tunnel structure, comprise the internal layer concrete lining (2) being arranged on drainage tunnel (1) end arch and abutment wall, and the outer concrete lining cutting (3) be arranged in internal layer concrete lining (4), it is characterized in that: underplate concrete lining cutting (4) one end of drainage tunnel (1) bottom is provided with gutter (5).
2. low discharge rock matter drainage tunnel structure according to claim 1, is characterized in that: gutter (5) bottom is provided with sand finish (6).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420840151.3U CN204551367U (en) | 2014-12-26 | 2014-12-26 | A kind of low discharge rock matter drainage tunnel structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420840151.3U CN204551367U (en) | 2014-12-26 | 2014-12-26 | A kind of low discharge rock matter drainage tunnel structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204551367U true CN204551367U (en) | 2015-08-12 |
Family
ID=53826500
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420840151.3U Active CN204551367U (en) | 2014-12-26 | 2014-12-26 | A kind of low discharge rock matter drainage tunnel structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204551367U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107761766A (en) * | 2017-11-18 | 2018-03-06 | 中国电建集团贵阳勘测设计研究院有限公司 | The method that underground power house lower floor collector drain and collector drain also serve as air inlet duct |
-
2014
- 2014-12-26 CN CN201420840151.3U patent/CN204551367U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107761766A (en) * | 2017-11-18 | 2018-03-06 | 中国电建集团贵阳勘测设计研究院有限公司 | The method that underground power house lower floor collector drain and collector drain also serve as air inlet duct |
CN107761766B (en) * | 2017-11-18 | 2022-06-21 | 中国电建集团贵阳勘测设计研究院有限公司 | Underground workshop lower drainage gallery and method for using drainage gallery as air inlet gallery |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203742623U (en) | Water-pressure-resistant composite structure for tunnel | |
CN204476419U (en) | Anti-screw machine of gushing | |
CN202337970U (en) | Plugging structure for diversion tunnel | |
CN104895586A (en) | Anti-disengaging tunnel secondary lining concrete pouring constructing method and formwork system | |
CN204002832U (en) | A kind of shield tunnel portal structure | |
CN204532364U (en) | Tunneling boring rock tunnel development machine engineering method subway tunnel pressure release type liner structure | |
CN202298577U (en) | Plugging structure for diversion tunnel | |
CN102287207A (en) | Assembling jacking method in relation to serious collapse of small-section tunnel | |
CN103628898B (en) | A kind of for preventing the diaphragm wall supporting method of Floor Heave in Roadway | |
CN204436407U (en) | The structure that the pre-Geological disaster prevention of the double-deck preliminary bracing of a kind of big cross section Support System in Soft Rock Tunnels occurs | |
CN204551367U (en) | A kind of low discharge rock matter drainage tunnel structure | |
CN204941551U (en) | A kind of subway station of Curve Pipe Jacking supporting and protection structure enlarging shield-tunneling construction | |
CN204402513U (en) | A kind of device solving the infiltration of underground chamber lining cutting surface and leak | |
CN204386617U (en) | A kind of consolidation grouting structure of low water head diversion tunnel | |
CN204212180U (en) | A kind of reinforcing cage for basement plugging dewatering well | |
CN203716116U (en) | Pulp stopping structure used in diversion tunnel concrete end plug vault backfill grouting | |
CN204002826U (en) | A kind of major diameter slurry balance push-bench cutterhead of applicable gumbo construction | |
CN204002825U (en) | A kind of chain type cutter assembly mechanism | |
CN204000861U (en) | Bored pile casing in a kind of water | |
CN103195032B (en) | A kind of plugging structure for diversion tunnel | |
CN103470275B (en) | A kind of large-span underground chamber usual friendship junctions excavation supporting method | |
CN203144985U (en) | Plugging structure for diversion tunnel | |
CN202370539U (en) | Front tunnel face excavated soil pre-reinforcing structure of tunnel | |
CN205152918U (en) | Structure that diversion tunnel and flood discharge hole combine | |
CN204716255U (en) | The concrete pouring construction template system of anti-Tunnel Second Lining of coming to nothing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |