CN204414321U - The box assembling die curing system of concrete - Google Patents
The box assembling die curing system of concrete Download PDFInfo
- Publication number
- CN204414321U CN204414321U CN201520020605.7U CN201520020605U CN204414321U CN 204414321 U CN204414321 U CN 204414321U CN 201520020605 U CN201520020605 U CN 201520020605U CN 204414321 U CN204414321 U CN 204414321U
- Authority
- CN
- China
- Prior art keywords
- concrete
- vertical beam
- hot water
- crossbeam
- hot
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model provides a kind of concrete box assembling die curing system, comprise crossbeam, vertical beam, hot-water line, hot water inlet and hot water outlet, crossbeam and vertical beam are prepared by I-steel, array crossbeam and the equidistant latticed mold frame of vertical beam composition, hot-water line is snakelikely be arranged in mold frame, hot water inlet and hot water outlet are arranged on outside same one end of vertical beam, are connected between above-mentioned component by welding manner.By arranging curing system in mould, effectively can solve the steam curing conservation problem of simultaneously producing polylith concrete panel, its simplicity of design, it is convenient to install, and can be widely used in the maintenance of the prefabricated concrete panel of the box assembling die of concrete.
Description
Technical field
The utility model belongs to concrete panel care field, relates to the box assembling die curing system of a kind of concrete, is widely used in the maintenance of the prefabricated concrete panel of the box assembling die of concrete.
Background technology
In precast concrete wall panel production process, through one-time-concreting concrete, lay steel reinforcement cage, build heat-insulation layer, secondary casting concrete, vibrate, the operation such as steam curing conservation, loaded down with trivial details, the consuming time length of its preparation technology, and floor space is large, production efficiency has much room for improvement.So, have developed the box assembling die of a kind of concrete, concrete walls board mold vertically arranged one by one, 1-25 block concrete wallboards can be produced simultaneously.But polylith concrete panel is produced simultaneously, in steam curing conservation operation, only by GEOTHERMAL WATER or enter steaming kiln maintenance, solidifying of concrete panel is affected to some extent.Therefore, the utility model provides the box assembling die curing system of a kind of concrete, in mould, curing system is set, effectively can solve the steam curing conservation problem of simultaneously producing polylith concrete panel, its simplicity of design, it is convenient to install, and can be widely used in the maintenance of the prefabricated concrete panel of the box assembling die of concrete.
Utility model content
The utility model object is to provide the box assembling die curing system of a kind of concrete, by arranging curing system in mould, effectively can solve the steam curing conservation problem of simultaneously producing polylith concrete panel, its simplicity of design, it is convenient to install, and can be widely used in the maintenance of the prefabricated concrete panel of the box assembling die of concrete.
The technical scheme that the utility model adopts is: the box assembling die curing system of a kind of concrete, comprise crossbeam, vertical beam, hot-water line, hot water inlet and hot water outlet, crossbeam and vertical beam are prepared by I-steel, array crossbeam and the equidistant latticed mold frame of vertical beam composition, hot-water line is snakelikely be arranged in mold frame, hot water inlet and hot water outlet are arranged on outside same one end of vertical beam, are connected between above-mentioned component by welding manner.
Described crossbeam and vertical beam, prepared by the I-steel cutting of same size, crossbeam and vertical beam junction arrange unnecessary web, are convenient to the two compact siro spinning technology.
Described hot-water line, realizes the maintenance of concrete panel by earthing hot water.
The beneficial effects of the utility model are: the box assembling die curing system of a kind of concrete that the utility model provides, in mould, curing system is set, effectively can solve the steam curing conservation problem of simultaneously producing polylith concrete panel, its simplicity of design, it is convenient to install, and can be widely used in the maintenance of the prefabricated concrete panel of the box assembling die of concrete.
Accompanying drawing explanation
Fig. 1 is a kind of concrete box assembling die curing system schematic diagram, and Fig. 2 is the box assembling die schematic diagram of single concrete.
Reference numeral: 1, crossbeam; 2, vertical beam; 3, hot-water line; 4, hot water inlet; 5, hot water outlet; 6, toughened glass panel.
Detailed description of the invention
As shown in Figure 1, concrete box assembling die curing system schematic diagram, comprise crossbeam (1), vertical beam (2), hot-water line (3), hot water inlet (4) and hot water outlet (5), crossbeam (1) and vertical beam (2) are prepared by I-steel, array crossbeam (1) and vertical beam (2) form latticed mold frame, hot-water line (3) is arranged in mold frame in snakelike, hot water inlet (4) and hot water outlet (5) are arranged on outside same one end of vertical beam (2), are connected between above-mentioned component by welding manner.
As shown in Figure 2, for the box assembling die schematic diagram of single concrete, on the two sides of the latticed mold frame that crossbeam (1) and vertical beam (2) form, toughened glass panel (6) is installed respectively, it is as the prefabricated mold panel of concrete panel, flat smooth degree is high, can reduce the operations such as concrete panel surface treatment.In actual production process, the box assembling die of several concrete is vertically lined up successively, it is precast concrete wall panel between mould and mould, when secondary casting concrete is complete, hot water inlet (4) to each mould passes into GEOTHERMAL WATER, GEOTHERMAL WATER flows through hot-water line (3), discharges from hot water outlet (5), and so circulation realizes the maintenance of concrete panel.
The utility model is not limited to above-mentioned embodiment, and anyone can draw other various forms of products under enlightenment of the present utility model.All equalizations done according to the utility model claim change and modify, and all should belong to covering scope of the present utility model.
Claims (3)
1. the box assembling die curing system of concrete, it is characterized in that, this system comprises crossbeam, vertical beam, hot-water line, hot water inlet and hot water outlet, crossbeam and vertical beam are prepared by I-steel, array crossbeam and the equidistant latticed mold frame of vertical beam composition, hot-water line is snakelikely be arranged in mold frame, and hot water inlet and hot water outlet are arranged on outside same one end of vertical beam, are connected between above-mentioned component by welding manner.
2. the box assembling die curing system of concrete according to claim 1, is characterized in that, described crossbeam and vertical beam, and prepared by the I-steel cutting of same size, crossbeam and vertical beam junction arrange unnecessary web, is convenient to the two compact siro spinning technology.
3. the box assembling die curing system of concrete according to claim 1, is characterized in that described hot-water line realizes the maintenance of concrete panel by earthing hot water.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520020605.7U CN204414321U (en) | 2015-01-13 | 2015-01-13 | The box assembling die curing system of concrete |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520020605.7U CN204414321U (en) | 2015-01-13 | 2015-01-13 | The box assembling die curing system of concrete |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204414321U true CN204414321U (en) | 2015-06-24 |
Family
ID=53464723
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520020605.7U Expired - Fee Related CN204414321U (en) | 2015-01-13 | 2015-01-13 | The box assembling die curing system of concrete |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204414321U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107263690A (en) * | 2016-03-30 | 2017-10-20 | 披思恩斯有限公司 | Prefabricated components curing means |
CN108760427A (en) * | 2018-06-06 | 2018-11-06 | 河南天祥新材料股份有限公司 | Artificial rock core makes mold and method |
-
2015
- 2015-01-13 CN CN201520020605.7U patent/CN204414321U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107263690A (en) * | 2016-03-30 | 2017-10-20 | 披思恩斯有限公司 | Prefabricated components curing means |
CN108760427A (en) * | 2018-06-06 | 2018-11-06 | 河南天祥新材料股份有限公司 | Artificial rock core makes mold and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201079988Y (en) | Composite multipurpose die | |
CN106272951A (en) | Assembling die precast concrete wall panel technology | |
CN204414321U (en) | The box assembling die curing system of concrete | |
CN203831566U (en) | Robot intelligent panel making system | |
CN205296891U (en) | Concrete steel pipe framework braced system with interior cooling function | |
CN105500510A (en) | Steam curing system for building elements | |
CN202943731U (en) | Demolding gypsum block molding machine | |
CN207073278U (en) | A kind of building engineering construction formwork for placing | |
CN102535841A (en) | Construction technology of prefabricated wall panel | |
CN201693661U (en) | Light concrete wallboard production line | |
CN102009431A (en) | Automatic production line for lightweight concrete wallboard | |
CN110466049A (en) | Three-dimensional expansible bidirectional flexible PC component production line | |
CN202498617U (en) | Mold used for special-shaped wallboard | |
CN203924473U (en) | For the reinforced concrete prefabricated compound external wall panel of frame structure system | |
CN106142315A (en) | Assembling die conduction oil maintenance technology | |
CN106003398B (en) | A kind of PC components High Efficiency Thermal die station | |
CN102953529B (en) | Small dimension veneer building materials mounting structure | |
CN202781376U (en) | Square cement flue molding equipment | |
CN203579840U (en) | Lower-die core beam lining plate of die of block making machine | |
CN106142299A (en) | Shuttering concrete surface quality controls technology | |
CN204645346U (en) | Bar frame structure | |
CN106113240A (en) | A kind of raw adobe dry in the sun support | |
CN218985210U (en) | Fixed assembled building prefabricated component production is with mould platform | |
CN105665648A (en) | Heat preservation device for cast grinding balls | |
CN204422079U (en) | Assembling die temperature alarm system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150624 Termination date: 20220113 |