CN204137712U - A kind of electric tower sliding conveying arrangement - Google Patents

A kind of electric tower sliding conveying arrangement Download PDF

Info

Publication number
CN204137712U
CN204137712U CN201420493401.0U CN201420493401U CN204137712U CN 204137712 U CN204137712 U CN 204137712U CN 201420493401 U CN201420493401 U CN 201420493401U CN 204137712 U CN204137712 U CN 204137712U
Authority
CN
China
Prior art keywords
electric tower
slip rope
cylinder
cross
conveying arrangement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201420493401.0U
Other languages
Chinese (zh)
Inventor
陈铭
谢秋平
林鑫
杨佳樱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Management and Training Center of State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Management and Training Center of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Fujian Electric Power Co Ltd, Management and Training Center of State Grid Fujian Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201420493401.0U priority Critical patent/CN204137712U/en
Application granted granted Critical
Publication of CN204137712U publication Critical patent/CN204137712U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a kind of electric tower sliding conveying arrangement, cross-tie plate is provided with in the middle part of described electric tower body, described cross-tie plate is provided with jacking system, described jacking system is fixedly connected with the slip rope adapter plate longitudinally arranged, described slip rope adapter plate is provided with the take-up cylinder for being wound around slip rope, described take-up cylinder is wound with slip rope, described take-up cylinder is provided with the actuating device that head roll rotates, the utility model by arranging jacking system on electric tower, slip rope, and the device such as movable pulley, the slip rope conveying being realized electric tower assembling parts in complex-terrain process by the slip rope equipment on the electric tower set up can be realized, significantly reduce the transport installation difficulty of electric tower assembly, effectively improve installation rate.

Description

A kind of electric tower sliding conveying arrangement
Technical field
The utility model relates to a kind of electric power conveyer, is specifically related to a kind of electric tower sliding conveying arrangement.
Background technology
electricity tower is a kind of device for fixing power transmission line, when some complex-terrain vehicles such as mountain region, marsh cannot transport, electricity tower needs manually to carry the frame section pieces of building electric tower and passes mountain forest or marsh, and install after arriving appointed place, this method extremely wastes time and energy.
Summary of the invention
The utility model improves the problems referred to above, and namely the technical problems to be solved in the utility model is that existing electric tower is installed to adopt when running into situation with a varied topography and manually transported installation frame, wastes time and energy.
Specific embodiments of the present utility model is: a kind of electric tower sliding conveying arrangement, comprise electric tower body, cross-tie plate is provided with in the middle part of described electric tower body, described cross-tie plate is provided with jacking system, described jacking system is fixedly connected with the slip rope adapter plate longitudinally arranged, described slip rope adapter plate is provided with the take-up cylinder for being wound around slip rope, described take-up cylinder is wound with slip rope, described take-up cylinder is provided with the actuating device that head roll rotates.
Further, described slip rope adapter plate upper end is fixed with a cross bar, and described cross bar is provided with a pair can along the pulley fixed link of cross bar slippage, and described pulley fixed link one end is provided with movable pulley.
Further, described cross bar is cross section is rectangle, and described pulley fixed link is provided with towards cross bar one end the rectangular through-hole matched with cross bar cross section.
Further, described jacking system is hydraulic actuating cylinder, and the upper end of hydraulic actuating cylinder is fixedly connected with slip rope adapter plate lower end.
Further, described actuating device is motor.
Further, the shank be fixed on slip rope adapter plate is provided with above described take-up cylinder.
Further, described electric tower body is provided with cross-tie plate, and cross-tie plate both sides are provided with the side shield be fixed on electric tower, and described side shield is provided with control box.
Compared with prior art, the utility model has following beneficial effect: the utility model structure is simple, utilize lowering rope device can be adapted at low and slope, mountain and carry electric tower mounting parts by high-altitude, do not need to install by manually bearing part mountain-climbing, thus saved manpower, improve installation effectiveness.
Accompanying drawing explanation
Fig. 1 is the utility model integral structure schematic diagram.
Fig. 2 is the utility model electricity tower sliding conveying arrangement structure enlarged diagram.
Fig. 3 is the utility model cross bar and pulley fixed link fit structure schematic diagram.
Fig. 4 is the utility model using state schematic diagram.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the utility model is described in more detail.
As shown in Fig. 1 ~ 2, a kind of electric tower sliding conveying arrangement, comprise electric tower body 10, cross-tie plate 110 is provided with in the middle part of described electric tower body 10, described cross-tie plate 110 is provided with hydraulic actuating cylinder 20, described hydraulic actuating cylinder 20 is fixedly connected with the slip rope adapter plate 30 longitudinally arranged, described slip rope adapter plate 30 is provided with the take-up cylinder 40 for being wound around slip rope, described take-up cylinder 40 is wound with slip rope, described take-up cylinder 40 is provided with the actuating device that head roll rotates, and actuating device is generally motor.
Described slip rope adapter plate 30 upper end is fixed with a cross bar 50, and described cross bar 50 is provided with a pair can along the pulley fixed link 510 of cross bar slippage, and described pulley fixed link one end is provided with movable pulley 520.Cross bar 50 for cross section be rectangle, described pulley fixed link 510 is provided with towards cross bar 50 one end the rectangular through-hole matched with cross bar cross section.
Be provided with the shank 60 be fixed on slip rope adapter plate above take-up cylinder 40, described electric tower body is provided with cross-tie plate 110, and cross-tie plate 110 both sides are provided with the side shield 70 be fixed on electric tower, and described side shield is provided with control box.
Cross-tie plate by bolt-locking on electric tower body 10, slip rope one end is fixed on take-up cylinder 40, the other end can be provided with the gib head that can match with shank 60, take-up cylinder 40 is generally provided with two or more, the position of pulley fixed link 510 can adjust along cross bar about 50, pulley fixed link also can be set to Collapsible structure, when ground object sling by needs, movable pulley 520 on pulley fixed link 510 is adjusted to mutually concordant with take-up cylinder 40, side is moved to when not using, plural take-up cylinder 40 is in order to ensure the steady of handling article.
During use, comprise the following steps:
(1) on electric tower, be fixedly installed cross-tie plate, on the supporting plate jacking system be installed, jacking system arranges slip rope adapter plate, slip rope adapter plate is provided with take-up cylinder, take-up cylinder is wound around slip rope, and take-up outer surface of cylinder is fixed in one end of slip rope, and the other end is provided with hook;
(2) slip rope adapter plate upper end dead sheave fixed link, pulley fixed link one end is provided with movable pulley, operating personal stands on cross-tie plate, and slip rope is walked around movable pulley from cylinder extraction and makes slip rope lower end transfer on ground, electric tower installing component is fixed on slip rope by ground handling operator;
(3) by actuating device, electric tower installing component is pulled on cross-tie plate by slip rope, unloads electric tower installing component and be placed on cross-tie platform;
(4) other end of slip rope is transferred the predeterminated position point being needed to install electric tower to ground by ground staff's tractive to the next one, and fixing, improved the height of take-up cylinder by jacking system, buffering pneumatic cushion is set at predeterminated position point;
(5) the electric tower installing component on cross-tie platform is placed on slip rope, by slip rope sliding to predeterminated position point.
After the electric tower of step (5) predeterminated position point completes and builds, the electric tower of predeterminated position point arranges electric tower sliding conveying arrangement equally, realized the change at the angle of inclination of slip rope by the jacking system of two electric towers, thus realize the conveying back and forth of subsequent material or instrument.
The foregoing is only preferred embodiment of the present utility model, all equalizations done according to the utility model claim change and modify, and all should belong to covering scope of the present utility model.

Claims (7)

1. an electric tower sliding conveying arrangement, it is characterized in that, comprise electric tower body, cross-tie plate is provided with in the middle part of described electric tower body, described cross-tie plate is provided with jacking system, described jacking system being fixedly connected with the slip rope adapter plate longitudinally arranged, described slip rope adapter plate being provided with the take-up cylinder for being wound around slip rope, described take-up cylinder is wound with slip rope, and described take-up cylinder is provided with the actuating device that head roll rotates.
2. one according to claim 1 electric tower sliding conveying arrangement, described slip rope adapter plate upper end is fixed with a cross bar, and described cross bar is provided with a pair can along the pulley fixed link of cross bar slippage, and described pulley fixed link one end is provided with movable pulley.
3. one according to claim 2 electric tower sliding conveying arrangement, described cross bar cross section is rectangle, and described pulley fixed link is provided with towards cross bar one end the rectangular through-hole matched with cross bar cross section.
4. one according to claim 3 electric tower sliding conveying arrangement, described jacking system is hydraulic actuating cylinder, and the upper end of hydraulic actuating cylinder is fixedly connected with slip rope adapter plate lower end.
5. one according to claim 4 electric tower sliding conveying arrangement, described actuating device is motor.
6. one according to claim 4 electric tower sliding conveying arrangement, is provided with the shank be fixed on slip rope adapter plate above described take-up cylinder.
7. one according to claim 1 electric tower sliding conveying arrangement, described electric tower body is provided with cross-tie plate, and cross-tie plate both sides are provided with the side shield be fixed on electric tower, and described side shield is provided with control box.
CN201420493401.0U 2014-08-29 2014-08-29 A kind of electric tower sliding conveying arrangement Withdrawn - After Issue CN204137712U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420493401.0U CN204137712U (en) 2014-08-29 2014-08-29 A kind of electric tower sliding conveying arrangement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420493401.0U CN204137712U (en) 2014-08-29 2014-08-29 A kind of electric tower sliding conveying arrangement

Publications (1)

Publication Number Publication Date
CN204137712U true CN204137712U (en) 2015-02-04

Family

ID=52414416

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420493401.0U Withdrawn - After Issue CN204137712U (en) 2014-08-29 2014-08-29 A kind of electric tower sliding conveying arrangement

Country Status (1)

Country Link
CN (1) CN204137712U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104192469A (en) * 2014-08-29 2014-12-10 国家电网公司 Electric tower sliding and conveying device and application method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104192469A (en) * 2014-08-29 2014-12-10 国家电网公司 Electric tower sliding and conveying device and application method thereof
CN104192469B (en) * 2014-08-29 2016-07-06 国家电网公司 A kind of electricity tower sliding conveying arrangement and using method thereof

Similar Documents

Publication Publication Date Title
CN202080836U (en) Material lifting equipment for aerial operation
CN204137712U (en) A kind of electric tower sliding conveying arrangement
CN104192469B (en) A kind of electricity tower sliding conveying arrangement and using method thereof
CN110803663B (en) Hoisting equipment for maintenance of power equipment
CN104150393A (en) Micro power electric equipment rotating and hoisting device
CN203345975U (en) Installation device of hoisting steel wire rope and tower crane
CN205204674U (en) Electricity tower cunning is sent and is carried slide rail positioner
CN208777136U (en) Kerbstone is laid with auxiliary trolley
CN204150578U (en) A kind of head moving type belt feeder
CN207183923U (en) A kind of insulator replacement device
CN202787930U (en) Hanging basket for high-place operations
CN204859074U (en) Portable installation and maintenance platform of photovoltaic module
CN204689566U (en) A kind of device installed for electric power distribution cabinet fast transportation
CN105347199A (en) Electric tower sliding conveying slideway positioning device and use method thereof
CN204702434U (en) A kind of device installed for electric power distribution cabinet fast transportation
CN104876165A (en) Mobile mounting and maintenance platform of photovoltaic component
CN107161892B (en) Simple heavy object conveyance device
CN204096759U (en) A kind of crawler type telpher
CN203888787U (en) Hanger for rope support sheave of aerial passenger transport system
CN203856216U (en) Complete equipment for transportation of arc-shaped transparent roof component
CN204778501U (en) Power line pole pile up neatly and hoist and mount auxiliary device
CN203306988U (en) High-place operation auxiliary transfer car
CN103274334A (en) High-place operation auxiliary transfer vehicle
CN204606915U (en) A kind of sandstone accepts conveyor lifting device
CN105905313A (en) Installation platform and installation method for overall floor of large transport aircraft

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20150204

Effective date of abandoning: 20160706

C25 Abandonment of patent right or utility model to avoid double patenting