Prior art keywords
shear wall
connecting pin
wall slab
vertical reinforcement
bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420609325.5U
Other languages
Chinese (zh)
Inventor
段尔焕
王文媛
刘洪波
段绍平
李益华
冯斌
黄云川
肖桂莲
方云飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Construction Engineering Group Co., Ltd.
Original Assignee
KUNMING YINGZAO PROJECT DESIGN CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KUNMING YINGZAO PROJECT DESIGN CO Ltd filed Critical KUNMING YINGZAO PROJECT DESIGN CO Ltd
Priority to CN201420609325.5U priority Critical patent/CN204126048U/en
Application granted granted Critical
Publication of CN204126048U publication Critical patent/CN204126048U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

Bracket steel bar concrete shear force wall connecting pin contact assembled architecture, belongs to technical field of buildings.Bracket is established in lower floor's shear wall slab upper end, the pre-erection of floor is placed on bracket table top, the headspace treating cast-in-situ concrete is provided with corresponding to the position in the middle part of bracket table top, cast-in-situ concrete in headspace becomes the cast-in-place part of floor, lower floor's shear wall slab has multiple vertical reinforcement to protruding upward from shear wall slab and passing headspace, there are multiple vertical reinforcements of equal number shear wall slab lower end, upper strata to stretching out downwards, each vertical reinforcement has one section of arcuation reinforcing bar to cross-over connection between the termination of two reinforcing bars thus forms the semicircle shape top of evagination, the right semicircle shape top of the lower floor's shear wall slab vertical reinforcement semicircle shape split-top right with upper strata shear wall slab vertical reinforcement becomes reinforcing bar circle, horizontal reinforcement as connecting pin passes said reinforcing bar circle.Joint structure simplifies, and anti-seismic performance improves, and connecting pin is wrapped up by concrete can be anticorrosion, and constructing operation is easy.

Description

Bracket steel bar concrete shear force wall connecting pin contact assembled architecture
Technical field
The utility model belongs to design of building structures and construction technology, is specifically related to a kind of bracket steel bar concrete shear force wall connecting pin contact assembled architecture.
Background technology
Along with developing rapidly of domestic and international industrialization assembled architecture, current China has not only promulgated Its Relevant Technology Standards, and provincial standard has also been formulated in drug in some provinces; But in the Areas of High Earthquake Intensity such as Yunnan, Sichuan area, high to the shockproof requirements of assembled architecture, in design and construction, all also there is larger gap in existing fabricated shear wall structural construction.
The purpose of this utility model is the shortcoming overcoming prior art, on the technical specification basis that existing country has promulgated, a kind of bracket steel bar concrete shear force wall connecting pin contact assembled architecture is provided, realize under the condition of equal seismic design, make the actual shock resistance of reinforced concrete shear wall assembled architecture stronger, and the higher requirement for anticorrosion of metalwork can be met, to guarantee structural safety.
Structure of the present utility model is: lower floor's shear wall slab upper end establish both sides encorbelment support bracket, the pre-erection of floor is placed on bracket table top, the position that floor pre-erection corresponds in the middle part of bracket table top is provided with the headspace treating cast-in-situ concrete, cast-in-situ concrete in headspace becomes the cast-in-place part of floor, lower floor's shear wall slab has multiple vertical reinforcement to protruding upward from shear wall slab and passing headspace, there are multiple vertical reinforcements of equal number shear wall slab lower end, upper strata to stretching out downwards, each vertical reinforcement has one section of arcuation reinforcing bar to cross-over connection between the termination of two reinforcing bars thus forms the semicircle shape top of evagination, the right semicircle shape top of the lower floor's shear wall slab vertical reinforcement semicircle shape split-top right with upper strata shear wall slab vertical reinforcement becomes reinforcing bar circle, horizontal reinforcement as connecting pin passes said reinforcing bar circle.The right effect of vertical reinforcement is exactly the dowel of connecting pin.
The diameter preferred value of vertical reinforcement to every root reinforcing bar is 14 ~ 18 millimeters.During actual production, can be 14 ~ 18 millimeters of reinforcing bars by a diameter be 180 degree of angle bendings, so just can become meet the utility model structural requirement a vertical reinforcement to use.
The beneficial effects of the utility model:
(1) Nodes is provided with the dowel of bracket, connecting pin and connecting pin, simplifies the connecting structure of site operation interior joint under the prerequisite meeting supporting capacity;
(2) improve the anti-seismic performance of reinforced concrete shear wall assembled architecture, make assembling industrialized building technique can be used for Areas of High Earthquake Intensity area;
(3) connecting pin is wrapped up by concrete, and Anticorrosion is solved;
(4) node connects reliable, simple structure, and constructing operation is easy, can accelerating construction progress, enhances productivity.
Accompanying drawing explanation
Fig. 1 is in embodiment, and the master at contact position, lower floor's shear wall slab upper end is not depending on cross-sectional view (drawing other arrangements of reinforcement).
Fig. 2 is in embodiment, and the master at contact position, shear wall slab lower end, upper strata is not depending on cross-sectional view (drawing other arrangements of reinforcement).
Fig. 3 is in embodiment, upper and lower story shear wallboard, and the master after floor assembly connection is also in the milk looks cross-sectional view.
Detailed description of the invention
See the embodiment of Fig. 1 ~ Fig. 3.
Lower floor's shear wall slab 1 upper end establishes both sides to encorbelment the bracket 2 supported, and the pre-erection 3 of floor is placed on the table top 4 of bracket 2, and the pre-erection of floor 3 position corresponded in the middle part of bracket table top 4 is provided with the headspace 5 treating cast-in-situ concrete filling.Lower floor's shear wall slab 1 has multiple vertical reinforcement protrude upward 6 (dowel of connecting pin) Zi Qiangding and pass headspace 5.Upper strata shear wall slab 7 lower end has multiple vertical reinforcements of equal number to stretch out 8 (dowels of connecting pin) downwards.Each vertical reinforcement has one section of arcuation reinforcing bar 9 to cross-over connection between the termination of two reinforcing bars thus forms the semicircle shape top of evagination.During actual fabrication, each vertical reinforcement is that 180 degree of angle bendings form to the reinforcing bar by a diameter 16 millimeters.The vertical reinforcement corresponding to upper strata shear wall slab right semicircle shape split-top in the right semicircle shape top of lower floor's shear wall slab vertical reinforcement becomes reinforcing bar circle, as Φ 22 reinforcing bar 10 of connecting pin horizontal through said reinforcing bar circle.11 is the cast-in-place part of floor, and 12 is wavy metal slurry anchor tube, and 13 be grout hole, and 14 is common vertical reinforcement in upper and lower shear wall slab, and 14 according to related specifications requirement value.15 for sitting pulp layer.16 is common arrangement of reinforcement in floor, and 16 require value according to related specifications.
Embodiment can be constructed like this:
(1) by designing requirement, precast yard's prefabricated band bracket 2 and the reinforcing bar that protrudes upward to 6 lower floor's shear wall slab 1, and band stretch out downwards reinforcing bar to 8 upper strata shear wall slab 7.The right spacing of reinforcing bar with other vertical muscle spacing of shear wall, by related specifications requirement value.When determining the sectional dimension of precast shear wall plate and bracket, amount of reinforcement, seismic behavior is different, and value is also different.Arrangement of reinforcement by calculating, will meet codes and standards.Bracket and lower floor's precast shear wall plate are prefabricated into T-shaped.Reinforcing bar checks according to related request the size of stretching out.Traditionally carry out prefabricated, only bracket and precast shear wall plate end side form are adjusted accordingly, after template support completes, the position that accurate spacer bars is right, subsequently concreting, maintenance.Prefabricated complete after be transported to job site, component is carried out lifting splicing.
(2) level installs connecting pin.
(3) floor pre-erection 3 carries out lifting splicing by reliable mode.To shear wall intermediate layer interior joint, water in node area after the floor pre-erection 3 bottom Reinforcement of node both sides is anchored at, after in-situ layer top Reinforcement runs through, water node area.In floor pre-erection 3, Reinforcement adopts overlapping mode to anchor in the in-situ layer part of floor, and in-situ layer thickness is not less than 60mm.Sit after pulp layer and water, and then by the high pressure grouting of reserved wavy metal slurry anchor tube, make connecting pin and connecting pin dowel (reinforcing bar to) and sit pulp layer, the cast-in-place part 11 of floor closely combines, the connection of node is more firm.
Meet on the basis of specification at connecting pin dowel (reinforcing bar to), according to building structure grade, load, analyze across footpath etc., during seismic design, anchorage length is 600mm.
Upper and lower story shear wallboard wall vertical reinforcement requires value according to related specifications.
If when connecting pin disturbs with upper and lower layer wallboard plain bars when installing, adjustment plain bars, is in the milk in gap.

Claims (3)

1. a bracket steel bar concrete shear force wall connecting pin contact assembled architecture, it is characterized in that: lower floor's shear wall slab upper end establish both sides encorbelment support bracket, the pre-erection of floor is placed on bracket table top, the position that floor pre-erection corresponds in the middle part of bracket table top is provided with the headspace treating cast-in-situ concrete, cast-in-situ concrete in headspace becomes the cast-in-place part of floor, lower floor's shear wall slab has multiple vertical reinforcement to protruding upward from shear wall slab and passing headspace, there are multiple vertical reinforcements of equal number shear wall slab lower end, upper strata to stretching out downwards, each vertical reinforcement has one section of arcuation reinforcing bar to cross-over connection between the termination of two reinforcing bars thus forms the semicircle shape top of evagination, the right semicircle shape top of the lower floor's shear wall slab vertical reinforcement semicircle shape split-top right with upper strata shear wall slab vertical reinforcement becomes reinforcing bar circle, horizontal reinforcement as connecting pin passes said reinforcing bar circle.The right effect of vertical reinforcement is exactly the dowel of connecting pin.
2. bracket steel bar concrete shear force wall connecting pin contact assembled architecture as claimed in claim 1, is characterized in that: the diameter of the every root reinforcing bar of vertical reinforcement centering is 14 ~ 18 millimeters.
3. bracket steel bar concrete shear force wall connecting pin contact assembled architecture as claimed in claim 2, is characterized in that: each vertical reinforcement is to the reinforcing bar for a diameter 14 ~ 18 millimeters in 180 degree of angle bendings.
CN201420609325.5U 2014-10-19 2014-10-19 Bracket steel bar concrete shear force wall connecting pin contact assembled architecture Active CN204126048U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420609325.5U CN204126048U (en) 2014-10-19 2014-10-19 Bracket steel bar concrete shear force wall connecting pin contact assembled architecture

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420609325.5U CN204126048U (en) 2014-10-19 2014-10-19 Bracket steel bar concrete shear force wall connecting pin contact assembled architecture

Publications (1)

Publication Number Publication Date
CN204126048U true CN204126048U (en) 2015-01-28

Family

ID=52382416

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420609325.5U Active CN204126048U (en) 2014-10-19 2014-10-19 Bracket steel bar concrete shear force wall connecting pin contact assembled architecture

Country Status (1)

Country Link
CN (1) CN204126048U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105937280A (en) * 2016-06-03 2016-09-14 长沙远大住宅工业集团股份有限公司 Novel prefabricated building connecting joint
CN106193451A (en) * 2016-08-31 2016-12-07 济南市人防建筑设计研究院有限责任公司 A kind of combination type prestressed beam slab system
CN106894573A (en) * 2017-03-31 2017-06-27 中民筑友科技投资有限公司 A kind of connecting node of multilayer wallboard and wallboard and floor
CN107254933A (en) * 2017-07-17 2017-10-17 广东省建科建筑设计院有限公司 The high-rise single through hole precast shear wall of assembled and its assembling structure and construction method
CN107299699A (en) * 2017-06-26 2017-10-27 东南大学 Assembled cavity shear wall horizontal joint Alveolus type dry type attachment structure
CN108978941A (en) * 2018-08-27 2018-12-11 深圳市市政工程总公司 Precast shear wall wall vertical connection structure
CN111074921A (en) * 2019-12-31 2020-04-28 浙江世润建创科技发展有限公司 Prefabricated ring beam reinforcing system for prefabricated slab disassembly-free thin slab tire mold and construction method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105937280A (en) * 2016-06-03 2016-09-14 长沙远大住宅工业集团股份有限公司 Novel prefabricated building connecting joint
CN106193451A (en) * 2016-08-31 2016-12-07 济南市人防建筑设计研究院有限责任公司 A kind of combination type prestressed beam slab system
CN106894573A (en) * 2017-03-31 2017-06-27 中民筑友科技投资有限公司 A kind of connecting node of multilayer wallboard and wallboard and floor
CN107299699A (en) * 2017-06-26 2017-10-27 东南大学 Assembled cavity shear wall horizontal joint Alveolus type dry type attachment structure
CN107299699B (en) * 2017-06-26 2019-05-21 东南大学 Assembled cavity shear wall horizontal joint Alveolus type dry type connection structure
CN107254933A (en) * 2017-07-17 2017-10-17 广东省建科建筑设计院有限公司 The high-rise single through hole precast shear wall of assembled and its assembling structure and construction method
CN108978941A (en) * 2018-08-27 2018-12-11 深圳市市政工程总公司 Precast shear wall wall vertical connection structure
CN108978941B (en) * 2018-08-27 2023-09-26 深圳市市政工程总公司 Vertical connection structure of prefabricated shear wall body
CN111074921A (en) * 2019-12-31 2020-04-28 浙江世润建创科技发展有限公司 Prefabricated ring beam reinforcing system for prefabricated slab disassembly-free thin slab tire mold and construction method
CN111074921B (en) * 2019-12-31 2021-11-30 浙江世润建创科技发展有限公司 Prefabricated ring beam reinforcing system for prefabricated slab disassembly-free thin slab tire mold and construction method

Similar Documents

Publication Publication Date Title
CN204126048U (en) Bracket steel bar concrete shear force wall connecting pin contact assembled architecture
CN107165272B (en) Prestressed assembled concrete frame node connecting structure and construction method thereof
CN203174770U (en) Connection structure of prefabricated column and construction site base and building
CN103850350A (en) Prefabricated, assembled and integrated type special-shaped column structure and jointing construction method thereof
CN105649360A (en) Integral assembling type building system and installing method
CN104652671A (en) Prefabricated assembly-type concrete outer-hanging wallboard fixing device and installation method
CN105569224A (en) Concrete-filled steel tube edge restraint overlapping integrated shear wall and preparing and installation methods thereof
CN108678220B (en) Concrete shear wall with integrally installed reinforcing steel bar templates
CN203452228U (en) Frame-shear wall architectural structure
CN105155724A (en) Construction method of structural column for simultaneous construction with frame-structured filled wall
CN203808235U (en) Integral fabricated precast special-shaped column structure
CN108775084B (en) Steel-concrete combined precast beam and precast column connecting structure and construction method
CN201288328Y (en) Fixed foundation for beam and plate integrated prefabricated split mounting type tower crane
CN105113660A (en) Construction method of constructional column constructed simultaneously with framework structure infill wall
CN113338451A (en) Assembly type structure adaptive to deformed steel pipe column and construction method thereof
CN207812741U (en) Pre-manufactured steel structure overlapped shear wall
CN107355008B (en) Prefabricated connection structure and method for newly added concrete filled steel tubular column and existing structure
CN105220792A (en) A kind of prefabricated concealed bracings energy-consuming shear wall and assemble method thereof
CN204098219U (en) Bracket steel bar concrete frame connecting pin contact assembled architecture
CN204530982U (en) A kind of prefabricated assembled special-shaped wallette limb industrialization Housing Structure System
CN204645343U (en) Prefabricated assembled concrete out-hung panel fastening devices
CN105019645B (en) Fetch earth in contrary sequence method and the template system and construction method of xoncrete structure are built at mouth
CN111749364B (en) Assembled composite wall based on C-shaped steel and construction method thereof
CN105649259B (en) A kind of wallboard structural system of the dark framework of band of precast concrete wall panel and its structure
CN102242551B (en) Reinforcing bars building block reinforced concrete structure and shock insulation, shock absorption system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 650000 Kunming Institute of science and technology, Kunming University of Science and Technology, Yunnan Road, science and Technology Park, building A, building No. 296, building, building, building 2

Patentee after: Yunnan Construction Engineering Group Co., Ltd.

Address before: 650000 Kunming Institute of science and technology, Kunming University of Science and Technology, Yunnan Road, science and Technology Park, building A, building No. 296, building, building, building 2

Patentee before: Kunming Yingzao Project Design Co., Ltd.