CN204024010U - The flat sliding platform of a kind of high long cornice construction water - Google Patents

The flat sliding platform of a kind of high long cornice construction water Download PDF

Info

Publication number
CN204024010U
CN204024010U CN201420293120.0U CN201420293120U CN204024010U CN 204024010 U CN204024010 U CN 204024010U CN 201420293120 U CN201420293120 U CN 201420293120U CN 204024010 U CN204024010 U CN 204024010U
Authority
CN
China
Prior art keywords
cornice
high long
platform
long cornice
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420293120.0U
Other languages
Chinese (zh)
Inventor
刘志宏
王彦理
刘军洪
杨志军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG DONGYANG THIRD CONSTRUCTION ENGINEERING Co Ltd
Original Assignee
ZHEJIANG DONGYANG THIRD CONSTRUCTION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG DONGYANG THIRD CONSTRUCTION ENGINEERING Co Ltd filed Critical ZHEJIANG DONGYANG THIRD CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201420293120.0U priority Critical patent/CN204024010U/en
Application granted granted Critical
Publication of CN204024010U publication Critical patent/CN204024010U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The utility model relates to one and to cornice construction platform, is particularly useful for the construction platform that cornices that terrain clearance is high, width of encorbelmenting is large, belongs to the realm of building construction.Comprise sliding rail, slippage support component, vertical parts and operating platform, can by high long cornice side plate inclination angle, choose width, C type that up and down synthesis of cornice discrepancy in elevation design team and high long cornice adapt constructs, be arranged in high long cornice main stress structure, as high long cornice construction operating platform.Advantage: clearly stressed, safe and reliable, flexible operation, peace are torn quick, the favourable reduction of erection time open and are reduced construction cost.

Description

The flat sliding platform of a kind of high long cornice construction water
Technical field
The utility model relates to one and to cornice construction platform, is particularly useful for the construction platform that cornices that terrain clearance is high, width of encorbelmenting is large, belongs to the realm of building construction.
Background technology
For highlighting facade effect, a lot of building engineering is designed with high long cornice.When high long cornice construction, usually console mode or overhanging type operating platform need be set up below high long cornice.Cost set up by console mode operating platform affects larger by terrain clearance, scaffolding height is higher, and to set up cost larger, to set up and the dismounting cycle is long, workload is large, and construction of cornicing, platform removal construction speed directly affect the construction speed setting up the subsequent projects such as region decorating inner and external walls, surface line laying, hardened ground.Overhanging type operating platform must depend on major structure of construction and arrange supporting construction, has certain use limitation, supporting construction many employings shaped steel or steel pipe manufacturing, reliability is affected low by quality of connection such as Site Weldings, assembled cumbersome with dismounting, hanging operation amount is many, and security risk is large.
Summary of the invention
The purpose of this utility model is exactly in order to avoid the weak point in background technology, provide a kind of safe and reliable, construction cost is low, the flat sliding platform of high long cornice construction water of easy construction, short construction period.
The utility model will solve the technical scheme that its technical problem will adopt:
The flat sliding platform of a kind of high long cornice construction water, comprise sliding rail, slippage support component, vertical parts and operating platform, it is characterized in that: described sliding rail is fixed on the structural member of high long cornice outer edge, described slippage support component side is supported on described sliding rail, side is supported on high long cornice inside structure part, can along the slippage of described sliding rail any level, described vertical component upper ends is with affixed by slippage support component end described in cornice place on high long cornice, lower end is affixed with the described operating platform one end being positioned at high long cornice side plate bottom.
Described horizontal sliding platform can by high long cornice side plate inclination angle, choose width, C type that up and down synthesis of cornice discrepancy in elevation design team and high long cornice adapt constructs.
Described slippage support component is made up of supporting rod, tie element, draw-gear, carriage, cover plate.
Described vertical parts are connected to form by the vertical truss of two Pin, multiple tracks horizontal support keel, multiple tracks skewed horizontal load keel, adopt section steel manufacture.
Described operating platform is made up of platform keel, pedal, baseboard, handrail and going along with sb. to guard him.
Advantage of the present utility model:
1, in horizontal sliding platform focus point drops on and cornices, clearly stressed, structure is reliable.
2, horizontal sliding platform can along sliding rail horizontal sliding, flexible operation, is convenient to the construction of high long cornice.
3, horizontal sliding stage+module and demolishing process easy, quick.
4, exempt scaffold etc. to set up and demolition cost, high long cornice construction cost is obviously reduced.
5, high long cornice construction does not affect other project construction of below that cornices, and is conducive to the reduction of erection time.
Accompanying drawing explanation
Fig. 1 is horizontal sliding platform perspective view;
Fig. 2 is slippage supporting part structure schematic diagram described in Fig. 1;
Fig. 3 is parts structural representation vertical described in Fig. 1;
Fig. 4 is operating platform structural representation described in Fig. 1;
Fig. 5 is that horizontal sliding platform slides onto high long cornice assigned address and fixes schematic diagram.
Wherein: 1, sliding rail; 2, slippage support component; 3, vertical parts; 4, operating platform; 21, supporting rod; 22, tie element; 23, draw-gear; 24, carriage; 25, cover plate; 31, truss; 32, horizontal support keel; 33, skewed horizontal load keel; 41; Platform keel; 42, pedal; 43, baseboard; 44, handrail; 45, go along with sb. to guard him.
Detailed description of the invention
Embodiment: as shown in Fig. 1 ~ Fig. 5.The flat sliding platform of a kind of high long cornice construction water, comprise sliding rail (1), slippage support component (2), vertical parts (3) and operating platform (4), it is characterized in that: described horizontal sliding platform is arranged in high long cornice main stress structure, as high long cornice construction operating platform.Described sliding rail (1) is fixed on the structural member of high long cornice outer edge, described slippage support component (2) side is supported on described sliding rail (1), side is supported on high long cornice inside structure part, can along described sliding rail (1) any level slippage, described vertical parts (3) upper end is with affixed by slippage support component (2) end described in cornice place on high long cornice, and lower end is affixed with described operating platform (4) one end being positioned at high long cornice side plate bottom.
As shown in Figure 1, described horizontal sliding platform can by high long cornice side plate inclination angle, choose width, C type that up and down synthesis of cornice discrepancy in elevation design team and high long cornice adapt constructs.
As shown in Figure 2, described slippage support component (2) is made up of supporting rod (21), tie element (22), draw-gear (23), carriage (24), cover plate (25).Described carriage (24) comprises rolling bearing and roller.
As shown in Figure 3, described vertical parts (3) are connected to form by the vertical truss of two Pin (31), multiple tracks horizontal support keel (32), multiple tracks skewed horizontal load keel (33), adopt section steel manufacture.
As shown in Figure 4, described operating platform (4) is by platform keel (41), pedal (42), baseboard (43), handrail (44) with go along with sb. to guard him (45) and form.

Claims (4)

1. the one kind high flat sliding platform of long cornice construction water, comprise sliding rail (1), slippage support component (2), vertical parts (3) and operating platform (4), it is characterized in that: described sliding rail (1) is fixed on the structural member of high long cornice outer edge, described slippage support component (2) side is supported on described sliding rail (1), side is supported on high long cornice inside structure part, can along described sliding rail (1) any level slippage, described vertical parts (3) upper end is with affixed by slippage support component (2) end described in cornice place on high long cornice, lower end is affixed with described operating platform (4) one end being positioned at high long cornice side plate bottom.
2. the flat sliding platform of one according to claim 1 high long cornice construction water, is characterized in that: described horizontal sliding platform can by high long cornice side plate inclination angle, choose width, C type that up and down synthesis of cornice discrepancy in elevation design team and high long cornice adapt constructs.
3. the flat sliding platform of one according to claim 1 high long cornice construction water, is characterized in that: described slippage support component (2) is made up of supporting rod (21), tie element (22), draw-gear (23), carriage (24), cover plate (25).
4. the flat sliding platform of one according to claim 1 high long cornice construction water, is characterized in that: described operating platform (4) is by platform keel (41), pedal (42), baseboard (43), handrail (44) and go along with sb. to guard him (45) and form.
CN201420293120.0U 2014-05-30 2014-05-30 The flat sliding platform of a kind of high long cornice construction water Expired - Lifetime CN204024010U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420293120.0U CN204024010U (en) 2014-05-30 2014-05-30 The flat sliding platform of a kind of high long cornice construction water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420293120.0U CN204024010U (en) 2014-05-30 2014-05-30 The flat sliding platform of a kind of high long cornice construction water

Publications (1)

Publication Number Publication Date
CN204024010U true CN204024010U (en) 2014-12-17

Family

ID=52063895

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420293120.0U Expired - Lifetime CN204024010U (en) 2014-05-30 2014-05-30 The flat sliding platform of a kind of high long cornice construction water

Country Status (1)

Country Link
CN (1) CN204024010U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110905181A (en) * 2019-11-07 2020-03-24 广西建工集团第五建筑工程有限责任公司 7-shaped large-angle inner-inclined high-altitude sliding operation platform and construction method thereof
CN113137049A (en) * 2021-04-14 2021-07-20 方远建设集团股份有限公司 Large-span steel limb cornice construction platform
CN114809574A (en) * 2022-05-16 2022-07-29 北京江河幕墙系统工程有限公司 Construction device and construction method for building with oblique cornice structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110905181A (en) * 2019-11-07 2020-03-24 广西建工集团第五建筑工程有限责任公司 7-shaped large-angle inner-inclined high-altitude sliding operation platform and construction method thereof
CN113137049A (en) * 2021-04-14 2021-07-20 方远建设集团股份有限公司 Large-span steel limb cornice construction platform
CN114809574A (en) * 2022-05-16 2022-07-29 北京江河幕墙系统工程有限公司 Construction device and construction method for building with oblique cornice structure

Similar Documents

Publication Publication Date Title
CN204024010U (en) The flat sliding platform of a kind of high long cornice construction water
CN204001731U (en) A kind of shuttering supporting vertical rod base fixing device
CN204717144U (en) A kind of concrete pump pipe setting tool cribbing
CN202509681U (en) C-type steel of reinforced structure
CN201991226U (en) Flange template support structure
CN202000265U (en) Concrete construction formwork for high pier of bridge
CN102777050A (en) Assembly type jig frame for longspan pipe truss roof girder
CN203213019U (en) Cast-in-situ construction bracket system of long cantilever bent cap
CN101575890A (en) Girder and profiled steel sheet concrete combined floor construction method without support of hack lever
CN104018657A (en) Method for constructing high and large cornice through horizontal sliding platform
CN203834906U (en) Triangular operation platform used for capital construction slope face
CN201284559Y (en) Fastener type steel pipe scaffold template stand
CN204456813U (en) A kind of single support operation platform for elevator hoistways
CN205116776U (en) Support access structure
CN201614739U (en) Template bracket for roofing oblique beam
CN205046843U (en) Reinforcing apparatus's stair template of marking time in middle of installation
CN203961258U (en) Builder's jack foot guard structure
CN203795824U (en) Suspension type fastener scaffold erecting device
CN206267039U (en) A kind of jack support platform of hollow slab girder jack-up construction
CN105649317A (en) Fixing mechanism for cantilever I-beam
CN103114713B (en) The construction method of hollow ultrahigh template section steel platform
CN203394008U (en) Suspension type hanging bracket used on plane truss
CN205840326U (en) A kind of stair template fixing device
CN202064621U (en) Conventionalized operation platform for construction of elevator shaft
CN203961239U (en) High-altitude overhanging awning construction operation platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant