CN204000874U - The structure of a kind of concrete plug backfill grouting - Google Patents

The structure of a kind of concrete plug backfill grouting Download PDF

Info

Publication number
CN204000874U
CN204000874U CN201420421162.8U CN201420421162U CN204000874U CN 204000874 U CN204000874 U CN 204000874U CN 201420421162 U CN201420421162 U CN 201420421162U CN 204000874 U CN204000874 U CN 204000874U
Authority
CN
China
Prior art keywords
grouting
concrete plug
backfill grouting
backfill
plug
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420421162.8U
Other languages
Chinese (zh)
Inventor
周先练
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201420421162.8U priority Critical patent/CN204000874U/en
Application granted granted Critical
Publication of CN204000874U publication Critical patent/CN204000874U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses the structure of a kind of concrete plug backfill grouting, it is to be hoop to distribute more than two backfill grouting supervisor (2) is set at concrete plug (1) crown position, and every backfill grouting supervisor's (2) both sides are extended two and above are responsible for backfill grouting the grouting arm (3) that (2) intersect; Be provided with a stack (4) that stretches into plug inside in the top of concrete plug (1), be respectively provided with an expansion waterstop (5) for grouting at the top at the two ends of concrete plug (1).The utility model carries out backfill grouting by replacing traditional backfill grouting gallery at the pre-buried backfill grouting pipe in concrete plug top to concrete plug top, and working procedure is simple, quick construction is convenient, technology is reliable.

Description

The structure of a kind of concrete plug backfill grouting
Technical field
The utility model relates to a kind of structure that solves the backfill grouting of concrete plug, belongs to Hydraulic and Hydro-Power Engineering technical field.
Background technology
At present, at home in hydroelectric project, Ni Po as genial in bridge in lattice power station, after Diversion Tunnel or a construction hole concrete plug have been constructed, concrete plug is carried out to backfill grouting, generally inner reserved irrigation gallery during concrete plug body construction, according to grouting construction requirement, irrigation gallery size is generally 3 × 3.5m(wide × height).When concrete plug possess backfill grouting condition be take grouting equipment by irrigation gallery injection backfill grouting hole to reach backfill grouting object.According to hydroelectric project feature, for reaching as early as possible dash object, the concrete plug engineering construction duration is generally very nervous, in the time that constructing, concrete plug reserves irrigation gallery therein, need installation form, assembling reinforcement etc., working procedure complexity, the construction period is longer, take effective construction period of concrete plug, had a strong impact on the construction speed of concrete plug; In addition, the backfill grouting post-grouting gallery of having constructed need carry out just carrying out concrete backfill after dabbing, has strengthened engineering human and material resources and has dropped into, and has increased construction investment.Therefore, the technical measures of existing concrete plug backfill grouting or not ideal enough, await further perfect.
Utility model content
The purpose of this utility model is as overcoming the deficiencies in the prior art, the structure of a kind of concrete plug backfill grouting is provided, can ensure concrete plug backfill grouting construction quality by pre-buried backfill grouting pipe and expansion waterstop, construction technology is simple simultaneously, quick construction convenient, accelerate the concrete plug construction period, save human and material resources resource and drop into, reduce construction cost.
The purpose of this utility model is achieved by following technical solution:
The structure of concrete plug of the present utility model backfill grouting, comprise concrete plug, be hoop distribution at this concrete plug crown position more than two backfill grouting supervisors is set, every backfill grouting supervisor's both sides are extended two and above be responsible fors with backfill grouting the grouting arm intersecting, and the slurries of grouting can flow in arm by being responsible for; Be provided with a stack that stretches into plug inside in the top of concrete plug, exhaust when stack is used for grouting construction, is respectively provided with an expansion waterstop for grouting at the top at the two ends of concrete plug.
Further, backfill grouting supervisor and stack adopt cleek to be fixed on concrete plug crown position.The quantity of cleek will guarantee to fixedly secure backfill grouting supervisor and stack.
Further, backfill grouting supervisor, grouting arm and stack are pvc pipe or PE pipe.Certainly, also can adopt other operable grouting pipeline in engineering.
The beneficial effects of the utility model are:
Compared with prior art, the utility model carries out backfill grouting by replacing traditional backfill grouting gallery at the pre-buried backfill grouting pipe in concrete plug top to concrete plug top, and working procedure is simple, quick construction is convenient, technology is reliable; By the pre-buried backfill grouting arm of being responsible for and being in the milk, when grouting construction, guarantee better fill concrete plug apex cavity of slurries, guarantee backfill grouting construction quality; When backfill grouting construction, slurries will squeeze the gas at concrete plug crown position, and gas is drained by the stack of top; Plug two ends adopt expansion waterstop grouting, after waterstop is met water, expand, and concrete plug apex cavity is played to good sealing effectiveness, guarantee that slurries can seepage; Backfill grouting pipe Embedment Construction technique is simple, and the later stage does not need to remove, and can not affect the operation of concrete plug engineering safety; Backfill grouting pipe and stack are generally taked PVC or PE pipe, and market plane is easy to buying, invest littlely, and backfill grouting pipe is for higher hardness, can not produce deformation and failure when backfill grouting, can ensure backfill grouting quality; Cleek is easy to construction, can preferably backfill grouting pipe and stack be fixed on to concrete plug top.The utility model construction technology is simple, and constructability is economic and practical, can be in Construction for Hydroelectric Project technical field wide popularization and application.
brief description of the drawings
Fig. 1 is that the utility model plane is shown schematic diagram;
Fig. 2 is the A-A sectional drawing of Fig. 1.
In figure: 1-concrete plug, 2-backfill grouting supervisor, 3-backfill grouting arm, 4-stack, 5-expansion waterstop, 6-cleek.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is described in further detail.
As shown in Figure 1 and Figure 2, this grouting structure of the present utility model, comprise concrete plug 1 and be embedded in advance backfill grouting supervisor 2, grouting arm 3, stack 4 and the expansion waterstop 5 at concrete plug 1 top, backfill grouting supervisor 2 and stack 4 are fixed on concrete plug 1 top by cleek 6, and backfill grouting supervisor 2 is connected with grouting arm 3.Adopt these technical measures, directly backfill grouting supervisor 2 and grouting arm 3 are embedded in to concrete plug 1 top formation backfill grouting construction passage in advance, backfill grouting supervisor 2 and grouting arm 3 installation operations are simple, efficient and convenient, accelerating construction progress greatly, and the later stage does not need to remove, and does not affect 1 safe operation of concrete plug; Backfill grouting supervisor 2 and grouting arm 3 are easy to buying, invest littlely, have reduced construction cost.
As shown in Figure 1, the utility model is in the time implementing, first before 1 construction of concrete plug, backfill grouting supervisor 2, grouting arm 3, stack 4 and expansion waterstop 5 are embedded in to concrete plug 1 top in advance, wherein stack 4 is placed in top, expansion waterstop 5 is placed in concrete plug 1 crown two ends, backfill grouting supervisor 2 is connected with grouting arm 3, backfill grouting supervisor 2 and stack 4 are fixed to (as shown in Figure 2) by some cleeks 6.In the time that 1 concrete construction of concrete plug completes and reaches the pustulation period, to be responsible for 2 by backfill grouting and to be in the milk, slurries enter grouting arm 3 and are finally filled in the space of concrete plug 1 from backfill grouting supervisor 2, reach the object of backfill grouting.In the time of grouting construction, the gas in concrete plug 1 is discharged by stack 4, and grouting is sealed by expansion waterstop 5 in the two ends of concrete plug 1.
Certainly, be more than concrete exemplary applications of the present utility model, the utility model also has other embodiment, and all employings are equal to the technical scheme of replacement or equivalent transformation formation, within all dropping on the desired protection domain of the utility model.

Claims (3)

1. the structure of concrete plug backfill grouting, comprise concrete plug (1), it is characterized in that: be hoop at described concrete plug (1) crown position and distribute more than two backfill grouting supervisor (2) is set, every backfill grouting supervisor's (2) both sides are extended two and above are responsible for backfill grouting the grouting arm (3) that (2) intersect; Be provided with a stack (4) that stretches into plug inside in the top of described concrete plug (1), be respectively provided with an expansion waterstop (5) for grouting at the top at the two ends of described concrete plug (1).
2. the structure of concrete plug according to claim 1 backfill grouting, is characterized in that: described backfill grouting supervisor (2) and stack (4) adopt cleek (6) to be fixed on concrete plug (1) crown position.
3. the structure of concrete plug according to claim 2 backfill grouting, is characterized in that: described backfill grouting supervisor (2), grouting arm (3) and stack (4) are pvc pipe or PE pipe.
CN201420421162.8U 2014-07-29 2014-07-29 The structure of a kind of concrete plug backfill grouting Active CN204000874U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420421162.8U CN204000874U (en) 2014-07-29 2014-07-29 The structure of a kind of concrete plug backfill grouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420421162.8U CN204000874U (en) 2014-07-29 2014-07-29 The structure of a kind of concrete plug backfill grouting

Publications (1)

Publication Number Publication Date
CN204000874U true CN204000874U (en) 2014-12-10

Family

ID=52040899

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420421162.8U Active CN204000874U (en) 2014-07-29 2014-07-29 The structure of a kind of concrete plug backfill grouting

Country Status (1)

Country Link
CN (1) CN204000874U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104790401A (en) * 2015-04-24 2015-07-22 浙江海洋学院 Material spraying and stirring construction device for filling foundation pit through building dredging mud
CN104929089A (en) * 2015-06-10 2015-09-23 中国电建集团贵阳勘测设计研究院有限公司 Small-section construction adit plugging structure and construction method thereof
CN106226129A (en) * 2016-07-06 2016-12-14 江苏科华医疗器械科技有限公司 A kind of closed type urine sampler

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104790401A (en) * 2015-04-24 2015-07-22 浙江海洋学院 Material spraying and stirring construction device for filling foundation pit through building dredging mud
CN104790401B (en) * 2015-04-24 2016-05-25 浙江海洋学院 A kind of building dredging mud foundation ditch embankment material spray stirs constructing device
CN104929089A (en) * 2015-06-10 2015-09-23 中国电建集团贵阳勘测设计研究院有限公司 Small-section construction adit plugging structure and construction method thereof
CN106226129A (en) * 2016-07-06 2016-12-14 江苏科华医疗器械科技有限公司 A kind of closed type urine sampler

Similar Documents

Publication Publication Date Title
CN203498799U (en) Prefabricated hollow pipe pile water-facing envelop enclosure
CN104115586B (en) Heavy salinized ground administering method in one
CN204000874U (en) The structure of a kind of concrete plug backfill grouting
CN203808265U (en) Blocking structure for small reserved opening members of floor
CN205857190U (en) A kind of steel-pipe pile segmenting slip casting structure
CN204282292U (en) A kind of wave wall structure reducing wave run-up
CN203795398U (en) Structure for backfilling and reconstructing diversion hole of reservoir into flood discharge hole
CN203307776U (en) Concrete face rock fill dam toe board structure
CN206438679U (en) Prefabricated components grout sleeve preventing clogging up device
CN204252119U (en) The special-shaped supporting pile structure of X
CN203716116U (en) Pulp stopping structure used in diversion tunnel concrete end plug vault backfill grouting
CN204212168U (en) A kind of dam water-retaining structure utilizing solution cavity to combine to build a dam
CN203113359U (en) Earth rock cofferdam structure
CN102182480B (en) Mortar anchor constructing method
CN207003440U (en) A kind of foundation ditch spring water treatment system
CN203729280U (en) Water retaining structure of lower sluice gate for blocking lower water head flow-guiding hole
CN209053074U (en) The surface grouting structure of diversion outlet closuring concrete
CN202645593U (en) Waterproof construction for anti-floating anchor node of shield tunnel
CN204570705U (en) Three-dimensional post jacking structure is held in a kind of artificial grouting layer method stake
CN104018475B (en) A kind of embedded penstock backfill grouting structure and grouting process thereof
CN204608695U (en) A kind of New-old concrete horizontal bedding syndeton
CN203654310U (en) Anchoring structure used for impervious layer of oil tank ring beam foundation
CN109706932A (en) A kind of solution cavity stopper structure and construction method
CN203890980U (en) Backfilling and grouting structure for buried pressure pipe
CN205012372U (en) Novel waterproof post -cast strip of side wall structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant