CN204608695U - A kind of New-old concrete horizontal bedding syndeton - Google Patents

A kind of New-old concrete horizontal bedding syndeton Download PDF

Info

Publication number
CN204608695U
CN204608695U CN201520203592.7U CN201520203592U CN204608695U CN 204608695 U CN204608695 U CN 204608695U CN 201520203592 U CN201520203592 U CN 201520203592U CN 204608695 U CN204608695 U CN 204608695U
Authority
CN
China
Prior art keywords
reinforcing bar
concrete
old concrete
reserved
old
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520203592.7U
Other languages
Chinese (zh)
Inventor
陈小东
雷声军
高传彬
李刚
李社凤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201520203592.7U priority Critical patent/CN204608695U/en
Application granted granted Critical
Publication of CN204608695U publication Critical patent/CN204608695U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The utility model discloses a kind of New-old concrete horizontal bedding syndeton, comprise old concrete and as placed concrete, reinforcing bar A is reserved with in described old concrete, post-installing rebar B in described as placed concrete, as placed concrete is adopted by reinforcing bar A reserved in post-installing rebar B and old concrete and is welded to connect; Described reinforcing bar B implants in old concrete in the boring of distance reinforcing bar A opposite position 10 ~ 20cm place, is weldingly connected after the top fold of described reinforcing bar B with the reinforcing bar A be reserved in old concrete.The utility model can determine the stability of superstructure, simultaneously more simple, convenient when the aspect of process, is conducive to accelerating engineering construction progress; And connecting reinforcement can be implanted in the position boring apart from the corresponding inner side 10cm ~ 20cm of former reserved steel bar, does not destroy the horizontal steel bar in old concrete and original concrete cover; Can drop into large number quipments, bit penetrating rate is fast, and efficiency is high.

Description

A kind of New-old concrete horizontal bedding syndeton
Technical field
The utility model belongs to Hydraulic and Hydro-Power Engineering technical field, particularly relates to a kind of New-old concrete horizontal bedding syndeton.
Background technology
In hydraulic structure, reserved steel bar in former concrete structure aspect usually, plays connection function to reinforcing bar during later stage top concrete construction.Because this building is flood discharge overcurrent building, construction by stages is needed to complete according to factors such as the function of itself and the impacts of duration; After the first stage has constructed, current need through completing part, and water flow is larger, top reserved part reinforcing bar is made to be in the effect of surge pressure frequently, so along with the prolongation of time, reserved steel bar intensity is reduced, structural plane is caused to be in weak link, stablizing of unfavorable structure.For the process of follow-up concrete structure aspect, prior art mainly carries out intensity detection to reserved steel bar, according to testing result, it is assessed, whether meet the requirement of strength of subsequent structural, if do not meet and need remove this part reinforcing bar, be welded to connect new reinforcing bar, this situation easily destroys original structure, unfavorable to structure.Whole detection simultaneously, replacement process time length, complex procedures, be unfavorable for quality and the progress of engineering.
Utility model content
For solving the problem, the utility model provides a kind of New-old concrete horizontal bedding syndeton.Thus determine the stability of superstructure, and more simple, convenient when the aspect of process, be conducive to accelerating engineering construction progress.
The utility model is achieved by following technical solution.
A kind of New-old concrete horizontal bedding syndeton, comprise old concrete and as placed concrete, be reserved with reinforcing bar A in described old concrete, post-installing rebar B in described as placed concrete, as placed concrete is adopted by reinforcing bar A reserved in post-installing rebar B and old concrete and is welded to connect.
Described reinforcing bar B implants in old concrete in the boring of distance reinforcing bar A opposite position 10 ~ 20cm place.
Be weldingly connected with the reinforcing bar A be reserved in old concrete after the top fold of described reinforcing bar B.
The beneficial effects of the utility model are:
Compared with prior art, the utility model enables later stage concrete structure meet the model of structural calculation, ensures that the combination of structural level meets the demands, determines the stability of superstructure, simultaneously more simple, convenient when the aspect of process, be conducive to accelerating engineering construction progress.Connecting reinforcement can be implanted in the position boring apart from the corresponding inner side 10cm ~ 20cm of former reserved steel bar simultaneously, does not destroy the horizontal steel bar in old concrete and original concrete cover; Can drop into large number quipments, bit penetrating rate is fast, and efficiency is high; After connecting reinforcement welds with reserved steel bar, structural integrity is good, has broad application prospects.
Accompanying drawing explanation
Fig. 1 is the syndeton schematic diagram of old concrete and as placed concrete;
Fig. 2 is old concrete deck structure schematic diagram in the utility model;
Fig. 3 is post-installing rebar structural representation in the utility model.
In figure: 1-old concrete, 2-bond between fresh and hardened concretes aspect, the outer as placed concrete of 3-reinforcing bar A, 4-, 5-reinforcing bar B.
Detailed description of the invention
The technical solution of the utility model is further described below in conjunction with accompanying drawing, but described in claimed scope is not limited to.
As shown in Figure 1 to Figure 3, a kind of New-old concrete horizontal bedding syndeton described in the utility model, comprise old concrete 1 and as placed concrete 4, reinforcing bar A3 is reserved with in described old concrete 1, post-installing rebar B5 in described as placed concrete 4, as placed concrete 4 is adopted by reinforcing bar A3 reserved in post-installing rebar B5 and old concrete 1 and is welded to connect.In the technical program, said as placed concrete 4 is rear pouring concrete, and old concrete 1 is first pouring concrete, when implementing, by implanting reinforcing bar B5 in bond between fresh and hardened concretes aspect 2, is weldingly connected by reinforcing bar A3 reserved in reinforcing bar B5 and old concrete 1.Reinforcing bar A3 reserved in described old concrete 1 is as the structure reinforcing bars of follow-up concreting.
Described reinforcing bar B5 implants in old concrete 1 in the boring of distance reinforcing bar A3 opposite position 10 ~ 20cm place.And the rear anchorage length of reinforcing bar B5 in old concrete 1 implanted meets code requirement.
Be weldingly connected with the reinforcing bar A3 be reserved in old concrete 1 after the top fold of described reinforcing bar B5.
As shown in Figure 2, the utility model mainly carries out in accordance with the following steps when implementing:
The first step, 10 ~ 20cm distance range internal drilling of corresponding reserved steel bar A3 on old concrete 1, and hole depth meets code requirement;
Second step, is processed into the pattern of bending by reinforcing bar B5;
3rd step, the first step the reinforcing bar B5 after being implanted into bending that holes;
4th step, adopts the working of neo-implanted reinforcing bar B5 and reserved steel bar A3 and is welded to connect.
The utility model has applied in the construction of one-level power station, pillow dam 3# ~ 5# sluice gate pier.Due to 3# ~ 5# sluice gate pier be poured into 595 elevations after need to carry out overcurrent as diversion canal section, but the reinforcing bar of Gate Piers needs to be reserved on gate pier in advance.Through the large discharge overcurrent in two flood seasons, reinforcing bar reserved on gate pier produces fatigue damage by the impact of current, and part reinforcing bar does not reach designing requirement in the intensity close to New-old concrete aspect position.For meeting field engineering schedule requirement, adopt bar planting inside reserved steel bar in aspect, implant reinforcing bar to be welded to connect by bending and former reserved steel bar on top, complete the connection of lower rebar and upper reinforcement in this way, from practical application achievement, respond well, and improve efficiency, accelerate construction speed.

Claims (3)

1. a New-old concrete horizontal bedding syndeton, it is characterized in that: comprise old concrete (1) and as placed concrete (4), reinforcing bar A (3) is reserved with in described old concrete (1), the interior post-installing rebar B (5) of described as placed concrete (4), as placed concrete (4) is adopted by reinforcing bar A (3) reserved in post-installing rebar B (5) and old concrete (1) and is welded to connect.
2. a kind of New-old concrete horizontal bedding syndeton according to claim 1, is characterized in that: described reinforcing bar B (5) is implanted in old concrete (1) in the boring of distance reinforcing bar A (3) opposite position 10 ~ 20cm place.
3. a kind of New-old concrete horizontal bedding syndeton according to claim 1, is characterized in that: be weldingly connected with the reinforcing bar A (3) be reserved in old concrete (1) after the top fold of described reinforcing bar B (5).
CN201520203592.7U 2015-04-07 2015-04-07 A kind of New-old concrete horizontal bedding syndeton Active CN204608695U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520203592.7U CN204608695U (en) 2015-04-07 2015-04-07 A kind of New-old concrete horizontal bedding syndeton

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520203592.7U CN204608695U (en) 2015-04-07 2015-04-07 A kind of New-old concrete horizontal bedding syndeton

Publications (1)

Publication Number Publication Date
CN204608695U true CN204608695U (en) 2015-09-02

Family

ID=53961256

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520203592.7U Active CN204608695U (en) 2015-04-07 2015-04-07 A kind of New-old concrete horizontal bedding syndeton

Country Status (1)

Country Link
CN (1) CN204608695U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107012892A (en) * 2017-04-14 2017-08-04 中建五局土木工程有限公司 New-old concrete interface waterproof construction and processing method
CN109518985A (en) * 2018-10-10 2019-03-26 广东省建筑设计研究院 A kind of design and construction method improving the power transmission of new-old concrete interface

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107012892A (en) * 2017-04-14 2017-08-04 中建五局土木工程有限公司 New-old concrete interface waterproof construction and processing method
CN109518985A (en) * 2018-10-10 2019-03-26 广东省建筑设计研究院 A kind of design and construction method improving the power transmission of new-old concrete interface

Similar Documents

Publication Publication Date Title
CN101614125B (en) Construction method of V-level surrounding rock tunnel
CN205116185U (en) A supporting construction for weak soil foundation ditch
CN105780719A (en) Heightened construction method for active service stone building bank protecting wall
CN109826084A (en) A kind of aqueduct method for repairing seepage
CN103225285A (en) Steel membrane concrete faced rockfill dam
CN204608695U (en) A kind of New-old concrete horizontal bedding syndeton
CN106592580B (en) A kind of the prefabricated pile device and its construction method of the fast permeable speed of self-pressurization
CN215629929U (en) Novel site operation structure of anti-floating anchor rod
CN203307776U (en) Concrete face rock fill dam toe board structure
CN105927246A (en) High-pressure tunnel lining concrete uplift failure repair method
CN207260148U (en) Service sleeve pile crown integrally abolishes device
CN203768914U (en) Foundation pit bracing diagonal support pile structure
CN203782695U (en) Reinforced tube pile concrete structure
CN106337530B (en) A kind of construction of frame beam seams stifled construction method
CN103741651B (en) A kind of concrete teeth groove stiling basin and construction method thereof
CN203741792U (en) Concrete tooth groove stilling basin
CN108755721A (en) A kind of novel cofferdam method for protecting support for crossing piping lane construction in water river
CN204356915U (en) The self waterproof structure that steel pipe column is crossing with concrete of basement exterior wall
CN210827553U (en) Consolidate retaining wall structure
CN107964975A (en) The PBL shear connectors connection structure and its construction method of steel pipe composite pile and cushion cap
CN209585028U (en) A kind of open caisson applies broken pile
CN203891028U (en) Supporting structure of reinforced steel sheet piles and core tube bracings in deep foundation pit
CN208455615U (en) A kind of prefabricated guide groove structure of concrete cut
CN203729280U (en) Water retaining structure of lower sluice gate for blocking lower water head flow-guiding hole
CN104762924A (en) Upper storage reservoir basin seepage preventing method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant