CN204000845U - A kind of dry energy-conservation down-hole hammer castinplace pile and equipment thereof of fetching earth - Google Patents

A kind of dry energy-conservation down-hole hammer castinplace pile and equipment thereof of fetching earth Download PDF

Info

Publication number
CN204000845U
CN204000845U CN201420228435.7U CN201420228435U CN204000845U CN 204000845 U CN204000845 U CN 204000845U CN 201420228435 U CN201420228435 U CN 201420228435U CN 204000845 U CN204000845 U CN 204000845U
Authority
CN
China
Prior art keywords
pile
hole hammer
energy
machine
conservation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420228435.7U
Other languages
Chinese (zh)
Inventor
陈开向
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou Rong Qiang Ocean Science Co Ltd
Original Assignee
Wenzhou Rong Qiang Ocean Science Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou Rong Qiang Ocean Science Co Ltd filed Critical Wenzhou Rong Qiang Ocean Science Co Ltd
Priority to CN201420228435.7U priority Critical patent/CN204000845U/en
Application granted granted Critical
Publication of CN204000845U publication Critical patent/CN204000845U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

A kind of dry feature that fetches earth energy-conservation down-hole hammer castinplace pile is: stake footpath 500-1000mm, the long <90m of stake, pile body upper soil horizon is completed by pipeline sinking pile machine or long-spiral drilling machine or the two collocation, pile body bottom hard rock, by energy-conservation down-hole hammer rig rock drilling pore-forming, then place the reinforced concrete pile of reinforcing cage and concrete perfusion.Its apparatus characteristic is in down-hole hammer impactor upper end, to be provided with permeable rock dust ballast aggregate bin, and drilling rod is polished rod under polished rod or upper spiral.Compare with existing down-hole hammer, no matter the tens of rice of hole depth also only needs 2 25m 3/ minute air compressor machine, whole pile Energy Consumption of Construction reduces by 50%, and equipment continuous productive process improves one times of work efficiency; Compare with percussive drill, mud-less pollution not only, more importantly work efficiency improves 8-10 doubly, completes a pile from several days, develops into and within one day, completes 5-10 pile.

Description

A kind of dry energy-conservation down-hole hammer castinplace pile and equipment thereof of fetching earth
Technology neck city
Utility model relates to building foundation field, relates in particular to a kind of dry energy-conservation down-hole hammer castinplace pile and equipment thereof of fetching earth.
Background technology
At home in pile foundation engineering, common seashore, Bian Huo hilly ground, mountain, pile foundation top is tens meters to tens meters thick sandy soil layers or Soft Soil Layer, and end is hard rock more than 50MPa, and as bearing stratum, design specifications requires into rock 1-3d, or more.At present, the conventional percussive drill construction of this class engineering, must take one to three day time in order to enter rock.
Down-hole hammer rig belongs to high energy consumption; Depth of pore forming 10-25m, needs 20-25m 3/ minute, 2 of the air compressor machines of 180kw power, add unit head 90-110kw on a machine, lower unit head 180-220kw, needs 630-670kw altogether.And the every increase of hole depth 10m, increases 20-25m 31 of/minute air compressor machine, therefore, hole depth surpasses 35m, in China, is to be constructed by percussive drill with several tons of weight heads substantially.
Utility model content
The purpose of this utility model is to provide a kind of dry energy-conservation down-hole hammer castinplace pile and equipment thereof of fetching earth, can be by pile body upper soil horizon pore-forming, the pipeline sinking pile machine of fast, the dry operation of, speed low by construction cost or long-spiral drilling machine or the two collocation complete, the pore-forming of pile body end hard rock, is completed by energy-conservation down-hole hammer rig.
The purpose of this utility model is to be achieved through the following technical solutions: a kind of dry feature that fetches earth energy-conservation down-hole hammer castinplace pile is: stake footpath 500-1000mm, the long <90m of stake, pile body upper soil horizon is completed by pipeline sinking pile machine or long-spiral drilling machine or the two collocation, pile body bottom hard rock, by energy-conservation down-hole hammer rig rock drilling pore-forming, then place the reinforced concrete pile of reinforcing cage and concrete perfusion.
A kind of equipment of the dry energy-conservation down-hole hammer castinplace pile that fetches earth like the prior art, all there is air compressor machine, high pressure airline hose, unit head, drilling rod, impactor and chisel head, it is characterized in that: in down-hole hammer impactor upper end, be provided with permeable rock dust ballast aggregate bin, aggregate bin bottom or side are established discharging switch, and drilling rod is polished rod under polished rod or upper spiral.Aggregate bin number is depending on muck removal amount, and aggregate bin back cut diameter equals or is not equal to diameter at the bottom of lower bucket.
No matter domestic abroad, existing down-the-hole hammer drill machine technology only considers ballast to go out the tap of ground at the bottom of tens meters of dark holes, so power, wind speed, air quantity can constantly increase along with the increase of the degree of depth.In Code For Design of Building regulation: entering rock stake is end bearing pile, its draw ratio≤80, so 0.6-0.8m be take as main in the stake footpath of China's wide geographic area architectural design, enter rock 1-3d (stake footpath), and rock dust ballast volume is 0.3-1.3m only 3, in fact, after rock drilling pore-forming, muck removal again while proposing drilling tool.With 2 air compressor machines, drive downhole hammer rocks like this, then ballast is blown to high several meters, and to fall into aggregate bin be energy-conserving product.When the water yield is larger in hole, above aggregate bin, establishes minor diameter submersible pump and draw water.
The utility model is compared with existing down-hole hammer, no matter the tens of rice of hole depth also only needs 2 25m 3/ minute air compressor machine, whole pile Energy Consumption of Construction reduces by 50%, and equipment continuous productive process improves one times of work efficiency; Compare with percussive drill, mud-less pollution not only, more importantly work efficiency improves 8-10 doubly, completes a pile from several days, develops into and within one day, completes 5-10 pile.
Accompanying drawing explanation
Fig. 1 is the embodiment generalized section of the utility model castinplace pile.
In Fig. 1: 1. basement bottom board, 2. layer of sand, 3. cushion cap, 4. goes up pile body, 5. mud, 6. argillic horizon, 7. descends pile body, 8. granite.
Fig. 2 is the generalized section of the utility model aggregate bin and down-hole hammer part.
9. the drilling rod of central airway, 10. aggregate bin, 11. impactors, 12. chisel heads.
The specific embodiment
As Fig. 1 and Fig. 2, the construction sequence of an exemplary embodiments of the utility model is as follows:
1. according to Fig. 1, embodiment geology is weak soil, if do not allowed soil compaction, two case pile machines are stood on stake position, shake heavy two sleeve pipes through layer of sand (2) and mud (5), extremely compared with hard viscosity layer (6), quiet pull out interior tube vibration unload soil or open folding inner tube pin unload soil outside hole, stay outer tube guard aperture; As allow soil compaction, and single pipeline sinking pile machine is stood on to stake position upper, immersed tube lower ending opening, and be placed in low grade element concrete pile top, the heavy single immersed tube that shakes, to compared with hard viscosity layer (), stays steel immersed tube guard aperture, and pipeline sinking pile machine moves to next position and continues construction;
2. long-spiral drilling machine is stood on to a limit, hole, from steel immersed tube bottom compared with hard viscosity layer (6), creep into granite (8) face, mention drilling tool, rig moves next position construction (without weak soil by the direct pore-forming of long-spiral drilling machine);
3. energy-conservation down-hole hammer rig is stood on to a limit, hole, the down-hole hammer of band chisel head (12) and impactor (11) is put into bedrock surface from steel immersed tube, start air compressor machine, compressed air acts on impactor (11), drive again chisel head (12) that granite (8) is cut a hole broken, the compressed air of discharging is upwards blown into aggregate bin (10) by rock dust ballast, until cut a hole to design elevation;
4. mention aggregate bin (10), impactor (11) and chisel head (12) that rock dust ballast is housed and unload quarrel outside stake hole, then move to next position construction;
5. by existing technology to install reinforcing cage in hole with fill with concrete, complete the construction of a basic utility model castinplace pile, go round and begin again, complete the construction of all the utility model castinplace piles.

Claims (2)

1. a dry feature that fetches earth energy-conservation down-hole hammer castinplace pile is: stake footpath 500-1000mm, the long < 90m of stake, pile body upper soil horizon is completed by pipeline sinking pile machine or long-spiral drilling machine or the two collocation, pile body bottom hard rock, by energy-conservation down-hole hammer rig rock drilling pore-forming, then place the reinforced concrete pile of reinforcing cage and concrete perfusion.
2. a kind of equipment of the dry energy-conservation down-hole hammer castinplace pile that fetches earth according to claim 1, there is air compressor machine, high pressure airline hose, unit head, drilling rod, impactor and chisel head, it is characterized in that: in down-hole hammer impactor upper end, be provided with permeable rock dust ballast aggregate bin, aggregate bin bottom or side are established discharging switch, and drilling rod is polished rod under polished rod or upper spiral.
CN201420228435.7U 2014-05-06 2014-05-06 A kind of dry energy-conservation down-hole hammer castinplace pile and equipment thereof of fetching earth Expired - Fee Related CN204000845U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420228435.7U CN204000845U (en) 2014-05-06 2014-05-06 A kind of dry energy-conservation down-hole hammer castinplace pile and equipment thereof of fetching earth

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420228435.7U CN204000845U (en) 2014-05-06 2014-05-06 A kind of dry energy-conservation down-hole hammer castinplace pile and equipment thereof of fetching earth

Publications (1)

Publication Number Publication Date
CN204000845U true CN204000845U (en) 2014-12-10

Family

ID=52040871

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420228435.7U Expired - Fee Related CN204000845U (en) 2014-05-06 2014-05-06 A kind of dry energy-conservation down-hole hammer castinplace pile and equipment thereof of fetching earth

Country Status (1)

Country Link
CN (1) CN204000845U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103981860A (en) * 2014-05-06 2014-08-13 温州荣强海洋科技有限公司 Energy-saving down-the-hole hammer cast-in-place pile and equipment for taking dry soil

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103981860A (en) * 2014-05-06 2014-08-13 温州荣强海洋科技有限公司 Energy-saving down-the-hole hammer cast-in-place pile and equipment for taking dry soil

Similar Documents

Publication Publication Date Title
CN104832208B (en) Anti-collapse method for long-distance horizontal hole drilling in soft coal seam of underground coal mine
CN203625893U (en) Rock-embedded cast-in-place pile
CN104295239A (en) Method for using rotary drilling rig to drill into hard rock stratum
CN103046931B (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN2866602Y (en) Long-auger drill reaming bottom stirring and in-hole reaming concrete pile-grouting piling apparatus
CN102383431A (en) Sinking device and novel sinking method of center dug prestressed centrifuge pipe pile (square pile)
CN103835648A (en) Raise-boring technology for improving rock stratum performance through ground grouting
CN106120789A (en) The interior pile sinking process boring vibration PHC tube pile of major diameter
CN106930276A (en) The deep hole blasting of rotary digging bored concrete pile and the construction method of conduit rotary digging removing obstacles
CN106149683A (en) A kind of cast-in-place pile construction method using double casing to pass through deep metalling
CN103981860A (en) Energy-saving down-the-hole hammer cast-in-place pile and equipment for taking dry soil
CN203584301U (en) Hole guide equipment
CN204299468U (en) A kind of positioning and guiding system and device of hidden hole drilling boring
CN103243712A (en) Caterpillar end-expanded filling pile with pneumatic down-the-hole hammer and quick construction method of caterpillar end-expanded filling pile
CN103485344A (en) Method for extracting construction engineering pile foundation
CN102383428B (en) Middle pick reverse drawing method prestressed centrifugally pile tube pile-sinking device and pile-sinking method thereof
CN102644274A (en) Pile-forming construction method for penetrating through existing structure by fender post
CN204000845U (en) A kind of dry energy-conservation down-hole hammer castinplace pile and equipment thereof of fetching earth
CN103850248A (en) Construction process and device of end-bearing pile hole
CN202611632U (en) Cast-in-place drilled/punched pile construction plant with mud pit and mud separating device
CN104264662A (en) Construction method for deeply embedding hard rock secant pile in soil layer being rich in water
CN205804362U (en) The long screw auger drilling deposited pile constructing device of rock can be entered
CN103452473B (en) One utilizes tunneling boring high counterweight drill bit device to carry out small-diameter deep well construction method
CN205934924U (en) A pile sinking device that in being used for, bores vibration major diameter PHC tubular pile
CN115559661A (en) Pile foundation hole digging machine for building engineering

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
DD01 Delivery of document by public notice

Addressee: Wenzhou Rong Qiang ocean science Co., Ltd

Document name: Notification to Pay the Fees

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141210

Termination date: 20160506