CN203947492U - 一种与基坑围护相结合的双排桩基挡土墙 - Google Patents
一种与基坑围护相结合的双排桩基挡土墙 Download PDFInfo
- Publication number
- CN203947492U CN203947492U CN201420269725.6U CN201420269725U CN203947492U CN 203947492 U CN203947492 U CN 203947492U CN 201420269725 U CN201420269725 U CN 201420269725U CN 203947492 U CN203947492 U CN 203947492U
- Authority
- CN
- China
- Prior art keywords
- wall
- pile
- foundation
- bracing
- foundation pit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
本实用新型公开的一种与基坑围护相结合的双排桩基挡土墙,包括:插入原状地面的前排桩或墙;间隔一定距离的插入原状地面的后排基桩;固定连接在所述前排桩或墙顶部和后排基桩顶部之间的底板:以及砌筑在所述底板上的挡墙墙身。本实用新型采用前排钢筋混凝土桩或墙和后排钢筋混凝土基桩以及底板共同构成挡墙的基础,也作为基坑开挖时的双排桩基坑围护结构;大大减少了建造挡墙墙身时的土方开挖及回填量,而且对墙后附近建筑物影响小,同时利用桩基作为部分挡土结构,减少墙身高度,施工速度快,工程费用低。本实用新型可用于水利、交通及市政等各种挡土墙,尤其适用于墙前土方开挖深墙后分布有管线及房屋等建筑物的软土地区挡土墙。
Description
技术领域
本实用新型涉及一种挡土墙,具体来说涉及一种与基坑围护相结合的双排桩基挡土墙,尤其适用于软土地基上墙前开挖深、墙后填土高且墙后有建筑物需要进行基坑围护的情况。
背景技术
在水利、交通及市政等工程中,许多支挡结构需进行墙前较深土方开挖,且其墙后分布管线及房屋等大量建筑物。传统的施工方法是:先基坑围护进行墙前土方开挖,再建造挡墙,最后进行墙后土方回填,但是按照该种施工方法进行操作,会导致以下问题的出现:1、临时工程基坑围护工程量大;2、对墙后建筑物影响大;3、挡墙墙身高度大;4、工期长,工程费用高。
实用新型内容
本实用新型所要解决的技术问题是:针对现有技术的不足而提供一种与基坑围护相结合的双排桩基挡土墙及其施工方法,用以克服传统方法中存在的施工麻烦、土方开挖量大、施工工期长、对墙后建筑物影响大及工程费用高的问题。
一种与基坑围护相结合的双排桩基挡土墙,包括:
插入原状地面的前排桩或墙;
间隔一定距离的插入原状地面的后排基桩;
固定连接在所述前排桩或墙顶部和后排基桩顶部之间的底板:以及
砌筑在所述底板上的挡墙墙身。
在本实用新型的一个优选实施例中,所述前排桩或墙为采用前排桩或墙单元所形成的连续封闭结构。
在本实用新型的一个优选实施例中,所述各前排桩或墙单元的接头处设置止水条。
在本实用新型的一个优选实施例中,所述前排桩(墙)单元根据实际情况选用板桩或钢筋混凝土地下墙。
在本实用新型的一个优选实施例中,所述后排基桩根据实际情况选用钢筋混凝土基桩。
在本实用新型的一个优选实施例中,所述钢筋混凝土基桩为方桩或管桩。
在本实用新型的一个优选实施例中,所述挡墙墙身根据实际情况选用钢筋混凝土、浆砌块石及其它结构。
本实用新型采用前排钢筋混凝土桩或墙和后排钢筋混凝土基桩以及底板共同构成挡墙的基础,也作为基坑开挖时的双排桩基坑围护结构;大大减少了建造挡墙墙身时的土方开挖及回填量,而且对墙后附近建筑物影响小,同时利用桩基作为部分挡土结构,减少墙身高度,施工速度快,工程费用低。
本实用新型可用于水利、交通及市政等各种挡土墙,尤其适用于墙前土方开挖深墙后分布有管线及房屋等建筑物的软土地区挡土墙。
附图说明
图1是本实用新型的结构示意图。
附图标记说明如下:
1、前排钢筋混凝土桩或墙,2、后排钢筋混凝土基桩,3、钢筋混凝土底板,4、挡墙墙身,5、原状地面高程,6、挡墙墙身前开挖后地面高程,7、挡墙墙身墙后回填土。
具体实施方式
为了使本实用新型实现的技术手段、创作特征、达成目的与功效易于明白了解,下面结合具体图示,进一步阐述本实用新型。
参看图1,一种与基坑围护相结合的双排桩基挡土墙,包括由插入原状地面的前排钢筋混凝土桩或墙单元连续封闭形成的前排钢筋混凝土桩或墙1、间隔一定距离的插入原状地面的后排钢筋混凝土基桩2、固定连接在前排钢筋混凝土桩或墙1的顶部和后排钢筋混凝土基桩2的顶部以及它们之间的钢筋混凝土底板3及砌筑在钢筋混凝土底板3上部的挡墙墙身4。
前排桩(墙)单元可以根据实际情况选用板桩或钢筋混凝土地下墙,后排钢筋混凝土基桩2可以根据实际情况选用方桩或管桩,挡墙墙身4根据实际情况选用钢筋混凝土、浆砌块石及其它结构。
本实用新型采用前排钢筋混凝土桩或墙1和后排钢筋混凝土基桩2以及钢筋混凝土底板3共同构成挡墙墙身4的基础,也作为基坑开挖时的双排桩基坑围护结构;大大减少了建造挡墙时的土方开挖及回填量,而且对墙后附近建筑物影响小,同时利用桩基作为部分挡土结构,减少墙身高度,施工速度快,工程费用低。
本实用新型可用于水利、交通及市政等各种挡土墙,尤其适用于墙前土方开挖深墙后分布有管线及房屋等建筑物的软土地区挡土墙。
上述的一种与基坑围护相结合的双排桩基挡土墙的施工方法:
A、在原状地面上打设由前排钢筋混凝土桩或墙单元连续封闭形成的前排钢筋混凝土桩或墙1,所述各前排钢筋混凝土桩或墙单元的接头处设置止水条(图中未示处);
B、在前排钢筋混凝土桩或墙1的后侧的原状地面上打设间隔一定距离的后排钢筋混凝土基桩2;
C、在前排钢筋混凝土桩或墙1的顶部上和后排钢筋混凝土基桩2的顶部上以及它们之间浇筑钢筋混凝土底板3,使前排钢筋混凝土桩或墙1和后排钢筋混凝土基桩2与钢筋混凝土底板3共同形成双排桩基坑围护结构;
D、开挖挡墙墙身4前侧的土体,在双排桩基坑围护结构挡土(水)作用下,将挡墙墙身4前侧的土体从原状地面高程5开挖到墙前开挖后地面高程6;
E、按照设计要求砌筑挡墙墙身4;
F、在挡墙墙身4的后侧填土至设计高程。
Claims (7)
1.一种与基坑围护相结合的双排桩基挡土墙,其特征在于,包括:
插入原状地面的前排桩或墙;
间隔一定距离的插入原状地面的后排基桩;
固定连接在所述前排桩或墙顶部和后排基桩顶部之间的底板:以及
砌筑在所述底板上的挡墙墙身。
2.如权利要求1所述的与基坑围护相结合的双排桩基挡土墙,其特征在于,所述前排桩或墙为采用前排桩或墙单元所形成的连续封闭结构。
3.如权利要求2所述的与基坑围护相结合的双排桩基挡土墙,其特征在于,所述各前排桩或墙单元的接头处设置止水条。
4.如权利要求3所述的与基坑围护相结合的双排桩基挡土墙,其特征在于,所述前排桩(墙)单元根据实际情况选用板桩或钢筋混凝土地下墙。
5.如权利要求1所述的与基坑围护相结合的双排桩基挡土墙,其特征在于,所述后排基桩根据实际情况选用钢筋混凝土基桩。
6.如权利要求5所述的与基坑围护相结合的双排桩基挡土墙,其特征在于,所述钢筋混凝土基桩为方桩或管桩。
7.如权利要求1所述的与基坑围护相结合的双排桩基挡土墙,其特征在于,所述挡墙墙身根据实际情况选用钢筋混凝土、浆砌块石及其它结构。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420269725.6U CN203947492U (zh) | 2014-05-23 | 2014-05-23 | 一种与基坑围护相结合的双排桩基挡土墙 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420269725.6U CN203947492U (zh) | 2014-05-23 | 2014-05-23 | 一种与基坑围护相结合的双排桩基挡土墙 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203947492U true CN203947492U (zh) | 2014-11-19 |
Family
ID=51889539
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420269725.6U Expired - Fee Related CN203947492U (zh) | 2014-05-23 | 2014-05-23 | 一种与基坑围护相结合的双排桩基挡土墙 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203947492U (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104005421A (zh) * | 2014-05-23 | 2014-08-27 | 上海市水利工程设计研究院有限公司 | 一种与基坑围护相结合的双排桩基挡土墙及其施工方法 |
CN106284408A (zh) * | 2016-09-20 | 2017-01-04 | 广东舍卫工程技术咨询有限公司 | 桩承加筋挡土墙 |
CN106988595A (zh) * | 2017-03-22 | 2017-07-28 | 中国人民解放军装甲兵工程学院 | 环防式手榴弹实弹投掷掩体 |
CN111622231A (zh) * | 2020-05-15 | 2020-09-04 | 江苏省中成建设工程总公司 | 一种与基坑围护相结合的双排桩基挡土墙 |
CN114960751A (zh) * | 2022-07-29 | 2022-08-30 | 中国铁路设计集团有限公司 | 一种地铁车站先明挖施工附属后盖挖逆作施工主体的方法 |
-
2014
- 2014-05-23 CN CN201420269725.6U patent/CN203947492U/zh not_active Expired - Fee Related
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104005421A (zh) * | 2014-05-23 | 2014-08-27 | 上海市水利工程设计研究院有限公司 | 一种与基坑围护相结合的双排桩基挡土墙及其施工方法 |
CN106284408A (zh) * | 2016-09-20 | 2017-01-04 | 广东舍卫工程技术咨询有限公司 | 桩承加筋挡土墙 |
CN106988595A (zh) * | 2017-03-22 | 2017-07-28 | 中国人民解放军装甲兵工程学院 | 环防式手榴弹实弹投掷掩体 |
CN106988595B (zh) * | 2017-03-22 | 2022-12-09 | 中国人民解放军装甲兵工程学院 | 环防式手榴弹实弹投掷掩体 |
CN111622231A (zh) * | 2020-05-15 | 2020-09-04 | 江苏省中成建设工程总公司 | 一种与基坑围护相结合的双排桩基挡土墙 |
CN114960751A (zh) * | 2022-07-29 | 2022-08-30 | 中国铁路设计集团有限公司 | 一种地铁车站先明挖施工附属后盖挖逆作施工主体的方法 |
CN114960751B (zh) * | 2022-07-29 | 2022-12-09 | 中国铁路设计集团有限公司 | 一种地铁车站先明挖施工附属后盖挖逆作施工主体的方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104005421A (zh) | 一种与基坑围护相结合的双排桩基挡土墙及其施工方法 | |
CN203947492U (zh) | 一种与基坑围护相结合的双排桩基挡土墙 | |
CN103074898B (zh) | 多排桩基坑支护结构及其施工方法 | |
CN105298507B (zh) | 一种上部明挖下部掘进机施工的地下管廊施工方法 | |
CN106049532B (zh) | 一种综合管廊明挖施工支挡装置及其施工方法 | |
CN103924602B (zh) | 深厚软土基坑施工方法 | |
CN204418187U (zh) | 地铁保护区域土钉墙结合双排桩深基坑复合支护结构 | |
CN107060771A (zh) | 中短隧道单向出洞开挖方法 | |
CN203684230U (zh) | 一种预制双排桩结构 | |
CN102444143B (zh) | 一种取消地下室外立面操作通道的施工方法 | |
CN103290850A (zh) | 一种拱形组合基坑支护体系及施工方法 | |
CN204738302U (zh) | 一种多层框架式双排桩支护结构 | |
CN104963705A (zh) | 一种地下空间暗挖构筑方法 | |
CN105421461A (zh) | 土岩地质条件下邻近既有隧道的建筑基坑开挖工法 | |
CN103437370A (zh) | 一种陡坡抗滑挡土的方法及支护结构 | |
CN107882042A (zh) | 一种囊式前撑支护结构及其施工方法 | |
CN104975606A (zh) | 逆作基坑与相邻基坑相邻处高低跨处理方法 | |
CN204825923U (zh) | 一种接力式基坑支护结构 | |
CN202401461U (zh) | 一种新型基坑支护结构 | |
CN104532855A (zh) | 一种深厚泥炭质土层中的组合桩支护结构 | |
CN102080551B (zh) | 软弱破碎围岩隧道初期支护仰拱三幅施工方法 | |
CN101871218B (zh) | 地下车站空间的非开挖施工方法及其弧形冻结管施工设备 | |
CN203334295U (zh) | 一种大直径弧形钢板桩基坑支护结构 | |
CN105239579A (zh) | 软土深基坑变形的封堵墙式控制方法 | |
CN103866779B (zh) | 一种软土地基建筑基坑的止水围护结构的施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20141119 Termination date: 20200523 |
|
CF01 | Termination of patent right due to non-payment of annual fee |