CN203924040U - 一种灌注桩桩头处理结构 - Google Patents
一种灌注桩桩头处理结构 Download PDFInfo
- Publication number
- CN203924040U CN203924040U CN201420265361.4U CN201420265361U CN203924040U CN 203924040 U CN203924040 U CN 203924040U CN 201420265361 U CN201420265361 U CN 201420265361U CN 203924040 U CN203924040 U CN 203924040U
- Authority
- CN
- China
- Prior art keywords
- pile
- pile crown
- main muscle
- crown
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
本实用新型涉及建筑浇筑技术领域,具体公开了一种灌注桩桩头处理结构,所述灌注桩上标记柱低标高线,所述灌注桩内主筋位于柱低标高线下方为桩身主筋,位于柱低标高线上方为桩头主筋,在所述桩头主筋和桩头砼之间设有泡棉套,所述泡棉套套设于桩头主筋上,桩头主筋顶部设有吊环。本实用新型优点是,由于在桩头主筋和桩头砼之间设有泡棉套,使桩头砼和桩头主筋之间不发生握裹,解决了现有技术施工中因砼强度大且与钢筋握裹力大导致桩头移除困难的问题。且桩头主筋泡棉套保护,可以很容易使桩头砼与桩头主筋分离,使桩基钢筋不受损伤,确保了桩基钢筋质量。
Description
技术领域
本实用新型涉及建筑浇筑领域,特别是指一种灌注桩桩头处理结构。
背景技术
传统灌注桩桩头錾除,是在桩顶切割线处,人工錾开缺口,用风镐剥离缺口上侧保护层后,将主筋向外侧拉出,随后用钢纤向桩头部分錾进,使其与桩身脱离,随后用起重设备移除,最后人工錾除剩余桩头。
由于砼本身强度高且与钢筋握裹力大,导致桩头与桩身断开困难。断开过程中极易造成桩身竖向及斜向裂纹、桩头标高误差及平整度等问题;也无形中加大了设备和人力的投入,降低了施工和经济效率;同时风镐长时间作业,噪音大,粉尘多,对环境的影污染严重。
此外,主筋向外拉出时,弯曲变形,从而降低抗拉强度,造成桩身和承台间的连接处减弱,给工程质量埋下隐患(如果地震时,该处就成为薄弱点)。
另外,錾除的桩头起吊及运输也极为困难,由于桩头标高及平整度无法控制,最后还需人工錾除桩头。
实用新型内容
本实用新型的目的是提供一种灌注桩桩头处理结构,其解决了现有技术施工中因砼强度大且与钢筋握裹力大导致桩头移除困难的问题,施工效率高,操作方便,工期短。
为了实现上述目的,本实用新型采用了以下的技术方案:一种灌注桩桩头处理结构,所述灌注桩上标记柱低标高线,所述灌注桩内主筋位于柱低标高线下方为桩身主筋,位于柱低标高线上方为桩头主筋,在所述桩头主筋和桩头砼之间设有泡棉套,所述泡棉套套设于桩头主筋上,桩头主筋顶部设有吊环。
进一步的,所述泡棉套通过胶带固定在桩头主筋上。
进一步的,所述胶带外通过铅丝缠绕固定。
本实用新型的有益效果在于:采用上述结构后,由于在桩头主筋和桩头砼之间设有泡棉套,使桩头砼和桩头主筋之间不发生握裹,解决了现有技术施工中因砼强度大且与钢筋握裹力大导致桩头移除困难的问题。且桩头主筋受泡棉套保护,可以很容易使桩头砼与桩头主筋分离,使桩基钢筋不受损伤,确保了桩基钢筋质量。
桩头与桩身完全分离时,采用浇筑到桩头主筋顶部的钢筋吊环把破除的桩头提出,移除现场,避免现有技术中需人工錾除桩头造成劳动量大的问题。
附图说明
为了更清楚地说明本实用新型实施例技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型为了更清楚地说明本实用新型实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,对于本领域普通技术人员来讲,在不付出创造性劳动性的前提下,还可以根据这些附图获得其他的附图。
图1为本实用新型的结构示意图;
图2为图1中I的放大结构示意图。
具体实施方式
下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。
如图1所示的一种灌注桩桩头处理结构,所述灌注桩上标记柱低标高线2,所述灌注桩内主筋位于柱低标高线2下方为桩身主筋1,位于柱低标高线2上方为桩头主筋3,在所述桩头主筋3和桩头砼之间设有泡棉套4,所述泡棉套4套设于桩头主筋3上,桩头主筋3顶部设有吊环6。使桩头砼和桩头主筋3之间不发生握裹,解决了现有技术施工中因桩头砼强度大且与钢筋握裹力大导致桩头移除困难的问题。
所述桩头主筋3受泡棉套4保护,可以很容易使桩头砼与桩头主筋3分离,使桩基钢筋不受损伤,确保了桩基钢筋质量。
在施工时,灌注桩桩头的錾除工艺如下:
1、灌注桩钢筋笼制作。
2、下笼前用事先加工好的如泡棉套4入钢筋笼外露承台主筋和声测管外端表面。泡棉套4主要设置在桩头部分,为了保证桩头的分离,泡棉套4底端设在桩头主筋3顶部下75mm位置处,采用胶带固定,胶带深入桩体5~10cm。为了保证泡棉套4的整体位置准确,在桩头内用22#铅丝5将缠绕在钢筋上的胶带绑扎固定,保证其不发生串动,将其位置固定。泡棉套4保证在灌注中不被混凝土挤扁失效,确保钢筋与复合脱模套分离。
3、在切割高度钻出一个洞与桩纵轴垂直,反方向作用的楔子插入洞内,桩头被垂直分开.在桩身砼初凝后到终凝前,把桩头上的砼可以竖直的从高于设计桩底标高的10cm处直接从该处断开,在桩顶高程以上10cm处采用钻孔,钻孔深度只要达到桩身的1/5即可,用分离楔子插入钻孔中,并采用外力进行敲击,直至桩头与桩身完全分离,随后用浇筑到桩头主筋3顶部的钢筋吊环6把破除的桩头提出,移除现场。
以上所述仅为本实用新型的较佳实施例而已,并不用以限制本实用新型,凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。
Claims (3)
1.一种灌注桩桩头处理结构,所述灌注桩上标记柱低标高线(2),所述灌注桩内主筋位于柱低标高线(2)下方为桩身主筋(1),位于柱低标高线(2)上方为桩头主筋(3),其特征在于,在所述桩头主筋(3)和桩头砼之间设有泡棉套(4),所述泡棉套(4)套设于桩头主筋(3)上,所述桩头主筋(3)顶部设有吊环(6)。
2.根据权利要求1所述的一种灌注桩桩头处理结构,其特征在于:所述泡棉套(4)通过胶带固定在桩头主筋(3)上。
3.根据权利要求1所述的一种灌注桩桩头处理结构,其特征在于:所述胶带外通过铅丝(1)缠绕固定。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420265361.4U CN203924040U (zh) | 2014-05-22 | 2014-05-22 | 一种灌注桩桩头处理结构 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420265361.4U CN203924040U (zh) | 2014-05-22 | 2014-05-22 | 一种灌注桩桩头处理结构 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203924040U true CN203924040U (zh) | 2014-11-05 |
Family
ID=51819894
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420265361.4U Expired - Fee Related CN203924040U (zh) | 2014-05-22 | 2014-05-22 | 一种灌注桩桩头处理结构 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203924040U (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105735317A (zh) * | 2016-03-09 | 2016-07-06 | 中天路桥有限公司 | 灌注桩破除桩头施工工艺 |
CN107130601A (zh) * | 2017-05-31 | 2017-09-05 | 中建二局第二建筑工程有限公司 | 一种提高桩头破除效率的装置及破除方法 |
-
2014
- 2014-05-22 CN CN201420265361.4U patent/CN203924040U/zh not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105735317A (zh) * | 2016-03-09 | 2016-07-06 | 中天路桥有限公司 | 灌注桩破除桩头施工工艺 |
CN107130601A (zh) * | 2017-05-31 | 2017-09-05 | 中建二局第二建筑工程有限公司 | 一种提高桩头破除效率的装置及破除方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102312429B (zh) | 混凝土灌注桩桩头快速分离与整体吊装方法 | |
CN102518124B (zh) | 灌注桩桩头混凝土快速凿除的方法 | |
CN103174156B (zh) | 杯口小于600mm×600mm独立基础施工内模板装置及其施工工法 | |
CN110306537A (zh) | 灌注桩桩头施工方法 | |
CN203429641U (zh) | 建筑施工用单侧支模加固结构体系 | |
CN203924040U (zh) | 一种灌注桩桩头处理结构 | |
CN204000830U (zh) | 分节接管式砂井机 | |
CN103867209A (zh) | 一种地铁竖井分层、分段转横通道施工开挖进洞的方法 | |
MX2021010866A (es) | Sistema de construccion de encofrado deslizante vertical con plataforma multifuncion, y metodo de construccion de un edificio con el mismo. | |
CN108487238A (zh) | 一种灌注桩桩头处理装置及其施工方法 | |
CN203270595U (zh) | 杯口小于600㎜×600㎜独立基础的施工内模板装置 | |
CN205314558U (zh) | 一种预应力钢绞线用穴模 | |
CN205314534U (zh) | 一种框架柱无损拉结钢模板结构 | |
CN110835911A (zh) | 快速分离的混凝土灌注桩桩头 | |
CN201746867U (zh) | 一种取土器 | |
CN202347519U (zh) | 快速分离的混凝土灌注桩桩头 | |
CN109723059A (zh) | 一种改进的用于砂卵石地基施工的全护筒及其使用方法 | |
CN104790578A (zh) | 建筑楼板混凝土施工中预留孔的制作装置及其施工方法 | |
CN202144668U (zh) | 装配式对拉螺栓 | |
CN211773584U (zh) | 快速分离的混凝土灌注桩桩头 | |
CN203729889U (zh) | 安装在钻机上的自动变径成孔器 | |
CN209585029U (zh) | 一种改进的用于砂卵石地基施工的全护筒 | |
CN204023579U (zh) | 一种逆作法柱插筋工具架 | |
CN211396679U (zh) | 一种施工现场梁内预埋线管的工具 | |
CN203213120U (zh) | 水下灌注混凝土导管与钻杆连接头 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20141105 |
|
CF01 | Termination of patent right due to non-payment of annual fee |