CN203850641U - Optimized 110kV cable wiring structure capable of realizing fault fast isolation - Google Patents

Optimized 110kV cable wiring structure capable of realizing fault fast isolation Download PDF

Info

Publication number
CN203850641U
CN203850641U CN201420222395.5U CN201420222395U CN203850641U CN 203850641 U CN203850641 U CN 203850641U CN 201420222395 U CN201420222395 U CN 201420222395U CN 203850641 U CN203850641 U CN 203850641U
Authority
CN
China
Prior art keywords
optimized
transformer
wiring structure
substations
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420222395.5U
Other languages
Chinese (zh)
Inventor
黄兴
蔡健威
严棣
田宝柱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Meaningful Power Engineering Design Co Ltd Converges In Guangzhou
Original Assignee
Meaningful Power Engineering Design Co Ltd Converges In Guangzhou
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Meaningful Power Engineering Design Co Ltd Converges In Guangzhou filed Critical Meaningful Power Engineering Design Co Ltd Converges In Guangzhou
Priority to CN201420222395.5U priority Critical patent/CN203850641U/en
Application granted granted Critical
Publication of CN203850641U publication Critical patent/CN203850641U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

The utility model discloses an optimized 110kV cable wiring structure capable of realizing fault fast isolation. The optimized 110kV cable wiring structure includes three main transformers arranged in the same substation; the 110kV side of each main transformer is provided with GIS equipment; the three main transformers are connected onto three different bus bars of a 220kV power source respectively through the GIS equipment; lines between main transformers of different substations, which are connected with the same bus bar of the 220kV power source, are provided with grounding switches 1 and disconnecting switches 1. According to the optimized 10kV cable wiring structure of the utility model, the line transformer unit groups are adopted; no bus bar is arranged at high-voltage sides, and the power source comes from different bus bars of different 220kV substations, and therefore, risk of voltage loss of all 110kV substations is very low; when three 110kV lines are all put into operation, line operation utilization rate can reach 100%; wiring designs of the 110kV sides of the 110kV substations are optimized, and an isolation function can be additionally realized in a 110kV power grid system, and therefore, rapid isolation of failed equipment or lines can be realized, and a power outage range when local faults occur can be decreased.

Description

A kind of 110kV cable connection of realizing the quick isolation of fault is optimized structure
Technical field
The utility model relates to electric power transportation technology field, particularly relates to a kind of 110kV cable connection of realizing the quick isolation of fault and optimizes structure.
Background technology
Along with Process of Urbanization Construction development, the 110kV of transformer station power distribution equipment general choice SF6 gas insulated metal enclosed swit chgear (GIS equipment) is to save land used, yet adopt more and more cable line to be connected between transformer station and transformer station, the 110kV side joint line that 110kV transformer station adopts is at present not easy to isolate fast the local fault of grid equipment, and faulty equipment can not be repaired fast, easily cause power failure in a big way.
Utility model content
For overcoming the deficiencies in the prior art, the purpose of this utility model is to provide a kind of 110kV cable connection of realizing the quick isolation of fault to optimize structure.
The utility model for solving the technical scheme of its technical problem employing is:
A kind of 110kV cable connection of realizing the quick isolation of fault is optimized structure, comprise three main transformers that are arranged in same transformer station, the 110kV side of every main transformer is provided with GIS equipment, three main transformers respectively through described GIS equipment connection on three of 220kV power supply different buses; Be connected on the circuit between the main transformer of the different substation on same 220kV power source bus and be provided with earthed switch one and isolating switch one.
Further, described GIS equipment comprises insulator, earthed switch two, circuit breaker, current transformer, earthed switch three, isolating switch two, high speed grounding switch, voltage transformer, the cable termination that is connected to main transformer 110kV side in turn.
The beneficial effects of the utility model are: the utility model adopts line transformer unit group, bus is not established in high-pressure side, power supply is from the different buses of different 220kV transformer stations, the risk of 110kV no-voltage of entire station is very low, article three, when 110kV circuit all puts into operation, line line efficiency can reach 100%.The utility model has also been optimized the wiring design of the 110kV side of 110kV transformer station, increased the isolation features in 110kV network system, when there is the local fault of grid equipment or circuit, by system call, the analysis of fault judged and carry out grid switching operation, the quick isolation of realization to faulty equipment or circuit, power failure range while reducing local fault, but also have arrangement compactness, takes up an area the advantages such as little, reduced investment.
Accompanying drawing explanation
Below in conjunction with accompanying drawing and example, the utility model is described in further detail.
Fig. 1 is wiring schematic diagram of the present utility model;
Fig. 2 is the structural representation of GIS equipment of the present utility model.
Embodiment
See figures.1.and.2, a kind of 110kV cable connection of realizing the quick isolation of fault of the present utility model is optimized structure, comprise three main transformers 2 that are arranged in same transformer station 1, the 110kV side of every main transformer 2 is provided with 3, three main transformers 2 of GIS equipment and through described GIS equipment 3, is connected on three different buses of 220kV power supply respectively; Be connected on the circuit between the main transformer 2 of the different substation 1 on same 220kV power source bus and be provided with earthed switch one ES1 and isolating switch one DS1.
The utility model adopts line transformer unit group, and bus is not established in high-pressure side, and power supply is from the different buses of different 220kV transformer stations, and the risk of 110kV no-voltage of entire station is very low, and when three 110kV circuits all put into operation, line line efficiency can reach 100%.In addition, main transformer 2 is connected with the main transformer 2 of another transformer station 1 with isolating switch one DS1 by earthed switch one ES1, increased the isolation features in 110kV network system, when there is the local fault of grid equipment or circuit, by system call, the analysis of fault judged and carry out grid switching operation, the quick isolation of realization to faulty equipment or circuit, the power failure range while reducing local fault.
Further, described GIS equipment 3 comprises insulator BUSH, earthed switch two ES2, circuit breaker CB, Current Transmit, earthed switch three ES3, isolating switch two DS2, high speed grounding switch FMES, voltage transformer VT, the cable termination CHD of the 110kV side that is connected to main transformer 2 in turn, because each 110kV circuit is provided with GIS equipment 3, thereby can greatly improve the reliability of transformer station's work.
The above, be preferred embodiment of the present invention, and the present invention is not limited to above-mentioned execution mode, as long as it reaches technique effect of the present invention with identical means, all should belong to protection scope of the present invention.

Claims (2)

1. a 110kV cable connection of realizing the quick isolation of fault is optimized structure, it is characterized in that: comprise three main transformers that are arranged in same transformer station, the 110kV side of every main transformer is provided with GIS equipment, three main transformers respectively through described GIS equipment connection on three of 220kV power supply different buses; Be connected on the circuit between the main transformer of the different substation on same 220kV power source bus and be provided with earthed switch one and isolating switch one.
2. a kind of 110kV cable connection of realizing the quick isolation of fault according to claim 1 is optimized structure, and it is characterized in that: described GIS equipment comprises insulator, earthed switch two, circuit breaker, current transformer, earthed switch three, isolating switch two, high speed grounding switch, voltage transformer, the cable termination that is connected to main transformer 110kV side in turn.
CN201420222395.5U 2014-04-30 2014-04-30 Optimized 110kV cable wiring structure capable of realizing fault fast isolation Expired - Lifetime CN203850641U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420222395.5U CN203850641U (en) 2014-04-30 2014-04-30 Optimized 110kV cable wiring structure capable of realizing fault fast isolation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420222395.5U CN203850641U (en) 2014-04-30 2014-04-30 Optimized 110kV cable wiring structure capable of realizing fault fast isolation

Publications (1)

Publication Number Publication Date
CN203850641U true CN203850641U (en) 2014-09-24

Family

ID=51563614

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420222395.5U Expired - Lifetime CN203850641U (en) 2014-04-30 2014-04-30 Optimized 110kV cable wiring structure capable of realizing fault fast isolation

Country Status (1)

Country Link
CN (1) CN203850641U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110208644A (en) * 2019-05-15 2019-09-06 广州供电局有限公司 GIS cable machinery

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110208644A (en) * 2019-05-15 2019-09-06 广州供电局有限公司 GIS cable machinery

Similar Documents

Publication Publication Date Title
CN204732777U (en) A kind of cable line uninterrupted operation system
CN203850641U (en) Optimized 110kV cable wiring structure capable of realizing fault fast isolation
CN202872241U (en) Bus bar chamber with bus bar isolation function and bus bar measuring function
CN205863765U (en) Double bus scheme structure based on disconnecting switch segmentation in GIS power distribution equipment
CN105024329A (en) Medium-voltage overhead trunk power distribution network construction structure and building method thereof
CN210443803U (en) 220kV HGIS power distribution device applied to single bus sectional wiring of transformer substation
CN205029223U (en) Movable type transformer station
CN209948370U (en) Bypass node type PT cabinet
CN204497572U (en) A kind of HGIS equipment
CN202094512U (en) Mechanism enabling medium pressure side of main transformer to be uninterruptible in overhaul
CN204156529U (en) A kind of have the flexible direct current back-to-back system (CCC-0) that redundancy switches no-power compensation function
CN203690076U (en) 6kV and 10kV high-voltage double-voltage transformer
CN207459723U (en) Spare phase transformer quickly puts into arrangement
CN106532754A (en) Voltage selection equipment of inverter station in high-voltage DC power transmission system and operation method of voltage selection equipment
CN203690075U (en) 20kV and 35kV high-voltage double-voltage transformer
CN208093426U (en) A kind of interlock of outdoor vacuum circuit breaker
CN202817588U (en) A GIS composite electrical apparatus
CN204886390U (en) High pressure dual power supply's wiring circuit
CN201298734Y (en) Main electrical wiring for starting fuel gas and steam combined cycle generator set in two-drive-one mode with variable frequency
CN111342549A (en) Power supply system is synthesized to inside of large-scale coal-electricity integration power station
CN205211625U (en) Prevent switch mistake and close circuit system
CN204558904U (en) A kind of low-voltage cable junction box bus-bar system
CN204271737U (en) Two small power supplies are simultaneously to the wiring construction of a Large Electrolytic Aluminium series power
CN204761029U (en) Connect electric system temporarily with phase shifting transformer
CN204144759U (en) ATS modular transformer substation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant