CN205863765U - Double bus scheme structure based on disconnecting switch segmentation in GIS power distribution equipment - Google Patents

Double bus scheme structure based on disconnecting switch segmentation in GIS power distribution equipment Download PDF

Info

Publication number
CN205863765U
CN205863765U CN201620859561.1U CN201620859561U CN205863765U CN 205863765 U CN205863765 U CN 205863765U CN 201620859561 U CN201620859561 U CN 201620859561U CN 205863765 U CN205863765 U CN 205863765U
Authority
CN
China
Prior art keywords
unit
bus
main transformer
disconnecting switch
standby
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620859561.1U
Other languages
Chinese (zh)
Inventor
翟云娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Guofu Electric Design Engineering Co Ltd
Original Assignee
Shanghai Guofu Electric Design Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Guofu Electric Design Engineering Co Ltd filed Critical Shanghai Guofu Electric Design Engineering Co Ltd
Priority to CN201620859561.1U priority Critical patent/CN205863765U/en
Application granted granted Critical
Publication of CN205863765U publication Critical patent/CN205863765U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The utility model discloses double bus scheme structure based on disconnecting switch segmentation in a kind of GIS power distribution equipment, including being sequentially connected the standby line unit connect, #1 main transformer unit, standby two wires unit, #2 main transformer unit, second outgoing line unit, mother unit, #3 main transformer module, first outgoing line unit, #1 main transformer unit, connect between the unit of standby two wires and have the first bus-bar potential transformer, second bus grounding switch, mother unit, connect between #3 main transformer module and have the second bus-bar potential transformer, first bus grounding switch, it is characterized in that: standby two wires unit, two groups of disconnecting switch segmentations are set between #2 main transformer unit.Original double bus scheme, according to GIS device operation characteristic, improved by this utility model, it is to avoid the problem that in GIS enlarging or maintenance process, the staff of authority has a power failure, compared with double-bus section wiring, save 2 choppers, greatly reduce investment of substations, improve transformer station's power supply reliability.

Description

Double bus scheme structure based on disconnecting switch segmentation in GIS power distribution equipment
Technical field
This utility model relates to distribution technique field, particularly relates in a kind of GIS power distribution equipment based on disconnecting switch segmentation Double bus scheme structure.
Background technology
Distribution technique provision of being correlated with specifies: " the 220kV power distribution equipment in 220kV transformer station, when occupying importantly in systems Position, transmission line circuit number be 4 times and above time, preferably use double bus scheme ".For open type distribution device, 220kV, 110kV join When electric installation uses double bus scheme, can realize a bus and have a power failure when extending or overhaul, an other bus is the most charged Run, it is ensured that entirely stand when extending or overhaul and do not have a power failure.But for GIS arrangement, when 220kV, 110kV power distribution equipment uses double During bus wiring, due to GIS device self, need power failure of entirely standing, bring very big inconvenience to substation operation.
Utility model content
In view of the drawbacks described above of prior art, technical problem to be solved in the utility model is to provide a kind of GIS distribution Double bus scheme structure based on disconnecting switch segmentation in device, to solve the deficiencies in the prior art.
For achieving the above object, this utility model is based on disconnecting switch segmentation double in providing a kind of GIS power distribution equipment Bus bar wiring structure, including be sequentially connected connect a standby line unit, #1 main transformer unit, standby two wires unit, #2 main transformer unit, Second outgoing line unit, mother unit, #3 main transformer module, the first outgoing line unit, between described #1 main transformer unit, standby two wires unit Connecting and have the first bus-bar potential transformer, the second bus grounding switch, connecting between described mother unit, #3 main transformer module has the Two bus-bar potential transformers, the first bus grounding switch, it is characterised in that: between described standby two wires unit, #2 main transformer unit Two groups of disconnecting switch segmentations are set.
Double bus scheme structure based on disconnecting switch segmentation, described disconnecting switch in above-mentioned a kind of GIS power distribution equipment Step-by-step arrangement, in the centre of bus, makes both sides line feeder number equal.
Double bus scheme structure based on disconnecting switch segmentation, described disconnecting switch in above-mentioned a kind of GIS power distribution equipment Segmentation both sides are respectively provided with 1 group of bus equipment and 1 group of earthed switch.
The beneficial effects of the utility model are:
Original double bus scheme, according to GIS device operation characteristic, improved by this utility model, it is to avoid GIS expansion Build or the problem of full station power failure in maintenance process, compared with double-bus section wiring, save 2 choppers, greatly reduce Investment of substations, improves transformer station's power supply reliability.
Below with reference to accompanying drawing, the technique effect of design of the present utility model, concrete structure and generation is made furtherly Bright, to be fully understood from the purpose of this utility model, feature and effect.
Accompanying drawing explanation
Fig. 1 is the electrical structure schematic diagram between a standby line of the present utility model and standby two wires.
Fig. 2 is this utility model standby two wires unit, the electrical structure schematic diagram of #2 main transformer unit improvement.
Fig. 3 is the second outgoing line unit electrical structure schematic diagram of the present utility model.
Fig. 4 is the first outgoing line unit electrical structure schematic diagram of the present utility model.
Detailed description of the invention
As it is shown in figure 1, double bus scheme structure based on disconnecting switch segmentation in a kind of GIS power distribution equipment, including successively The standby line unit that is connected, #1 main transformer unit, standby two wires unit, #2 main transformer unit, the second outgoing line unit, mother list Unit, #3 main transformer module, the first outgoing line unit, connect between described #1 main transformer unit, standby two wires unit and have the first busbar voltage Transformer, the second bus grounding switch, between described mother unit, #3 main transformer module connect have the second bus-bar potential transformer, First bus grounding switch, it is characterised in that: between described standby two wires unit, #2 main transformer unit, two groups of disconnecting switch are set and divide Section.
This utility model installs 2 groups of disconnecting switch on I mother, mother II respectively additional, then when pressure test is done in GIS enlarging, and can To use sectionalizer to be disconnected with running end by enlarging end, it is ensured that one section of bus can be properly functioning.As extended standby one During line, on the left of disconnecting switch segmentation, bus has a power failure, and right side bus is properly functioning, it is to avoid what during enlarging, full station had a power failure asks Topic.For realizing above-mentioned functions, when using this kind of connection type, should be noted following problem:
(1) disconnecting switch segmentation should be arranged in the centre of two groups of buses as far as possible, makes both sides line feeder number roughly equal;
(2) compared with double bus scheme, 1 group of bus equipment and 1 group of ground connection should be respectively provided with in disconnecting switch segmentation both sides Switch, during to ensure that sectionalizer is opened, two side bus all can run.
Original double bus scheme, according to GIS device operation characteristic, improved by this utility model, it is to avoid GIS expansion Build or the problem of full station power failure in maintenance process, compared with double-bus section wiring, save 2 choppers, greatly reduce Investment of substations, improves transformer station's power supply reliability.
Preferred embodiment of the present utility model described in detail above.Should be appreciated that the ordinary skill people of this area Member just can make many modifications and variations according to design of the present utility model without creative work.Therefore, all technology neck In territory, technical staff passes through logical analysis, reasoning or limited reality on the basis of existing technology according to design of the present utility model Test available technical scheme, all should be in the protection domain being defined in the patent claims.

Claims (3)

1. a double bus scheme structure based on disconnecting switch segmentation in GIS power distribution equipment, including being sequentially connected connect standby One line unit, #1 main transformer unit, standby two wires unit, #2 main transformer unit, the second outgoing line unit, mother unit, #3 main transformer module, First outgoing line unit, connects between described #1 main transformer unit, standby two wires unit and has the first bus-bar potential transformer, the second bus Earthed switch, connects between described mother unit, #3 main transformer module and has the second bus-bar potential transformer, the first busbar grounding to open Close, it is characterised in that: between described standby two wires unit, #2 main transformer unit, two groups of disconnecting switch segmentations are set.
2. double bus scheme structure based on disconnecting switch segmentation in GIS power distribution equipment as claimed in claim 1, its feature exists In: described disconnecting switch step-by-step arrangement, in the centre of bus, makes both sides line feeder number equal.
3. double bus scheme structure based on disconnecting switch segmentation in GIS power distribution equipment as claimed in claim 1, its feature exists In: described disconnecting switch segmentation both sides are respectively provided with 1 group of bus equipment and 1 group of earthed switch.
CN201620859561.1U 2016-08-10 2016-08-10 Double bus scheme structure based on disconnecting switch segmentation in GIS power distribution equipment Expired - Fee Related CN205863765U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620859561.1U CN205863765U (en) 2016-08-10 2016-08-10 Double bus scheme structure based on disconnecting switch segmentation in GIS power distribution equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620859561.1U CN205863765U (en) 2016-08-10 2016-08-10 Double bus scheme structure based on disconnecting switch segmentation in GIS power distribution equipment

Publications (1)

Publication Number Publication Date
CN205863765U true CN205863765U (en) 2017-01-04

Family

ID=57658596

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620859561.1U Expired - Fee Related CN205863765U (en) 2016-08-10 2016-08-10 Double bus scheme structure based on disconnecting switch segmentation in GIS power distribution equipment

Country Status (1)

Country Link
CN (1) CN205863765U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110165563A (en) * 2019-06-27 2019-08-23 安徽华电工程咨询设计有限公司 A kind of 220kV HGIS power distribution equipment applied to substation's single-trunk segmental wiring
CN112271728A (en) * 2020-10-15 2021-01-26 华能重庆珞璜发电有限责任公司 Method for improving flexibility of thermal generator set switching station and operation method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110165563A (en) * 2019-06-27 2019-08-23 安徽华电工程咨询设计有限公司 A kind of 220kV HGIS power distribution equipment applied to substation's single-trunk segmental wiring
CN112271728A (en) * 2020-10-15 2021-01-26 华能重庆珞璜发电有限责任公司 Method for improving flexibility of thermal generator set switching station and operation method thereof

Similar Documents

Publication Publication Date Title
CN103904564B (en) High-voltage distribution device with double breakers used for single bus segmentation and application thereof
CN205863765U (en) Double bus scheme structure based on disconnecting switch segmentation in GIS power distribution equipment
CN203895766U (en) Double busbar and double subsection based substation main wiring system
CN204835226U (en) Line arrangement structure of two complete clusters is joined in marriage into in wiring of one and half circuit breakers
CN203312905U (en) Portable mobile direct-current power cabinet
CN205863657U (en) 220kV double bus scheme transmission line circuit wiring optimizes structure
CN204992272U (en) Dual supply massive quantity power supply and high expanded pull -out type measuring equipment that does not repeat of low meter that supplies
CN204577857U (en) A kind of 110kV transformer station adopting novel wire connecting way
CN208078653U (en) Double-bus and single busbar mixing wiring high voltage distribution installation
CN203367775U (en) Duplicate-busbar disconnecting switch segmented electric main connection wire
CN202997335U (en) Ring network cabinet
CN210443803U (en) 220kV HGIS power distribution device applied to single bus sectional wiring of transformer substation
CN203774631U (en) High-voltage distribution device with dual circuit breakers in single bus sectionalizing mode
CN209948370U (en) Bypass node type PT cabinet
CN203850641U (en) Optimized 110kV cable wiring structure capable of realizing fault fast isolation
CN207098633U (en) Gas electricity generator for heating-cooling-power cogeneration accesses circuit
CN202817512U (en) Wiring system for 110kV transformer station
CN204720935U (en) Terminal tower line interval arrangement
CN206041016U (en) Practical earth connection in indoor GIS terminal
CN204992273U (en) Expanded pull -out type measuring equipment that does not repeat of dual power supply
CN203690075U (en) 20kV and 35kV high-voltage double-voltage transformer
CN208479185U (en) A kind of substation's spare phase quick-switching system
CN216390531U (en) New forms of energy booster station owner becomes low pressure side secondary voltage collection system
CN211183418U (en) 220KV bus differential system
CN201188504Y (en) 500kV, 220kV female and male transforming plant

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Di Yunjuan

Inventor before: Di Yunjuan

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170104