CN204577857U - A kind of 110kV transformer station adopting novel wire connecting way - Google Patents
A kind of 110kV transformer station adopting novel wire connecting way Download PDFInfo
- Publication number
- CN204577857U CN204577857U CN201520176687.4U CN201520176687U CN204577857U CN 204577857 U CN204577857 U CN 204577857U CN 201520176687 U CN201520176687 U CN 201520176687U CN 204577857 U CN204577857 U CN 204577857U
- Authority
- CN
- China
- Prior art keywords
- main
- circuit breaker
- main transformer
- breaker
- side circuit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
本实用新型公开了一种采用新型接线方式的110kV变电站,主要解决110kV出线为4回的变电站现有接线方式存在的问题,该110kV变电站分别通过4回出线线路与电厂和接入电网的220kV变电站相连,它包括4个出线断路器、4个110kV母线、2个母线分段断路器、4个主变高压侧断路器、4个主变、4个主变低压侧断路器、4个主接线和3个主接线分段断路器。本实用新型通过对110kV出线为4回的变电站采用交叉式双单母线分段接线方式,解决了双电源环网运行的问题,而且通过对称布置,内含着一次线路交叉,从而避免了输电线路交叉而导致的问题出现,为优化输电线路设计方案打下了良好的基础。
The utility model discloses a 110kV substation adopting a new wiring mode, which mainly solves the problems existing in the existing wiring mode of the substation with 4 outgoing lines for 110kV. Connected, it includes 4 outlet circuit breakers, 4 110kV busbars, 2 busbar section circuit breakers, 4 main transformer high-voltage side circuit breakers, 4 main transformers, 4 main transformer low-voltage side circuit breakers, and 4 main wiring and 3 main wiring section circuit breakers. The utility model solves the problem of the operation of the double power supply ring network by adopting the cross-type double-single bus segmental wiring mode for the substation with 4 outgoing lines of 110kV, and through the symmetrical arrangement, it contains a line crossing, thereby avoiding the transmission line The emergence of problems caused by crossover has laid a good foundation for optimizing the design scheme of transmission lines.
Description
技术领域 technical field
本实用新型涉及电力系统变电站技术领域,具体地说是一种采用新型接线方式的110kV变电站,用于解决110kV出线为4回的变电站现有接线方式存在的问题。 The utility model relates to the technical field of power system substations, in particular to a 110kV substation adopting a new wiring mode, which is used to solve the problems existing in the existing wiring mode of the 110kV substation with 4 outgoing lines.
背景技术 Background technique
电力系统是由变压器、输电线路、用电设备组成的网络,它包括通过电的或机械的方式连接在网络中的所有设备。电力系统中的这些互联元件可以分为两类,一类是电力元件,它们对电能进行生产(发电机)、变换(变压器、整流器、逆变器)、输送和分配(电力传输线、配电网),消费(负荷);另一类是控制元件,它们改变系统的运行状态,如同步发电机的励磁调节器,调速器以及继电器等。 The power system is a network composed of transformers, transmission lines, and electrical equipment, including all equipment connected to the network by electrical or mechanical means. These interconnected elements in the power system can be divided into two categories, one is the power element, which produces (generators), transforms (transformers, rectifiers, inverters), transmits and distributes electric energy (power transmission lines, distribution network ), consumption (load); the other is the control element, which changes the operating state of the system, such as the excitation regulator, governor and relay of the synchronous generator.
变电站是联系发电厂和用户的中间环节,是电力系统中变换电压、接受和分配电能、控制电力的流向和调整电压的电力设备,它通过其变压器将各级电压的电网联系起来,起着变换和分配电能的作用。 The substation is the intermediate link between the power plant and the user. It is the power equipment in the power system that transforms the voltage, receives and distributes electric energy, controls the flow of power and adjusts the voltage. and the role of distributing electrical energy.
由于条件限制,还有很多110kV出线为4回的110kV变电站存在,根据这些变电站的负荷特点,其在接线形式选择上受到很多限制,而现有的接线方式又带来了很多问题。 Due to limited conditions, there are still many 110kV substations with four 110kV outgoing lines. According to the load characteristics of these substations, there are many restrictions on the selection of wiring forms, and the existing wiring methods have brought many problems.
目前110kV变电站的主接线型式一般采用线变组接线、桥型接线、双母线接线和单母线分段接线。 At present, the main wiring types of 110kV substations generally adopt line-to-substation wiring, bridge wiring, double busbar wiring and single busbar segmental wiring.
1、线变组接线是一种接线最简单、设备最少、不需要高压配电装置的最简洁的接线方式,但有些110kV变电站不是纯末端变电站,还有一定的穿越容量要求,并且负荷的保安容量较大,这样难以从其他电源引入,只能靠自身的电源线路之问互为备用,因此,线变组接线难以满足可靠性要求。 1. Line-to-line substation wiring is the most concise wiring method with the simplest wiring, the least equipment, and no need for high-voltage power distribution devices. However, some 110kV substations are not pure terminal substations, and there are certain cross-through capacity requirements, and the security of the load The capacity is large, so it is difficult to introduce it from other power sources, and it can only rely on its own power lines for mutual backup. Therefore, it is difficult for the line-to-line transformer wiring to meet the reliability requirements.
2、桥型接线分为双内桥接线和双外桥接线两种。 2. Bridge connection is divided into double inner bridge connection and double outer bridge connection.
(1)双内桥接线。桥型接线和扩大桥型接线一般用于110kV线路出线3回及以下,不适于110kV线路出线4回以上的情况。如果变电站负荷没有穿越功率的要求,可采用双内桥接线,它是由双进线的变压器,变电站从内桥接线转化过来。多年运行经验表明,内桥接线是一种安全、可靠、经济性好的主接线方式。如果穿越功率虽然是间歇性的,而且穿越功率不大,但内桥接线在穿越功率运行时,进行断路器的二次整定困难,这种情况则不宜采用双内桥接线。 (1) Double inner bridge wiring. Bridge connection and enlarged bridge connection are generally used for 110kV line with 3 or less outlets, and are not suitable for 110kV lines with more than 4 outlets. If the substation load does not require crossing power, a double inner bridge connection can be used, which is a transformer with double incoming lines, and the substation is converted from the inner bridge connection. Years of operating experience show that inner bridge wiring is a safe, reliable and economical main wiring method. If the ride-through power is intermittent and the ride-through power is not large, it is difficult to perform secondary setting of the circuit breaker when the inner bridge wiring is running through the power. In this case, it is not suitable to use the double inner bridge wiring.
(2)双外桥接线。考虑到电厂并网的电力系统的穿越功率。可采用双外桥接线方式,但考虑到一些变电站负荷较大,双外桥接线方式对变电站内部的操作灵活性影响较大,这样则不宜采用双外桥接线方式。 (2) Double outer bridge wiring. Taking into account the ride-through power of the power system where the power plant is connected to the grid. The double-outer bridge connection method can be used, but considering that some substations have a large load, the double-outer bridge connection method has a greater impact on the operational flexibility inside the substation, so it is not suitable to use the double-outer bridge connection method.
3、双母线接线方式是一种供电可靠性最高、调度灵活、扩建方便并且便于实现的主接线方式,但根据(35-110kV变电所设计规范), 110kV线路为6回及以上的,宜采用双母线接线,但是如果110kV变电站的出线只有4回,则达不到双母线配置条件。 3. The double-bus wiring method is a main wiring method with the highest power supply reliability, flexible scheduling, convenient expansion and easy realization. However, according to (35-110kV substation design specifications), the 110kV line is 6 circuits or more, and it is suitable Double-busbar wiring is used, but if there are only 4 outgoing lines in the 110kV substation, the configuration conditions for double-busbars cannot be met.
4、单母线分段接线是用断路器把母线分段,对重要用户可以从不同段引出两个回路,由两个电源供电;当一段母线发生故障时,分段断路器自动将故障段切除,保证正常段母线不间断供电和不致使重要用户停电。 4. Segmented wiring of single busbar is to use circuit breaker to divide the busbar into sections. For important users, two circuits can be drawn from different sections and powered by two power sources; when a section of busbar fails, the sectioned circuit breaker will automatically cut off the faulty section , to ensure the uninterrupted power supply of the bus in the normal section and not cause power outages for important users.
从以上的分析可以看出,对于只具有4回110kV 出线的110kV变电站的主接线应以配置单母线分段接线较为适宜。 From the above analysis, it can be seen that for the main wiring of a 110kV substation with only 4 circuits of 110kV outgoing lines, it is more appropriate to configure single-bus section wiring.
常规的单母线分段接线方式如图1所示。具有4回110kV 出线的110kV变电站的4回电源来电厂和220kV变电站110kV母线。如果采用单母线分段接线将长期造成110kV电源并网运行,而且目前地市电网为了避免环流和便于电网管理,110kV一级电网一般是不允许两个电源并网运行的。因此常规的单母线分段接线方式不能满足电网管理制度的要求。 The conventional single-bus section wiring method is shown in Figure 1. 110kV substation with 4 circuits of 110kV outgoing lines, 4 circuits of power supply to the power plant and 110kV busbar of 220kV substation. If the single-bus section wiring is used, the 110kV power supply will be connected to the grid for a long time, and in order to avoid circulating currents and facilitate grid management, the 110kV primary grid generally does not allow two power supplies to operate in parallel. Therefore, the conventional single-bus section wiring method cannot meet the requirements of the power grid management system.
为了避免电源环网的问题,可以采用双母线接线和单母线多分段的接线方式加以解决,但双母线接线和单母线多分段接线方式在经济性和灵活性方而均明显存在不足。 In order to avoid the problem of the power ring network, it can be solved by double-bus wiring and single-bus multi-section wiring, but the double-bus wiring and single-bus multi-section wiring are obviously insufficient in terms of economy and flexibility.
实用新型内容 Utility model content
针对上述不足,本实用新型提供了一种采用新型接线方式的110kV变电站,能够有效解决110kV出线为4回的变电站现有接线方式存在的问题。 In view of the above shortcomings, the utility model provides a 110kV substation using a new wiring method, which can effectively solve the problems existing in the existing wiring method of the 110kV substation with 4 outgoing lines.
本实用新型解决其技术问题采取的技术方案是:一种采用新型接线方式的110kV变电站,所述110kV变电站设置在电厂和接入电网的220kV变电站之间,并通过2回出线线路与电厂相连,通过2回出线线路与220kV变电站相连,其特征是,包括第一出线断路器、第二出线断路器、第三出线断路器、第四出线断路器、第一110kV母线、第二110kV母线、第三110kV母线、第四110kV母线、第一母线分段断路器、第二母线分段断路器、第一主变高压侧断路器、第二主变高压侧断路器、第三主变高压侧断路器、第四主变高压侧断路器、第一主变、第二主变、第三主变、第四主变、第一主变低压侧断路器、第二主变低压侧断路器、第三主变低压侧断路器、第四主变低压侧断路器、第一主接线、第二主接线、第三主接线、第四主接线、第一主接线分段断路器、第二主接线分段断路器和第三主接线分段断路器;所述第一110kV母线通过第一出线断路器与电厂第一供电线路相连,且通过第一主变高压侧断路器与第一主变相连,所述第一主变通过第一主变低压侧断路器与第一主接线相连;所述第二110kV母线通过第二出线断路器与电厂第二供电线路相连,且通过第二主变高压侧断路器与第二主变相连,所述第二主变通过第二主变低压侧断路器与第二主接线相连;所述第三110kV母线通过第三出线断路器与220kV变电站第一供电线路相连,且通过第三主变高压侧断路器与第三主变相连,所述第三主变通过第三主变低压侧断路器与第三主接线相连;所述第四110kV母线通过第四出线断路器与220kV变电站第二供电线路相连,且通过第四主变高压侧断路器与第四主变相连,所述第四主变通过第四主变低压侧断路器与第四主接线相连;第二110kV母线与第三110kV母线之间连接有第一母线分段断路器,第一110kV母线与第四110kV母线之间连接有第二母线分段断路器;第一主接线与第二主接线之间连接有第一主接线分段断路器,第二主接线与第三主接线之间连接有第二主接线分段断路器,第三主接线与第四主接线之间连接有第三主接线分段断路器。 The technical solution adopted by the utility model to solve the technical problem is: a 110kV substation adopting a new wiring method, the 110kV substation is arranged between the power plant and the 220kV substation connected to the power grid, and connected to the power plant through 2 outgoing lines, It is connected to the 220kV substation through 2 outgoing lines, which is characterized by including the first outgoing line circuit breaker, the second outgoing line circuit breaker, the third outgoing line circuit breaker, the fourth outgoing line circuit breaker, the first 110kV bus, the second 110kV bus, the second The third 110kV bus, the fourth 110kV bus, the first bus segment circuit breaker, the second bus segment circuit breaker, the first main transformer high voltage side circuit breaker, the second main transformer high voltage side circuit breaker, the third main transformer high voltage side circuit breaker breaker, fourth main transformer high-voltage side circuit breaker, first main transformer, second main transformer, third main transformer, fourth main transformer, first main transformer low-voltage side circuit breaker, second main transformer low-voltage side circuit breaker, second main transformer The circuit breaker on the low-voltage side of the third main transformer, the circuit breaker on the low-voltage side of the fourth main transformer, the first main wiring, the second main wiring, the third main wiring, the fourth main wiring, the first main wiring section circuit breaker, and the second main wiring Sectional circuit breaker and third main wiring section circuit breaker; the first 110kV bus is connected to the first power supply line of the power plant through the first outlet circuit breaker, and connected to the first main transformer through the high-voltage side circuit breaker of the first main transformer , the first main transformer is connected to the first main wiring through the first main transformer low-voltage side circuit breaker; the second 110kV busbar is connected to the second power supply line of the power plant through the second outlet circuit breaker, and the high-voltage The side circuit breaker is connected to the second main transformer, and the second main transformer is connected to the second main wiring through the second main transformer low-voltage side circuit breaker; the third 110kV bus is connected to the first power supply of the 220kV substation through the third outlet circuit breaker The third main transformer is connected to the third main transformer through the circuit breaker on the high-voltage side of the third main transformer, and the third main transformer is connected to the third main wiring through the circuit breaker on the low-voltage side of the third main transformer; the fourth 110kV busbar is connected to the third main transformer through the The four-outlet circuit breaker is connected to the second power supply line of the 220kV substation, and is connected to the fourth main transformer through the fourth main transformer high-voltage side circuit breaker, and the fourth main transformer is connected to the fourth main transformer through the fourth main transformer low-voltage side circuit breaker. The first bus section circuit breaker is connected between the second 110kV bus and the third 110kV bus, and the second bus section circuit breaker is connected between the first 110kV bus and the fourth 110kV bus; the first main wiring and the second The first main wiring sectional circuit breaker is connected between the two main wirings, the second main wiring sectional circuit breaker is connected between the second main wiring and the third main wiring, and the third main wiring and the fourth main wiring are connected There is a third main wiring section breaker.
优选地,所述的第一出线断路器、第二出线断路器、第三出线断路器和第四出线断路器的两端分别设置有出线隔离开关。 Preferably, the two ends of the first outgoing line circuit breaker, the second outgoing line circuit breaker, the third outgoing line circuit breaker and the fourth outgoing line circuit breaker are respectively provided with outgoing line isolating switches.
优选地,所述的第一母线分段断路器和第二母线分段断路器的两端分别设置有分段隔离开关。 Preferably, the two ends of the first bus section circuit breaker and the second bus section circuit breaker are respectively provided with section disconnectors.
优选地,所述的第一主接线分段断路器、第二主接线分段断路器和第三主接线分段断路器的两端分别设置有分段隔离开关。 Preferably, the two ends of the first main wiring section circuit breaker, the second main wiring section circuit breaker and the third main wiring section circuit breaker are respectively provided with section isolating switches.
优选地,所述的第一主变高压侧断路器、第二主变高压侧断路器、第三主变高压侧断路器和第四主变高压侧断路器的两端分别设置有分段隔离开关。 Preferably, the two ends of the high voltage side circuit breaker of the first main transformer, the high voltage side circuit breaker of the second main transformer, the high voltage side circuit breaker of the third main transformer and the high voltage side circuit breaker of the fourth main transformer are respectively provided with section isolation switch.
优选地,所述的第一主变低压侧断路器、第二主变低压侧断路器、第三主变低压侧断路器和第四主变低压侧断路器的两端分别设置有分段隔离开关。 Preferably, the two ends of the low-voltage side circuit breaker of the first main transformer, the low-voltage side circuit breaker of the second main transformer, the low-voltage side circuit breaker of the third main transformer and the low-voltage side circuit breaker of the fourth main transformer are respectively provided with section isolation switch.
本实用新型的有益效果是:本实用新型通过对110kV出线为4回的变电站采用交叉式双单母线分段接线方式,解决了双电源环网运行的问题,而且通过对称布置,内含着一次线路交叉,从而避免了输电线路交叉而导致的问题出现,为优化输电线路设计方案打下了良好的基础。 The beneficial effects of the utility model are: the utility model solves the problem of the operation of the dual power supply ring network by adopting the cross-type double-single bus segment wiring mode for the substation with 4 circuits of 110kV outlets, and through the symmetrical arrangement, it contains a Line crossing avoids the problems caused by transmission line crossing, and lays a good foundation for optimizing the design scheme of transmission lines.
本实用新型针对110kV出线只有4回的变电站的特点,采用双单母线分段接线方式较好地满足了一些工程的需要,这种双单母线分段主接线方式虽然较为少见,但在一定的工程特殊条件下,不失为一种灵活、适用的接线方式。 The utility model aims at the characteristics of the 110kV substation with only 4 outgoing lines, and adopts the double-single busbar segmented wiring mode to better meet the needs of some projects. Although this double-single busbar segmental main wiring mode is relatively rare, it can Under the special conditions of the project, it is a flexible and applicable wiring method.
附图说明 Description of drawings
图1为现有技术中采用单母线分段接线方式的11110kV变电站主接线系统的结构示意图; Fig. 1 is a structural schematic diagram of the main wiring system of a 11110kV substation using a single-bus section wiring method in the prior art;
图2为本实用新型的结构示意图; Fig. 2 is the structural representation of the utility model;
图中,11电厂第一供电线路、12电厂第二供电线路、13 220kV变电站第一供电线路、14 220kV变电站第二供电线路、21第一出线断路器、22第二出线断路器、23第三出线断路器、24第四出线断路器、31第一110kV母线、32第二110kV母线、33第三110kV母线、34第四110kV母线、41第一母线分段断路器、42第二母线分段断路器、51第一主变高压侧断路器、52第二主变高压侧断路器、53第三主变高压侧断路器、54第四主变高压侧断路器、61第一主变、62第二主变、63第三主变、64第四主变、71第一主变低压侧断路器、72第二主变低压侧断路器、73第三主变低压侧断路器、74第四主变低压侧断路器、81第一35kV主接线、82第二35kV主接线、83第三35kV主接线、84第四35kV主接线、91第一主接线分段断路器、92第二主接线分段断路器、93第三主接线分段断路器。 In the figure, the first power supply line of 11 power plant, the second power supply line of 12 power plant, the first power supply line of 13 220kV substation, the second power supply line of 14 220kV substation, the first outlet circuit breaker of 21, the second outlet circuit breaker of 22, the third Outgoing circuit breaker, 24 fourth outgoing circuit breaker, 31 first 110kV busbar, 32 second 110kV busbar, 33 third 110kV busbar, 34 fourth 110kV busbar, 41 first busbar section circuit breaker, 42 second busbar section Circuit breaker, 51 high voltage side circuit breaker of the first main transformer, 52 high voltage side circuit breaker of the second main transformer, 53 high voltage side circuit breaker of the third main transformer, 54 high voltage side circuit breaker of the fourth main transformer, 61 first main transformer, 62 The second main transformer, 63 the third main transformer, 64 the fourth main transformer, 71 the first main transformer low-voltage side circuit breaker, 72 the second main transformer low-voltage side circuit breaker, 73 the third main transformer low-voltage side circuit breaker, 74 the fourth Main transformer low-voltage side circuit breaker, 81 first 35kV main wiring, 82 second 35kV main wiring, 83 third 35kV main wiring, 84 fourth 35kV main wiring, 91 first main wiring section circuit breaker, 92 second main wiring Sectional circuit breaker, 93 third main wiring section circuit breaker.
具体实施方式 Detailed ways
为能清楚说明本方案的技术特点,下面通过具体实施方式,并结合其附图,对本实用新型进行详细阐述。下文的公开提供了许多不同的实施例或例子用来实现本实用新型的不同结构。为了简化本实用新型的公开,下文中对特定例子的部件和设置进行描述。此外,本实用新型可以在不同例子中重复参考数字和/或字母。这种重复是为了简化和清楚的目的,其本身不指示所讨论各种实施例和/或设置之间的关系。应当注意,在附图中所图示的部件不一定按比例绘制。本实用新型省略了对公知组件和处理技术及工艺的描述以避免不必要地限制本实用新型。 In order to clearly illustrate the technical features of this solution, the utility model will be described in detail below through specific implementation methods and in conjunction with the accompanying drawings. The following disclosure provides many different embodiments or examples for realizing different structures of the present invention. To simplify the disclosure of the present invention, components and arrangements of specific examples are described below. Furthermore, the present invention may repeat reference numerals and/or letters in different instances. This repetition is for the purpose of simplicity and clarity and does not in itself indicate a relationship between the various embodiments and/or arrangements discussed. It should be noted that components illustrated in the figures are not necessarily drawn to scale. The present invention omits descriptions of known components and processing techniques and processes to avoid unnecessarily limiting the present invention.
如图2所示,本实用新型的一种采用新型接线方式的110kV变电站,所述110kV变电站设置在电厂和接入电网的220kV变电站之间,它包括第一出线断路器21、第二出线断路器22、第三出线断路器23、第四出线断路器24、第一110kV母线31、第二110kV母线32、第三110kV母线33、第四110kV母线34、第一母线分段断路器41、第二母线分段断路器42、第一主变高压侧断路器51、第二主变高压侧断路器52、第三主变高压侧断路器53、第四主变高压侧断路器54、第一主变61、第二主变62、第三主变63、第四主变64、第一主变低压侧断路器71、第二主变低压侧断路器72、第三主变低压侧断路器73、第四主变低压侧断路器74、第一35kV主接线81、第二35kV主接线82、第三35kV主接线83、第四35kV主接线84、第一主接线分段断路器91、第二主接线分段断路器92和第三主接线分段断路器93;所述第一110kV母线31通过第一出线断路器21与电厂第一供电线路11相连,且通过第一主变高压侧断路器51与第一主变11相连,所述第一主变51通过第一主变低压侧断路器61与第一35kV主接线81相连;所述第二110kV母线32通过第二出线断路器22与电厂第二供电线路12相连,且通过第二主变高压侧断路器52与第二主变62相连,所述第二主变62通过第二主变低压侧断路器72与第二35kV主接线82相连;所述第三110kV母线33通过第三出线断路器23与220kV变电站第一供电线路13相连,且通过第三主变高压侧断路器53与第三主变63相连,所述第三主变63通过第三主变低压侧断路器73与第三35kV主接线83相连;所述第四110kV母线34通过第四出线断路器24与220kV变电站第二供电线路14相连,且通过第四主变高压侧断路器54与第四主变64相连,所述第四主变64通过第四主变低压侧断路器74与第四35kV主接线84相连;第二110kV母线32与第三110kV母线33之间连接有第一母线分段断路器41,第一110kV母线31与第四110kV母线34之间连接有第二母线分段断路器42;第一35kV主接线81与第二35kV主接线82之间连接有第一主接线分段断路器91,第二35kV主接线82与第三35kV主接线83之间连接有第二主接线分段断路器92,第三35kV主接线83与第四35kV主接线84之间连接有第三主接线分段断路器93。 As shown in Fig. 2, a kind of 110kV substation of the utility model adopts the new wiring mode, and described 110kV substation is arranged between the power plant and the 220kV substation connected to the power grid, and it includes the first outlet circuit breaker 21, the second outlet circuit breaker 22, the third outlet circuit breaker 23, the fourth outlet circuit breaker 24, the first 110kV bus 31, the second 110kV bus 32, the third 110kV bus 33, the fourth 110kV bus 34, the first bus section circuit breaker 41, The second bus section circuit breaker 42, the first main transformer high voltage side circuit breaker 51, the second main transformer high voltage side circuit breaker 52, the third main transformer high voltage side circuit breaker 53, the fourth main transformer high voltage side circuit breaker 54, the The first main transformer 61, the second main transformer 62, the third main transformer 63, the fourth main transformer 64, the first main transformer low-voltage side circuit breaker 71, the second main transformer low-voltage side circuit breaker 72, the third main transformer low-voltage side circuit breaker 73, the fourth main transformer low-voltage side circuit breaker 74, the first 35kV main wiring 81, the second 35kV main wiring 82, the third 35kV main wiring 83, the fourth 35kV main wiring 84, the first main wiring section circuit breaker 91 , the second main wiring section circuit breaker 92 and the third main wiring section circuit breaker 93; the first 110kV bus bar 31 is connected to the first power supply line 11 of the power plant through the first outgoing line circuit breaker 21, and the first main transformer The high-voltage side circuit breaker 51 is connected to the first main transformer 11, and the first main transformer 51 is connected to the first 35kV main connection 81 through the first main transformer low-voltage side circuit breaker 61; the second 110kV bus bar 32 is connected to the second outgoing line The circuit breaker 22 is connected to the second power supply line 12 of the power plant, and is connected to the second main transformer 62 through the second main transformer high-voltage side circuit breaker 52, and the second main transformer 62 is connected to the second main transformer 62 through the second main transformer low-voltage side circuit breaker 72. Two 35kV main wirings 82 are connected; the third 110kV busbar 33 is connected to the first power supply line 13 of the 220kV substation through the third outlet circuit breaker 23, and is connected to the third main transformer 63 through the third main transformer high voltage side circuit breaker 53, The third main transformer 63 is connected to the third 35kV main wiring 83 through the third main transformer low-voltage side circuit breaker 73; the fourth 110kV busbar 34 is connected to the second power supply line 14 of the 220kV substation through the fourth outlet circuit breaker 24, And the fourth main transformer 64 is connected to the fourth main transformer 64 through the fourth main transformer high-voltage side circuit breaker 54, and the fourth main transformer 64 is connected to the fourth 35kV main connection 84 through the fourth main transformer low-voltage side circuit breaker 74; the second 110kV bus bar 32 The first bus section circuit breaker 41 is connected with the third 110kV bus 33, the second bus section circuit breaker 42 is connected between the first 110kV bus 31 and the fourth 110kV bus 34; the first 35kV main wiring 81 and The first main wiring section circuit breaker 91 is connected between the second 35kV main wiring 82, the second main wiring section circuit breaker 92 is connected between the second 35kV main wiring 82 and the third 35kV main wiring 83, and the third 35kV There is a connection between the main wiring 83 and the fourth 35kV main wiring 84 The third main line section circuit breaker 93 .
优选地,上述所述的所有断路器的两端都设置有隔离开关。 Preferably, both ends of all the above-mentioned circuit breakers are provided with isolating switches.
本实用新型在正常运行方式下,母线分段断路器断开,线路以线变组的方式运行,运行方式清晰可靠;当其中一条电源线路发生故障进线断路器断开时,合上母线分段断路器,可实现减备用供电;当需要电厂向系统输送上网电量时,只需将分段断路器合闸即可。 In the normal operation mode of the utility model, the circuit breaker of the bus section is disconnected, and the line operates in the mode of line change group, and the operation mode is clear and reliable; The section circuit breaker can realize the reduction of standby power supply; when the power plant is required to transmit the on-grid electricity to the system, it only needs to close the section circuit breaker.
通过对110kV出线为4回的变电站采用交叉式双单母线分段接线方式,解决了双电源环网运行的问题,而且通过对称布置,内含着一次线路交叉,从而避免了输电线路交叉而导致的问题出现,为优化输电线路设计方案打下了良好的基础。 By adopting the cross-type double-single bus segmental wiring method for the substation with 4 outgoing lines of 110kV, the problem of the operation of the double power supply ring network is solved, and through the symmetrical arrangement, there is a line crossing included, thereby avoiding the transmission line crossing. The emergence of problems has laid a good foundation for optimizing the design scheme of transmission lines.
针对110kV出线为4回的变电站的特点,双单母线分段接线较好地满足了变电工程的需要。双单母线分段具有一定要求:一是出线回路数要求为4回;二是变电站为受电用户变电站,并且多回电源供电;三是线路供电负荷较大,备用输电容量较小,因此对灵活性要求较低;四是变电站不适用于线变组接线。虽然双单母线分段上接线方式虽然较为少见,但在一定的工程特殊条件下,不失为一种灵活、适用的接线方式,它能够有效地解决110kV出线为4回的变电站现有接线方式存在的问题。 In view of the characteristics of the 110kV substation with 4 outgoing lines, the segmented wiring of double-single busbars better meets the needs of the substation project. The double-single bus section has certain requirements: first, the number of outgoing circuits is required to be 4; second, the substation is a substation for power receiving users, and multi-circuit power supply; third, the power supply load of the line is relatively large, and the reserve transmission capacity is small. The flexibility requirements are low; Fourth, the substation is not suitable for line-to-line transformation group wiring. Although the double-single bus section wiring method is relatively rare, it is a flexible and applicable wiring method under certain special engineering conditions. It can effectively solve the problems existing in the existing wiring method of a 110kV substation with 4 outgoing lines. question.
以上所述只是本实用新型的优选实施方式,对于本技术领域的普通技术人员来说,在不脱离本实用新型原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也被视为本实用新型的保护范围。 The above is only a preferred embodiment of the utility model, and for those of ordinary skill in the art, without departing from the principle of the utility model, some improvements and modifications can also be made, and these improvements and modifications are also regarded as It is the protection scope of the utility model.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520176687.4U CN204577857U (en) | 2015-03-27 | 2015-03-27 | A kind of 110kV transformer station adopting novel wire connecting way |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520176687.4U CN204577857U (en) | 2015-03-27 | 2015-03-27 | A kind of 110kV transformer station adopting novel wire connecting way |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204577857U true CN204577857U (en) | 2015-08-19 |
Family
ID=53870452
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520176687.4U Expired - Fee Related CN204577857U (en) | 2015-03-27 | 2015-03-27 | A kind of 110kV transformer station adopting novel wire connecting way |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204577857U (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109038248A (en) * | 2018-09-20 | 2018-12-18 | 深圳供电规划设计院有限公司 | A kind of wiring construction of substation low-voltage side |
| CN111244767A (en) * | 2020-03-11 | 2020-06-05 | 中铁二院工程集团有限责任公司 | AT traction substation 2X 27.5kV main wiring structure and fault isolation method |
| CN112510706A (en) * | 2020-12-04 | 2021-03-16 | 深圳供电局有限公司 | A close ring circuit with mother for 10kV distribution network |
| CN116031924A (en) * | 2022-12-28 | 2023-04-28 | 中国电力工程顾问集团中南电力设计院有限公司 | Current transformer station power system wiring and operation method with security section |
-
2015
- 2015-03-27 CN CN201520176687.4U patent/CN204577857U/en not_active Expired - Fee Related
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109038248A (en) * | 2018-09-20 | 2018-12-18 | 深圳供电规划设计院有限公司 | A kind of wiring construction of substation low-voltage side |
| CN111244767A (en) * | 2020-03-11 | 2020-06-05 | 中铁二院工程集团有限责任公司 | AT traction substation 2X 27.5kV main wiring structure and fault isolation method |
| CN112510706A (en) * | 2020-12-04 | 2021-03-16 | 深圳供电局有限公司 | A close ring circuit with mother for 10kV distribution network |
| CN116031924A (en) * | 2022-12-28 | 2023-04-28 | 中国电力工程顾问集团中南电力设计院有限公司 | Current transformer station power system wiring and operation method with security section |
| CN116031924B (en) * | 2022-12-28 | 2024-04-16 | 中国电力工程顾问集团中南电力设计院有限公司 | Current transformer station power system wiring and operation method with security section |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN205231835U (en) | Structure for large -scale thermal power factory unit high pressure service power each other is being equipped with | |
| CN104882883A (en) | 10 KV power distribution network system | |
| CN102403780A (en) | Power supply device for bypass to operate without power failure | |
| CN204577857U (en) | A kind of 110kV transformer station adopting novel wire connecting way | |
| CN105305431A (en) | Snowflake grid type grid construction method suitable for urban medium voltage distribution networks | |
| CN204835226U (en) | Line arrangement structure of two complete clusters is joined in marriage into in wiring of one and half circuit breakers | |
| CN205178525U (en) | Asynchronous conversion device for power grid at both ends of high-voltage DC | |
| CN104333126A (en) | Large hydropower engineering power supply system | |
| CN204067884U (en) | A kind of distribution line based on double bus scheme | |
| Rani et al. | Power upgradation and possibility of small power tapping from composite acdc transmission system | |
| CN104052084A (en) | 110 kilovolt substation micro-grid system used for large electricity consumption places | |
| CN208479185U (en) | A kind of substation's spare phase quick-switching system | |
| CN201219177Y (en) | Low-voltage distribution main konode system | |
| CN104218457A (en) | Power distribution device and electric master system thereof | |
| CN203481822U (en) | Closed loop power supply model of medium voltage 10 kilovolt power distribution network | |
| CN207459723U (en) | Spare phase transformer quickly puts into arrangement | |
| CN202405780U (en) | medium voltage distribution network | |
| CN111342549A (en) | Power supply system is synthesized to inside of large-scale coal-electricity integration power station | |
| CN203932698U (en) | A kind of single busbar connection dual-breaker sectional wiring structure | |
| CN106655254B (en) | A kind of inverter and transformer integrated equipment | |
| CN204424772U (en) | Two main transformer four segmentation integrated automation converting stations | |
| CN210780123U (en) | A fully centralized monitoring and protection device for electrical equipment of wind power booster station | |
| RU117732U1 (en) | HIGH VOLTAGE DISTRIBUTION DEVICE | |
| CN211182805U (en) | Wiring structure of low-voltage side of transformer substation | |
| CN207967937U (en) | A kind of power switching apparatus and power supply and distribution of electric power system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150819 Termination date: 20200327 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |