CN110208644A - GIS cable machinery - Google Patents
GIS cable machinery Download PDFInfo
- Publication number
- CN110208644A CN110208644A CN201910407412.XA CN201910407412A CN110208644A CN 110208644 A CN110208644 A CN 110208644A CN 201910407412 A CN201910407412 A CN 201910407412A CN 110208644 A CN110208644 A CN 110208644A
- Authority
- CN
- China
- Prior art keywords
- cable
- test window
- test
- fault
- gis
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/08—Locating faults in cables, transmission lines, or networks
- G01R31/081—Locating faults in cables, transmission lines, or networks according to type of conductors
- G01R31/086—Locating faults in cables, transmission lines, or networks according to type of conductors in power transmission or distribution networks, i.e. with interconnected conductors
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/12—Testing dielectric strength or breakdown voltage ; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing
- G01R31/1227—Testing dielectric strength or breakdown voltage ; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing of components, parts or materials
- G01R31/1263—Testing dielectric strength or breakdown voltage ; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing of components, parts or materials of solid or fluid materials, e.g. insulation films, bulk material; of semiconductors or LV electronic components or parts; of cable, line or wire insulation
- G01R31/1281—Testing dielectric strength or breakdown voltage ; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing of components, parts or materials of solid or fluid materials, e.g. insulation films, bulk material; of semiconductors or LV electronic components or parts; of cable, line or wire insulation of liquids or gases
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02B—BOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
- H02B13/00—Arrangement of switchgear in which switches are enclosed in, or structurally associated with, a casing, e.g. cubicle
- H02B13/02—Arrangement of switchgear in which switches are enclosed in, or structurally associated with, a casing, e.g. cubicle with metal casing
- H02B13/035—Gas-insulated switchgear
- H02B13/0358—Connections to in or out conductors
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
- Y04S10/52—Outage or fault management, e.g. fault detection or location
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Gas-Insulated Switchgears (AREA)
Abstract
本申请公开一种GIS电缆设备,包括分别一一对应连接各高压出线电缆的各T接筒;T接筒包括筒体,设于筒体内的隔离装置,以及设于筒体的筒壁上的试验窗;隔离装置的第一端连接主变压器,第二端连接高压出线电缆的电缆头,第三端接地;试验窗的一端用于连接隔离装置的第三端;试验窗的另一端用于连接故障监测设备。通过在T接筒上加装试验窗,实现不需放气(GIS气体)即可对电缆进行试验(故障检测),进而实现发现电缆故障后,可通过隔离装置操作实现故障电缆隔离,正常电缆运行,大大减少了停电时间和范围。提高了线路检修维护的便携性,以及提高了T接线路的故障定位与隔离的效率。
The present application discloses a GIS cable equipment, which includes T-connectors for connecting high-voltage outgoing cables one by one; Test window; the first end of the isolation device is connected to the main transformer, the second end is connected to the cable head of the high-voltage outgoing cable, and the third end is grounded; one end of the test window is used to connect the third end of the isolation device; the other end of the test window is used for Connect fault monitoring equipment. By installing a test window on the T-connector, the cable can be tested (fault detection) without degassing (GIS gas), and then after the cable fault is found, the faulty cable can be isolated through the operation of the isolation device, and the normal cable operation, greatly reducing the time and scope of power outages. The portability of line inspection and maintenance is improved, and the efficiency of fault location and isolation of T-connection lines is improved.
Description
技术领域technical field
本申请涉及配电技术领域,特别是涉及一种GIS电缆设备。This application relates to the technical field of power distribution, in particular to a GIS cable device.
背景技术Background technique
高压变电站的简化接线,采用线路--变压器组接线,每站最终按3台主变、3路电源配置,每回电源线路“T”接3台主变供电的原则性方案,简称“3T”接线。当高压电网采用3T接线设计时,电缆T接点设置在变电站内,为了方便在变电站内完成T接,需要变电站内增加GIS(Gas Insulated Switchgear,气体绝缘组合电器设备)电缆T接筒。The simplified wiring of high-voltage substations adopts line-transformer group wiring, and each station is finally configured with 3 main transformers and 3 power supplies, and the principle scheme that each power line "T" is connected to 3 main transformers for power supply, referred to as "3T" wiring. When the high-voltage power grid adopts the 3T wiring design, the cable T-connection is set in the substation. In order to facilitate the completion of the T-connection in the substation, it is necessary to add a GIS (Gas Insulated Switchgear, gas insulated combined electrical equipment) cable T-connector in the substation.
目前,高压主设备“线路电缆化、变电GIS化”进程不断加快,高压电缆和GIS设备均无裸露带电部分,检修方式下无法灵活解列隔离工作段或故障段,检修维护极为不便;且3T接线本身的特点会导致线路停电涉及站点多,操作时间长,影响范围广,加大检修工作量,因此线路故障时大大增加了巡视范围和故障查找的时间,线路常规停电检修时,涉及的变电站多,操作时间长,检修工作量加大,大大降低维护效率。电缆T接线路一旦发生永久性故障,故障定位困难,T接头难以解开,无法快速切除故障段,修复耗时长;电缆线路故障定位存在脉冲信号混乱和故障点判断困难的现象,在故障定位方面存在困难。而存在分支接头的电缆线路,更是电缆故障测寻的难点,故障测寻时间难以保证。At present, the process of "line cable transformation and power transformation GIS transformation" of high-voltage main equipment is constantly accelerating. Neither high-voltage cables nor GIS equipment have exposed live parts. Under the maintenance mode, it is impossible to flexibly separate and isolate the working section or the fault section, which is extremely inconvenient for maintenance; and The characteristics of 3T wiring itself will lead to many sites involved in line power outages, long operation time, wide range of influence, and increased maintenance workload. There are many substations, the operation time is long, the maintenance workload is increased, and the maintenance efficiency is greatly reduced. Once a permanent fault occurs in the T-connection line of the cable, it is difficult to locate the fault. There are difficulties. The cable lines with branch joints are even more difficult to find cable faults, and the time to find faults is difficult to guarantee.
在实现过程中,发明人发现传统技术中至少存在如下问题:传统的采用“3T”接线的高压电网中,线路检修维护不便,且T接线路的故障定位与隔离效率低。During the implementation process, the inventor found at least the following problems in the traditional technology: In the traditional high-voltage power grid using "3T" wiring, it is inconvenient to repair and maintain the line, and the fault location and isolation efficiency of the T-connected line is low.
发明内容Contents of the invention
基于此,有必要针对传统的采用“3T”接线的高压电网中,线路检修维护不便,且T接线路的故障定位与隔离效率低的问题,提供一种GIS电缆设备。Based on this, it is necessary to provide a GIS cable device to solve the problems of inconvenient line maintenance and low fault location and isolation efficiency of T-connected lines in the traditional high-voltage power grid using "3T" wiring.
为了实现上述目的,本发明实施例提供了一种GIS电缆设备,包括分别一一对应连接各高压出线电缆的各T接筒;In order to achieve the above object, the embodiment of the present invention provides a GIS cable equipment, including each T connector connected to each high-voltage outlet cable in one-to-one correspondence;
T接筒包括筒体,设于筒体内的隔离装置,以及设于筒体的筒壁上的试验窗;隔离装置的第一端连接主变压器,第二端连接高压出线电缆的电缆头,第三端接地;试验窗的一端用于连接隔离装置的第三端;试验窗的另一端用于连接故障监测设备。The T-joint barrel includes a barrel, an isolating device inside the barrel, and a test window on the wall of the barrel; the first end of the isolating device is connected to the main transformer, and the second end is connected to the cable head of the high-voltage outgoing cable. The three ends are grounded; one end of the test window is used to connect the third end of the isolation device; the other end of the test window is used to connect the fault monitoring equipment.
在其中一个实施例中,隔离装置包括隔离开关和快速接地开关;In one of the embodiments, the isolation device includes an isolation switch and a quick earthing switch;
隔离开关的第一端连接主变压器,第二端连接高压出线电缆的电缆头;快速接地开关的一端连接隔离开关的第二端;快速接地开关的另一端接地。The first end of the isolating switch is connected to the main transformer, and the second end is connected to the cable head of the high-voltage outgoing cable; one end of the quick earthing switch is connected to the second end of the isolating switch; the other end of the quick earthing switch is grounded.
在其中一个实施例中,试验窗包括导体接线板;In one of the embodiments, the test window comprises a conductor terminal block;
导体接线板的第一端连接快速接地开关的一端;导体接线板的第二端连接故障监测设备。The first end of the conductor wiring board is connected to one end of the quick grounding switch; the second end of the conductor wiring board is connected to the fault monitoring equipment.
在其中一个实施例中,试验窗还包括设于筒体的筒壁上的试验窗盖;试验窗盖内设有试验腔体;导体接线板设于试验腔体内。In one of the embodiments, the test window further includes a test window cover arranged on the cylinder wall of the cylinder body; a test cavity is arranged in the test window cover; and a conductor wiring board is arranged in the test cavity.
在其中一个实施例中,试验窗还包括用于隔离T接筒的气室的盆式绝缘子;盆式绝缘子设于试验腔体内。In one of the embodiments, the test window further includes a basin-type insulator for isolating the air chamber of the T-joint; the basin-type insulator is arranged in the test chamber.
在其中一个实施例中,试验窗还包括支柱绝缘子;支柱绝缘子连接导体接线板。In one of the embodiments, the test window further includes a post insulator; the post insulator is connected to the conductor terminal block.
在其中一个实施例中,隔离开关为高压隔离开关。In one embodiment, the isolating switch is a high voltage isolating switch.
在其中一个实施例中,主变压器分别连接2条高压出线电缆。In one of the embodiments, the main transformer is connected to two high-voltage outgoing cables respectively.
在其中一个实施例中,还包括用于对主变压器的断路器与隔离装置之间联锁的电气闭锁装置。In one of the embodiments, an electrical locking device for interlocking between the circuit breaker of the main transformer and the isolating device is also included.
在其中一个实施例中,故障监测设备为绝缘监测设备或故障测距设备。In one of the embodiments, the fault monitoring device is an insulation monitoring device or a fault distance measuring device.
上述技术方案中的一个技术方案具有如下优点和有益效果:One of the above technical solutions has the following advantages and beneficial effects:
基于各T接筒与各高压出线电缆一一对应连接;隔离装置的第一端连接主变压器,第二端连接高压出线电缆的电缆头,第三端接地;试验窗的一端用于连接隔离装置的第三端;试验窗的另一端用于连接故障监测设备。通过在原有的T接筒内加装隔离装置,实现T接电缆之间及与主回路之间的分离;通过在T接筒上加装试验窗,实现不需放气(GIS气体)即可对电缆进行试验(故障检测),进而实现发现电缆故障后,可通过隔离装置操作实现故障电缆隔离,正常电缆运行,大大减少了停电时间和范围。提高了线路检修维护的便携性,以及提高了T接线路的故障定位与隔离的效率。Based on the one-to-one connection between each T connector and each high-voltage outgoing cable; the first end of the isolation device is connected to the main transformer, the second end is connected to the cable head of the high-voltage outgoing cable, and the third end is grounded; one end of the test window is used to connect to the isolation device The third end of the test window; the other end of the test window is used to connect fault monitoring equipment. By installing an isolation device in the original T-connector, the separation between the T-connector cables and the main circuit can be realized; by installing a test window on the T-connector, it is possible to realize that there is no need to deflate (GIS gas) Test the cable (fault detection), and then realize that after the cable fault is found, the faulty cable can be isolated through the operation of the isolation device, and the normal cable operation can greatly reduce the power failure time and scope. The portability of line inspection and maintenance is improved, and the efficiency of fault location and isolation of T-connection lines is improved.
附图说明Description of drawings
图1为一个实施例中GIS电缆设备的第一结构示意图;Fig. 1 is the first structural representation of GIS cable equipment in an embodiment;
图2为一个实施例中GIS电缆设备的第二结构示意图;Fig. 2 is the second structural representation of GIS cable equipment in an embodiment;
图3为一个实施例中试验窗的结构示意图。Fig. 3 is a schematic diagram of the structure of the test window in one embodiment.
具体实施方式Detailed ways
为了便于理解本申请,下面将参照相关附图对本申请进行更全面的描述。附图中给出了本申请的首选实施例。但是,本申请可以以许多不同的形式来实现,并不限于本文所描述的实施例。相反地,提供这些实施例的目的是使对本申请的公开内容更加透彻全面。In order to facilitate the understanding of the present application, the present application will be described more fully below with reference to the relevant drawings. A preferred embodiment of the application is shown in the drawings. However, the present application can be embodied in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of this application more thorough and comprehensive.
除非另有定义,本文所使用的所有的技术和科学术语与属于本发明的技术领域的技术人员通常理解的含义相同。本文中在本发明的说明书中所使用的术语只是为了描述具体的实施例的目的,不是旨在于限制本发明。本文所使用的术语“及/或”包括一个或多个相关的所列项目的任意的和所有的组合。Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the technical field of the invention. The terms used herein in the description of the present invention are for the purpose of describing specific embodiments only, and are not intended to limit the present invention. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.
传统的采用“3T”接线的高压电网中,110kV主设备“线路电缆化及变电GIS化”进程不断加快,110kV高压电缆和GIS设备均无裸露带电部分,且两回并列110kV出线之间未设置任何故障隔离装置,检修方式下无法灵活解列隔离工作段或故障段,检修维护极为不便;且3T接线本身的特点会导致线路停电涉及站点多,操作时间长,影响范围广,加大检修工作量。例如,1条或2条110kV线路停电,就会造成3个110kV变电站各1台或2台主变停电,存在主变“N-1”、“N-2”或10kV配网转供电能力的要求,110kV线路操作或110kV设备启动充电所涉及的变电站4至5座,所需的操作人员8至10人,需联系较多的110kV变电站(一般为3个)。因此线路故障时,大大增加了巡视范围和故障查找的时间,线路常规停电检修时,涉及的变电站多,操作时间长,检修工作量加大。且若主干线为双回或四回共塔,但线路进行杆塔改造时需要进行6次停电操作,比双回链式接线多4次,大大降低维护效率。In the traditional high-voltage power grid using "3T" wiring, the 110kV main equipment "line cable and substation GIS" process continues to accelerate, the 110kV high-voltage cable and GIS equipment have no exposed live parts, and there is no gap between the two parallel 110kV outgoing lines. If any fault isolation device is installed, it is impossible to flexibly separate and isolate the working section or the fault section in the maintenance mode, and the maintenance is extremely inconvenient; and the characteristics of the 3T wiring itself will cause the power outage of the line to involve many stations, the operation time is long, and the scope of influence is wide, which requires more maintenance. workload. For example, if one or two 110kV lines lose power, one or two main transformers in each of the three 110kV substations will lose power. Requirements, there are 4 to 5 substations involved in 110kV line operation or 110kV equipment start-up charging, 8 to 10 operators are required, and more 110kV substations (generally 3) need to be contacted. Therefore, when the line fails, the scope of inspection and the time for fault finding are greatly increased. When the line is routinely powered off for maintenance, many substations are involved, the operation time is long, and the maintenance workload is increased. And if the main line is a double-circuit or four-circuit common tower, 6 power outage operations are required when the line is transformed into a pole and tower, which is 4 times more than the double-circuit chain connection, which greatly reduces maintenance efficiency.
此外,由于两回并列的110kV出线之间未设置任何故障隔离或者测量装置,电缆T接线路一旦发生永久性故障,故障定位困难,T接头难以解开,无法快速切除故障段,修复耗时长;电缆线路故障定位存在脉冲信号混乱和故障点判断困难的现象,在故障定位方面存在困难。而存在分支接头的电缆线路,更是电缆故障测寻的难点,故障测寻时间难以保证。存在T接线路故障定位工作量大、事故抢修耗时长,且现有T接线路的故障切除依靠电源侧220kV变电站内出线断路器实现,故障切除T接线导致该T接线路中其它变电站的主变停电,存在扩大停电范围的可能性。In addition, since there is no fault isolation or measuring device between the two parallel 110kV outgoing lines, once a permanent fault occurs in the T-connection line of the cable, it is difficult to locate the fault, and it is difficult to untie the T-connector, and it is impossible to quickly remove the faulty section, which takes a long time to repair; The fault location of the cable line has the phenomena of chaotic pulse signal and difficulty in judging the fault point, which makes it difficult to locate the fault. The cable lines with branch joints are even more difficult to find cable faults, and the time to find faults is difficult to guarantee. There is a large workload for fault location of the T-connection line, and it takes a long time to repair the accident, and the fault removal of the existing T-connection line depends on the outgoing line circuit breaker in the 220kV substation on the power supply side. There is a possibility that the scope of the power outage will be extended.
传统的采用“3T”接线的高压电网中,线路一旦发生永久性故障,无法快速判定和切除故障段,全部线路均需停电,影响范围较大。另外,T接头难以开断,造成故障定位困难,尤其当三个终端均为GIS终端时,需要将GIS终端放气拆开后才能进行故障定位测试,更是花费大量的人力物力和时间;分支越多,行波法的波形变得越复杂,增加故障查找难度和时间。In the traditional high-voltage power grid using "3T" wiring, once a permanent fault occurs in the line, it is impossible to quickly determine and remove the faulty section, and all lines need to be powered off, which has a large impact range. In addition, the T connector is difficult to disconnect, which makes it difficult to locate the fault, especially when the three terminals are all GIS terminals, the GIS terminal needs to be deflated and disassembled before the fault location test can be performed, which takes a lot of manpower, material resources and time; The more, the more complex the waveform of the traveling wave method becomes, increasing the difficulty and time of fault finding.
而本申请提供的GIS电缆设备中,可通过在原有的T接筒内加装隔离装置,实现T接电缆之间的分离;通过在T接筒上加装试验窗,实现不需放气(GIS气体)即可对电缆进行试验(故障检测),进而实现发现电缆故障后,可通过隔离装置操作实现故障电缆隔离,正常电缆运行,大大减少了停电时间和范围。提高了线路检修维护的便携性,以及提高了T接线路的故障定位与隔离的效率。And in the GIS cable equipment provided by the application, the separation between the T-connection cables can be realized by adding an isolating device in the original T-connector; GIS gas) can test the cable (fault detection), and then realize that after the cable fault is found, the faulty cable can be isolated through the operation of the isolation device, and the normal cable operation can greatly reduce the power failure time and scope. The portability of line inspection and maintenance is improved, and the efficiency of fault location and isolation of T-connection lines is improved.
在一个实施例中,如图1所示,提供了一种GIS电缆设备,包括分别一一对应连接各高压出线电缆110的各T接筒120。In one embodiment, as shown in FIG. 1 , a GIS cable device is provided, including T-connectors 120 connected to high-voltage outgoing cables 110 in one-to-one correspondence.
T接筒120包括筒体122,设于筒体122内的隔离装置124,以及设于筒体122的筒壁上的试验窗126;隔离装置124的第一端连接主变压器130,第二端连接高压出线电缆110的电缆头,第三端接地;试验窗126的一端用于连接隔离装置124的第三端;试验窗126的另一端用于连接故障监测设备140。The T-connector 120 includes a cylinder body 122, an isolating device 124 disposed in the cylinder body 122, and a test window 126 disposed on the wall of the cylinder body 122; the first end of the isolating device 124 is connected to the main transformer 130, and the second end Connect the cable end of the high-voltage outlet cable 110 , and ground the third end; one end of the test window 126 is used to connect the third end of the isolation device 124 ; the other end of the test window 126 is used to connect the fault monitoring device 140 .
其中,T接筒120指的是用于T接线路的六氟化硫气体绝缘高压配电装置;T接线路指的是在高压供电中,从甲方向乙方供电的线路中间接出一条线路,向第三方丙供电。高压出线电缆110指的是用于连接变电站母线的高压出线。例如高压出线电缆110可以是110kV出线电缆。电缆头指的是高压出线电缆末端的电缆接头。筒体122可以是金属筒体,筒体122内设有气室,气室可用来设置隔离开关、接地开关母线、连接件和出线终端等;在气室内充有绝缘性能和灭弧性能优异的SF6(六氟化硫)气体作为绝缘和灭弧介质。隔离装置124可用来在线路出现故障时,对T接筒内的高压出线电缆进行断开隔离。故障监测设备140可用来监测线路故障;试验窗126指的是用于将故障监测设备连接在隔离装置接地侧的中间设备。主变压器130指的是一个单位或变电站中主要用于输变电的总降压变压器。Among them, the T-connection barrel 120 refers to the sulfur hexafluoride gas-insulated high-voltage power distribution device used for the T-connection line; the T-connection line refers to a line connected from the middle of the line supplying power from Party A to Party B in the high-voltage power supply, Supply power to third parties. The high-voltage outgoing cable 110 refers to the high-voltage outgoing line used to connect to the busbar of the substation. For example, the high voltage outgoing cable 110 may be a 110 kV outgoing cable. The cable end refers to the cable connector at the end of the high-voltage outgoing cable. The cylinder 122 can be a metal cylinder, and there is an air chamber inside the cylinder 122. The air chamber can be used to set the isolating switch, the busbar of the grounding switch, the connector and the outlet terminal, etc.; SF6 (sulfur hexafluoride) gas is used as insulation and arc extinguishing medium. The isolating device 124 can be used to disconnect and isolate the high-voltage outgoing cable in the T-connector when the line fails. Fault monitoring equipment 140 may be used to monitor line faults; test window 126 refers to an intermediate device for connecting the fault monitoring equipment on the ground side of the isolator. The main transformer 130 refers to a general step-down transformer mainly used for power transmission and transformation in a unit or a substation.
具体地,在“3T”接线的高压电网系统中(例如110kV电网系统),变电站接线形式为线路至变压器组的形式,出线为T接筒的电缆出线,即各T接筒120与各高压出线电缆110一一对应连接。通过隔离装置124的第一端连接主变压器130,隔离装置124的第二端连接高压出线电缆110的电缆头,隔离装置124的第三端接地;试验窗126的一端可用于连接隔离装置124的第三端;试验窗126的另一端可用于连接故障监测设备140。在电网系统正常运行时,隔离装置124的第一端和隔离装置124的第二端之间导通,隔离装置124的第三端断开,即高压出线电缆110导通,使得主变压器130的电力能够通过高压出线电缆110传输至母线。在电网系统运行出现故障时,隔离装置124的第一端和隔离装置124的第二端之间断开,隔离装置124的第三端导通接地;即高压出线电缆110断开,且靠近母线侧的高压出线电缆110接地,整段线路停运以及主变压器130停运,防止线路漏电等发生事故。Specifically, in a high-voltage power grid system with "3T" wiring (such as a 110kV power grid system), the wiring form of the substation is in the form of a line to a transformer group, and the outgoing line is the cable outgoing line of the T-connector, that is, each T-connector 120 and each high-voltage outgoing line The cables 110 are connected in one-to-one correspondence. Connect the main transformer 130 by the first end of the isolating device 124, the second end of the isolating device 124 connects the cable head of the high-voltage outlet cable 110, and the third end of the isolating device 124 is grounded; one end of the test window 126 can be used to connect the The third end; the other end of the test window 126 can be used to connect a fault monitoring device 140 . When the grid system is in normal operation, the first end of the isolation device 124 is connected to the second end of the isolation device 124, and the third end of the isolation device 124 is disconnected, that is, the high-voltage outgoing cable 110 is conducted, so that the main transformer 130 Electricity can be transmitted to the busbars through high voltage outgoing cables 110 . When the power grid system fails, the first end of the isolation device 124 is disconnected from the second end of the isolation device 124, and the third end of the isolation device 124 is connected to the ground; that is, the high-voltage outgoing cable 110 is disconnected and close to the bus side The high-voltage outgoing cable 110 is grounded, and the entire section of the line is out of service and the main transformer 130 is out of service to prevent accidents such as line leakage.
在电网系统运行出现故障后进入维修状态时,可开启试验窗126,进而故障监测设备140可通过试验窗126向高压出线电缆110传输试验电压信号进行试验;故障监测设备140根据试验结果,进而可实现发生故障的线路以及故障线路的相应位置,无需对整个T接筒120进行放气和充气,简化了试验工序,试验快捷方便。在对故障线路试验完成后,正常高压出线电缆上的隔离装置124的第一端和隔离装置124的第二端之间导通,隔离装置124的第三端断开,即正常线路恢复供电;出现故障的高压出线电缆上的隔离装置124的第一端和隔离装置124的第二端之间断开,隔离装置124的第三端导通接地,即故障线路保持隔离断开,主变压器130恢复供电,大大减少了停电时间和停电范围。When the power grid system fails and enters the maintenance state, the test window 126 can be opened, and then the fault monitoring device 140 can transmit a test voltage signal to the high-voltage outlet cable 110 through the test window 126 for testing; the fault monitoring device 140 can further perform tests according to the test results. Realizing the faulty line and the corresponding position of the faulty line, it is not necessary to deflate and inflate the entire T-joint 120 , which simplifies the test procedure and makes the test fast and convenient. After the fault line test is completed, conduction is conducted between the first end of the isolating device 124 on the normal high-voltage outlet cable and the second end of the isolating device 124, and the third end of the isolating device 124 is disconnected, that is, the normal line resumes power supply; The first end of the isolation device 124 on the faulty high-voltage outgoing cable is disconnected from the second end of the isolation device 124, and the third end of the isolation device 124 is connected to ground, that is, the faulty line remains isolated and disconnected, and the main transformer 130 recovers. Power supply, greatly reducing the power outage time and power outage scope.
进一步的,线路出现故障后,输电所首先要对相关线路进行绝缘检测,绝缘破损即为故障线路。对故障线路进行耐压试验,即故障测寻,找出故障点。通过开启试验窗126,进而故障监测设备140通过试验窗126对高压出线电缆110进行试验,实现无需充气和放气即可进行绝缘监测及故障测寻试验。在通过试验窗126快速查找故障点后,即可利用加装的隔离装置124断开故障线路进行维修,同时恢复T接线路中主变压器130的送电,大大减少了变电站停电时间。Furthermore, after a fault occurs on a line, the power transmission station must first conduct an insulation test on the relevant line, and if the insulation is damaged, it is the faulty line. Carry out a withstand voltage test on the faulty line, that is, fault detection to find out the fault point. By opening the test window 126, the fault monitoring device 140 can test the high-voltage outgoing cable 110 through the test window 126, so that insulation monitoring and fault finding tests can be performed without inflation and deflation. After quickly finding the fault point through the test window 126, the additional isolation device 124 can be used to disconnect the fault line for maintenance, and at the same time restore the power transmission of the main transformer 130 in the T-connection line, which greatly reduces the power outage time of the substation.
在一个示例中,故障监测设备140可向高压出线电缆输出10kV的直流脉冲电压信号进行试验监测。In an example, the fault monitoring device 140 can output a 10 kV DC pulse voltage signal to the high voltage outgoing cable for test monitoring.
需要说明的是,隔离装置124设于筒体的气室内,试验窗126设于筒体气室外,即试验窗126与T接筒120的气室隔开。It should be noted that the isolation device 124 is arranged in the air chamber of the barrel, and the test window 126 is arranged outside the air chamber of the barrel, that is, the test window 126 is separated from the air chamber of the T-joint 120 .
上述GIS电缆设备中,基于各T接筒与各高压出线电缆一一对应连接;隔离装置的第6一端连接主变压器,第二端连接高压出线电缆的电缆头,第三端接地;试验窗的一端连接隔离装置的第三端;试验窗的另一端用于连接故障监测设备。通过在原有的T接筒内加装隔离装置,实现T接电缆之间的分离;通过在T接筒上加装试验窗,实现不需放气(GIS气体)即可对电缆进行试验(故障检测),进而实现发现电缆故障后,可通过隔离装置操作实现故障电缆隔离,正常电缆运行,大大减少了停电时间和范围。提高了线路检修维护的便携性,以及提高了T接线路的故障定位与隔离的效率。In the above-mentioned GIS cable equipment, each T connector is connected to each high-voltage outgoing cable in one-to-one correspondence; the sixth end of the isolation device is connected to the main transformer, the second end is connected to the cable head of the high-voltage outgoing cable, and the third end is grounded; the test window One end is connected to the third end of the isolation device; the other end of the test window is used to connect the fault monitoring equipment. By installing an isolation device in the original T-joint barrel, the separation between the T-joint cables can be realized; by installing a test window on the T-joint barrel, the cable can be tested without degassing (GIS gas) (fault Detection), and then realize that after the cable fault is found, the faulty cable can be isolated through the operation of the isolation device, and the normal cable operation can greatly reduce the power failure time and scope. The portability of line inspection and maintenance is improved, and the efficiency of fault location and isolation of T-connection lines is improved.
在一个具体的实施例中,如图1所示,主变压器130分别连接2条高压出线电缆110。In a specific embodiment, as shown in FIG. 1 , the main transformer 130 is respectively connected to two high-voltage outgoing cables 110 .
具体地,主变压器130带两条高压出线电缆110,2条高压出线电缆110并列设置。各个高压出线电缆110通过电缆头连接母线。例如,主变压器130带两条110kV出线电缆,2条110kV出线电缆并列设置。各个110kV出线电缆通过电缆头连接110kV母线。通过在T接筒120内的高压出线电缆110上加装隔离装置124,以实现T接电缆之间的分离,进而电缆发生故障时,开启试验窗126,通过故障监测设备140进行故障监测,进而可检测出故障电缆。在通过试验窗126快速查找故障点后,即可断开故障线路进行维修,同时恢复主变压器的供电,大大减少了变电站停电时间。Specifically, the main transformer 130 has two high-voltage outgoing cables 110, and the two high-voltage outgoing cables 110 are arranged side by side. Each high-voltage outgoing cable 110 is connected to the bus bar through a cable head. For example, the main transformer 130 has two 110kV outgoing cables, and the two 110kV outgoing cables are arranged side by side. Each 110kV outgoing cable is connected to the 110kV bus through the cable head. By installing an isolating device 124 on the high-voltage outgoing cable 110 in the T-connector 120, the separation between the T-connected cables is realized, and then when the cable fails, the test window 126 is opened, and the fault monitoring device 140 is used for fault monitoring. Faulty cables can be detected. After quickly finding the fault point through the test window 126, the fault line can be disconnected for maintenance, and the power supply of the main transformer can be restored at the same time, which greatly reduces the power outage time of the substation.
进一步的,如图2所示,在3T接线线路中可包括3个主变压器130,每一台主变压器130带两回高压出线电缆110。Further, as shown in FIG. 2 , three main transformers 130 may be included in the 3T wiring line, and each main transformer 130 has two high-voltage outgoing cables 110 .
在一个实施例中,如图1所示,提供了一种GIS电缆设备,隔离装置124包括隔离开关222和快速接地开关224。隔离开关222的第一端连接主变压器130,第二端连接高压出线电缆110的电缆头;快速接地开关224的一端连接隔离开关222的第二端;快速接地开关224的另一端接地。In one embodiment, as shown in FIG. 1 , a GIS cable device is provided, and the isolation device 124 includes an isolation switch 222 and a quick grounding switch 224 . The first end of the isolating switch 222 is connected to the main transformer 130, and the second end is connected to the cable head of the high-voltage outgoing cable 110; one end of the quick earthing switch 224 is connected to the second end of the isolating switch 222; the other end of the quick earthing switch 224 is grounded.
其中,隔离开关222可用来保证高压电器及装置在检修工作时的安全,起隔离电压的作用;例如,隔离开关222可以是高压隔离开关。快速接地开关224指的是具有一定关合短路电流能力的一种特殊用途的接地开关。Wherein, the isolating switch 222 can be used to ensure the safety of the high-voltage electrical appliances and devices during maintenance work, and play the role of isolating voltage; for example, the isolating switch 222 can be a high-voltage isolating switch. The fast earthing switch 224 refers to a special-purpose earthing switch with a certain closing short-circuit current capability.
具体地,基于隔离开关222的第一端连接主变压器130,隔离开关222的第二端连接高压出线电缆110的电缆头;快速接地开关224的一端连接隔离开关222的第二端;快速接地开关224的另一端接地。在电网系统正常运行时,隔离开关222闭合,快速接地开关224断开,即高压出线电缆110导通,使得主变压器130的电力能够通过高压出线电缆110传输至母线。在电网系统运行出现故障时,隔离开关222断开,快速接地开关224闭合;即高压出线电缆110断开,整段线路停运以及主变压器130停运。在电网系统运行出现故障后进入维修状态时,可开启试验窗126,进而故障监测设备140可通过试验窗126向高压出线电缆110传输试验电压信号进行试验;故障监测设备140根据试验结果,进而可实现发生故障的线路以及故障线路的相应位置,无需对整个T接筒120进行放气和充气,简化了试验工序,试验快捷方便。在对故障线路试验完成后,正常高压出线电缆上的隔离开关222闭合,快速接地开关224断开,即正常线路恢复供电;出现故障的高压出线电缆上的隔离开关222断开,快速接地开关224闭合,即故障线路保持隔离断开,主变压器130恢复供电,大大减少了停电时间和停电范围。Specifically, based on the first end of the isolating switch 222 connected to the main transformer 130, the second end of the isolating switch 222 is connected to the cable head of the high-voltage outgoing cable 110; one end of the quick earthing switch 224 is connected to the second end of the isolating switch 222; the quick earthing switch The other end of 224 is grounded. When the grid system is running normally, the isolating switch 222 is closed and the fast earthing switch 224 is opened, that is, the high-voltage outgoing cable 110 is turned on, so that the power of the main transformer 130 can be transmitted to the bus through the high-voltage outgoing cable 110 . When the grid system fails, the isolating switch 222 is opened and the fast grounding switch 224 is closed; that is, the high-voltage outgoing cable 110 is disconnected, and the entire line and the main transformer 130 are out of service. When the power grid system fails and enters the maintenance state, the test window 126 can be opened, and then the fault monitoring device 140 can transmit a test voltage signal to the high-voltage outlet cable 110 through the test window 126 for testing; the fault monitoring device 140 can further perform tests according to the test results. Realizing the faulty line and the corresponding position of the faulty line, it is not necessary to deflate and inflate the entire T-joint 120 , which simplifies the test procedure and makes the test fast and convenient. After the faulty line test is completed, the isolating switch 222 on the normal high-voltage outgoing cable is closed, and the fast grounding switch 224 is disconnected, that is, the normal line resumes power supply; Closed, that is, the fault line remains isolated and disconnected, and the main transformer 130 restores power supply, which greatly reduces the power outage time and power outage range.
上述GIS电缆设备中,通过在原有的T接筒内加装隔离开关和快速接地开关,实现T接电缆之间的分离;通过在T接筒上加装试验窗,实现不需放气(GIS气体)即可对电缆进行试验(故障检测),进而实现发现电缆故障后,可通过隔离装置操作实现故障电缆隔离,正常电缆运行,大大减少了停电时间和范围。提高了线路检修维护的便携性,以及提高了T接线路的故障定位与隔离的效率。In the above-mentioned GIS cable equipment, the separation between the T-connection cables is realized by installing an isolation switch and a quick grounding switch in the original T-connector; Gas) can test the cable (fault detection), and then realize that after the cable fault is found, the faulty cable can be isolated through the operation of the isolation device, and the normal cable operation can greatly reduce the power failure time and scope. The portability of line inspection and maintenance is improved, and the efficiency of fault location and isolation of T-connection lines is improved.
在一个具体的实施例中,故障监测设备为绝缘监测设备或故障测距设备。In a specific embodiment, the fault monitoring device is an insulation monitoring device or a fault distance measuring device.
其中,绝缘监测设备指的是用于检测电力电缆的绝缘状态的设备。故障测距设备指的是用于对电力电缆故障测距的设备。绝缘监测设备通过试验窗连接隔离装置的接地侧,进而绝缘监测设备可对相应的高压出线电缆进行绝缘检测,若检测到该高压出线电缆出现绝缘破损,则判断该高压出线电缆为故障线路。故障测距设备通过试验窗连接隔离装置的接地侧,进而故障测距设备可对故障线路进行耐压试验,通过故障测寻,找出故障点。进而实现无需充气及放气即可进行线路绝缘监测及故障测寻试验,提高了T接线路的故障定位与隔离的效率。Wherein, the insulation monitoring device refers to a device for detecting the insulation state of the power cable. Fault location equipment refers to the equipment used for fault location of power cables. The insulation monitoring equipment is connected to the grounding side of the isolation device through the test window, and then the insulation monitoring equipment can perform insulation detection on the corresponding high-voltage outgoing cable. If the insulation damage of the high-voltage outgoing cable is detected, it is judged that the high-voltage outgoing cable is a faulty line. The fault location equipment is connected to the ground side of the isolation device through the test window, and then the fault location equipment can perform withstand voltage tests on the fault line, and find out the fault point through fault detection. Further, the line insulation monitoring and fault detection test can be carried out without inflation and deflation, and the efficiency of fault location and isolation of the T-connection line is improved.
在一个实施例中,如图3所示,试验窗126包括导体接线板232;导体接线板232的第一端连接快速接地开关224的一端;导体接线板232的第二端连接故障监测设备140。In one embodiment, as shown in FIG. 3 , the test window 126 includes a conductor wiring board 232; a first end of the conductor wiring board 232 is connected to one end of the quick earthing switch 224; a second end of the conductor wiring board 232 is connected to the fault monitoring device 140 .
其中,导体接线板140可用来将故障监测设备140与快速接地开关224实现连接;导体接线板140可以是三相导体接线板。Wherein, the conductor wiring board 140 can be used to connect the fault monitoring equipment 140 and the fast grounding switch 224; the conductor wiring board 140 can be a three-phase conductor wiring board.
具体地,导体接线板140的第一端可固定连接快速接地开关的一端;导体接线板232的第二端可插接故障监测设备140。在电网系统运行出现故障后进入维修状态时,可开启试验窗126,将故障监测设备140插接在导体接线板232上,进而故障监测设备140可通过导体接线板232向高压出线电缆110传输试验电压信号进行试验;故障监测设备140根据试验结果,进而可实现发生故障的线路以及故障线路的相应位置,无需对整个T接筒进行放气和充气,简化了试验工序,试验快捷方便。Specifically, the first end of the conductor wiring board 140 can be fixedly connected to one end of the quick grounding switch; the second end of the conductor wiring board 232 can be plugged into the fault monitoring device 140 . When the power grid system enters the maintenance state after a fault occurs, the test window 126 can be opened, and the fault monitoring device 140 can be plugged into the conductor terminal board 232, and then the fault monitoring device 140 can transmit the test to the high-voltage outgoing cable 110 through the conductor terminal board 232. The voltage signal is tested; the fault monitoring equipment 140 can realize the faulty line and the corresponding position of the faulty line according to the test results, without deflation and inflation of the entire T-connector, which simplifies the test process and makes the test fast and convenient.
在一个具体的实施例中,试验窗还包括设于筒体的筒壁上的试验窗盖;试验窗盖内设有试验腔体;导体接线板设于试验腔体内。In a specific embodiment, the test window further includes a test window cover arranged on the cylinder wall of the cylinder body; a test cavity is arranged in the test window cover; and a conductor wiring board is arranged in the test cavity.
具体地,试验腔体可设于筒体内,试验腔体与筒体内的气室相互封闭隔离,进而对线路进行试验时,无需对T接筒放气,试验快捷方便。试验窗盖与筒体的筒壁活动连接,在电网系统运行出现故障后进入维修状态时,可打开试验窗盖,进而可将故障监测设备插接在导体接线板上进行试验监测。Specifically, the test cavity can be arranged in the barrel, and the test cavity and the air chamber in the barrel are sealed and isolated from each other, so that when the circuit is tested, there is no need to deflate the T-connector, and the test is quick and convenient. The test window cover is movably connected with the cylinder wall of the cylinder body. When the power grid system fails and enters the maintenance state, the test window cover can be opened, and then the fault monitoring equipment can be plugged into the conductor terminal board for test monitoring.
在一个具体的实施例中,如图3所示,试验窗126还包括用于隔离T接筒的气室的盆式绝缘子234;盆式绝缘子234设于试验腔体内。In a specific embodiment, as shown in FIG. 3 , the test window 126 further includes a pot insulator 234 for isolating the air chamber of the T-joint; the pot insulator 234 is arranged in the test cavity.
具体地,可将盆式绝缘子234设于试验腔体内,用于隔离T接筒的气室,起到密封作用。Specifically, the basin-type insulator 234 can be arranged in the test cavity to isolate the air chamber of the T-joint and play a sealing role.
进一步的,如图3所示,试验窗126还包括支柱绝缘子236;支柱绝缘子236连接导体接线板232。具体地,支柱绝缘子236指的是一种绝缘控件。基于支柱绝缘子236连接在导体接线板232上,进而可增加爬电距离,提高试验窗的安全性能。Further, as shown in FIG. 3 , the test window 126 further includes a post insulator 236 ; the post insulator 236 is connected to the conductor wiring board 232 . Specifically, post insulator 236 refers to an insulating control. Based on the fact that the post insulator 236 is connected to the conductor wiring board 232, the creepage distance can be increased and the safety performance of the test window can be improved.
在一个实施例中,还包括用于对主变压器的断路器与隔离装置之间联锁的电气闭锁装置。In one embodiment, an electrical blocking device for interlocking between the circuit breaker of the main transformer and the isolating device is also included.
其中,电气闭锁装置可用于将断路器和隔离装置(隔离开关和快速接地开关)等设备的辅助接点接入相关电气设备的操作电源回路构成闭锁。电气闭锁装置可用来只能防止断路器和隔离装置(隔离开关和快速接地开关)的误操作。Among them, the electrical locking device can be used to connect the auxiliary contacts of equipment such as circuit breakers and isolating devices (isolating switches and quick earthing switches) to the operating power circuits of related electrical equipment to form a locking. Electrical interlocking devices can be used only to prevent misoperation of circuit breakers and isolating devices (disconnectors and quick earthing switches).
具体地,断路器连接在主变压器的输出端和高压出线电缆之间,通过加装电气闭锁装置,可实现断路器与隔离装置之间的联锁,防止隔离开关和快速接地开关的误操作,进而提高了T接筒的安全性能。Specifically, the circuit breaker is connected between the output terminal of the main transformer and the high-voltage outgoing cable. By installing an electrical locking device, the interlock between the circuit breaker and the isolating device can be realized to prevent misoperation of the isolating switch and the fast earthing switch. Then the safety performance of the T-joint is improved.
以上所述实施例的各技术特征可以进行任意的组合,为使描述简洁,未对上述实施例中的各个技术特征所有可能的组合都进行描述,然而,只要这些技术特征的组合不存在矛盾,都应当认为是本说明书记载的范围。The various technical features of the above-mentioned embodiments can be combined arbitrarily. To make the description concise, all possible combinations of the various technical features in the above-mentioned embodiments are not described. However, as long as there is no contradiction in the combination of these technical features, should be considered as within the scope of this specification.
以上所述实施例仅表达了本申请的几种实施方式,其描述较为具体和详细,但并不能因此而理解为对发明专利范围的限制。应当指出的是,对于本领域的普通技术人员来说,在不脱离本申请构思的前提下,还可以做出若干变形和改进,这些都属于本申请的保护范围。因此,本申请专利的保护范围应以所附权利要求为准。The above-mentioned embodiments only represent several implementation modes of the present application, and the description thereof is relatively specific and detailed, but it should not be construed as limiting the scope of the patent for the invention. It should be noted that those skilled in the art can make several modifications and improvements without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the scope of protection of the patent application should be based on the appended claims.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910407412.XA CN110208644A (en) | 2019-05-15 | 2019-05-15 | GIS cable machinery |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910407412.XA CN110208644A (en) | 2019-05-15 | 2019-05-15 | GIS cable machinery |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN110208644A true CN110208644A (en) | 2019-09-06 |
Family
ID=67787449
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910407412.XA Pending CN110208644A (en) | 2019-05-15 | 2019-05-15 | GIS cable machinery |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110208644A (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110672886A (en) * | 2019-10-15 | 2020-01-10 | 国网天津市电力公司 | Adapter for GIS cable termination testing |
| CN112054382A (en) * | 2020-09-07 | 2020-12-08 | 广东电网有限责任公司广州供电局 | GIS cable T connects a section of thick bamboo circuit |
| CN114217181A (en) * | 2021-11-25 | 2022-03-22 | 广东电网有限责任公司广州供电局 | GIS cable sleeve test window |
| CN114217183A (en) * | 2021-11-25 | 2022-03-22 | 广东电网有限责任公司广州供电局 | A GIS cable device |
Citations (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1055066A (en) * | 1990-03-09 | 1991-10-02 | 株式会社日立制作所 | Electrical device and method for detecting faults in electrical equipment |
| JPH0898350A (en) * | 1994-09-26 | 1996-04-12 | Nissin Electric Co Ltd | Faulty point orientating equipment of gas insulating switchgear |
| KR101231766B1 (en) * | 2011-08-11 | 2013-02-08 | 현대중공업 주식회사 | Gas insulated switch-gear |
| CN103091609A (en) * | 2013-01-09 | 2013-05-08 | 中国电力科学研究院 | Performance detecting system and method thereof of gas insulated substation (GIS) partial discharge on-line monitoring device |
| CN203850641U (en) * | 2014-04-30 | 2014-09-24 | 广州汇隽电力工程设计有限公司 | Optimized 110kV cable wiring structure capable of realizing fault fast isolation |
| CN104218457A (en) * | 2014-09-28 | 2014-12-17 | 国家电网公司 | Power distribution device and electric master system thereof |
| CN104638618A (en) * | 2015-02-11 | 2015-05-20 | 国网山东省电力公司潍坊供电公司 | Method for quickly recovering power supply of GIS bus device after tripping |
| CN105572545A (en) * | 2014-10-29 | 2016-05-11 | 中国石油化工股份有限公司 | Power line fault location device and method |
| CN107436417A (en) * | 2017-06-05 | 2017-12-05 | 国网重庆市电力公司电力科学研究院 | The calibration method of ultrahigh frequency partial discharge on-Line Monitor Device under a kind of site environment |
| CN107727989A (en) * | 2017-10-10 | 2018-02-23 | 大唐国际发电股份有限公司北京高井热电厂 | The test method of oil-gas casing structure transformer |
| CN210514508U (en) * | 2019-05-15 | 2020-05-12 | 广州供电局有限公司 | GIS cable equipment |
| CN112054382A (en) * | 2020-09-07 | 2020-12-08 | 广东电网有限责任公司广州供电局 | GIS cable T connects a section of thick bamboo circuit |
| CN114217183A (en) * | 2021-11-25 | 2022-03-22 | 广东电网有限责任公司广州供电局 | A GIS cable device |
| CN114217181A (en) * | 2021-11-25 | 2022-03-22 | 广东电网有限责任公司广州供电局 | GIS cable sleeve test window |
-
2019
- 2019-05-15 CN CN201910407412.XA patent/CN110208644A/en active Pending
Patent Citations (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1055066A (en) * | 1990-03-09 | 1991-10-02 | 株式会社日立制作所 | Electrical device and method for detecting faults in electrical equipment |
| JPH0898350A (en) * | 1994-09-26 | 1996-04-12 | Nissin Electric Co Ltd | Faulty point orientating equipment of gas insulating switchgear |
| KR101231766B1 (en) * | 2011-08-11 | 2013-02-08 | 현대중공업 주식회사 | Gas insulated switch-gear |
| CN103091609A (en) * | 2013-01-09 | 2013-05-08 | 中国电力科学研究院 | Performance detecting system and method thereof of gas insulated substation (GIS) partial discharge on-line monitoring device |
| CN203850641U (en) * | 2014-04-30 | 2014-09-24 | 广州汇隽电力工程设计有限公司 | Optimized 110kV cable wiring structure capable of realizing fault fast isolation |
| CN104218457A (en) * | 2014-09-28 | 2014-12-17 | 国家电网公司 | Power distribution device and electric master system thereof |
| CN105572545A (en) * | 2014-10-29 | 2016-05-11 | 中国石油化工股份有限公司 | Power line fault location device and method |
| CN104638618A (en) * | 2015-02-11 | 2015-05-20 | 国网山东省电力公司潍坊供电公司 | Method for quickly recovering power supply of GIS bus device after tripping |
| CN107436417A (en) * | 2017-06-05 | 2017-12-05 | 国网重庆市电力公司电力科学研究院 | The calibration method of ultrahigh frequency partial discharge on-Line Monitor Device under a kind of site environment |
| CN107727989A (en) * | 2017-10-10 | 2018-02-23 | 大唐国际发电股份有限公司北京高井热电厂 | The test method of oil-gas casing structure transformer |
| CN210514508U (en) * | 2019-05-15 | 2020-05-12 | 广州供电局有限公司 | GIS cable equipment |
| CN112054382A (en) * | 2020-09-07 | 2020-12-08 | 广东电网有限责任公司广州供电局 | GIS cable T connects a section of thick bamboo circuit |
| CN114217183A (en) * | 2021-11-25 | 2022-03-22 | 广东电网有限责任公司广州供电局 | A GIS cable device |
| CN114217181A (en) * | 2021-11-25 | 2022-03-22 | 广东电网有限责任公司广州供电局 | GIS cable sleeve test window |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110672886A (en) * | 2019-10-15 | 2020-01-10 | 国网天津市电力公司 | Adapter for GIS cable termination testing |
| CN112054382A (en) * | 2020-09-07 | 2020-12-08 | 广东电网有限责任公司广州供电局 | GIS cable T connects a section of thick bamboo circuit |
| CN114217181A (en) * | 2021-11-25 | 2022-03-22 | 广东电网有限责任公司广州供电局 | GIS cable sleeve test window |
| CN114217183A (en) * | 2021-11-25 | 2022-03-22 | 广东电网有限责任公司广州供电局 | A GIS cable device |
| CN114217181B (en) * | 2021-11-25 | 2024-04-12 | 广东电网有限责任公司广州供电局 | GIS cable sleeve test window |
| CN114217183B (en) * | 2021-11-25 | 2024-05-28 | 广东电网有限责任公司广州供电局 | A GIS cable device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP5615839B2 (en) | Medium voltage distribution cubicle | |
| CN102916362B (en) | A kind of Intelligent inflatable high-voltage vacuum switch cabinet for metros | |
| CN110208644A (en) | GIS cable machinery | |
| CN201490613U (en) | Two-phase railway switchgear | |
| CN112736789A (en) | Bypass drainage device for low-voltage line of distribution network | |
| CN106129887B (en) | GIS prepared separations, outside line enlargement method and GIS device | |
| CN106885959B (en) | Test method for replacing short-circuit copper bar by grounding knife switch in power plant electric main start test | |
| CN117833090A (en) | A gas tank structure for aerifing cabinet | |
| CN106058709B (en) | A kind of GIS prepared separations and a kind of GIS device | |
| CN101582568A (en) | Butting unit for GIS equipment and method thereof | |
| CN210514508U (en) | GIS cable equipment | |
| JP2013029479A (en) | Insulation resistance measurement device and insulation resistance measurement system | |
| CN111239601B (en) | Method for detecting double-break bus isolating switch in 220 KV power transformation combined electrical equipment | |
| CN219643432U (en) | Uninterrupted power supply is expanded with two bus connection devices of high voltage GIS and transformer substation | |
| CN205657374U (en) | Solid insulation boundary switch cabinet | |
| JPH02210389A (en) | Cell for medium or high pressure metal clad station and station built with cell of this type | |
| KR101097616B1 (en) | Multipurpose case module of gas insulated switchgear | |
| CN116260066B (en) | A high-voltage GIS double busbar connection device and substation for uninterrupted power supply expansion | |
| CN218996645U (en) | Quick docking device for vertical circuit breaker and isolating switch | |
| CN222381181U (en) | Environment-friendly gas-insulated ring main unit with cable testing function | |
| CN218240320U (en) | Calibration device and high-temperature reactor switching station with same | |
| CN221651981U (en) | Expansion device and double busbar gas-insulated metal-enclosed switchgear | |
| CN222563371U (en) | Gas-insulated switchgear with parallel bus system | |
| CN110854685B (en) | Automatic switching device and system for looped network inflation unit insulation test | |
| CN110346710B (en) | Ring main unit outgoing line starting method for avoiding customer power failure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| TA01 | Transfer of patent application right | ||
| TA01 | Transfer of patent application right |
Effective date of registration: 20200925 Address after: 510620 Tianhe District, Guangzhou, Tianhe South Road, No. two, No. 2, No. Applicant after: Guangzhou Power Supply Bureau of Guangdong Power Grid Co.,Ltd. Address before: 510620 Tianhe District, Guangzhou, Tianhe South Road, No. two, No. 2, No. Applicant before: GUANGZHOU POWER SUPPLY Co.,Ltd. |
|
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190906 |