CN203835403U - Clearance strengthening system for serious cracking of existing tunnel lining arch - Google Patents

Clearance strengthening system for serious cracking of existing tunnel lining arch Download PDF

Info

Publication number
CN203835403U
CN203835403U CN201420255811.1U CN201420255811U CN203835403U CN 203835403 U CN203835403 U CN 203835403U CN 201420255811 U CN201420255811 U CN 201420255811U CN 203835403 U CN203835403 U CN 203835403U
Authority
CN
China
Prior art keywords
arch
steel frame
shaped steel
lining
existing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420255811.1U
Other languages
Chinese (zh)
Inventor
张剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN201420255811.1U priority Critical patent/CN203835403U/en
Application granted granted Critical
Publication of CN203835403U publication Critical patent/CN203835403U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model relates to a clearance strengthening system for serious cracking of an existing tunnel lining arch. The existing tunnel lining arch is prone to being damaged by defects, and only proper strengthening processing can be carried out on the condition of not removing or rebuilding the existing tunnel lining arch. According to the clearance strengthening system, a reinforcing mesh is laid on the arch of an existing concrete lining, multiple H-type steel frames are arranged in the reinforcing mesh in the longitudinal direction of a tunnel, anchor rods are arranged in a hit mode, and the end of each anchor rod is fixed to the corresponding H-type steel frame through an anchor rod cushion board and a connecting bolt; holes are punched between the anchor rods at the H-type steel frames at intervals, and arch grouting pipes for carrying out pouring on the back of the lining to tamp cavities are embedded in the holes; concrete is sprayed in the existing concrete lining to cover the H-type steel frames. By means of the clearance strengthening system, grouting is carried out on the back of the serious cracking portion of the existing tunnel lining arch, the cavities are tamped, the H-type steel frames are selected and used in cooperation with the reinforcing mesh, the anchor rods and pneumatically placed concrete to form the combined strengthening system, the serious cracking of the arch is strengthened, construction is easy, and investment is reduced.

Description

The serious cracking of a kind of existing tunnel Arch lining has headroom reinforcement system
Technical field
the utility model belongs to tunnel traffic field of engineering technology, and being specifically related to the serious cracking of a kind of existing tunnel Arch lining has headroom reinforcement system.
Background technology
China railways, the traffic engineering such as highway are larger in the tunnel quantity of building, early stage a large amount of tunnels of building in mountain area are also still using, what have reaches projected life at that time, due to construction quality, corrosive environment, concrete durability, the impact of the factors such as strata pressure, much still produce lining cutting cracking in the tunnel using, the diseases such as flake-off piece, especially lining cutting arch more easily occurs, as develop as one pleases, can minor illness form great trouble, traffic safety is caused to significant damage, and tunnel do not dismantle rebuild condition, therefore can only carry out suitable consolidation process according to the disease order of severity, select economical rationality, easy construction, treatment measures are very crucial safely and reliably.
Summary of the invention
The purpose of this utility model is to provide the serious cracking of a kind of existing tunnel Arch lining headroom reinforcement system, can effectively process concrete cracking disease, is applicable to the operating mode that existing tunnel Arch lining seriously ftractures and has headroom.
The technical scheme that the utility model adopts is:
The serious cracking of a kind of existing tunnel Arch lining has headroom reinforcement system, it is characterized in that:
Lay steel mesh reinforcement in existing concrete-lined arch, in steel mesh reinforcement, multiple tracks H shaped steel frame is longitudinally set along tunnel, some anchor poles radially, that squeeze into country rock are set at H shaped steel frame place, anchor pole end is fixed on H shaped steel frame by roof bolt plate and connecting bolt;
Between the anchor pole at per pass H shaped steel frame place, interval punching is embedded with for tamp empty arch Grouting Pipe at lining cutting back-grouting;
In existing concrete lining, sprayed mortar covers H shaped steel frame.
Between H shaped steel frame, be welded with longitudinal connecting reinforcement.
Described existing concrete-lined arch springing place and the end of H shaped steel frame are provided with the steelframe lock pin anchor tube of squeezing into country rock.
The anchor pole at per pass H shaped steel frame place is laterally broken line and distributes, and end is staggered front to back and is fixed on H shaped steel frame edge.
The utlity model has following advantage:
The utility model is to the existing tunnel Arch lining part back-grouting that seriously ftractures, tamp cavity, select the H profile steel frame highly little, rigidity is large to coordinate steel mesh reinforcement, anchor pole to form integrative consolidation system, can carry out the radical cure of putting things right once and for all to the arch disease that seriously ftractures, have construction simple, save investment, the advantage such as safe and reliable.
Brief description of the drawings
Fig. 1 is the utility model cross-sectional drawing.
Fig. 2 is the utility model layout plan.
Fig. 3 is the utility model fragmentary detail view.
In figure, the existing concrete lining of 1-, 2-anchor pole, 3-steel mesh reinforcement, 4-arch Grouting Pipe, 5-H shaped steel frame, the longitudinal connecting reinforcement of 6-, 7-steelframe lock pin anchor tube, 8-roof bolt plate, 9-connecting bolt, 10-sprayed mortar.
Detailed description of the invention
Below in conjunction with detailed description of the invention, the utility model is described in detail.
The serious cracking of a kind of existing tunnel Arch lining that the utility model relates to has headroom reinforcement system, be applicable to the operating mode that tunnel Arch lining seriously ftractureed, had headroom, must process, the compages such as anchor, net, band, slip casting are adopted, or local arrange continuously longitudinal in tunnel as required, little, easy construction takes up room.Concrete structure is: steel mesh reinforcement 3 is laid in the arch in existing concrete lining 1, and the interior multiple tracks H shaped steel frame 5 that longitudinally arranges along tunnel of steel mesh reinforcement 3, is welded with longitudinal connecting reinforcement 6 between H shaped steel frame 5.Some anchor poles 2 radially, that squeeze into country rock are set at H shaped steel frame 5 places, and anchor pole 2 ends are fixed on H shaped steel frame 5 by roof bolt plate 8 and connecting bolt 9.The anchor pole 2 at per pass H shaped steel frame 5 places is laterally broken line and distributes, and end is staggered front to back and is fixed on H shaped steel frame 5 edges.Between the anchor pole 2 at per pass H shaped steel frame 5 places, interval punching is embedded with for tamp empty arch Grouting Pipe 4 at lining cutting back-grouting.Cover H shaped steel frame 5 in the interior sprayed mortar of existing concrete lining 1.The arch springing place of existing concrete lining 1 and the end of H shaped steel frame 5 are provided with the steelframe lock pin anchor tube 7 of squeezing into country rock.
It is cited that content of the present utility model is not limited to embodiment, and the conversion of any equivalence that those of ordinary skill in the art take technical solutions of the utility model by reading the utility model manual, is claim of the present utility model and contains.

Claims (4)

1. the serious cracking of existing tunnel Arch lining has a headroom reinforcement system, it is characterized in that:
Steel mesh reinforcement (3) is laid in arch in existing concrete lining (1), multiple tracks H shaped steel frame (5) is longitudinally set along tunnel in steel mesh reinforcement (3), locate to arrange some anchor poles radially, that squeeze into country rock (2) at H shaped steel frame (5), anchor pole (2) end is fixed on H shaped steel frame (5) by roof bolt plate (8) and connecting bolt (9);
Between the anchor pole (2) that per pass H shaped steel frame (5) is located, interval punching is embedded with for tamp empty arch Grouting Pipe (4) at lining cutting back-grouting;
In existing concrete lining (1), sprayed mortar covers H shaped steel frame (5).
2. the serious cracking of a kind of existing tunnel Arch lining according to claim 1 has headroom reinforcement system, it is characterized in that:
Between H shaped steel frame (5), be welded with longitudinal connecting reinforcement (6).
3. the serious cracking of a kind of existing tunnel Arch lining according to claim 2 has headroom reinforcement system, it is characterized in that:
The arch springing place of described existing concrete lining (1) and the end of H shaped steel frame (5) are provided with the steelframe lock pin anchor tube (7) of squeezing into country rock.
4. the serious cracking of a kind of existing tunnel Arch lining according to claim 3 has headroom reinforcement system, it is characterized in that:
The anchor pole (2) that per pass H shaped steel frame (5) is located is laterally broken line and distributes, and end is staggered front to back and is fixed on H shaped steel frame (5) edge.
CN201420255811.1U 2014-05-20 2014-05-20 Clearance strengthening system for serious cracking of existing tunnel lining arch Expired - Lifetime CN203835403U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420255811.1U CN203835403U (en) 2014-05-20 2014-05-20 Clearance strengthening system for serious cracking of existing tunnel lining arch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420255811.1U CN203835403U (en) 2014-05-20 2014-05-20 Clearance strengthening system for serious cracking of existing tunnel lining arch

Publications (1)

Publication Number Publication Date
CN203835403U true CN203835403U (en) 2014-09-17

Family

ID=51513259

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420255811.1U Expired - Lifetime CN203835403U (en) 2014-05-20 2014-05-20 Clearance strengthening system for serious cracking of existing tunnel lining arch

Country Status (1)

Country Link
CN (1) CN203835403U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103953361A (en) * 2014-05-20 2014-07-30 中铁第一勘察设计院集团有限公司 Clearance strengthening system for serious cracks of existing tunnel arch lining
CN104389321A (en) * 2014-10-31 2015-03-04 中国电建集团成都勘测设计研究院有限公司 Safety structure of underground building
CN104790970A (en) * 2015-03-31 2015-07-22 同济大学 Method for utilizing combined structure to conduct shield tunnel strengthening
CN107420121A (en) * 2017-09-20 2017-12-01 中铁十四局集团有限公司 A kind of interim steelframe locks pin construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103953361A (en) * 2014-05-20 2014-07-30 中铁第一勘察设计院集团有限公司 Clearance strengthening system for serious cracks of existing tunnel arch lining
CN104389321A (en) * 2014-10-31 2015-03-04 中国电建集团成都勘测设计研究院有限公司 Safety structure of underground building
CN104790970A (en) * 2015-03-31 2015-07-22 同济大学 Method for utilizing combined structure to conduct shield tunnel strengthening
CN107420121A (en) * 2017-09-20 2017-12-01 中铁十四局集团有限公司 A kind of interim steelframe locks pin construction method

Similar Documents

Publication Publication Date Title
CN103953361A (en) Clearance strengthening system for serious cracks of existing tunnel arch lining
CN103437791B (en) The mounting method of buried water stop in a kind of tunnel lining trolley termination
CN203835404U (en) Non-clearance strengthening system for serious cracking of existing tunnel lining arch
CN103953362A (en) Clearance-free strengthening system for serious cracks of existing tunnel arch lining
CN103939110A (en) Strengthening system for slight cracking of existing tunnel arch portion lining
CN203835403U (en) Clearance strengthening system for serious cracking of existing tunnel lining arch
CN103953366B (en) Mid-board top former lining cutting cavity backfill construction method when single hole tunnel changes arcading into
CN204877493U (en) Soft rock tunnel supporting construction
CN208280965U (en) Coal mine deep well tunnel smooth surface concrete spraying support structure
CN104405411A (en) Oversized variable cross section tunnel supporting structure
CN204783046U (en) Tunnel lining restores structure fast based on carbon fiber mesh grid
CN109372543A (en) Mangnolia officinalis competent structure and construction method are owed in a kind of tunnel-liner
CN104533450A (en) One-time-concreting construction method of inverted arch low wall of single-track tunnel
CN203835407U (en) Arch lining slight-cracking reinforcing system for existing tunnel
CN204851287U (en) Big section moving as a whole formula formwork support
CN105041339A (en) Clutch type formwork trolley, trolley assembly and underground passage concrete construction method
CN110107319A (en) A method of utilizing embedding arch shotcrete composite structure Strengthening Tunnel lining cutting
CN204457800U (en) Large Cross-section Tunnel in Subway Engineering two serves as a contrast the simple and easy chassis mould of arch wall separate type and builds construction equipment
CN204782044U (en) Reinforced structure of existing structure roof beam
CN104632228A (en) Main track entering construction method for cross aisle and cross aisle
CN209443765U (en) A kind of steel form of the pouring after settlement shear wall for banketing in advance
CN201400959Y (en) Silo concrete protecting layer locating piece in slipform construction
CN209195426U (en) A kind of deficient Mangnolia officinalis competent structure of tunnel-liner
CN209556422U (en) The ruggedized construction of radiation shield concrete floor construction construction joint
CN204551172U (en) A kind of prefabricated road surface of assembled steel reinforced concrete hollow

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20140917