CN203826847U - A steel tube tower unkeep working platform - Google Patents

A steel tube tower unkeep working platform Download PDF

Info

Publication number
CN203826847U
CN203826847U CN201420220254.XU CN201420220254U CN203826847U CN 203826847 U CN203826847 U CN 203826847U CN 201420220254 U CN201420220254 U CN 201420220254U CN 203826847 U CN203826847 U CN 203826847U
Authority
CN
China
Prior art keywords
hanging
rope
quadra
steel tube
tube tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420220254.XU
Other languages
Chinese (zh)
Inventor
林世忠
操松元
聂立新
吴维国
苏灿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Anhui Power Transmission and Transformation Engineering Co Ltd
Original Assignee
State Grid Corp of China SGCC
Anhui Power Transmission and Transformation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Anhui Power Transmission and Transformation Engineering Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201420220254.XU priority Critical patent/CN203826847U/en
Application granted granted Critical
Publication of CN203826847U publication Critical patent/CN203826847U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a steel tube tower unkeep working platform composed of a square framework, a hanging rope, a hanging point hanging board which are assembled. The square framework is made of aluminium alloy section bars. The bottom surface of the square framework is provided with a polyamide rope net. The rear surface of the square framework is provided with the polyamide rope net as a support net. The front surface of the square framework is provide with a transverse soft intercepting rope. The two sides of the square framework are provided with tool bags made of canvas. The top end of the square framework is provided with hanging rings used for connecting the hanging rope. The hanging rope is a sectionalized polyamide rope. The sectionalized polyamide rope is connected into the integral hanging rope through loop buckles. The loop buckles can be used as hanging buckling points adjusting the length of the polyamide rope. The ends of the hanging ropes are provided with opening-and-closing type clamping rings. The upper end of the hanging point hanging board is provided with a U-Shaped ring. The hanging point hanging board is provided with two hanging holes used for connecting to the hanging rope. The steel tube tower unkeep working platform of the utility model is simple in structure, and is convenient in usage and fast in loading and unloading. In addition, the steel tube tower unkeep working platform is portable and firm.

Description

A kind of steel tube tower upkeep operation platform
Technical field
The utility model relates to a kind of upkeep operation platform of steel tube tower in electric transmission line.
Background technology
Along with UHV transmission networking constantly advances, common-tower double-return or many back transmission lines constantly build up and put into operation.Because circuit returns, number is many, wire division quantity is many, and tower load is required to improve constantly, and tower structure intensity is had higher requirement, and conventional angular head tower can not meet the demands.Therefore, 1000kV extra-high voltage same tower double circuit line has generally adopted steel tube tower structure.
After circuit puts into operation, because of needs of work such as circuit mounting rod number plate, phase place board, warning alarm plate, on-Line Monitor Device and line maintenances, maintainer often need to carry out corresponding operation on shaft tower.On conventional angle steel tower, operating personnel climbs to job position by angle iron component conventionally, stands or rides on angle iron component, can, by holding up, keeping homeostasis by angle iron component, carry out events in operation.Because steel tube tower main body is round steel pipe, diameter is many more than 180mm, and the distance between structural member is larger, cannot sit or hold up, leans on steel tube component to keep homeostasis by riding, and therefore cannot carry out operation.
In order to meet extra-high voltage steel tube tower service work needs, need a kind of steel tube tower job platform of development, job platform is suspended near setting on steel pipe, operating personnel be take job platform as foothold, carries out upkeep operation.Meanwhile, because line maintenance mostly is single-point operation, personnel amount is few, Work tool is simple, and needs continuous special show, therefore require job platform have simple in structure, volume is little, the feature such as lightweight, easy and simple to handle.
Summary of the invention
The technical problems to be solved in the utility model is to provide a kind of upkeep operation platform of the 1000kV of being suitable for extra-high voltage steel tube tower, and require that platform structure is simple, volume is little, lightweight, easy and simple to handle.
In order to solve the problems of the technologies described above, the technical solution adopted in the utility model is: a kind of steel tube tower upkeep operation platform, by quadra, suspension cord, the assembling of hanging point link plate, formed, quadra adopts aluminium alloy extrusions to make, the bottom surface of quadra is provided with polyamide fibre netting, quadra to be below provided with polyamide fibre netting be support net; Horizontal soft rope is by the waist set before quadra; The both sides of quadra are provided with the kit bag that canvas is made; The top of quadra is provided for connecting the link of suspension cord;
Suspension cord is the polyamide fibre cable of segmentation, and the polyamide fibre cable of segmentation connects by latch closure, and latch closure can be used as and regulates buckling a little of polyamide fibre cable length; The end of suspension cord is provided with opening and closing type clasp;
U-shaped ring is equipped with in hanging point link plate upper end, and two hanging holes for being connected with suspension cord are set on hanging point link plate.
As preferably, the frame of quadra is provided with connecting hole, and connecting hole is lined with abrasionproof packing ring; Polyamide fibre netting is connected with the frame of quadra through abrasionproof packing ring.
As preferably, the length of suspension cord regulates according to the position of setting and distance and operating personnel's height.
The beneficial effects of the utility model are:
The steel tube tower job platform that the utility model provides is for 1000kV extra-high voltage steel tube tower upkeep operation, during operation, job platform is hung near setting by suspension cord or hanging point link plate, latch closure, open-close type clasp adjusting suspension cord length be can pass through, different work distance, different height operating personnel's operation needs met.During operation, personnel can be seated on platform, by rope by the waist, ensure operating personnel's safety, meet operation needs.
Job platform adopts aluminum alloy frame, and bottom surface adopts caprone cable web frame, and this structure makes platform and integrally weight lighter; Bottom surface is soft netting support personnel operation comfortableness, has increased bottom surface coefficient of friction simultaneously, ensures that operating personnel can arbitrarily not slide.On frame, connecting hole is connected with bottom surface polyamide fibre netting by abrasionproof packing ring, ensures that netting is not easy to wear, guarantees safety.Framework both sides are provided with canvas bag, can storing name utensil and repair materials.Suspension cord adopts sectionally assembled caprone cable, adopts latch closure, open-close type clasp to connect, and is beneficial to and regulates platform suspension height, is convenient to the convenience of installing, removing.
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
Fig. 1 is the front view of the utility model steel tube tower upkeep operation platform embodiment.
Fig. 2 is the vertical view of the utility model steel tube tower upkeep operation platform embodiment.
Fig. 3 is the left view of the utility model steel tube tower upkeep operation platform embodiment.
In figure, 1-connecting ring, 2-abrasionproof packing ring, 3-kit bag, 4-quadra, the 5-netting that insulate, 6-is rope by the waist, 7-connection cord, 8-latch closure, 9-open-close type latch closure, 10-hanging point link plate.
Embodiment
A upkeep operation platform for 1000kV extra-high voltage steel tube tower, is applicable to steel tube tower circuit, for personnel's upkeep operation provides job platform.
As shown in Figure 1, the main body of job platform is the quadra 4 made from aluminium alloy extrusions, on bottom surface, side and the frame below of quadra, be provided with for the connecting hole of netting is installed, on each connecting hole, be lined with for preventing the abrasionproof packing ring 2 of rope wear fracture, the insulation netting 5 that polyamide fibre is made is contained in respectively the bottom surface, side of quadra 4 and below.And the outside, both sides at quadra 4 is provided with the kit bag 3 that canvas is made, before quadra 4, fixedly mount a soft rope by the waist 6, rope can be opened and be fastened on frame above by the waist, top at 4 four columns of quadra is fixed with connecting ring 1, forms thus job platform support body.In addition connection cord 7 and latch closure 8, open-close type clasp 9 are connected to form to suspension cord.Hanging point link plate 10 is standby.
Before operation, the job platform support body that assembling is completed, then the suspension cord that connection is combined is connected to connecting ring 1, formation job platform.
During operation, when setting top is steel pipe, job platform is promoted to steel pipe place, suspension cord is wound around on steel pipe to one to twice, according to setting height and operating personnel's height needs, by open-close type clasp 9, be buckled on connection cord 7 or latch closure 8 the last assembling of the platform that fulfils assignment.
Operating personnel, on job platform, is seated on the polyamide fibre netting 5 of job platform upper bottom surface, and rope 6 is buckled well by the waist, can carry out operation.
While having construction hole as setting top, as above-mentioned steps completes platform and suspension cord assembling, suspension cord is buckled on hanging point link plate 10 hanging holes, the more U-shaped ring of hanging point link plate 10 is connected with construction hole, the fulfil assignment assembling of platform, then carries out corresponding operation.
Above-described the utility model execution mode, does not form the restriction to the utility model protection range.Any modification of doing within spirit of the present utility model and principle, be equal to and replace and improvement etc., within all should being included in claim protection range of the present utility model.

Claims (3)

1. a steel tube tower upkeep operation platform, by quadra, suspension cord, the assembling of hanging point link plate, formed, it is characterized in that: described quadra adopts aluminium alloy extrusions to make, and the bottom surface of quadra is provided with polyamide fibre netting, quadra to be provided with polyamide fibre netting be below support net; Horizontal soft rope is by the waist set before quadra; The both sides of described quadra are provided with the kit bag that canvas is made; The top of quadra is provided for connecting the link of suspension cord;
Described suspension cord is the polyamide fibre cable of segmentation, and the polyamide fibre cable of segmentation connects by latch closure, and described latch closure can be used as and regulates buckling a little of polyamide fibre cable length; The end of suspension cord is provided with opening and closing type clasp;
U-shaped ring is equipped with in described hanging point link plate upper end, and two hanging holes for being connected with suspension cord are set on hanging point link plate.
2. steel tube tower upkeep operation platform as claimed in claim 1, is characterized in that: the frame of described quadra is provided with connecting hole, and described connecting hole is lined with abrasionproof packing ring; Described polyamide fibre netting is connected with the frame of quadra through abrasionproof packing ring.
3. steel tube tower upkeep operation platform as claimed in claim 1, is characterized in that: the length of described suspension cord regulates according to the position of setting and distance and operating personnel's height.
CN201420220254.XU 2014-04-30 2014-04-30 A steel tube tower unkeep working platform Expired - Fee Related CN203826847U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420220254.XU CN203826847U (en) 2014-04-30 2014-04-30 A steel tube tower unkeep working platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420220254.XU CN203826847U (en) 2014-04-30 2014-04-30 A steel tube tower unkeep working platform

Publications (1)

Publication Number Publication Date
CN203826847U true CN203826847U (en) 2014-09-10

Family

ID=51482311

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420220254.XU Expired - Fee Related CN203826847U (en) 2014-04-30 2014-04-30 A steel tube tower unkeep working platform

Country Status (1)

Country Link
CN (1) CN203826847U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103956679A (en) * 2014-04-30 2014-07-30 国家电网公司 Steel tube tower maintenance operation platform and using method thereof
CN114678804A (en) * 2022-04-22 2022-06-28 国网江苏省电力有限公司南通供电分公司 Distribution network live working platform of ascending a height

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103956679A (en) * 2014-04-30 2014-07-30 国家电网公司 Steel tube tower maintenance operation platform and using method thereof
CN103956679B (en) * 2014-04-30 2016-05-11 国家电网公司 Steel tube tower upkeep operation platform and using method thereof
CN114678804A (en) * 2022-04-22 2022-06-28 国网江苏省电力有限公司南通供电分公司 Distribution network live working platform of ascending a height
CN114678804B (en) * 2022-04-22 2023-08-18 国网江苏省电力有限公司南通供电分公司 Live working platform of ascending a height of distribution network

Similar Documents

Publication Publication Date Title
CN204024005U (en) Assembly type suspension platform
CN203826847U (en) A steel tube tower unkeep working platform
CN103956679B (en) Steel tube tower upkeep operation platform and using method thereof
CN207245138U (en) Boat scaffold adjustable in pitch
CN202550405U (en) Special ladder for maintenance of strain insulator
CN203318638U (en) Mast capable of being put down
CN207673269U (en) A kind of rope ladder head for high ferro repair
CN206376507U (en) Prefabrication outrigger
CN108775196A (en) A kind of lifting set up for power transmission tower and the combined mechanism that climbs certainly
CN103213910B (en) Hoisting frame for attachment of inner climbing type tower crane
CN109256721A (en) A kind of helicopter live-line maintenance operation hanging basket
CN207647136U (en) A kind of easy disassembly and the engineering scaffold with stair
CN207200123U (en) A kind of four line march-past wire lifting devices
CN201908907U (en) Rope stick
CN207098443U (en) A kind of helicopter live-line maintenance operation hanging basket
CN209860475U (en) Transmission line strides across construction protection network
CN104410009A (en) Climbing type steel wire rope ladder
CN208445196U (en) It is a kind of for lead wire and earth wire in transmission line and the Multifunctional hanging line device of optical cable
CN208749208U (en) Communicate shaft tower
CN209293395U (en) Construction adhesion type safety work protective platform
CN207221129U (en) High-rise building escape device
CN208525688U (en) A kind of steel I-beam spraying safety belt suspension protective device
CN106219331B (en) Portable ground wire accepting rack
CN215510876U (en) Rope lintel structure
CN202337658U (en) Energy storage hoisting device for heavy objects

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140910

Termination date: 20180430