CN203809985U CN201320822980.4U CN201320822980U CN203809985U CN 203809985 U CN203809985 U CN 203809985U CN 201320822980 U CN201320822980 U CN 201320822980U CN 203809985 U CN203809985 U CN 203809985U
Authority
CN
China
Prior art keywords
bottom end
cross beams
end rail
tunnel device
upper beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320822980.4U
Other languages
Chinese (zh)
Inventor
赵学军
齐万里
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING JINRIHENGSHENG TECHNOLOGY Co Ltd
Original Assignee
BEIJING JINRIHENGSHENG TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING JINRIHENGSHENG TECHNOLOGY Co Ltd filed Critical BEIJING JINRIHENGSHENG TECHNOLOGY Co Ltd
Priority to CN201320822980.4U priority Critical patent/CN203809985U/en
Application granted granted Critical
Publication of CN203809985U publication Critical patent/CN203809985U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a tunnel equipment installation device. The device comprises upper cross beams, lower cross beams, polished rods, wire grooves and supports, wherein the number of the polished rods is not less than two; the upper cross beams and the lower cross beams are fixedly mounted on the polished rods and are vertical to the polished rods; the upper cross beams and the lower cross beams are in parallel; the upper cross beams and the lower cross beams are fixedly connected by the supports in a detachable way; the wire grooves are fixedly mounted in the polished rods in a detachable way and are located below the lower cross beams in parallel; the upper cross beams and the lower cross beams are provided with mounting holes used for fixing tunnel equipment; the tunnel equipment installation device comprises a plurality of upper cross beams and a plurality of lower cross beams; two adjacent upper cross beams are fixed by upper connecting pieces; two adjacent lower cross beams are fixed by lower connecting pieces; the upper cross beams and the lower cross beams are steel angles. The tunnel equipment installation device has the advantages that the installation difficulty is reduced, the installation efficiency is increased, the effective utilization of resources is increased, and the cost is saved.

Description

Tunnel device erecting device
Technical field
The utility model relates to a kind of tunnel device erecting device.
Background technique
Existing media device hangs the hang that technique for fixing mostly adopts free-standing framework, the equipment of a unit will adopt a framework to be fixed in tube wall, separate each other, the equipment of a display unit will be fixed on tube wall with a framework.So not only cause the rising of waste, cost of resource, strengthened especially the destruction to subway tube wall concrete structure.And separate each other between display unit and display unit, the precision of two unit intervals can only guarantee by installation, implements very difficult.Both increase the difficulty of operability, and can cause again the unstable of media device that the display effect generation of media device is beated, affected result of broadcast.
Model utility content
The utility model provides a kind of tunnel device erecting device, and it is installed simple and easy and can increase the stability of tunnel device.
The utility model discloses a kind of tunnel device erecting device, it comprises upper beam, bottom end rail, light beam, wire casing and support, light beam quantity is for being no less than 2, upper beam, bottom end rail are fixedly mounted on light beam, and all vertical with light beam, it between upper beam, bottom end rail, is parallel direction, and by support, carry out dismountable being fixedly connected with between upper beam and bottom end rail, wire casing is dismountable to be fixedly mounted on light beam, and the parallel below that is positioned at bottom end rail, and on described upper beam and bottom end rail, offer for the fixing mounting hole of tunnel device.
As technique scheme preferably, described upper beam also comprises a secondary crossbeam, and secondary crossbeam is also fixedly mounted on light beam, and all vertical with light beam, and between secondary crossbeam and upper beam, by crossbeam, link up with and be connected, to reach the fixedly more stable object of tunnel device.
Upper beam and bottom end rail can be angle steel.Upper beam and bottom end rail can be made by Q235.
On upper beam or bottom end rail, can offer a plurality of mounting holes.In an embodiment, the spacing of adjacent two square holes is 50mm.And on the support being attached thereto, offer out two 61mm slotted holes.
Tunnel device can be fixed on upper beam or bottom end rail by mounting hole.In the present embodiment, mounting hole is square opening.Tunnel device is fixed on erecting device by T-nut or T bolt.Square opening coordinates fastening with T-shaped nut or T-shaped bolt, T-shaped nut like this is embedded in square opening, only needs a spanner just bolts and nuts can be coordinated and tighten, convenient and swift.Tunnel device can be display device, distribution box or control box etc.
One preferred embodiment in, on bottom end rail, be provided with wire casing hook.
One preferred embodiment in, tunnel device erecting device comprises a plurality of upper beams and a plurality of bottom end rail, adjacent two upper beams are fixed by upper connector, adjacent two bottom end rails are fixed by lower link.
The utility model adopts above structure, and it has the following advantages:
1, avoid the precision of display unit spacing to guarantee by installation precision, reduce installation difficulty, increase installation efficiency; Adopt the utility model, tunnel device unification to be arranged on tunnel device and install in qualification, support subtracts and is a half like this, and effective utilization of increase resource, has saved cost, has alleviated the destruction to subway tube wall concrete structure.
Tunnel device unification is arranged on upper beam or bottom end rail, thereby has good continuity.Especially, the display effect of display device can not produce and beat, thereby result of broadcast is better.
2, well guarantee the spacing between two display units, strengthened the display effect of display unit; On upper beam or bottom end rail, can offer a plurality of mounting holes, while so just making angle steel be connected with support, angle steel any movement in level can tighten two groups of bolts, increases greatly the adjustability of crossbeam angle steel.
3, equipment connection is become to an integral body, be conducive to increase stabilization of equipment performance.Make equipment fastening more firm.Adopt angle steel as lower and upper cross-member, alleviated weight and be convenient to and installed, reduced largely installation workload.Tunnel device erecting device comprises a plurality of upper beams and a plurality of bottom end rail, adjacent two upper beams are fixed by upper connector, adjacent two bottom end rails are fixed by lower link, strengthened the stability of whole through twin-spar construction, can make local pressure alleviate concentration of local to whole twin-spar construction transmission stressed.Wire casing hook can be used in connection wire casing.Adopt this structure, facilitate the gathering of cable, whole installation qualification is more clean and tidy, has prevented that cable from hanging the vertical metro operation that affects.
Accompanying drawing explanation
Fig. 1 has shown the structural representation of tunnel device erecting device.
Embodiment
Below in conjunction with accompanying drawing, preferred embodiment of the present utility model is described in detail, thereby so that advantage of the present utility model and feature can be easier to be those skilled in the art will recognize that, protection domain of the present utility model is made to more explicit defining.
As shown in Figure 1, the utility model discloses tunnel device erecting device, it comprises upper beam 2, bottom end rail 3, light beam 1, wire casing 4 and support 5, light beam 1 quantity is for being no less than 2, upper beam 2, bottom end rail 3 is fixedly mounted on light beam 1, and all vertical with light beam 1, upper beam 2, it between bottom end rail 3, is parallel direction, and by support 5, carry out dismountable being fixedly connected with between upper beam 2 and bottom end rail 3, wire casing 4 is dismountable to be fixedly mounted on light beam 1, and the parallel below that is positioned at bottom end rail 3, and on described upper beam 2 and bottom end rail 3, offer for the fixing mounting hole of tunnel device 6, on bottom end rail 3, be provided with wire casing hook 7.
One preferred embodiment in, on bottom end rail, be provided with wire casing hook 7.Wire casing hook 7 can be used in and connects wire casing 4.Adopt this structure, facilitate the gathering of cable, whole installation qualification is more clean and tidy, has prevented that cable from hanging the vertical metro operation that affects.
One preferred embodiment in, tunnel device erecting device comprises a plurality of upper beams and a plurality of bottom end rail, adjacent two upper beams are fixed by upper connector, adjacent two bottom end rails are fixed by lower link.Adopt this structure, strengthened the stability of whole through twin-spar construction, can make local pressure alleviate concentration of local to whole twin-spar construction transmission stressed.
As technique scheme preferably, described upper beam 2 also comprises a secondary crossbeam 8, and secondary crossbeam 8 is also fixedly mounted on light beam 1, and all vertical with light beam 1, and between secondary crossbeam 8 and upper beam 2, by crossbeam, link up with 9 and be connected, to reach the fixedly more stable object of tunnel device.
Upper beam and bottom end rail can be angle steel.Adopt angle steel as lower and upper cross-member, alleviated weight and be convenient to and installed, reduced largely installation workload.Upper beam and bottom end rail can be made by Q235 angle steel.On upper beam or bottom end rail, can offer a plurality of mounting holes.In the present embodiment, the spacing of adjacent two square holes is 50mm.And on the support being attached thereto, offer out two 61mm slotted holes.While so just making angle steel be connected with support, angle steel any movement in level can tighten two groups of bolts, increases greatly the adjustability of crossbeam angle steel.
Tunnel device can be fixed on upper beam or bottom end rail by mounting hole.In the present embodiment, mounting hole is square opening.Tunnel device is fixed on erecting device by T-nut or T bolt.Square opening coordinates fastening with T-shaped nut or T-shaped bolt, T-shaped nut like this is embedded in square opening, only needs a spanner just bolts and nuts can be coordinated and tighten, convenient and swift.Tunnel device can be display device, distribution box or control box etc.
Adopt the utility model, tunnel device unification to be arranged on tunnel device and install in qualification, support subtracts and is a half like this, and effective utilization of increase resource, has saved cost, has alleviated the destruction to subway tube wall concrete structure.
Tunnel device unification is arranged on upper beam or bottom end rail, thereby has good continuity.Especially, the display effect of display device can not produce and beat, thereby result of broadcast is better.
Each embodiment in this specification all adopts the mode of going forward one by one to describe, and each embodiment stresses is the difference with other embodiments, between each embodiment identical similar part mutually referring to.
Above-described embodiment is only technical conceive and the feature of this real model utility of explanation, and its object is to allow person skilled in the art can understand content of the present utility model and implement according to this, can not limit protection domain of the present utility model with this.All equivalences of doing according to the utility model Spirit Essence change or modify, within all should being encompassed in protection domain of the present utility model.

Claims (10)

1. a tunnel device erecting device, it is characterized in that: it comprises upper beam, bottom end rail, light beam, wire casing and support, light beam quantity is for being no less than 2, upper beam, bottom end rail are fixedly mounted on light beam, and all vertical with light beam, it between upper beam, bottom end rail, is parallel direction, and by support, carry out dismountable being fixedly connected with between upper beam and bottom end rail, wire casing is dismountable to be fixedly mounted on light beam, and the parallel below that is positioned at bottom end rail, and on described upper beam and bottom end rail, offer for the fixing mounting hole of tunnel device.
2. tunnel device erecting device according to claim 1, it is characterized in that: described upper beam also comprises a secondary crossbeam, secondary crossbeam is also fixedly mounted on light beam, and all vertical with light beam, and between secondary crossbeam and upper beam, by crossbeam, link up with and be connected, to reach the fixedly more stable object of tunnel device.
3. tunnel device erecting device according to claim 1, is characterized in that: described upper beam or described bottom end rail are angle steel.
4. tunnel device erecting device according to claim 3, is characterized in that: on described angle steel, offer a plurality of square openings.
5. tunnel device erecting device according to claim 1, is characterized in that: the spacing of adjacent two square holes is 50mm.
6. tunnel device erecting device according to claim 1, is characterized in that: described upper beam or described bottom end rail are fixed by T-nut or T bolt.
7. tunnel device erecting device according to claim 1, is characterized in that: on described bottom end rail, be provided with wire casing hook.
8. tunnel device erecting device according to claim 1, is characterized in that: it comprises a plurality of upper beams, and adjacent two upper beams are fixed by upper connector.
9. tunnel device erecting device according to claim 1, is characterized in that: it comprises a plurality of bottom end rails, and adjacent two bottom end rails are fixed by lower link.
10. tunnel device erecting device according to claim 1, is characterized in that: on described upper beam or described bottom end rail, be provided with display unit.
CN201320822980.4U 2013-12-12 2013-12-12 Tunnel equipment installation device Expired - Fee Related CN203809985U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320822980.4U CN203809985U (en) 2013-12-12 2013-12-12 Tunnel equipment installation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320822980.4U CN203809985U (en) 2013-12-12 2013-12-12 Tunnel equipment installation device

Publications (1)

Publication Number Publication Date
CN203809985U true CN203809985U (en) 2014-09-03

Family

ID=51448733

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320822980.4U Expired - Fee Related CN203809985U (en) 2013-12-12 2013-12-12 Tunnel equipment installation device

Country Status (1)

Country Link
CN (1) CN203809985U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112762417A (en) * 2020-12-31 2021-05-07 北京金日恒升科技有限公司 Installation positioning method for enabling light beam display picture to be parallel to car window
CN112856172A (en) * 2020-12-31 2021-05-28 北京金日恒升科技有限公司 Mounting and positioning method for tunnel media system light column

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112762417A (en) * 2020-12-31 2021-05-07 北京金日恒升科技有限公司 Installation positioning method for enabling light beam display picture to be parallel to car window
CN112856172A (en) * 2020-12-31 2021-05-28 北京金日恒升科技有限公司 Mounting and positioning method for tunnel media system light column
EP4024376A1 (en) * 2020-12-31 2022-07-06 Beijing Jinri Hengsheng Technology Co., Ltd. Installing and positioning method for light columns of tunnel media system

Similar Documents

Publication Publication Date Title
CN201842567U (en) Lifting frame for modular tube panel of waste heat boiler
CN203809985U (en) Tunnel equipment installation device
CN202809885U (en) Energy dissipation wall structure
CN203173749U (en) Assembled integral type vertical self-jacking device of hydraulic double-type crane tower
CN204717144U (en) A kind of concrete pump pipe setting tool cribbing
CN203430706U (en) Protective fixing device for nacelle of wind driven generator
CN202706508U (en) Overhanging strength bearing steel beam construction member of scaffold
CN203334679U (en) Steel reinforced concrete beam suspending and supporting structure
CN103615103A (en) Hanging type assembled movable platform
CN203499259U (en) Tool type cantilevered unloading platform
CN202733377U (en) LCD TV wall-hung bracket convenient to mount
CN204940662U (en) A kind of hall suspended ceiling mounting structure
CN204057560U (en) Be attached to attached wall connection structure in the jacking system of section
CN209780003U (en) fixing structure of reverse furred ceiling of big space grid structure
CN203783106U (en) Hanging assembling moving platform
CN203783050U (en) Special-shaped stone point hanging structure
CN203878779U (en) Rectangular concrete-filled steel tube column and I-steel beam rebar penetrating type joint
CN210238296U (en) Large tower crane wall-attached space steel truss foundation
CN203905008U (en) Diagonal brace supporting structure for superior angle of foundation pit
CN204099722U (en) A kind of adjustable type comprehensive support
CN206429760U (en) Industrial premises pipe gallery para-seismic support
CN216312562U (en) Construction cable bracket under crane beam
CN215519355U (en) Steel tube bundle combined shear wall structure
CN210086725U (en) Assembled for building externally-hung wallboard fossil fragments convenient to installation
CN203546898U (en) Detachable clamp-fixing engineering scaffold for factory building installation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140903

Termination date: 20211212