CN203625926U - Reinforced soil wall - Google Patents

Reinforced soil wall Download PDF

Info

Publication number
CN203625926U
CN203625926U CN201320821330.8U CN201320821330U CN203625926U CN 203625926 U CN203625926 U CN 203625926U CN 201320821330 U CN201320821330 U CN 201320821330U CN 203625926 U CN203625926 U CN 203625926U
Authority
CN
China
Prior art keywords
gravel
layer
stopper layer
stopper
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320821330.8U
Other languages
Chinese (zh)
Inventor
聂承凯
赵虎生
王文光
满冠峰
刘文进
刘宇鹏
张明欣
肖俊秀
贾计林
李晓俊
刘晓梁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Traffic Planning Survey Design Institute Co Ltd
Original Assignee
Shanxi Traffic Planning Survey Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Traffic Planning Survey Design Institute Co Ltd filed Critical Shanxi Traffic Planning Survey Design Institute Co Ltd
Priority to CN201320821330.8U priority Critical patent/CN203625926U/en
Application granted granted Critical
Publication of CN203625926U publication Critical patent/CN203625926U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model relates to a reinforced soil wall, and solves the problems of high construction difficulty, long construction period, high requirement to foundation carrying capacity, high engineering cost and large land occupation area because of existing masonry structures. The reinforced soil wall comprises a gravel cushion set under the face of land; the gravel cushion has a gravel blocking layer set vertically on the edge of earth road shoulder; the outer side of the gravel blocking layer has a stopper layer; the stopper layer is formed by overlapping a plurality of stoppers from top to the bottom; each stopper is connected to geotechnical gratings inside the earth road shoulder in parallel; the upper end surfaces of the gravel blocking layer and the stopper layer are provided with hat stones; the hat stones are provided with an exhausting pipe at the outer side of the stopper layer; and the exhausting pipe is fixed with a pipe clamp. The utility model has reasonable and reliable composition and design, can contract slope toe and reduce land occupation; the cost and requirement of engineering to foundation carrying capacity are reduced; the construction period is shortened; the construction progress is accelerated, and good seismic performance is provided at the same time.

Description

Reinforced earth bulkhead
Technical field
The utility model relates to subgrade construction barricade, is specially a kind of reinforced earth bulkhead.
Background technology
Expressway construction plays huge impetus to national scientific research development, along with the quickening of developing steps, the increasing project of expressway construction will be in mountain area, build hills area, the engineering problem that the difficulty such as high slope, soft base is larger also runs into again and again, has brought the phenomenon that construction costs is high, land occupation is many thereupon.
Adopt traditional method of constructing roadway, otherwise extend and need a large amount of occupation of land without a gear backfilled slope, otherwise bricklaying structure is too huge, requires bearing capacity of foundation soil high, construction cost is large.In some entry portion engineering structures is built, all can realize by the past traditional way, but the expenditure of construction of Yin Gaoang and a large amount of land occupation are difficult to put into practice.
Summary of the invention
There is in order to solve existing masonry masonry structure the problem that difficulty of construction is large, the construction period long, high to ground requirement for bearing capacity, engineering cost is high and floor space is large in the utility model, a kind of reinforced earth bulkhead is provided.
The utility model is to adopt following technical scheme to realize: reinforced earth bulkhead, comprise the Base with Sand Gravel Cushion that is arranged on below, earth's surface, on Base with Sand Gravel Cushion, be provided with vertical setting and be positioned at the gravel gear layer at earth shoulder edge, gravel gear layer arranged outside has block layer, block layer is to be formed by stacking by several block bodies that distribute up and down, on each block body, be all connected with and be positioned at earth shoulder inside and horizontally disposed geo-grid, gravel gear layer and block layer upper surface are provided with cap stone, on cap stone, be provided with the gutter that is positioned at block layer outside, on gutter, be fixed with pipe clamp.
This barricade adopts upright structures, greatly reduce body of wall bricklaying consumption, the design of prefabricated block, has saved construction period, has overcome existing masonry masonry structure and has had the problem that difficulty of construction is large, the construction period long, high to ground requirement for bearing capacity, engineering cost is high and floor space is large.
The utility model reasonable in design is reliable, the effect of shrinking toe, reducing occupation of land is played in the setting of vertical type barricade, and lowered cost and the requirement for bearing capacity of engineering to ground, arranging of prefabricated block shortened the duration, accelerated construction speed, has good anti-seismic performance simultaneously.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
In figure: 1-Base with Sand Gravel Cushion, 2-gravel gear layer, 3-block layer, 4-geo-grid, 5-cap stone, 6-gutter, 7-pipe clamp.
The specific embodiment
Reinforced earth bulkhead, comprise the Base with Sand Gravel Cushion 1 that is arranged on below, earth's surface, on Base with Sand Gravel Cushion 1, be provided with vertical setting and be positioned at the gravel gear layer 2 at earth shoulder edge, gravel gear layer 2 arranged outside have block layer 3, block layer 3 is to be formed by stacking by several block bodies that distribute up and down, on each block body, be all connected with and be positioned at earth shoulder inside and horizontally disposed geo-grid 4, gravel gear layer 2 and block layer 3 upper surface are provided with cap stone 5, on cap stone 5, be provided with the gutter 6 that is positioned at block layer 3 outside, on gutter 6, be fixed with pipe clamp 7.
In specific implementation process, block body is No. 25 precast concrete blocks, and cap stone 5 is No. 15 precast concrete blocks, and 49.5 centimetres of the prefabricated block lengths of cap stone 5 are mixed 35% I level flyash, and two kinds of cap stone putting positions and traffic engineering chamber anticollision barrier plan match; Interior 10 centimetres of the prefabricated block body of geo-grid 4,40 centimetres of Grill spaces; Gutter 6 is every 5.0 meters of pvc pipes of establishing a horizontal external diameter 125mm, pvc pipe wall thickness 3.2 mm, and fixing with pipe clamp 7, pipe clamp 7 spacing are generally 1.0 meters; The tensile strength of geo-grid 4 requires to be not less than 160KN/m; Geo-grid 4 seams adopt plastic tape colligation, without overlap joint, require colligation spacing 1.0m.

Claims (1)

1. a reinforced earth bulkhead, it is characterized in that: comprise the Base with Sand Gravel Cushion (1) that is arranged on below, earth's surface, on Base with Sand Gravel Cushion (1), be provided with vertical setting and be positioned at the gravel gear layer (2) at earth shoulder edge, gravel gear layer (2) arranged outside has block layer (3), block layer (3) is to be formed by stacking by several block bodies that distribute up and down, on each block body, be all connected with and be positioned at earth shoulder inside and horizontally disposed geo-grid (4), gravel gear layer (2) and block layer (3) upper surface are provided with cap stone (5), on cap stone (5), be provided with the gutter (6) that is positioned at block layer (3) outside, on gutter (6), be fixed with pipe clamp (7).
CN201320821330.8U 2013-12-16 2013-12-16 Reinforced soil wall Expired - Lifetime CN203625926U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320821330.8U CN203625926U (en) 2013-12-16 2013-12-16 Reinforced soil wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320821330.8U CN203625926U (en) 2013-12-16 2013-12-16 Reinforced soil wall

Publications (1)

Publication Number Publication Date
CN203625926U true CN203625926U (en) 2014-06-04

Family

ID=50812418

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320821330.8U Expired - Lifetime CN203625926U (en) 2013-12-16 2013-12-16 Reinforced soil wall

Country Status (1)

Country Link
CN (1) CN203625926U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107977465A (en) * 2017-12-21 2018-05-01 福建省晨曦信息科技股份有限公司 A kind of project cost display methods and terminal

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107977465A (en) * 2017-12-21 2018-05-01 福建省晨曦信息科技股份有限公司 A kind of project cost display methods and terminal

Similar Documents

Publication Publication Date Title
CN105464134B (en) Multi-layer underground space is along inverse combining construction method and supporting construction under existing facility
CN102296961A (en) Karst tunnel large-scale cavern processing method
US10233595B2 (en) Hard pavement construction method for natural groundwater recharge
CN102900088A (en) Cast-in-place ecological slope protection and construction method thereof
CN108930284B (en) Assembled retaining wall structure and backfilling method
CN105064711B (en) Method for constructing underground garage between residential buildings
CN104499502B (en) A kind of river course arch barrier wall structure and construction method thereof
CN105256682B (en) The buried lattice frame of pile and construction method for protecting elevated formation level
CN204662494U (en) A kind of Road Retaining Walls ruggedized construction
CN207176700U (en) A kind of solid matter perfusion inner support of pile foundation ditch permanent support structure under complex environment
CN203625926U (en) Reinforced soil wall
CN106836034B (en) High-fill cover plate culvert flexible load shedding system and construction method
CN102720136B (en) Island and cofferdam construction method for roads, bridges and bearing platforms
CN205669211U (en) A kind of prefabricated Gravity Retaining Wall
CN202830673U (en) Existing embankment heightening structure for limited using land area
CN209759925U (en) Assembled roadbed construction system suitable for deep and thick soft foundation
CN112144548A (en) Semi-embedded multifunctional frame supporting structure and construction method thereof
CN201660852U (en) Culvert beneficial for animals to pass through
CN110172988A (en) A kind of piling formula composite concrete placement ground and its construction method
CN108677998A (en) A kind of corner type reinforced earth retaining wall structure and production method
CN105544598B (en) Assembly concrete tubulose building block ecology retaining wall
CN208717919U (en) A kind of road based on contrary sequence method changes bridge section foundation pit supporting construction
CN210458918U (en) Space stacked bridge structure
CN210177295U (en) Soil-rock mixed filling roadbed structure
CN202440824U (en) Three-line-pile super-deep foundation-pit support structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20140604

CX01 Expiry of patent term