CN203625846U CN201320791516.3U CN201320791516U CN203625846U CN 203625846 U CN203625846 U CN 203625846U CN 201320791516 U CN201320791516 U CN 201320791516U CN 203625846 U CN203625846 U CN 203625846U
Authority
CN
China
Prior art keywords
stopping means
pile
floating type
operation platform
type operation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320791516.3U
Other languages
Chinese (zh)
Inventor
万伟
潘海峰
杨飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Harzone Industry Corp Ltd
Original Assignee
China Harzone Industry Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Harzone Industry Corp Ltd filed Critical China Harzone Industry Corp Ltd
Priority to CN201320791516.3U priority Critical patent/CN203625846U/en
Application granted granted Critical
Publication of CN203625846U publication Critical patent/CN203625846U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses an overwater floating type operation platform pile fixing device. The pile fixing device belongs to a modularized independent unit and consists of pile fixing frames, a propping device and position limiting devices, wherein the pile fixing frames are symmetrically arranged at two sides of a floating type operation platform, are of framework structures and are divided into an upper layer, a middle layer and a lower layer, panels are respectively paved at the upper layer and the middle layer, pile holes for steel piles to pass are formed in the panels, the position limiting devices are symmetrically arranged around the pile holes formed in each layer of panels of the pile fixing frame, and the propping device is arranged at the back end of one of the two position limiting devices with symmetrical pile holes. Through the propping device and the position limiting devices at two layers of the pile fixing frames, a friction hoop form is formed to act on the steel piles, so a fixing effect on an overwater floating type operation platform is realized through the fixing effect on the steel piles. The overwater floating type operation platform pile fixing device has the advantages that the structure form is simple, the operation is convenient, and the dismounting and the removal are convenient.

Description

The solid stake of a kind of floating job platform waterborne device
Technical field
The utility model relates to the solid stake of a kind of floating job platform waterborne device.
Background technology
Floating job platform waterborne, when operation, general employing thrown anchor mode holding position, and its weak point is: job platform is subject to the effect of current and stormy waves, is always ceaselessly jolting, and affects operation at sea.
Some floating job platform waterborne is opened a hole in platform structure, and employing is installed pile platform is fixed in stake hole, and its weak point is: platform complex manufacturing, cost is high, in the time of SEA LEVEL VARIATION, platform can not rise or decline with the variation of water level, and compliance is poor.
Also have some floating job platforms waterborne to adopt special fastening devices, its weak point is: this fastening devices is built for the environment for use scene of platform, after use, does not re-use along with the dismounting of platform, causes its cost relatively high.
Utility model content
The utility model provides the solid stake of a kind of floating job platform waterborne device, this solid stake device is a kind of modularization separate unit, can adopt various ways to be connected with floating job platform side, and do not change the form of structure of platform self inside, make solid stake device and piling bar form very easily stationary state, thereby implementation platform is fixing.
The utility model is realized by following scheme: the solid stake of a kind of floating job platform waterborne device, is made up of wedge bracket, holding device, stopping means.
Wedge bracket is arranged symmetrically in floating job platform both sides, and wedge bracket is frame construction, and wedge bracket is divided into three layers of upper, middle and lowers, and the upper two-layer panel that is all covered with has the stake hole of passing through for piling bar on panel.
Stopping means symmetry is arranged on the surrounding in the every aspect sheet pile of wedge bracket hole.Stopping means is made up of push rod, limit base, and push rod is T-shaped structure, is sleeved in limit base hole.
Holding device is made up of Manual hydraulic jack and jack pad assembly, jack pad assembly is arranged on one of them the rear end in two symmetrical stopping means of a hole, Manual hydraulic jack level is arranged on jack pad assembly, and the piston rod of Manual hydraulic jack and the push rod of stopping means keep same axis.
The stopping means that holding device is not set is furnished with limited block, holds out against spacing after piling bar for the push rod of this stopping means.
Operating principle: regulate the push rod of the stopping means that holding device is not set, make push rod in jack-up state, settle limited block, make push rod spacing; Regulate Manual hydraulic jack, the push rod in the stopping means of its effect of pushing tow, by the two-layer stopping means of wedge bracket and holding device, the form and the piling bar that form friction anchor ear are fixed, thereby realize the fixation to floating job platform waterborne.
The utility model has following advantage:
1. a solid device is connected with platform is outside, does not change the structure of platform self;
2. a solid apparatus structure form is simple, easy to operate, and it is convenient to remove;
3. by two-layer stopping means and the holding device of wedge bracket, the form and the piling bar that form friction anchor ear are fixed, thereby realize the fixation to floating job platform waterborne, effectively improve the installation rate of job platform, reduce construction cost.
Brief description of the drawings
Fig. 1 is the solid stake of a kind of floating job platform waterborne of the utility model device front view;
Fig. 2 is the solid stake of a kind of floating job platform waterborne of the utility model device top view;
Fig. 3 is schematic diagram before the solid stake of a kind of floating job platform waterborne of the utility model device effect piling bar;
Schematic diagram when Fig. 4 is the solid stake of a kind of floating job platform waterborne of the utility model device effect piling bar;
Fig. 5 is the front view of the fixing floating job platform waterborne of the solid stake of a kind of floating job platform waterborne of the utility model device;
Fig. 6 is the top view of the fixing floating job platform waterborne of the solid stake of a kind of floating job platform waterborne of the utility model device.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is elaborated:
As shown in Figure 1, 2, the solid stake of a kind of floating job platform waterborne device, is made up of wedge bracket 1, stopping means 2, holding device 3.
Wedge bracket 1 is frame construction, is divided into three layers of upper, middle and lowers, and the upper two-layer panel that is all covered with has the stake hole of passing through for piling bar 4 on panel.
As shown in Figure 1,2,3, 4, stopping means 2 symmetries are arranged on the surrounding in the every aspect sheet pile of wedge bracket 1 hole.Stopping means 2 is made up of push rod 5, limit base 6, and push rod 5 is T-shaped structure, is sleeved in limit base 6 holes.Holding device 3 is made up of Manual hydraulic jack 7 and jack pad assembly 8, jack pad assembly 8 is arranged on one of them the rear end in two symmetrical stopping means 2 of a hole, Manual hydraulic jack 7 levels are arranged on jack pad assembly 8, and the piston rod of Manual hydraulic jack 7 and the push rod of stopping means 5 keep same axis.
The stopping means 2 that holding device 3 is not set is furnished with limited block 9, holds out against spacing after piling bar 4 for the push rod 5 of this stopping means 2.
As shown in Figure 5,6, wedge bracket 1 is arranged symmetrically in floating job platform both sides, the multiple connected mode such as can take according to actual conditions.When piling bar 4 is deep into behind the bottom, rely on solid stake device to be fixed on the both sides of floating platform 10, carry out fixing to floating platform 10, effectively improve the installation rate of platform, reduce construction cost.
Gu stake device is to the fixation procedure of platform following (as shown in Fig. 3,4,5,6):
Gu before stake, hydraulic jack 7 is in off working state, corresponding push rod 5 is not by pushing tow, and stopping means 3 does not act on piling bar 4, does not also play fixation.The push rod 5 that regulates the stopping means 2 that holding device 3 is not set, makes this push rod 5 in jack-up state, settles limited block 9, makes push rod 5 spacing; Regulate Manual hydraulic jack 7, the push rod 5 in the stopping means 2 of its effect of pushing tow, forms friction anchor ear piling bar 4 by the two-layer stopping means 2 of wedge bracket and holding device 3, thereby realizes the fixation to floating job platform 10 waterborne.

Claims (2)

1. the solid stake of a floating job platform waterborne device, it is characterized in that: Gu stake device is made up of wedge bracket (1), stopping means (2), holding device (3), wedge bracket 1 is arranged symmetrically in floating job platform both sides, wedge bracket (1) is tower structure, be divided into three layers of upper, middle and lowers, the upper two-layer panel that is all covered with, has the stake hole of passing through for piling bar (4) on panel; Stopping means (2) symmetry is arranged on the surrounding in the every aspect sheet pile of wedge bracket (1) hole, holding device (3) is made up of Manual hydraulic jack (7) and jack pad assembly (8), jack pad assembly (8) is arranged on one of them the rear end in symmetrical two stopping means (2) in a hole, it is upper that Manual hydraulic jack (7) level is arranged on jack pad assembly (8), and the push rod (5) of the piston rod of Manual hydraulic jack (7) and stopping means (2) keeps same axis.
2. the solid stake of one according to claim 1 floating job platform waterborne device, it is characterized in that: stopping means (2) is made up of push rod (5), limit base (5), push rod (5) is T-shaped structure, is sleeved in limit base (6) hole.
CN201320791516.3U 2013-12-05 2013-12-05 Overwater floating type operation platform pile fixing device Expired - Fee Related CN203625846U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320791516.3U CN203625846U (en) 2013-12-05 2013-12-05 Overwater floating type operation platform pile fixing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320791516.3U CN203625846U (en) 2013-12-05 2013-12-05 Overwater floating type operation platform pile fixing device

Publications (1)

Publication Number Publication Date
CN203625846U true CN203625846U (en) 2014-06-04

Family

ID=50812338

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320791516.3U Expired - Fee Related CN203625846U (en) 2013-12-05 2013-12-05 Overwater floating type operation platform pile fixing device

Country Status (1)

Country Link
CN (1) CN203625846U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695383A (en) * 2013-12-05 2015-06-10 湖北华舟重工应急装备股份有限公司 Pile fixing device of water floating type work platform
CN106429958A (en) * 2016-10-20 2017-02-22 湖北华舟重工应急装备股份有限公司 Water platform hydraulic lifting device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695383A (en) * 2013-12-05 2015-06-10 湖北华舟重工应急装备股份有限公司 Pile fixing device of water floating type work platform
CN106429958A (en) * 2016-10-20 2017-02-22 湖北华舟重工应急装备股份有限公司 Water platform hydraulic lifting device
CN106429958B (en) * 2016-10-20 2018-11-27 湖北华舟重工应急装备股份有限公司 Pier hydraulic lifting apparatus

Similar Documents

Publication Publication Date Title
CN103669216A (en) Steel box girder scattered-splicing sliding device and installation method
CN106120787B (en) A kind of construction method carrying out pile sinking based on pushing tow travelling platform
CN202644575U (en) Pile foundation framework type retaining wall
CN207608812U (en) A kind of anti-device that comes to nothing of laminated rubber bearing
CN203625846U (en) Overwater floating type operation platform pile fixing device
CN101922158A (en) Device and method for integral underpinned vibration isolation of subway underpass building foundation
CN103161334B (en) Overhead parking space capable of accommodating vehicles above green belt and being hidden in non-work state
CN204418654U (en) For the aluminum alloy pattern plate between body of wall
CN104695383A (en) Pile fixing device of water floating type work platform
CN202529677U (en) Machine room-less rope hitch base
CN201952777U (en) Pile wharf steel hoop support structure
CN204455848U (en) The installation positioning system of large-scale steel box-girder
CN206097918U (en) Portable matrix cylinder anechoic sheet structure
CN201554033U (en) Tower crane foundation for deep foundation ditch
CN204475842U (en) Packaged type single side formwork for building
CN208604566U (en) Mobile platform for underwater gate slot inspection
CN203639940U (en) Retaining wall for hydraulic engineering
CN202298621U (en) Tubular pile driving device
CN207625490U (en) A kind of photovoltaic installation equipment waterborne
CN202064364U (en) Earth-rock cofferdam structure capable of filling water in foundation pit
CN201770969U (en) Dam of reservoir
CN205558809U (en) Truck -mounted drilling rig platform
CN203440743U (en) Damping device for bridge
CN203229852U (en) Intercepting ditch in urban underpass
CN204530702U (en) A kind of ships and light boats harbour pile driver

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140604

Termination date: 20191205

CF01 Termination of patent right due to non-payment of annual fee