CN203583886U - Concrete excess material recovery device for high-rise buildings - Google Patents
Concrete excess material recovery device for high-rise buildings Download PDFInfo
- Publication number
- CN203583886U CN203583886U CN201320592491.4U CN201320592491U CN203583886U CN 203583886 U CN203583886 U CN 203583886U CN 201320592491 U CN201320592491 U CN 201320592491U CN 203583886 U CN203583886 U CN 203583886U
- Authority
- CN
- China
- Prior art keywords
- material recovery
- recovery device
- excess material
- tube body
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model discloses a concrete excess material recovery device for high-rise buildings, relates to a concrete excess material recovery device, and aims to provide the concrete excess material recovery device for the high-rise buildings which is convenient to construct, reliable, safe and controllable in quality, saves labor power and improves efficiency. The device comprises a tube body (1), and further comprises a bend and a sedimentation pond (3), wherein the tube body (1) consists of a plurality of sections of long pipes, the last two sections of long pipes of the tube body (1) are connected by the bend, the terminal of the tube body (1) is connected with the sedimentation pond (3) and the sedimentation pond (3) is arranged at the bottom layer of the basement of a floor (2). By adopting a pipeline conveying way, labor cost can be saved, working efficiency can be improved, resources can be saved, quality accidents can be effectively prevented and construction safety can be guaranteed; due to the sedimentation pond, the precipitated waste water can be reused, the dug waste materials can be used for refilling the basement, and the excess material recovery tube body can be recycled, so that the construction cost can be saved.
Description
Technical field
The utility model relates to a kind of concrete surplus material recovery device, particularly a kind of concrete surplus material recovery device for highrise building.
Background technology
In building operations, the concreting of highrise building generally adopts Vehicle loaded pump, by pump line, concrete conveyance is arrived to construction operation layer, also has such problem simultaneously: how the mortar of building front profit pipe is processed with the clout of having built rear cleaning pump line.Common practices is that profit pipe mortar and cleaning clout are transported in the hopper being put in advance on floor, is even directly spread across on flooring, then clears up handling to processing downstairs.First this way is the waste of the resource such as artificial, and has very large security-hidden trouble: if mortar is poured in structure, will lead to quality accident, difficult treatment and often poor effect.
Utility model content
In order to overcome above-mentioned defect, the technical problems to be solved in the utility model is: the concrete surplus material recovery device for highrise building that a kind of easy construction, reliable in quality, safety are controlled, save manpower, raise the efficiency is provided.
The utility model is that the technical scheme that solves the problems of the technologies described above employing is: a kind of concrete surplus material recovery device for highrise building, comprise body, also comprise elbow and settling tank, described body is comprised of multistage long tube, between last two segment length's pipes of body, by elbow, connected, the end of body connects settling tank, and settling tank is located at the basement bottom of floor.
Described long tube height is identical with the story height of its installation.
It between described long tube, is horn mouth connection.
The fixation kit of the shear wall of described body and floor is U-shaped steel bar and setscrew.
Described body is bellows.
Described elbow is 90 degree elbows.
Described settling tank is secondary settling tank.
The beneficial effects of the utility model are:
1, the utility model adopts the mode that pipeline is carried, and has both saved human cost, and improved work efficiency, has saved resource, effectively prevented again quality accident generation, guaranteed construction safety.
2, be provided with settling tank, can secondary utilization after wastewater sedimentation, after digging out, waste material can be used for basement backfill, and clout reclaims body and can reuse, and has saved construction cost.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, illustrate the concrete surplus material recovery device for highrise building described in the utility model.
Fig. 1 is the utility model structural representation;
Fig. 2 is body and floor body of wall fixed structure schematic diagram.
In figure: 1, body, 2, floor, 3, settling tank, 4, U-shaped steel bar, 5, setscrew.
The specific embodiment
As shown in Figure 1-2, a kind of concrete surplus material recovery device for highrise building, comprise body 1,90 degree elbow and settling tanks 3, described body 1 is comprised of multistage long tube, and every segment length manages highly identical with the story height of its installation, adopts horn mouth to connect between long tube, between last two segment length's pipes of body 1, by 90 degree elbows, connected, the end of body 1 connects settling tank 3, and settling tank is located at the basement bottom of floor 2, and the top of body 1 exceeds operation top layer 55-65cm.Described body 1 is bellows, adopts U-shaped steel bar 4 and setscrew 5 and the shear wall of floor 2 to fix.Described settling tank 3 is secondary settling tank.
Concrete installation process: build secondary sedimentation pond by laying bricks or stones at basement bottom, in elevator shaft or the staircase position of selecting body to install, water pipe hole to be provided being installed by shear wall position, avoid punching specially as far as possible; Bellows, according to story height cutting section, is exceeded to work layer 55-65cm and is advisable after installation; With the power drill of 12mm spiral bit in fixedly bellows shear wall position punching; Bellows is installed, between every two sections, with horn mouth, is connected; With the fixing bellows of 80cmU shape steel bar, two ends, in the perforate of setscrew reserved opening, is then fixed U-shaped steel bar and bellows with setscrew.
Claims (7)
1. the concrete surplus material recovery device for highrise building, comprise body (1), it is characterized in that: also comprise elbow and settling tank (3), described body (1) is comprised of long tube, between last two segment length's pipes of body (1), by elbow, connected, the end of body (1) connects settling tank (3), and settling tank (3) is located at the basement bottom of floor (2).
2. the concrete surplus material recovery device for highrise building according to claim 1, is characterized in that: described long tube height is identical with the story height of its installation.
3. the concrete surplus material recovery device for highrise building according to claim 1, is characterized in that: between described long tube, be horn mouth connection.
4. the concrete surplus material recovery device for highrise building according to claim 1, is characterized in that: described body (1) is U-shaped steel bar (4) and setscrew (5) with the fixation kit of the shear wall of floor (2).
5. the concrete surplus material recovery device for highrise building according to claim 1, is characterized in that: described body (1) is bellows.
6. the concrete surplus material recovery device for highrise building according to claim 1, is characterized in that: described elbow is 90 degree elbows.
7. the concrete surplus material recovery device for highrise building according to claim 1, is characterized in that: described settling tank (3) is secondary settling tank.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320592491.4U CN203583886U (en) | 2013-09-25 | 2013-09-25 | Concrete excess material recovery device for high-rise buildings |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320592491.4U CN203583886U (en) | 2013-09-25 | 2013-09-25 | Concrete excess material recovery device for high-rise buildings |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203583886U true CN203583886U (en) | 2014-05-07 |
Family
ID=50581826
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320592491.4U Expired - Fee Related CN203583886U (en) | 2013-09-25 | 2013-09-25 | Concrete excess material recovery device for high-rise buildings |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203583886U (en) |
-
2013
- 2013-09-25 CN CN201320592491.4U patent/CN203583886U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104343239A (en) | Electric threading pipe dark laying construction technology for aerated concrete filler wall punching | |
CN202596175U (en) | Building construction site water recovery system | |
CN103726508A (en) | Prefabricated reinforced concrete board molding bed and construction method | |
CN203583886U (en) | Concrete excess material recovery device for high-rise buildings | |
CN202644519U (en) | Special fixing clamp for preventing reinforcement cage of cast-in-situ bored pile from floating upward | |
CN209443765U (en) | A kind of steel form of the pouring after settlement shear wall for banketing in advance | |
CN202667204U (en) | Cleaning device for concrete-pumping pump tube of high-rise | |
CN216819356U (en) | PVC spool rubber protection stopper | |
CN204000919U (en) | A kind of novel from drainage type tower-crane foundation structure | |
CN203891470U (en) | Fastening bolt for shear wall formwork | |
CN205323369U (en) | High -rise building wastewater collection system recycles device | |
CN201644490U (en) | Concrete placing waste treatment and recovery system | |
CN108457340A (en) | High-building construction washes pump water discharge recycling system | |
CN207920101U (en) | Skyscraper casting concrete delivery pipe cleaning system | |
CN205549702U (en) | Tertiary sedimentation tank of assembled | |
CN204531405U (en) | A kind of traveling formwork device being convenient to the cleaning of stair construction joint position | |
CN104264992B (en) | The construction method of skyscraper pipeline enclosure | |
CN207672711U (en) | A kind of equipment recycling clout in drag pump pump line | |
CN203067936U (en) | High-altitude pipeline installation safe lifting bracket | |
CN207633335U (en) | Telescopic madjack pipe for Pile end post grouting construction | |
CN204311758U (en) | A kind of highrise building concrete surplus material recovery device | |
CN201339218Y (en) | Environmentally-friendly discharge device of waterstone milling pulp | |
CN203769410U (en) | Communication tower mast device | |
CN201358582Y (en) | Shear wall template internal stay used for construction | |
CN205637571U (en) | Do not have outside secret building wall who is detained pipe and pour template |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140507 |