CN203546599U - Pier-side bracket - Google Patents

Pier-side bracket Download PDF

Info

Publication number
CN203546599U
CN203546599U CN201320602605.9U CN201320602605U CN203546599U CN 203546599 U CN203546599 U CN 203546599U CN 201320602605 U CN201320602605 U CN 201320602605U CN 203546599 U CN203546599 U CN 203546599U
Authority
CN
China
Prior art keywords
pier
bracket
side bracket
steel truss
truss girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320602605.9U
Other languages
Chinese (zh)
Inventor
杨梦纯
王跃年
宋伟俊
涂满明
侯爵
马永强
刘晓阳
刘铿
李军堂
许颖强
江湧
叶荣华
国洪光
张鹏
段立波
宋小三
周燕飞
唐明
周瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
1st Engineering Co Ltd of MBEC
Original Assignee
No1 Engineering Co Ltd Zhongtie Bridge Bureau Group
China Railway Major Bridge Engineering Co Ltd
China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No1 Engineering Co Ltd Zhongtie Bridge Bureau Group, China Railway Major Bridge Engineering Co Ltd, China Railway Major Bridge Engineering Group Co Ltd MBEC filed Critical No1 Engineering Co Ltd Zhongtie Bridge Bureau Group
Priority to CN201320602605.9U priority Critical patent/CN203546599U/en
Application granted granted Critical
Publication of CN203546599U publication Critical patent/CN203546599U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a pier-side bracket and relates to the field of bridge construction. The pier-side bracket comprises a plurality of bracket stand columns and horizontal connecting systems. The bracket stand columns arranged on the two sides of a pier body are integrally connected through the horizontal connecting systems. The bracket stand columns are directly supported on a bearing platform, an expanded foundation or a pile foundation. A sliding way beam is arranged on the pier-side bracket and a pier top to enable the pier-side bracket and a bridge pier to form an integral body. A plurality of counter-pulled prestressed finishing tied rebar are arranged on the side surface of the sliding way beam and form an integral body together with pad stones at the pier top. One end of the sliding way beam is welded with an embedded part at the top of the pier body and the other end of the sliding way beam is welded with an embedded part at the top of the bracket stand columns. The pier-side bracket has the advantages that the lifting onto the pier is smoothly realized by adjusting the padding height of front and rear supporting points; since a guide beam at the front end of a steel trussed beam is canceled, the manpower, the material resources and the financial resources can be effectively saved, the requirements on the stress and the stability of the steel trussed beam are met and the steel trussed beam can also be guaranteed to be smoothly lifted onto the pier.

Description

Pier-side bracket
Technical field
The utility model relates to field of bridge construction, particularly relates to a kind of pier-side bracket.
Background technology
Along with developing rapidly of China's economy, need the project of construction increasing, the bridge of Steel truss structure is more and more, more and more higher to safety, quality, the schedule requirement of construction, must employ new technology, new technology, could realize the high-quality, high-quality of infrastructure requirement.At present, steel truss girder sets up the loose method of spelling of general employing to carry out, and for greatly, across, long connection steel truss girder incremental launching construction, generally at steel truss girder front end, nose girder is set, and to alleviate front end cantilever segment weight, improves stress condition and upper pier condition.For the multi-joint steel truss girder construction of multispan, generally first will often across every steel truss girder, with interim rod member, be connected, form a long connection and carry out free cantilever erection or incremental launching construction, needing increases interim connecting rod and the nose girder rod member between a large amount of connection and connection, expends a large amount of human and material resources, financial resources.
Utility model content
The purpose of this utility model is in order to overcome the deficiency of above-mentioned background technology, a kind of pier-side bracket is provided, adjust front and rear fulcrum pad height, realize smoothly upper pier, cancel the nose girder of steel truss girder front end, can effectively save human and material resources, financial resources, meet the stressed and stability requirement of steel truss girder, can also guarantee that steel truss girder goes up pier smoothly.
The utility model provides a kind of pier-side bracket, pier-side bracket comprises bracket column and is laterally connected system, it is to link into an integrated entity by horizontal connection that respectively there are some bracket columns pier shaft both sides, bracket column is directly supported in cushion cap, expands in basis or pile foundation, on pier-side bracket and Dun Ding, be provided with slipway beam, make pier-side bracket and bridge pier form an integral body; Slipway beam side is provided with some and forms integral body to drawing prestressing force essence to prick indented bars or steel strand or rod iron or shaped steel pull bar with the pinner of Dun Ding, slipway beam one end and the welding of pier shaft top built-in fitting, the built-in fitting welding at the other end and bracket column top.
On the basis of technique scheme, described slipway beam horizontal spacing is corresponding with steel truss girder lower chord center, and vertical bridge is greater than each panel length of steel truss girder to length, is respectively greater than half steel truss girder panel length in bridge pier both sides.
On the basis of technique scheme, described slipway beam two ends are connected by bolt or pin joint between pushing up with Dun Ding and bracket.
Compared with prior art, advantage of the present utility model is as follows:
The utility model arranges special pier-side bracket and pier top slipway beam, adjusts front and rear fulcrum pad height, realizes smoothly upper pier, cancel the nose girder of steel truss girder front end, can effectively save human and material resources, financial resources, meet the stressed and stability requirement of steel truss girder, can also guarantee that steel truss girder goes up pier smoothly.
Accompanying drawing explanation
Fig. 1 is the middle pier slipway beam of the utility model embodiment and the structural representation of bracket.
Fig. 2 is the abutment pier slipway beam of the utility model embodiment and the structural representation of bracket.
Fig. 3 is the view of steel truss girder front end maximum cantilever in the utility model embodiment.
Fig. 4 is the view of steel truss girder rear end maximum cantilever in the utility model embodiment.
The specific embodiment
Below in conjunction with drawings and the specific embodiments, the utility model is described in further detail.
Shown in Fig. 1, Fig. 2, the utility model embodiment provides a kind of pier-side bracket and pier top slipway beam, pier-side bracket comprises bracket column and is laterally connected system, it is to link into an integrated entity by horizontal connection that respectively there are some bracket columns pier shaft both sides, bracket column is directly supported in cushion cap, expands in basis or pile foundation, slipway beam is arranged on bracket and Dun Ding is upper, makes bracket and bridge pier form an integral body, together stressed; Each Dun Ding all arranges slideway, upstream and downstream synchronously starts horizontal continuity jack, slipway beam side is provided with some to drawing prestressing force essence to prick indented bars or steel strand or rod iron or shaped steel pull bar, form integral body with the pinner of Dun Ding, slipway beam one end and the welding of pier shaft top built-in fitting, the built-in fitting welding at the other end and bracket column top; Slipway beam horizontal spacing is corresponding with steel truss girder lower chord center, and vertical bridge is greater than each panel length of steel truss girder to length, is respectively greater than half steel truss girder panel length in bridge pier both sides, guarantees joints in steel truss girder pushing tow process, and reserves operating space.Slipway beam two ends are connected by bolt or pin joint between pushing up with Dun Ding and bracket.
Slipway beam is longitudinally divided into three sections, be respectively the slipway beam between Dun Ding and two heel posts, bearing pad stone top slipway beam, after its root slipway beam length composition puts in place according to girder steel pushing tow, remove both sides slipway beam, top lifting jack is installed, after jacking girder steel, remove bearing pad stone top slipway beam, erection support.
For realizing the function of steel truss girder self-balancing pushing tow, the utility model embodiment is provided with special pier-side bracket and pier top slipway beam, guarantees that steel truss girder meets stressed and stability requirement by Equilibrium, and can above pier.Shown in Figure 3, when simply connected twin spans steel truss girder is forward during pushing tow, at first half connection steel truss girder, also do not go up the slipway beam of last Dun Ding and while forming large cantilever position, after later half steel truss girder backend nodes is also supported on the pier top slipway beam of a pier.Now, integrin steel truss girder is being still longitudinally that 2 supports of intermediate pier and rear pier are stressed, and the center of gravity of steel truss girder is still between two strong points, and the coefficient of stability meets safety requirements; Shown in Figure 4, after first half has joined on steel truss girder after the pier top slipway beam of last pier, and later half steel truss girder just departs from, the pier top slipway beam of pier, has formed the front pier of steel truss girder and 2 supports of intermediate pier stressed, and rear end steel truss girder has become large cantilever position.Now, the center of gravity of steel truss girder is still between two strong points, and steel truss girder is stressed and the coefficient of stability meets safety requirements.In steel truss girder pushing tow process, just realized simply connected twin spans steel truss girder self-balancing pushing tow and advanced like this.
Pier-side bracket and slide into beam and possess the function that scoops out pier on steel truss girder and steel truss girder slide plane is provided, the nose girder having arranged at steel truss girder front end while having saved conventional incremental launching construction.After each internode of steel truss girder pushing tow puts in place, by steel truss girder top lifting, the slide block under steel truss girder node moves an internode toward post-tensioning, again steel truss girder is fallen on slide block, starts horizontal continuity jack, by steel truss girder internode of pushing tow forward.So repeatedly, realize constantly slippage forward of steel truss girder.
Those skilled in the art can carry out various modifications and variations to the utility model embodiment; if these are revised and modification belongs within the scope of the utility model claim and equivalent technologies thereof, these modifications and modification are also within protection domain of the present utility model.
The prior art that the content of not describing in detail in manual is known to the skilled person.

Claims (3)

1. a pier-side bracket, pier-side bracket comprises bracket column and is laterally connected system, it is to link into an integrated entity by horizontal connection that respectively there are some bracket columns pier shaft both sides, bracket column is directly supported in cushion cap, expands in basis or pile foundation, it is characterized in that: on pier-side bracket and Dun Ding, be provided with slipway beam, make pier-side bracket and bridge pier form an integral body; Slipway beam side is provided with some and forms integral body to drawing prestressing force essence to prick indented bars or steel strand or rod iron or shaped steel pull bar with the pinner of Dun Ding, slipway beam one end and the welding of pier shaft top built-in fitting, the built-in fitting welding at the other end and bracket column top.
2. pier-side bracket as claimed in claim 1, is characterized in that: described slipway beam horizontal spacing is corresponding with steel truss girder lower chord center, and vertical bridge is greater than each panel length of steel truss girder to length, is respectively greater than half steel truss girder panel length in bridge pier both sides.
3. pier-side bracket as claimed in claim 1 or 2, is characterized in that: described slipway beam two ends are connected by bolt or pin joint between pushing up with Dun Ding and bracket.
CN201320602605.9U 2013-09-27 2013-09-27 Pier-side bracket Expired - Lifetime CN203546599U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320602605.9U CN203546599U (en) 2013-09-27 2013-09-27 Pier-side bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320602605.9U CN203546599U (en) 2013-09-27 2013-09-27 Pier-side bracket

Publications (1)

Publication Number Publication Date
CN203546599U true CN203546599U (en) 2014-04-16

Family

ID=50464736

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320602605.9U Expired - Lifetime CN203546599U (en) 2013-09-27 2013-09-27 Pier-side bracket

Country Status (1)

Country Link
CN (1) CN203546599U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108265634A (en) * 2018-03-12 2018-07-10 中铁建大桥工程局集团第四工程有限公司 A kind of high pier girder steel pushing tow support device and construction method
CN108677741A (en) * 2018-07-27 2018-10-19 中国铁建大桥工程局集团有限公司 A kind of construction method promoting high pier large-tonnage steel bearing
CN109356036A (en) * 2018-11-26 2019-02-19 中铁六局集团有限公司 Middle pier pier-side bracket and its construction method
CN110258293A (en) * 2019-07-22 2019-09-20 中铁大桥局集团有限公司 Cable-stayed bridge steel truss girder main pylon pier top erection construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108265634A (en) * 2018-03-12 2018-07-10 中铁建大桥工程局集团第四工程有限公司 A kind of high pier girder steel pushing tow support device and construction method
CN108265634B (en) * 2018-03-12 2023-09-29 中铁建大桥工程局集团第四工程有限公司 High pier steel beam pushing supporting device and construction method
CN108677741A (en) * 2018-07-27 2018-10-19 中国铁建大桥工程局集团有限公司 A kind of construction method promoting high pier large-tonnage steel bearing
CN109356036A (en) * 2018-11-26 2019-02-19 中铁六局集团有限公司 Middle pier pier-side bracket and its construction method
CN110258293A (en) * 2019-07-22 2019-09-20 中铁大桥局集团有限公司 Cable-stayed bridge steel truss girder main pylon pier top erection construction method

Similar Documents

Publication Publication Date Title
CN103510475B (en) Three main truss steel truss girder simply connected twin spans are without nose girder long distance push construction method
CN109868755B (en) Hanging basket construction method for diamond truss hanging basket and cantilever beam
CN203546599U (en) Pier-side bracket
CN103938552B (en) Steel truss arched bridge self-balancing cantilever construction method and the spacing bearing of main pier
CN103074854A (en) Rear supporting point triangular bracket hanging basket and bridge construction method using same
CN105839549A (en) Truss type cantilever construction hanging basket
CN102535348B (en) Method for tensioning stayed cables of hinged tower cable stayed bridge
CN109736206A (en) Wavelike steel webplate continuous bridge end bay closes up cast-in-place support structure and construction method
CN103898834A (en) Concrete-filled steel tube composite beam and trussed cable tower cable-stayed bridge and construction method thereof
CN202380390U (en) Flexible arch support frame with vault pushing steel truss girder
CN203049471U (en) Rear fulcrum triangular bracket hanging basket
CN207244469U (en) Beam body aids in thrustor
CN205421022U (en) Suspension bridge stiffening beam handing equipment that slides
CN102926330B (en) Installation method of hanging basket suitable for bridge construction
CN205636521U (en) Basket is hung in construction of truss -like cantilever
CN205242238U (en) Be applied to self anchored suspension bridge's main girder structure
CN211815595U (en) Lower tower column tension and compression structure for cable tower
CN101831872B (en) Front and rear fulcrum combined cradle
CN204644869U (en) Drag-line bridge tower anchoring structure
CN207700074U (en) The double limb triangle hanging baskets of continuous rigid frame bridge cantilever beam section construction
CN110219234A (en) Temperature self-adaptation tower Liang Shunqiao is to constant temperature reinforcing pull rod constrained procedure and system
CN203741729U (en) Pre-stress supporting system used for bridge incremental launching construction method
CN203361021U (en) Double-spliced type truss hanging basket
CN202416192U (en) Rhombus truss hanging basket used in bridge construction
CN103132461B (en) For the flexible carrier device of steel truss beam bridge cantilever construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU

Free format text: FORMER OWNER: CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING CO., LTD.

Effective date: 20150225

Owner name: NO.1 ENGINEERING CO., LTD., ZHONGTIE BRIDGE BUREAU

Free format text: FORMER OWNER: NO.1 ENGINEERING CO., LTD., ZHONGTIE BRIDGE BUREAU GROUP GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU

Effective date: 20150225

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 430074 WUHAN, HUBEI PROVINCE TO: 430050 WUHAN, HUBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20150225

Address after: 430050 Hanyang Road, Hanyang District, Hubei, No. 38, No.

Patentee after: CHINA RAILWAY MAJOR BRIDGE ENGINEERING GROUP Co.,Ltd.

Patentee after: 1ST ENGINEERING CO., LTD. OF CHINA RAILWAY MAJOR BRIDGE ENGINEERING GROUP Co.,Ltd.

Address before: 430074 Hubei province Wuhan Dongxin East Lake New Technology Development Zone Road SBI Venture Street No. 6 Building 12 layer

Patentee before: CHINA RAILWAY MAJOR BRIDGE ENGINEERING Co.,Ltd.

Patentee before: 1ST ENGINEERING CO., LTD. OF CHINA RAILWAY MAJOR BRIDGE ENGINEERING GROUP Co.,Ltd.

Patentee before: CHINA RAILWAY MAJOR BRIDGE ENGINEERING GROUP Co.,Ltd.

CX01 Expiry of patent term

Granted publication date: 20140416

CX01 Expiry of patent term