CN203531377U - Lifting mould base for building - Google Patents
Lifting mould base for building Download PDFInfo
- Publication number
- CN203531377U CN203531377U CN201320719440.3U CN201320719440U CN203531377U CN 203531377 U CN203531377 U CN 203531377U CN 201320719440 U CN201320719440 U CN 201320719440U CN 203531377 U CN203531377 U CN 203531377U
- Authority
- CN
- China
- Prior art keywords
- building
- lifting
- platform
- mould base
- climbing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model discloses a lifting mould base for a building, which structurally comprises a main beam (1), and is characterized in that the two sides of the main beam (1) are connected with side beams (15), the side beams (15) and a climbing mechanism (16) are connected, the climbing mechanism (16) is fixedly connected with a climbing rail (10) through an oil cylinder and a choking body (11), the main beam (1) is provided with a reinforcement banding platform (4) and a travelling car (3), the travelling car (3) is connected with a lifting rope (14) which is used for a hoisting template (6), and an inner mould working platform (12) is arranged in the main beam (1). The lifting mould base for the building has the advantages that the lifting mould base for the building combines a building lifting platform and a concrete casting module, a hydraulic climbing mechanism uses remote control and automatic climbing, and the lifting mould base for the building is convenient to operate and high in safety, can achieve continuous construction work, and enables form fixers, steel fixers and concrete workers to operate in parallel and across at the same time period.
Description
Technical field
The utility model relates to a kind of lifting mould bases for building, belongs to the casting equipment of building concrete.
Background technology
In prior art, the cast of concrete construction adopts pouring template mode always, in the casting process of building, uses template layer-by-layer casting, after pouring first floor, uses tower crane moving die plate, then toward upper, until concrete construction casting complete.Shortcoming is the continuous rising along with building, difficulty to workman's operation is increasing, operative employee's safety factor constantly reduces simultaneously, and due to template spacing, promote, need many auxiliary technological equipments, after casting complete, also need artificial modification and installation, each node needs building platform, and having wasted the set-up time has also increased installation cost.
Summary of the invention
The purpose of this utility model is: a kind of lifting mould bases for building is provided.Can more effective guarantee Employee Security, save the step of building platform, save time and cost, improve pouring quality.
The utility model is to form like this: lifting mould bases for building, structure comprises girder, connects curb girder in girder both sides, curb girder is connected with climbing device, described climbing device by oil cylinder, grip body and climb rail and be connected and fixed; On girder, be provided with reinforcing bar binding platform and travelling car, travelling car is connected with the lifting rope that lifting template is used, and at girder, has internal mold working platform.
Above-mentioned lifting mould bases for building arranges respectively the first platform, the second platform and the 3rd platform on climbing device.
The utlity model has following advantage: building lifting operation platform and concrete casting built module are combined, hydraulic climbing mechanism takes Long-distance Control and automatic climbing, easy to operate and safe, after pouring, without tower crane, move moulds, directly adopt hydraulic lifting, tower crane wants safety a lot of relatively, because in tower crane lifting process, need manually to have coordinated, and buildings in general height is higher, along with the lifting of template, operation easier is larger, and safety can not effectively be guaranteed.Adopt hydraulic climbing mechanism, after being ready to climb, only need primer fluid press operation handle can complete the lifting of a whole set of mould bases.Adopt hydraulic climbing mechanism advantage: safety, automaticity is high, raising efficiency is high.Can realize continuous construction operation, same time period form fixer, bar bender, concreter can carry out parallel, cross-operation simultaneously.Concrete appearance is without obvious seam, surfacing, smooth.In construction, next sections template is arranged on the flange of a sections template.Make the concrete can spillage in seam, smooth excessively.
Accompanying drawing explanation
Accompanying drawing 1 is structural representation of the present utility model.
The specific embodiment
Embodiment of the present utility model: sliding form turning device of hydraulic climbing frame for high pier lifting mould bases for building, as shown in Figure 1, structure comprises girder 1, in girder 1 both sides, connects curb girder 15, curb girder 15 stage are connected with climbing device 16, climbing device 16 by oil cylinder, grip body 11 and climb rail 10 and be connected and fixed; Reinforcing bar binding platform 4 and travelling car 3 are set on girder 1, and travelling car 3 is connected with the lifting rope 14 of lifting template 6 use, at girder 1, has internal mold working platform 12.The first platform 7, the second platform 8 and the 3rd platform 9 are set respectively on climbing device 16.Travelling car 3 is connected with the lifting rope 14 of lifting template 6 use, for lifting template 6 to building station.Guardrail 13 is installed on reinforcing bar binding platform 4, safer.Curb girder platform 5 is set on curb girder 15.
The first platform 7, the second platform 8 and the 3rd platform 9, the first platforms 7 are set respectively on climbing device 16 above climbing device 16, the second platform 8 is in the middle of climbing device 16, and the 3rd platform 9 is below climbing device 16, so that more operating platform to be provided.
The course of work is as follows, adopts existing casting craft to build the sections of construction bottom, and after having built the first sections, stripping, installs climbing device 16 and climb rail 10.Regulate oil cylinder, grip body 11, make to climb rail 10 in lifting state, start apply device, allow and climb rail 10 and progressively climb, until the hook of climbing rail 10 be fixed on architectural hanging seat body and be connected, then fix and climb rail 10, regulate oil cylinder, grip body 11 parts, allow climbing device 16 upwards climb, until device rises to the distance of requirement, insert load-bearing wedge, fix mould bases, by travelling car 3 and lifting rope 14 by template 6 handlings to sections to be built, and on each working platform, template is installed, fix after template 6, realize and building for the second time.Repeat above operation, until building casting complete.
Claims (2)
1. a lifting mould bases for building, structure comprises girder (1), it is characterized in that: in girder (1) both sides, connect curb girder (15), curb girder (15) is connected with climbing device (16), described climbing device (16) by oil cylinder, grip body (11) and climb rail (10) and be connected and fixed; On girder (1), be provided with reinforcing bar binding platform (4) and travelling car (3), travelling car (3) is connected with the lifting rope (14) of lifting template (6) use, at girder (1), has internal mold working platform (12).
2. lifting mould bases for building according to claim 1, is characterized in that: the first platform (7), the second platform (8) and the 3rd platform (9) are set respectively on climbing device (16).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320719440.3U CN203531377U (en) | 2013-11-13 | 2013-11-13 | Lifting mould base for building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320719440.3U CN203531377U (en) | 2013-11-13 | 2013-11-13 | Lifting mould base for building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203531377U true CN203531377U (en) | 2014-04-09 |
Family
ID=50417601
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320719440.3U Expired - Fee Related CN203531377U (en) | 2013-11-13 | 2013-11-13 | Lifting mould base for building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203531377U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104847108A (en) * | 2015-03-06 | 2015-08-19 | 中国建筑第八工程局有限公司 | Hydraulic climbing formwork structure and construction method of hydraulic climbing formwork structure |
CN106049855A (en) * | 2016-06-28 | 2016-10-26 | 上海建工集团股份有限公司 | Closed-curve guide groove type full-automatic direction adjustment anti-falling device and using method thereof |
CN108286332A (en) * | 2018-03-12 | 2018-07-17 | 上海建工建集团有限公司 | A kind of concrete of crossing soars aloft beam from climbing monoblock type bylinder system and construction method |
CN109834442A (en) * | 2017-11-28 | 2019-06-04 | 宁波富信模胚有限公司 | A kind of processing method of assembly mould bases |
-
2013
- 2013-11-13 CN CN201320719440.3U patent/CN203531377U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104847108A (en) * | 2015-03-06 | 2015-08-19 | 中国建筑第八工程局有限公司 | Hydraulic climbing formwork structure and construction method of hydraulic climbing formwork structure |
CN106049855A (en) * | 2016-06-28 | 2016-10-26 | 上海建工集团股份有限公司 | Closed-curve guide groove type full-automatic direction adjustment anti-falling device and using method thereof |
CN106049855B (en) * | 2016-06-28 | 2019-01-29 | 上海建工集团股份有限公司 | The full-automatic tuning anti-fall device of closed curve guide type and its application method |
CN109834442A (en) * | 2017-11-28 | 2019-06-04 | 宁波富信模胚有限公司 | A kind of processing method of assembly mould bases |
CN108286332A (en) * | 2018-03-12 | 2018-07-17 | 上海建工建集团有限公司 | A kind of concrete of crossing soars aloft beam from climbing monoblock type bylinder system and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201908664U (en) | Movable trestle bridge invert form board trolley | |
CN201865054U (en) | Hydraulic climbing formwork device for high bridge pier | |
CN202247703U (en) | Sliding form turning device of hydraulic climbing frame for high pier | |
CN105365042A (en) | Manufacturing method of small prefabricated box girder | |
CN203531377U (en) | Lifting mould base for building | |
CN103982200B (en) | Slide rail Mobile steel mould trolley in tunneling boring | |
CN207047691U (en) | A kind of cantilever type movable crosshead | |
CN105839542A (en) | High bridge pier self-lifting outer frame over-form device | |
CN208280592U (en) | Automatic climbing formula hoistway cylinder mould panel assembly | |
CN202064281U (en) | Slip form frame | |
CN214424048U (en) | Template transfer device is pour to aluminum alloy between floor among cast-in-place construction of high-rise building | |
CN107829408B (en) | Rectangular aqueduct construction steel mould trolley | |
CN105887885A (en) | Symmetric rock anchor beam concrete pouring trolley | |
CN105401525A (en) | Cast-in-situ construction method of beam flange plates of acoustic barriers through movable mold base vehicles | |
CN206091283U (en) | Hydraulic pressure is from climbing formula elevartor shaft regularization operation platform | |
CN107791368A (en) | Fixed integral prefabricated box girder formwork structure and its construction method | |
CN112482317A (en) | Door slot second-stage concrete self-climbing slip form pouring system and construction method | |
CN107815971A (en) | High pier is from climbing liquid press to turn over molds system | |
CN205241086U (en) | Template hoist and mount and ann gun carriage of disassembling and using | |
CN204173804U (en) | A kind of inside-climbing tower crane of structural beams bearing-type is installed and climbing structure | |
CN201567784U (en) | City elevated collision-preventing wall formwork and scaffold combination device | |
CN202416191U (en) | Descending-type movable mould frame offshore dismounting main beam lifting device | |
CN203924652U (en) | The operation platform of periphery shear wall between a kind of precast stair | |
CN110714785A (en) | Pipe gallery top plate construction trolley, trolley set and construction method | |
CN104131635A (en) | Method and platform for constructing peripheral shear wall of prefabricated staircase |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140409 Termination date: 20141113 |
|
EXPY | Termination of patent right or utility model |