CN203484036U - Novel spraying device of desulfurizing absorption tower - Google Patents

Novel spraying device of desulfurizing absorption tower Download PDF

Info

Publication number
CN203484036U
CN203484036U CN201320626325.1U CN201320626325U CN203484036U CN 203484036 U CN203484036 U CN 203484036U CN 201320626325 U CN201320626325 U CN 201320626325U CN 203484036 U CN203484036 U CN 203484036U
Authority
CN
China
Prior art keywords
arm
main pipeline
spray equipment
absorption tower
tower wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320626325.1U
Other languages
Chinese (zh)
Inventor
段居伟
王海宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HEBEI DATANG INTERNATIONAL ZHANGJIAKOU THERMAL POWER CO Ltd
Original Assignee
HEBEI DATANG INTERNATIONAL ZHANGJIAKOU THERMAL POWER CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HEBEI DATANG INTERNATIONAL ZHANGJIAKOU THERMAL POWER CO Ltd filed Critical HEBEI DATANG INTERNATIONAL ZHANGJIAKOU THERMAL POWER CO Ltd
Priority to CN201320626325.1U priority Critical patent/CN203484036U/en
Application granted granted Critical
Publication of CN203484036U publication Critical patent/CN203484036U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Treating Waste Gases (AREA)
  • Gas Separation By Absorption (AREA)

Abstract

The utility model relates to a novel spraying device of a desulfurizing absorption tower in an electric power industry. The spraying device is arranged on a horizontal cross section of a desulfurizing absorption tower wall; the spraying device comprises a main pipeline which is arranged in a manner of running through the tower wall, wherein the left and right sides of the main pipeline are symmetrically provided with at least one branch pipe; supporting frames for supporting the pipelines are arranged below the main pipeline and the branch pipes; one end of each branch pipe is connected to the main pipeline and the other end is connected to the tower wall or is erected on the supporting frame; and the branch pipes are connected to the tower wall through supporting pipes. The spraying device, through the devices above, reduces the number of elbows therein and improves strength of the pipeline; and in particular, through the first supporting pipe and the second supporting pipe connected to the tower wall, the fixing points of the pipelines on the tower wall are increased and support strength of the pipeline is effectively improved. The spraying device is simple in structure, obvious in effect, and suitable for popularization and application.

Description

The spray equipment on a kind of Novel desulphurization absorption tower
Technical field
The utility model relates to the spray equipment on a kind of Novel desulphurization absorption tower of power industry.
Background technology
At present, desulfuration absorbing tower is the indispensable production equipment of electricity power enterprise, and the spray equipment of desulfuration absorbing tower is its important component part.If sprinkling equipment is installed the unreasonable phenomenon that easily causes spray equipment to occur heavy wear, even there is the situation forelock lifes such as spray equipment ruptures, subsides, this is just easily because plant issue two causes environmental protection event.
As Fig. 1, for conventional at present a kind of spray equipment, it runs through a main pipeline 2 on the tower wall 1 of desulfuration absorbing tower, described main pipeline 1 divides the cross section on absorption tower for two semicircular equally, the symmetrical both sides of described main pipeline 2, respectively stretch out and be provided with the first arm 21, the second arm 22, the 3rd arm 23, the 4th arm 24 and the 5th arm 25 from left to right, the axis of the relative main pipeline 1 of each arm of main pipeline 1 both sides is symmetrical arranged.On above-mentioned cross section, be evenly equipped with some nozzles 3, each described nozzle 3 is connected with corresponding the first arm 21 or the second arm 22 or the 3rd arm 23 or the 4th arm 24 or the 5th arm 25 respectively.Described pipeline below is provided with bracing frame 4, described bracing frame 4 by two relative main pipeline axis symmetries, at a distance of the vertical beam of certain interval, form with two crossbeams that vertical beam is connected, symmetrical setting.
In order to save pipeline, shorten the mounting distance of pipeline, need to be by the first arm 21 connecting bends, so that the first arm Xiang Tabi center bending; Meanwhile, in order to make arm connect more nozzle 3, need to make the 4th 24 pipe connecting bend, so that the 4th arm bends laterally.
The shortcoming of above-mentioned spray equipment is as follows: 1, to prop up pipe bend many for spraying layer, and without firmly supporting, arm intensity is low, easy fracture; 2, outermost layer shower nozzle and tower span, from too small, are easily washed away Ta Bi.
Based on needing above and shortcoming, the special the utility model that proposes.
Utility model content
The purpose of this utility model is for the spray equipment on a kind of Novel desulphurization absorption tower is provided, and to increase the firm degree of installation of spray equipment, improves the object of spray efficiency.
The technical solution of the utility model is: the spray equipment on a kind of Novel desulphurization absorption tower, described spray equipment is arranged on a horizontal slice of desulfuration absorbing tower wall, described spray equipment comprises: run through the main pipeline that tower wall arranges, the left and right sides of described main pipeline is symmetrically arranged with at least one arm, and described main pipeline and arm below are provided with the bracing frame that pipeline is supported; One end of described arm is connected with main pipeline, and the other end is connected with Ta Bi or takes and put on bracing frame, and described arm is connected with Ta Bi through stay pipe.
Further, the left and right sides of described main pipeline is disposed with respectively the first arm, the second arm, the 3rd arm, the 4th arm and the 5th arm from left to right.
Further, one end of the first described arm is connected with main pipeline through elbow, and described the first arm Xiang Tabi center bending is taken the other end of the first arm and put on bracing frame.
Further, one end of the second described arm, the 3rd arm and the 4th arm is connected with main pipeline respectively, and the other end is connected with tower wall respectively, and middle part is taken and put on bracing frame respectively.
Further, the first end of the 5th described arm is connected with main pipeline, and the second end is through the first stay pipe and the 4th arm; The middle part of the 5th arm bends through elbow Xiang Tabi center; The middle part of the 5th arm is taken and is put on bracing frame.
Further, one end of the first stay pipe is connected with the 4th arm, and the other end is connected with Ta Bi, and middle part is connected with the 5th arm.
Further, on the 5th arm between elbow and first end, be connected with the second stay pipe, the other end of the second described stay pipe is connected with Ta Bi.
Further, be evenly equipped with a plurality of nozzles on cross section, described nozzle is connected with corresponding arm respectively.
Further, the distance between described nozzle and tower wall is greater than 700mm.
Further, the outside of support frame as described above is provided with the protective cover consisting of high temperature resistant material, to avoid causing liquid to cause erosion damage to bracing frame.
The beneficial effects of the utility model are: pass through said apparatus, reduced the quantity of elbow in spray equipment, improved the intensity of pipeline, effectively solved the breakage problem of spraying layer pipeline, increased the distance of outermost nozzle and absorbing tower wall in spray equipment simultaneously, solved the problem that spraying layer nozzle washes away tower wall and brace summer, the maintenance workload of spraying layer has been greatly reduced even non-maintaining, the defect that spraying layer fracture and nozzle come off has also thoroughly been eliminated in this time transformation simultaneously.Meanwhile, set up the first stay pipe and the second stay pipe that are connected with tower wall, the fixing point of pipeline and tower wall is increased, effectively improved the support strength of pipeline.This new structure is simple, and effect is remarkable, suitable promoting the use of.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the utility model is further illustrated.
Fig. 1 is the structural representation of prior art;
Fig. 2 is structural representation of the present utility model;
Fig. 3 is structure for amplifying schematic diagram of the present utility model.
Annex explanation: 1-tower wall, 2-main pipeline, 3-nozzle, 4-bracing frame, the 21-the first arm, the 22-the second arm, the 23-the three arm, the 24-the four arm, the 25-the five arm, the 51-the first stay pipe, the 52-the second stay pipe.
The specific embodiment
As shown in Figure 2, in the present embodiment, introduced the spray equipment on a kind of Novel desulphurization absorption tower, described spray equipment is arranged on a cross section of desulfuration absorbing tower, described spray equipment comprises: run through the main pipeline 2 that tower wall 1 arranges, the left and right sides of described main pipeline 2 is symmetrically arranged with at least one arm, and described main pipeline 2 and arm below are provided with the bracing frame 4 that pipeline is supported; One end of described arm is connected with main pipeline 2, and the other end is connected with tower wall 1 or takes and put on bracing frame 4, and described arm is connected with tower wall 1 through stay pipe.
In the present embodiment, support frame as described above 4 by relative main pipeline 2 axis symmetries, at a distance of the vertical beam of certain interval, the crossbeam with two, vertical beam being connected, vertical beam Central Symmetry arranges relatively forms.In the present embodiment, the outside of support frame as described above 4 is provided with the protective cover consisting of high temperature resistant material, to avoid, because spray can cover bracing frame 4, causing liquid to cause erosion damage to bracing frame 4.
As shown in Figure 3, in the present embodiment, the left and right sides of described main pipeline 2 is disposed with respectively the first arm 21, the second arm 22, the 3rd arm 23, the 4th arm 24 and the 5th arm 25, the symmetrical setting of each arm of both sides from left to right.One end of the first described arm 21 is connected with main pipeline 2 through elbow, and the first described arm 22 is to the 1 center bending of tower wall, the other end of the first arm 21 is taken and put on the vertical beam of bracing frame 4 respective side.Described the second arm 22, the 3rd arm 23 and the 4th arm 24 consist of straight pipeline respectively, one end of the second arm 22, the 3rd arm 23 and the 4th arm 24 is connected with main pipeline 2 respectively, the other end is connected with tower wall 1 respectively, and middle part is taken respectively and put on the vertical beam of bracing frame 4 respective side.The first end of the 5th described arm 25 is connected with main pipeline 2, and the second end is through the first stay pipe 51 and the 4th arm 24; The middle part of the 5th arm 25 bends inwards through elbow; The middle part of the 5th arm 25 is taken and is put on the vertical beam of bracing frame 4 respective side.One end of the first stay pipe 51 is connected with the 4th arm 24, and the other end is connected with tower wall 1, and middle part is connected with the 5th arm 25.On the 5th arm 25 between elbow and first end, be connected with the second stay pipe 52, the other end of the second described stay pipe 22 is connected with tower wall 1.
In the present embodiment, be evenly equipped with a plurality of nozzles 3 on the cross section that above-mentioned pipeline is installed of desulfuration absorbing tower, described nozzle 3 is connected with corresponding the first arm 21 or the second arm 22 or the 3rd arm 23 or the 4th arm 24 or the 5th arm 25 respectively.Preferably, described nozzle 3 equally spaced arranges a circle nozzle 3 along tower wall 1, described outer ring nozzle 3 is greater than 700mm with the distance of tower wall 1, but be less than 1000mm, thereby both avoided spraying liquid in nozzle 3, tower wall 1 was washed away to tower wall 1 corrosion phenomenon causing, guaranteed again nozzle 3 area coverage, guaranteed spraying effect.And in the left and right sides of the second arm 22 or the 3rd arm 23 or the 4th arm 24, a plurality of nozzles 3 are installed respectively equally spacedly, to guarantee all can be sprayed covering in spray column.
It should be noted that; above-mentioned specific embodiment is only exemplary; under above-mentioned instruction of the present utility model, those skilled in the art can carry out various improvement and distortion on the basis of above-described embodiment, and these improvement or distortion drop in protection domain of the present utility model.
It will be understood by those skilled in the art that specific descriptions are above in order to explain the purpose of this utility model, not for limiting the utility model.Protection domain of the present utility model is limited by claim and equivalent thereof.

Claims (10)

1. the spray equipment on a Novel desulphurization absorption tower, described spray equipment is arranged on a horizontal slice of desulfuration absorbing tower wall (1), described spray equipment comprises: run through the main pipeline (2) that tower wall arranges, the left and right sides of described main pipeline (2) is symmetrically arranged with at least one arm, and described main pipeline (2) and arm below are provided with the bracing frame (4) that pipeline is supported;
It is characterized in that: one end of described arm is connected with main pipeline (2), the other end is connected with Ta Bi (1) or takes and put at bracing frame (4) above, and described arm is connected with Ta Bi (1) through stay pipe.
2. the spray equipment on a kind of Novel desulphurization according to claim 1 absorption tower, is characterized in that: the left and right sides of described main pipeline (2) is disposed with respectively the first arm (21), the second arm (22), the 3rd arm (23), the 4th arm (24) and the 5th arm (25) from left to right.
3. the spray equipment on a kind of Novel desulphurization according to claim 2 absorption tower, it is characterized in that: one end of described the first arm (21) is connected with main pipeline (2) through elbow, the bending of described the first arm (21) Xiang Tabi center, takes the other end of the first arm (21) and puts on bracing frame (4).
4. the spray equipment on a kind of Novel desulphurization according to claim 2 absorption tower, it is characterized in that: one end of described the second arm (22), the 3rd arm (23) and the 4th arm (24) is connected with main pipeline (2) respectively, the other end is connected with tower wall (1) respectively, and middle part is taken respectively and put on bracing frame (4).
5. the spray equipment on a kind of Novel desulphurization according to claim 2 absorption tower, is characterized in that: the first end of the 5th described arm (25) is connected with main pipeline (2), and the second end is through the first stay pipe (51) and the 4th arm (24);
The middle part of the 5th arm (25) bends through elbow Ta Bi center; The middle part of the 5th arm (25) is taken and is put on bracing frame (4).
6. the spray equipment on a kind of Novel desulphurization according to claim 5 absorption tower, is characterized in that: one end of the first stay pipe (51) is connected with the 4th arm (24), and the other end is connected with Ta Bi (1), and (250 are connected with the 5th arm at middle part.
7. the spray equipment on a kind of Novel desulphurization according to claim 5 absorption tower, it is characterized in that: on the 5th arm (25) between elbow and first end, be connected with the second stay pipe (52), the other end of described the second stay pipe (52) is connected with Ta Bi (1).
8. according to the spray equipment on the arbitrary described a kind of Novel desulphurization absorption tower of claim 1 to 7, it is characterized in that: on cross section, be evenly equipped with a plurality of nozzles (3), described nozzle (3) is connected with corresponding arm respectively.
9. the spray equipment on a kind of Novel desulphurization according to claim 8 absorption tower, is characterized in that: the distance between described nozzle (3) and tower wall (1) is greater than 700mm.
10. the spray equipment on a kind of Novel desulphurization according to claim 1 absorption tower, is characterized in that: the outside of support frame as described above (4) is provided with the protective cover consisting of high temperature resistant material.
CN201320626325.1U 2013-10-11 2013-10-11 Novel spraying device of desulfurizing absorption tower Expired - Fee Related CN203484036U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320626325.1U CN203484036U (en) 2013-10-11 2013-10-11 Novel spraying device of desulfurizing absorption tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320626325.1U CN203484036U (en) 2013-10-11 2013-10-11 Novel spraying device of desulfurizing absorption tower

Publications (1)

Publication Number Publication Date
CN203484036U true CN203484036U (en) 2014-03-19

Family

ID=50254898

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320626325.1U Expired - Fee Related CN203484036U (en) 2013-10-11 2013-10-11 Novel spraying device of desulfurizing absorption tower

Country Status (1)

Country Link
CN (1) CN203484036U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105169915A (en) * 2015-09-18 2015-12-23 江苏华星电力环保设备有限公司 Novel desulphurization absorption tower
CN112978635A (en) * 2021-02-24 2021-06-18 广东大唐国际雷州发电有限责任公司 Lifting device for operation platform of absorption tower
CN114887373A (en) * 2022-06-14 2022-08-12 江苏新宏大集团有限公司 Split type modularization towards sediment device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105169915A (en) * 2015-09-18 2015-12-23 江苏华星电力环保设备有限公司 Novel desulphurization absorption tower
CN112978635A (en) * 2021-02-24 2021-06-18 广东大唐国际雷州发电有限责任公司 Lifting device for operation platform of absorption tower
CN114887373A (en) * 2022-06-14 2022-08-12 江苏新宏大集团有限公司 Split type modularization towards sediment device

Similar Documents

Publication Publication Date Title
CN203484036U (en) Novel spraying device of desulfurizing absorption tower
CN104857836A (en) Flue gas desulfurization absorber interactive spray system
CN203329849U (en) Spray system of wet-type electric precipitator
CN203458973U (en) Spray pipe device
CN204865457U (en) Wet flue gas desulfurization carries torrent pipe bars device and desulfurization absorption tower of effect
CN206810022U (en) A kind of desulfuration absorbing tower shower group support meanss
CN203546242U (en) Spraying and humidifying device for opener
CN204469544U (en) A kind of spraying device of desulfurizing tower
CN204816209U (en) Desulfurizing tower spray piping strutting arrangement
CN103590147A (en) Mist spray humidifying device of opener
CN103469234A (en) Surface watermark control device for acid pickling of hot-rolled strip steel and watermark control method
CN202855544U (en) Novel high-tension power capacitor fixing bracket
CN103521472A (en) Aluminum profile cleaning device with multi-angle nozzles
CN201643975U (en) Spraying device of circulating slurry for desulfurizing flue gas
CN203508466U (en) Aluminum profile cleaning device provided with multi-angle nozzles
CN203253325U (en) Liquid distributor convenient to clean and maintain
CN205700112U (en) A kind of desulfurization washing tower shower
CN204891596U (en) Wet flue gas desulfurization tower entry flue gas equipartition device
CN204672130U (en) The interactive spray system of fume desulfurating absorption tower
CN106311105A (en) Exhaust gas reaction device
CN203701555U (en) Movable type pipe truss installation platform
CN219471378U (en) Overhauling channel of roof solar equipment
CN205142677U (en) Formula spray tube swayd frame in one minute two
CN204601980U (en) For the spray bracket of desulfurizing tower inner bag
CN209828669U (en) Spray layer of flue gas desulfurization absorption tower

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140319

Termination date: 20211011

CF01 Termination of patent right due to non-payment of annual fee