CN203417748U - Separation ship for beach placer - Google Patents

Separation ship for beach placer Download PDF

Info

Publication number
CN203417748U
CN203417748U CN201320179349.7U CN201320179349U CN203417748U CN 203417748 U CN203417748 U CN 203417748U CN 201320179349 U CN201320179349 U CN 201320179349U CN 203417748 U CN203417748 U CN 203417748U
Authority
CN
China
Prior art keywords
deck
separation
ship
ore
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320179349.7U
Other languages
Chinese (zh)
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mcc Shenkan Qinghuangdao Design Institute Co ltd
Shen Kan Engineering and Technology Corp of MCC
Original Assignee
Qinhuangdao Engineering Co Ltd Is Surveyed In Middle Smelting Shen
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qinhuangdao Engineering Co Ltd Is Surveyed In Middle Smelting Shen filed Critical Qinhuangdao Engineering Co Ltd Is Surveyed In Middle Smelting Shen
Priority to CN201320179349.7U priority Critical patent/CN203417748U/en
Application granted granted Critical
Publication of CN203417748U publication Critical patent/CN203417748U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model discloses separation ship equipment applicable to exploitation and separation of a beach placer. The separation ship equipment comprises a ship body structure, a mineral separation and production process system, a power generation system, a power distribution and control system, a material (including crude ore sand, rough concentrates, slag, tailings and water) conveying system, office life and ancillary facilities and the like. The separation ship equipment is simple in process implementation, compact and reasonable in spatial structure, free of external power supplies, convenient to move, capable of giving consideration to both production and living and saving investments, low in operation cost, high in mineral separation efficiency, good in separation effect, most applicable to beach placer bodies, free of resource waste and capable of exploiting the beach placer bodies completely and ensuring that beach placer resources are used fully; and meanwhile, landforms can be restored quickly, so that the natural environment is protected to the maximum extent.

Description

A kind of beach placer ore dressing ship
Technical field
The utility model belongs to mine ore dressing technical field, the Mineral Dressing Process that exploitation utilizes for beach placer especially.
Background technology
The many coastal state's along the coastlines in the world have a large amount of iron ore deposits, develop beach placer resource, the artificial shovel of original adoption digs elutriation, conventional is the simple and crude ore dressing ship with fishing boat or small-sized bullk reform now, directly screening and preparation equipment are erected on fishing boat, although this way investment economizes, but production capacity and production efficiency are extremely low, production operation condition is poor, the transportation problem, confession distribution problem, overhaul of the equipments problem, the problem concerning life that are difficult to solve a large amount of ore pulps, this way is difficult to realize extensive mineral processing production.Especially in the area that there is no externally fed condition, outside land transport condition, production technology feasibility is less.
The raw ore slurry that mining dredger hinge drinks up generally contains the foreign material such as great Liang Zuo grass, tree root, if do not separated before entering ore-dressing technique, certainly will greatly affect ore dressing effect, after separating also will be got rid of outside hull in time, otherwise cause accumulation, in research process, carry out the selection of several screening modes and marker method, effect is not clearly, finally attempted belt feeder discharge, allow foreign material waste residue have compass screen surface to turn and be discharged to belt feeder, by belt feeder, be transported to stern and dump ashore, do not affect the clean of mining lake lake surface.
Mining area, most beach is far away apart from city, lacks external power source, and some ore deposits are placed on generating equipment on the bank, and electric power is by cable transfer to ore dressing ship, and because ore dressing ship is mobile, transmission distance changes, and electric power is carried both inconvenient, and power consumption is also large.If placed aboard ship, electricity generation system (comprising generating set, boiler unit, air compressor plant, cooler, emergent unit, fuel oil supply unit, transformer, oil tank etc.) weight of equipment and take up room larger, in the limited space of hull, arrange more difficultly, need to solve hull draft problem, gravity balance problem, hull stable problem, space Layout Problem.If the overweight drinking water of hull is too dark, hull is easily stranded; If each forms module, put bias, hull easily topples; The beach stormy waves of holding concurrently is larger, and hull is too high, is subject to stormy waves and threatens.Overcome the above problems; so all wts such as equipment, material, pipeline will be carried out to three-dimensional planning; Spatial Coupling distributes; upper lower leaf, front and back subdivision, by functional module, divide and distribute usage space, making hull center of gravity occupy hull center, compressing hull height and space size as far as possible; allow hull meet production and application requirement; have and can accomplish that hull space minimizes, function is distributed rationalization, uses safe, energy-conserving and environment-protective.
Be used at present the simple and easy ore dressing ship of production and there is no indoor office recreating facility and dining room, dining room, while running into wind and rain, direct labor hides nowhere, work under bad environment, operate dangerous, run into severe weather conditions and want breaks in production, the utility model comprehensive division hull usage space, make full use of hold as dining room, dining room, utilize the space of top layer deck boiler unit side as office lobby, multideck and surrounding enclosed structure are that hull forms enclosure space, have improved work production environment, have improved production efficiency.
Summary of the invention
The purpose of this utility model overcomes the weak point of existing simple and crude ore dressing ship, provide a kind of Process configuration compact and reasonable, easy to operate, equipment moving flexibly, investment saves, operating cost is low, beneficiating efficiency is high, sorting result is good, the most applicable to beach placer body, can realize the complete exploitation of beach placer body, do not waste resource, guarantee making full use of beach placer resource; Can recover rapidly landforms, protected to greatest extent natural environment simultaneously.
The technical scheme that realizes foregoing invention comprises: Ship Structure, ore-dressing technique system, electricity generation system, distribution and control system, material (comprising former ore in sand form, rough concentrate, slag, mine tailing, water) induction system, office life and affiliated facility etc.
Owing to having adopted technique scheme, compared with prior art the utility model has the following advantages:
1. technology arrangement is flexible, equipment configuration is compact, save space, security of operation is stable, easy to operate;
2. occupation of land is little, saves the energy, and environmental protection condition is good, and work situation is good;
3. effectively improve technique and working condition;
4. slag and mine tailing directly enter behind mining lake, recover former sandy beach, eliminate environmental pollution;
5. handling safety.
Accompanying drawing explanation
Fig. 1 is three layers of deck plan
Fig. 2 is Tween deck plane
Fig. 3 is one deck deck plan
Fig. 4 is hold plane
Fig. 5 is profilograph
Fig. 6 is drawing in side sectional elevation
Fig. 7 is equipment image contact figure
In above-mentioned figure: 1-divides ore collecting box, 2-sieves unit, 3-magnetic separation unit, 4-concentrate mine tailing sub-sand pump assembly, the total sand pump unit of 5-concentrate, 6-slag belt conveyer, 7-crane, 8-electric block, 9-generating set, 10-boiler unit, 11-distribution electric control chamber, 12-oil tank chamber, 13-kitchen and dining room, 14-maintenance is across, the 15-lobby of handling official business, 16 stair, 17-collection stock tank.
The specific embodiment
The utility model overall structure is as shown in Fig. 1 ~ 6.
(1) ore-dressing technique main equipment is arranged
Ore dressing ship is by formations such as hull, ore-dressing technique system, electricity generation system, distribution and control system, material (comprising former ore in sand form, rough concentrate, mine tailing, slag, water) induction system, office life and affiliated facilities.Ore dressing ship divides four layers from top to bottom, divides three cabins to arrange from front to back.
1) third deck: front deck is boiler unit 10 and office lobby 15, middle deck is minute ore collecting box 1 and screening unit 2, two layers of overhead of deck store, for maintenance is across 14.
2) second deck: front deck is distribution electric control chamber 11, middle deck is magnetic separation unit 3 and slag belt conveyer 6, deck store is for maintenance is across 14 and slag belt conveyer 6.
3) ground floor deck: front deck bottom overhead, middle deck is concentrate mine tailing sub-sand pump assembly 4, deck store bottom overhead is space for maintenance 14.
4) hold: front deck is that generating set 9, middle deck are that oil tank chamber 12 and kitchen and dining room 13, deck store are the total sand pump unit 5 of concentrate.
The technology arrangement distribution of hull space sees attached list 1.
Figure DEST_PATH_IMAGE002
(2) electrical equipment is arranged
Generating set 9, maintenance Kua14, air compressor plant, fuel oil supply unit are arranged in bottom front deck; The electrical equipments such as auxiliary engine room and transformer room, switch cubicle, centralized arrangement is at the second deck of front deck.
For guaranteeing power supply reliability, adopt double circuit power supply; For guaranteeing power supply safety, adopt whole ship to unify ground connection, earth connection is guided on the bank with concentrate pipeline, on the coast arranging movable grounding box; On ship top, arrange lighting proof strip or lightning conduction; Insulating Design is done in hull railing, control room, lobby etc.On ore dressing ship, cable adopts along cable testing bridge or wears the bright system of laying of steel pipe; Workshop adopts metal halide lamp illumination, and ore dressing ship Dynamo Room is all consumer distribution on ore dressing ship.
(3) ore dressing ship production water supply system
Ore dressing ship industrial water is mainly magnetic separation water, directly extracts mining lake water.At ore dressing depth, enter suction pump suction hose arranged around stainless steel screen pack in lake to carrying out coarse filtration, on ship, the high equipment water of water quality requirement is filtered as water seal water carries out essence.Industrial water water pump adopts VFC.
Ore dressing marine railway tailings stock pump, this pump is joined grit water separator, and water seal water can be directly with mining lake water.
(4) layout of miscellaneous equipment
According to the layout of front deck, middle deck, deck store, arrange the layout of miscellaneous equipment, pipeline, circuit, thick pipeline, heavier pipeline, in himself weight and pipe after medium-weight, square body is arranged symmetrically with, and guarantees that hull center of gravity is not inclined to one side as calculated.
(5) Ship Structure and structure
Hull superstructure adopts portal frame, and on ship, workshop inner platform adopts steel-frame structure, and hull end face adopts real abdomen girder steel, steel purlin bar, composite laminboard, colored steel vertical hinged door.
Art production process summary:
Former ore in sand form adopts hinge suction method by the ore in sand form sucking-off in lake, ore deposit through mining dredger, through the vertical tube of ore dressing ship front end outside and the horizontal pipe at top, is transported in minute ore collecting box 1 on ore dressing ship, flows automatically to screening unit 2 remove the gred through a minute ore collecting box; Slag (Zuo on sieve grass, tree root etc.) through belt feeder 6, be transported on the ore deposit loke shore of ore dressing quarter and transport; Undersize ore mortar flows automatically to magnetic separation unit 3 and carries out magnetic concentration working.Wherein: the concentrate that magnetic separation unit is selected flows automatically to and collects in stock tank 17, then is transported on the bank and is filtered and store up by lake surface movement pipeline, land booster station through the total sand pump unit 5 of concentrate.Mine tailing, through goaf, lake, last person's system charge ore deposit, recovers seabeach or builds a dam.Ore dressing ship is established mine tailing gravity tank, and gravity tank connects a pipe gravity flow pipeline, and the direct Artesian Drainage of a part of mine tailing is to underwater; Part mine tailing is delivered to Fu Tian sandy beach, bank or is built breakwater by pipeline by 4 pressurizations of slag stock pump.
The walking of ore dressing ship drags walking by the hoisting system on mining dredger.
This mineral processing production system process is reasonable, equipment moving convenient, cost is low, operating cost is low, beneficiating efficiency is high, sorting result is good, the most applicable to beach placer body, can realize the complete exploitation of beach placer body, not waste and do not lose resource, guarantee making full use of beach placer resource; Mining lake along the coastline moves, and selecting and purchasing ship can move freely again on mining lake, maneuverability, and Bian Caibian selects limit to fill out again, recovers rapidly landforms, has protected to greatest extent natural environment, takes into account the economic benefit of knowing clearly, social benefit, environmental benefit simultaneously.This technique can wide popularization and application.
Mineral processing circuit is shown in Fig. 7.

Claims (1)

1. beach placer ore dressing ship is characterised in that: ore dressing ship comprises four layers of deck from top to down, be followed successively by third deck, second deck, ground floor deck and hold, every layer of deck on described four layers of deck comprises three sections of cabins from front to back, is followed successively by front deck, middle deck and deck store;
The front deck of described third deck is provided with boiler unit and office lobby, and middle deck is provided with minute ore collecting box and screening unit, two layers of overhead of deck store be provided with overhaul across;
The front deck of described second deck is provided with distribution electric control chamber, and middle deck is provided with magnetic separation unit and slag belt conveyer, deck store be provided with described maintenance across with described slag belt conveyer;
The front deck bottom overhead on described ground floor deck, middle deck is provided with concentrate mine tailing sub-sand pump assembly, deck store bottom overhead be provided with maintenance across;
The front deck of described hold is provided with generating set, and middle deck is provided with oil tank chamber and kitchen and dining room, and deck store is provided with the total sand pump unit of concentrate;
Wherein, divide ore collecting box to be connected to the total sand pump unit of concentrate by screening unit, magnetic separation unit;
Divide ore collecting box to be connected to slag belt conveyer by screening unit.
CN201320179349.7U 2013-04-11 2013-04-11 Separation ship for beach placer Expired - Lifetime CN203417748U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320179349.7U CN203417748U (en) 2013-04-11 2013-04-11 Separation ship for beach placer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320179349.7U CN203417748U (en) 2013-04-11 2013-04-11 Separation ship for beach placer

Publications (1)

Publication Number Publication Date
CN203417748U true CN203417748U (en) 2014-02-05

Family

ID=50016853

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320179349.7U Expired - Lifetime CN203417748U (en) 2013-04-11 2013-04-11 Separation ship for beach placer

Country Status (1)

Country Link
CN (1) CN203417748U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104923397A (en) * 2014-03-20 2015-09-23 北京中凯宏德科技有限公司 Ore mining and dressing integrated ship
CN106179738A (en) * 2016-08-26 2016-12-07 中冶北方(大连)工程技术有限公司 The ore-sorting system of a kind of iron content sea sand and ore-dressing technique
CN107661814A (en) * 2017-10-31 2018-02-06 中冶北方(大连)工程技术有限公司 One kind screening magnetic separation mill ore magnetic selection flow sheet equipment arrangement system
CN108104525A (en) * 2017-12-14 2018-06-01 中国航空规划设计研究总院有限公司 A kind of blocking " U " font solid pharmaceutical preparation workshop
WO2019061672A1 (en) * 2017-09-26 2019-04-04 北京中凯宏德科技有限公司 Ore mining and dressing integrated ship
WO2021201188A1 (en) * 2020-04-03 2021-10-07 川崎重工業株式会社 Floating boiler facility

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104923397A (en) * 2014-03-20 2015-09-23 北京中凯宏德科技有限公司 Ore mining and dressing integrated ship
CN106179738A (en) * 2016-08-26 2016-12-07 中冶北方(大连)工程技术有限公司 The ore-sorting system of a kind of iron content sea sand and ore-dressing technique
WO2019061672A1 (en) * 2017-09-26 2019-04-04 北京中凯宏德科技有限公司 Ore mining and dressing integrated ship
CN107661814A (en) * 2017-10-31 2018-02-06 中冶北方(大连)工程技术有限公司 One kind screening magnetic separation mill ore magnetic selection flow sheet equipment arrangement system
CN107661814B (en) * 2017-10-31 2023-08-22 中冶北方(大连)工程技术有限公司 Screening-magnetic separation-ore grinding-magnetic separation flow equipment arrangement system
CN108104525A (en) * 2017-12-14 2018-06-01 中国航空规划设计研究总院有限公司 A kind of blocking " U " font solid pharmaceutical preparation workshop
WO2021201188A1 (en) * 2020-04-03 2021-10-07 川崎重工業株式会社 Floating boiler facility

Similar Documents

Publication Publication Date Title
CN203417748U (en) Separation ship for beach placer
CN103523183B (en) Power supply platform on removable half submerged floating Multifunction fishing
CN107460858B (en) Multifunction fishing upper mounting plate
CN104118539B (en) Large multifunctional deep sea floating base
CN106089543A (en) Ultra-large type water-power plant
CN102878007B (en) (Ultra-large) hydroelectric power plant
KR20100027087A (en) For the ocean a generating plant in global village zero calmity tidal power generator used with in it's a level pipes seesow type
US11274648B2 (en) Pumped storage system with waterfall control subsystem
CN105173019A (en) Waterborne refuse collection ship
CN206636562U (en) A kind of discontinuous deep sea mineral resources mining system
CN101049854A (en) Waterborne multi purpose spatial transportation platform
CN203594452U (en) Mining device for oceanic mineral resources
CN201774482U (en) Offshore photovoltaic power generation system
CN113431583B (en) Dynamic blocking device and method for sediment diffusion problem caused by submarine mining
CN111203313B (en) Coastal zirconium titanium ore sand mining and selecting platform and mining and selecting process thereof
CN112127894B (en) Deep and remote sea distributed mineral development system based on seabed production operation platform
CN205034304U (en) Refuse collection ship on water
CN108313218A (en) A kind of marine mining and ore dressing platform
CN109552569B (en) Integrated ship for mining and ore dressing
Fard et al. Investigation of AC and DC power distributions to seafloor mining equipment
KR20170043487A (en) Marine steel works with metal smelting furnaces and construction machinery
KR20140005836A (en) Peace retained reclamation construction machinery processing unit which is equipped with
CN211755937U (en) Coastal zirconite sand mining and selecting platform
KR20170081589A (en) Typhoon Disaster Discharge Distribution Input Device
CN209324120U (en) Scalable mechanical return water tower

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 066001 No. 57 Yingbin Road, Haigang District, Qinhuangdao City, Hebei Province

Patentee after: MCC SHENKAN QINGHUANGDAO DESIGN INSTITUTE CO.,LTD.

Address before: 066001 No. 57 Yingbin Road, Haigang District, Qinhuangdao City, Hebei Province

Patentee before: SHEN KAN QINHUANGDAO ENGINEERING & TECHNOLOGY CORPORATION, MCC

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20190130

Address after: 110117 No. 300 Baita Third Street, Hunnan District, Shenyang City, Liaoning Province

Patentee after: SHEN KAN ENGINEERING & TECHNOLOGY CORPORATION, MCC

Address before: 066001 No. 57 Yingbin Road, Haigang District, Qinhuangdao City, Hebei Province

Patentee before: MCC SHENKAN QINGHUANGDAO DESIGN INSTITUTE CO.,LTD.

TR01 Transfer of patent right
CX01 Expiry of patent term

Granted publication date: 20140205

CX01 Expiry of patent term