CN203175134U - Truss used for lifting electric transmission line tower connecting legs - Google Patents
Truss used for lifting electric transmission line tower connecting legs Download PDFInfo
- Publication number
- CN203175134U CN203175134U CN 201320098675 CN201320098675U CN203175134U CN 203175134 U CN203175134 U CN 203175134U CN 201320098675 CN201320098675 CN 201320098675 CN 201320098675 U CN201320098675 U CN 201320098675U CN 203175134 U CN203175134 U CN 203175134U
- Authority
- CN
- China
- Prior art keywords
- angle steel
- transmission line
- base
- main material
- truss
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Electric Cable Installation (AREA)
Abstract
本实用新型涉及一种桁架,特别涉及一种用于升高输电线路塔接腿的桁架,属于电力系统装置领域,包括安装基础台,其特征在于:还包括四条支撑横材,四条支撑横材首尾连接形成一个正方形结构,相邻两条支撑横材的交点处安装支撑基座,支撑基座下端安装主材角钢,主材角钢下端安装固定基座,固定基座安装在安装基础台上。本实用新型不但解决了原输电线路通道内杆塔的运行限距问题,保证了线路安全运行,而且在原有输电线路塔的桩位基础上提升加高,无需要征地改变路径,额外增加成本生产新的输电线路塔,架设操作方便、省时省力、可安全运行,架设施工方法实施简单可靠、架设难度小、灵活性好、实用性强。
The utility model relates to a truss, in particular to a truss for raising transmission line tower legs, which belongs to the field of electric power system devices, and includes an installation foundation platform, and is characterized in that it also includes four supporting beams, four supporting beams The end-to-end connection forms a square structure, and the supporting base is installed at the intersection of two adjacent supporting beams, the main material angle steel is installed at the lower end of the supporting base, the fixed base is installed at the lower end of the main material angle steel, and the fixed base is installed on the installation foundation platform. The utility model not only solves the operation distance limit problem of the tower in the channel of the original transmission line, but also ensures the safe operation of the line, and increases the height on the basis of the pile position of the original transmission line tower, without the need to requisition the land to change the path, and increase the cost to produce a new The transmission line tower is easy to erect and operate, saves time and effort, and can be operated safely. The erection construction method is simple and reliable, the erection difficulty is small, the flexibility is good, and the practicability is strong.
Description
技术领域 technical field
本实用新型涉及一种桁架,特别涉及一种用于升高输电线路塔接腿的桁架,属于电力系统装置领域,主要用于输电线路塔杆塔的升高。 The utility model relates to a truss, in particular to a truss for raising the legs of transmission line towers, which belongs to the field of power system devices and is mainly used for raising power transmission line towers. the
背景技术 Background technique
目前由于很多地区的城镇化建设的建筑物、建设道路、铁路等高度逐渐增高,导致原输电线路塔的对地距离、限距不够,需要升高。但是输电线路塔的尺寸和档距必须满足一定的要求,建筑物、地面、公路及其他架空线路之间、导线与避雷线之间均应保持必要的最小安全限距,如果重新架设新的输电线路塔,则架设位置土地资源紧张非常难确定,若在原位置重新更换新的输电线路塔,则由于输电线路塔的数量多,分布面广,自然条件及地形条件复杂多变,不利于使用大型机具运输和架设,费时费力,增加成本。 At present, due to the gradual increase in the height of buildings, roads, and railways in urbanization construction in many areas, the distance to the ground and the limit distance of the original transmission line tower are not enough, and they need to be raised. However, the size and span of transmission line towers must meet certain requirements. Necessary minimum safety distances should be maintained between buildings, ground, roads and other overhead lines, and between conductors and lightning conductors. For transmission line towers, it is very difficult to determine the location where land resources are tight. If new transmission line towers are replaced at the original location, due to the large number of transmission line towers, wide distribution, complex and changeable natural conditions and terrain conditions, it is not conducive to the use of large-scale transmission line towers. Equipment transportation and erection are time-consuming and labor-intensive, increasing costs. the
实用新型内容 Utility model content
根据以上现有技术的不足,本实用新型要解决的技术问题是:提供一种结构简单合理、成本低、操作方便、省时省力、可安全运行的用于升高输电线路塔接腿的桁架。 According to the deficiencies of the prior art above, the technical problem to be solved by the utility model is: to provide a truss for raising transmission line tower legs with simple and reasonable structure, low cost, convenient operation, time-saving and labor-saving, and safe operation . the
本实用新型解决其技术问题所采用的技术方案是: The technical scheme that the utility model solves its technical problem adopts is:
所述的用于升高输电线路塔接腿的桁架,包括安装基础台,其特征在于:还包括四条支撑横材,四条支撑横材首尾连接形成一个正方形结构,相邻两条支撑横材的交点处安装支撑基座,支撑基座下端安装主材角钢,主材角钢下端安装固定基座,固定基座安装在安装基础台上。 The truss for raising transmission line tower legs includes an installation foundation platform, and is characterized in that it also includes four support beams, the four support beams are connected end to end to form a square structure, and the two adjacent support beams The supporting base is installed at the intersection, the main material angle steel is installed at the lower end of the supporting base, the fixed base is installed at the lower end of the main material angle steel, and the fixed base is installed on the installation foundation platform. the
所述的用于提升输电线路塔接腿的桁架,用于输电线路塔接腿的原桩位提升加高,解决了架设新的输电线路塔接腿的尺寸和档距的问题,保证了线路运行安全距离,在原有输电线路塔的基础上提升,无需要占地和青赔,额外增加成本开挖新的输电线路塔基坑和基础浇注,结构简单合理、架设操作方便、省时省力、安全运行。 The truss used to lift the tower legs of the transmission line is used to lift and heighten the original pile position of the tower legs of the transmission line, which solves the problem of the size and span of the tower legs of the erection of a new transmission line, and ensures that the line The operation safety distance is improved on the basis of the original transmission line tower, no land occupation and green compensation are required, and additional cost is added to excavate the foundation pit and foundation pouring of the new transmission line tower. The structure is simple and reasonable, the erection operation is convenient, time-saving and labor-saving, safe operation. the
其中优选方案是: The preferred options are:
所述的支撑基座包括一个基座钢板和两块垂直交错相接的固定加劲钢板,固定加劲钢板垂直基座钢板设置,两块固定加劲钢板上设置○型圆孔。 The support base includes a base steel plate and two vertically interlaced fixed stiffened steel plates, the fixed stiffened steel plate is arranged vertically to the base steel plate, and ○-shaped round holes are arranged on the two fixed stiffened steel plates. the
所述的主材角钢的两侧面成90度角,主材角钢两侧面的上部和下部都设置有○型圆孔,固定加劲钢板上的○型圆孔与主材角钢两侧面的○型圆孔相对应; The two sides of the main material angle steel form an angle of 90 degrees, and the upper and lower parts of the two sides of the main material angle steel are provided with ○-shaped round holes. Corresponding to the hole;
所述的支撑基座的结构与固定基座的结构相同,成镜像结构安装在主材角钢的两端。 The structure of the support base is the same as that of the fixed base, and the mirror image structure is installed at both ends of the main material angle steel. the
支撑基座的支撑钢板设计的大小与原输电线路塔接腿的底部支撑板相同,方便输电线路 塔的稳定、安装方便,设置两个垂直交错相接固定加劲钢板和两侧面成90度角主材角钢相对应,安装方便,稳定性好,固定基座与支撑基座结构相同,固定基座与安装基础台相连接,固定基座可以方便的与主材角钢相固定,设计结构简单合理、安装方便、实用性高。 The size of the supporting steel plate supporting the base is designed to be the same as the bottom supporting plate of the original transmission line tower leg, which is convenient for the transmission line tower to be stable and easy to install. Two vertically staggered fixed stiffening steel plates are set and the two sides are at an angle of 90 degrees. Corresponding to the angle steel of the main material, it is easy to install and has good stability. The structure of the fixed base is the same as that of the support base. The fixed base is connected with the installation base. Easy installation and high practicability. the
所述的四条支撑横材中间位置都设置联板,联板连接第一加固角钢斜材的一端,第一加固角钢斜材的另一端连接固定基座。增强桁架侧面的稳定性。 The middle positions of the four supporting beams are provided with connecting plates, the connecting plates are connected to one end of the first reinforced angle steel oblique material, and the other end of the first reinforced angle steel oblique material is connected to the fixed base. Enhance the stability of the sides of the truss. the
所述的第一加固角钢斜材的中间设置连接第二加固角钢斜材和第三加固角钢斜材的一端,第二加固角钢斜材的另一端与主材角钢的中间位置相连接,第三加固角钢斜材的另一端连接支撑基座。 The middle of the first reinforced angle steel oblique material is arranged to connect one end of the second reinforced angle steel oblique material and the third reinforced angle steel oblique material, the other end of the second reinforced angle steel oblique material is connected with the middle position of the main material angle steel, and the third The other end of the reinforcement angle steel slant is connected to the support base. the
所述的主材角钢两侧相邻的两根第一加固角钢斜材中间位置通过第四加固角钢斜材固定连接。增强桁架整体的稳定性。 The middle positions of the two first reinforcement angle steel slant materials adjacent to both sides of the main material angle steel are fixedly connected by the fourth reinforcement angle steel slant material. Enhance the overall stability of the truss. the
所述的四条支撑横材的每相邻两条支撑横材中间位置通过第五加固角钢斜材固定连接。加强稳定性。 The middle positions of every two adjacent support beams of the four support beams are fixedly connected by the fifth reinforcement angle steel oblique material. Enhanced stability. the
所述的主材角钢成90度角的两侧面的上端和下端都设置有○型圆孔,支撑基座和固定基座的固定加劲钢板上设置有○型圆孔,主材角钢的○型圆孔与支撑基座和固定基座的○型圆孔相对应,主材角钢、支撑基座和固定基座通过穿过○型圆孔的螺栓和螺母固定为一体。安装方便,实用性强。 The upper and lower ends of the two sides of the main material angle steel at an angle of 90 degrees are provided with ○-shaped round holes, and the fixed stiffening steel plates of the supporting base and the fixed base are provided with ○-shaped round holes, and the ○-shaped round holes of the main material angle steel The circular holes correspond to the ○-shaped circular holes of the support base and the fixed base, and the main material angle steel, the support base and the fixed base are fixed as a whole by bolts and nuts passing through the ○-shaped circular holes. Easy installation and strong practicability. the
所述的主材角钢上设置接地极联板和爬钉。增强安全性,方便攀爬。 The main material angle steel is provided with a ground electrode connecting plate and climbing nails. Enhanced safety for easy climbing. the
本实用新型所具有的有益效果是:所述的用于提升输电线路塔接腿的桁架,主要用于输电线路塔接腿的原桩位提升加高,保证了线路运行安全距离,而且在原有输电线路塔的基础上升高无需要占地和青赔,额外增加成本开挖新的输电线路塔基坑和基础浇注,结构简单合理、架设操作方便、省时省力、安全运行。所述的用于提升输电线路塔接腿的桁架的架设方法,可以把新桁架架设组装好后,直接联接于原输电线路塔接腿上,也可以先把原输电线路塔的基座地脚螺栓拆除,然后将带基座的原输电线路塔整体吊起,联结即可,所述的架设方法实施简单、架设难度小、灵活性好、实用性强。 The beneficial effect of the utility model is: the truss used for lifting the tower leg of the transmission line is mainly used for lifting and heightening the original pile position of the tower leg of the transmission line, which ensures the safe distance of the line operation, and in the original There is no need to occupy land and pay for the elevation of the foundation of the transmission line tower, and the additional cost is increased to excavate the foundation pit and foundation pouring of the new transmission line tower. The structure is simple and reasonable, the erection is convenient, time-saving and labor-saving, and safe operation. In the method for erecting the trusses for lifting the tower legs of the transmission line, after the new trusses are erected and assembled, they can be directly connected to the legs of the towers of the original transmission lines, or the base feet of the towers of the original transmission lines can be installed first. The bolts are removed, and then the original transmission line tower with the base is hoisted as a whole and connected. The erection method described is simple in implementation, less difficult in erection, good in flexibility and strong in practicability. the
附图说明 Description of drawings
图1为本实用新型结构示意图; Fig. 1 is a structural representation of the utility model;
图2为本实用新型俯视图; Fig. 2 is a top view of the utility model;
图3为本实用新型主支撑杆的结构示意图; Fig. 3 is the structural representation of main support bar of the present utility model;
其中:1、安装基础台2、固定基座3、主材角钢4、支撑基座5、支撑横材6、基座钢板7、固定加劲钢板8、第三加固角钢斜材9、联板10、第四加固角钢斜材11、第二加固角钢斜材12、第一加固角钢斜材13、第五加固角钢斜材14、 接地极联板15、爬钉。
Among them: 1.
具体实施方式 Detailed ways
下面结合附图对本实用新型的实施例做进一步描述: Embodiments of the utility model are further described below in conjunction with the accompanying drawings:
实施例1: Example 1:
如图1所示,用于升高输电线路塔接腿的桁架,包括安装基础台1,其特征在于:还包括四条支撑横材5,四条支撑横材5首尾连接形成一个正方形结构,相邻两条支撑横材5的交点处安装支撑基座4,支撑基座4下端安装主材角钢3,主材角钢3下端安装固定基座2,固定基座2安装在安装基础台1上。
As shown in Figure 1, the truss used to raise the tower leg of the transmission line includes the installation foundation platform 1, and is characterized in that it also includes four
所述的支撑基座4包括一个基座钢板6和两块垂直交错相接的固定加劲钢板7,固定加劲钢板7垂直基座钢板6设置,两块固定加劲钢板7上设置○型圆孔;
The support base 4 includes a base steel plate 6 and two vertically staggered fixed stiffened
所述的主材角钢3的两侧面成90度角,主材角钢3两侧面的上部和下部都设置有○型圆孔,固定加劲钢板7上的○型圆孔与主材角钢3两侧面的○型圆孔相对应;
The two sides of the main
所述的支撑基座4的结构与固定基座2的结构相同,成镜像结构安装在主材角钢3的两端。
The structure of the support base 4 is the same as that of the fixed
所述的用于提升输电线路塔接腿的桁架用于输电线路塔接腿的原地(桩位)升高,解决了架设新的输电线路塔接腿的尺寸和档距的问题,保证了线路运行安全距离,在原有输电线路塔的基础上提升,无需要占地和青赔,额外增加成本开挖新的输电线路塔基坑和基础浇注,结构简单合理、架设操作方便、省时省力、安全运行。 The truss used to lift the tower legs of the transmission line is used to raise the tower legs of the transmission line in situ (pile position), which solves the problem of the size and span of the tower legs of the new transmission line, and ensures The safe distance of line operation is improved on the basis of the original transmission line tower, no land occupation and green compensation are required, and additional costs are increased to excavate the new transmission line tower foundation pit and foundation pouring, the structure is simple and reasonable, the erection operation is convenient, time-saving and labor-saving ,safe operation. the
基座的设计的大小与原输电线路塔底部基座相同,方便输电线路塔接腿的稳定、安装方便,设置两个垂直交错相接固定加劲钢板和两侧面成90度角钢板相对应,安装方便,稳定性好,固定基座与支撑基座结构相同,固定基座的钢板与安装基础相联接,固定基座的固定钢板可以方便的与主材相联接固定,结构设计典型,简单合理、安装方便、实用性高。 The size of the design of the base is the same as that of the bottom base of the original transmission line tower, which is convenient for the stability of the transmission line tower legs and easy installation. Two vertically staggered fixed stiffening steel plates and steel plates with a 90-degree angle on both sides correspond to each other. Convenient, good stability, the structure of the fixed base is the same as that of the supporting base, the steel plate of the fixed base is connected with the installation base, the fixed steel plate of the fixed base can be easily connected and fixed with the main material, the structure design is typical, simple and reasonable, Easy installation and high practicability. the
实施例2: Example 2:
如图1、图2、图3所示,在实施例1的基础上,所述的四条支撑横材5中间位置都设置联板9,联板9连接第一加固角钢斜材12的一端,第一加固角钢斜材12的另一端连接固定基座2。
As shown in Fig. 1, Fig. 2 and Fig. 3, on the basis of Embodiment 1, the middle positions of the four supporting
实施例3: Example 3:
如图1、图2、图3所示,在实施例1和实施例2的基础上,所述的第一加固角钢斜材12的中间设置连接第二加固角钢斜材11和第三加固角钢斜材8的一端,第二加固角钢斜材11的另一端与主材角钢3的中间位置相连接,第三加固角钢斜材8的另一端连接支撑基座4。
As shown in Fig. 1, Fig. 2 and Fig. 3, on the basis of Embodiment 1 and
所述的主材角钢3两侧相邻的两根第一加固角钢斜材12中间位置通过第四加固角钢斜材10固定连接。
The middle positions of the two first reinforcement angle
所述的四条支撑横材5的每相邻两条支撑横材5中间位置通过第五加固角钢斜材13固定连 接。
Every adjacent two
所述的主材角钢3成90度角的两侧面的上端和下端都设置有○型圆孔,支撑基座4和固定基座2的固定加劲钢板7上设置有○型圆孔,主材角钢3的○型圆孔与支撑基座4和固定基座2的○型圆孔相对应,主材角钢3、支撑基座4和固定基座2通过穿过○型圆孔的螺栓和螺母固定为一体。所述的主材角钢3上设置接地极联板14和爬钉15。
The upper and lower ends of the two sides of the main
使用效果: Effect:
所述的用于提升加高输电线路塔接腿的桁架,解决了架设新的输电线路塔的尺寸和档距的问题,保证了线路运行安全距离,而且在原有输电线路塔的基础上升高无需要占地和青赔,额外增加成本开挖新的输电线路塔基坑和基础浇注,结构简单合理、架设操作方便、省时省力、安全运行。所述的用于提升输电线路塔接腿的桁架的架设方法,可以把新桁架架设组装好后,直接联接于原输电线路塔接腿上,也可以先把原输电线路塔的基座地脚螺栓拆除,然后将带基座的原输电线路塔整体吊起,联结即可,所述的架设方法实施简单、架设难度小、灵活性好、实用性强。 The truss used for raising and heightening the legs of transmission line towers solves the problem of the size and span of erecting new transmission line towers, ensures a safe distance for line operation, and raises the transmission line tower on the basis of the original transmission line tower. It requires land occupation and compensation, and additional cost is required to excavate the new transmission line tower foundation pit and foundation pouring. The structure is simple and reasonable, the erection is convenient, time-saving and labor-saving, and safe operation. In the method for erecting the trusses for lifting the tower legs of the transmission line, after the new trusses are erected and assembled, they can be directly connected to the legs of the towers of the original transmission lines, or the base feet of the towers of the original transmission lines can be installed first. The bolts are removed, and then the original transmission line tower with the base is hoisted as a whole and connected. The erection method described is simple in implementation, less difficult in erection, good in flexibility and strong in practicability. the
所述的用于提升加高输电线路塔接腿的桁架的架设组装施工方法,可以把桁架架设好后直接将原输电线路塔架设到支撑基座上,也可以先把基座架设到原输电线路塔,再把固定基座和主材组装架设好,然后将带支撑基座的原输电线路塔吊起,组装即可,所述的架设施工方法实施简单、架设难度小、灵活性好、实用性强。 In the erection and assembly construction method of the truss used for lifting and heightening the tower legs of the transmission line, the original transmission line tower can be directly erected on the supporting base after the truss is erected, or the base can be erected on the original transmission line tower first. Line tower, then assemble and erect the fixed base and main material, then lift the original transmission line tower with supporting base, and assemble it. The erection construction method described is simple to implement, less difficult to erect, good in flexibility and practical Strong. the
所述的用于提升加高输电线路塔接腿的桁架台段组立时,杆塔上的铁件均镀锌,镀锌损坏时应涂防锈漆,杆塔构件组装应牢固符合国家标准,相关验收运行要求。 When the above-mentioned truss platform section for lifting and heightening transmission line tower legs is assembled, the iron parts on the tower are all galvanized. run requirements. the
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 201320098675 CN203175134U (en) | 2013-03-05 | 2013-03-05 | Truss used for lifting electric transmission line tower connecting legs |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 201320098675 CN203175134U (en) | 2013-03-05 | 2013-03-05 | Truss used for lifting electric transmission line tower connecting legs |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN203175134U true CN203175134U (en) | 2013-09-04 |
Family
ID=49071857
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN 201320098675 Expired - Lifetime CN203175134U (en) | 2013-03-05 | 2013-03-05 | Truss used for lifting electric transmission line tower connecting legs |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN203175134U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103132766A (en) * | 2013-03-05 | 2013-06-05 | 山东电力集团公司淄博供电公司 | Truss for lifting power transmission line tower connecting leg and erection method |
| CN116607555A (en) * | 2023-06-30 | 2023-08-18 | 湖北工建集团第三建筑工程有限公司 | A plug-in steel column foot and its construction method |
-
2013
- 2013-03-05 CN CN 201320098675 patent/CN203175134U/en not_active Expired - Lifetime
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103132766A (en) * | 2013-03-05 | 2013-06-05 | 山东电力集团公司淄博供电公司 | Truss for lifting power transmission line tower connecting leg and erection method |
| CN103132766B (en) * | 2013-03-05 | 2014-12-10 | 国家电网公司 | Truss for lifting power transmission line tower connecting leg and erection method |
| CN116607555A (en) * | 2023-06-30 | 2023-08-18 | 湖北工建集团第三建筑工程有限公司 | A plug-in steel column foot and its construction method |
| CN116607555B (en) * | 2023-06-30 | 2024-12-20 | 湖北工建集团第三建筑工程有限公司 | Insertion type steel column foot and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103132766B (en) | Truss for lifting power transmission line tower connecting leg and erection method | |
| CN208430687U (en) | Self-anchored suspension cable structure support structure and system | |
| CN106760529B (en) | Roof steel truss sliding assembly construction platform and installation method | |
| CN201671391U (en) | Light Line Repair Tower | |
| CN101775896B (en) | Rigid suspended scaffold for installing pipeline of steel roof equipment | |
| CN204186123U (en) | Mast type communication head tower mast | |
| CN205531399U (en) | Interim support frame is installed in high -order steel truss segmentation | |
| CN111119222A (en) | An assembly device for towers of UHVDC transmission lines in alpine regions | |
| CN203175134U (en) | Truss used for lifting electric transmission line tower connecting legs | |
| CN211500006U (en) | A 220kV frame structure suitable for larger slope sites | |
| CN203640375U (en) | Switching structure for different tower crane bases | |
| CN103397638A (en) | Tie bar for supporting system in high-rigidity integral prestressed fabricated foundation pit support | |
| CN219175028U (en) | Double-limb pier climbing formwork | |
| CN217232982U (en) | Four return circuit 10kV overhead line's tower of acting as go-between | |
| CN203223035U (en) | Unit body for combined type urgent repair tower for high voltage lines | |
| CN206109965U (en) | Steel plank road in water and electricity building site | |
| CN208235587U (en) | A kind of large-span deep foundation pit underground power house rack assembling construction platform | |
| CN106121341B (en) | Extra high voltage network emergency first-aid repair strain rod tower | |
| CN203225074U (en) | Grid structure billboard | |
| CN212927216U (en) | Assembled steel structure foundation of prefabricated cabin transformer substation | |
| CN103982076A (en) | Single cycle 110 kV/35 stay wire type aluminum alloy urgent repair tower | |
| CN103882882A (en) | Integral jacking type tower crane foundation platform structure | |
| CN104074389A (en) | Combined high-voltage line iron power upright post type rush repair tower | |
| CN203429557U (en) | Anchor pole back beam applied to underpass bridge jacking construction | |
| CN203271221U (en) | Self-standing type ground combined derrick with equipment platform |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| AV01 | Patent right actively abandoned |
Granted publication date: 20130904 Effective date of abandoning: 20141210 |
|
| RGAV | Abandon patent right to avoid regrant |