CN203626356U - Rapid communication pipe tower - Google Patents

Rapid communication pipe tower Download PDF

Info

Publication number
CN203626356U
CN203626356U CN201320782767.5U CN201320782767U CN203626356U CN 203626356 U CN203626356 U CN 203626356U CN 201320782767 U CN201320782767 U CN 201320782767U CN 203626356 U CN203626356 U CN 203626356U
Authority
CN
China
Prior art keywords
pipe tower
tower
steel frame
tower body
support bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320782767.5U
Other languages
Chinese (zh)
Inventor
和树海
田琳
陈明军
孙欢启
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Is Along Communication Technology Ltd Co Of Nation
Original Assignee
Liaoning Is Along Communication Technology Ltd Co Of Nation
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning Is Along Communication Technology Ltd Co Of Nation filed Critical Liaoning Is Along Communication Technology Ltd Co Of Nation
Priority to CN201320782767.5U priority Critical patent/CN203626356U/en
Application granted granted Critical
Publication of CN203626356U publication Critical patent/CN203626356U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Support Of Aerials (AREA)

Abstract

The utility model discloses a rapid communication pipe tower. The rapid communication pipe tower comprises a tower body of the pipe tower, a communication antenna holding pole, a steel frame base, a supporting rod and a concrete balancing weight, wherein the communication antenna holding pole is fixedly connected with the tower body of the pipe tower; the tower body of the pipe tower is detachably connected with the steel frame base; the supporting rod is respectively and rotatably connected with the tower body of the pipe tower and the steel frame base; the concrete balancing weight is arranged on the steel frame base. The rapid communication pipe tower provided by the utility mode has the beneficial effects that the structure is simple; the whole body is beautiful and elegant; an outer climbing design is adopted and the installation is rapid; cast-in-place is not needed so that the time of early period foundation construction is shortened and the damage to a field land is reduced; the occupied land is saved and the installation is not influenced by seasons.

Description

High-speed traffic pipe tower
Technical field
The utility model relates to communication equipment technical field, relates in particular to a kind of high-speed traffic pipe tower of using for radio communication.
Background technology
At present, in order to guarantee communication network coverage requirement, common carrier mainly meets the deployment of communication network by setting up communication tower.Traditional communication tower mainly contains angle steel tower and Guan Ta, they are all the area coverages of mobile communication antenna being raised to certain height and met communication antenna, this type of communication tower is all to calculate by strict basic engineering, carry out the making on pre-buried concrete odor type basis at the scene, infield of specifying, these bases all need to carry out a large amount of site work, as dig foundation ditch, wiretie, the work such as foot bolt and concreting regularly, base concrete needs preserving period, it is generally 28 days, add transportation and set-up time, whole completion of works at least needed about 30 days.If it is bad to run into field condition, the masses obstruct, and that selected base station just cannot be set up, and to winter, substantially can not carry out foundation construction, causes to carry out base station construction whole winter, the basic like this requirement of building a station that cannot meet current operator.
Utility model content
The purpose of this utility model is effectively to overcome the deficiency of above-mentioned technology, provide a kind of and install fast, save the set-up time, simple in structure, can save occupation of land and not be subject to the high-speed traffic pipe tower of seasonal effect.
The technical solution of the utility model is achieved in that it comprises pipe tower tower body, communication antenna pole, Foundation of steel frame, support bar and concrete balancing weight, described communication antenna pole is fixedly connected with described pipe tower tower body, described pipe tower tower body and described Foundation of steel frame removably connect, described support bar is rotatably connected with pipe tower tower body and Foundation of steel frame respectively, and described concrete balancing weight is placed on Foundation of steel frame.
In said structure, on four angles of described Foundation of steel frame, be respectively equipped with the first support bar junction plate, on described pipe tower tower body, corresponding position is respectively equipped with the second support bar junction plate, and described support bar two ends have junction plate and are rotatably connected with described the first support bar junction plate and described the second support bar junction plate respectively.
In said structure, described pipe tower tower body comprises lightning rod, safety rope and safety rope fixed head, described lightning rod is arranged on the top of pipe tower tower body, described safety rope fixed head is arranged on the bottom of pipe tower tower body, described safety rope one end is arranged on the top of pipe tower tower body, and the other end is arranged on safety rope fixed head.
In said structure, described concrete balancing weight is four, is placed on respectively on the four direction of Foundation of steel frame.
In said structure, described Foundation of steel frame is provided with connector, and described connector is connected with described pipe tower tower body bottom by flange.
In said structure, described junction plate is hinged with described the first support bar junction plate and described the second support bar junction plate respectively.
In said structure, described communication antenna pole and the welding of described pipe tower tower body.
The beneficial effects of the utility model are: the high-speed traffic pipe tower that the utility model provides, simple in structure, overall appearance is generous, and adopt the outer design of climbing, install fast, do not need cast in situs, reduce the time of foundation construction in early stage and the destruction of reducing on-the-spot soil, save and take up an area, and the impact that is not subject to season is installed.
Accompanying drawing explanation
Fig. 1 is the front view of the utility model high-speed traffic pipe tower
Fig. 2 is the top view of the utility model high-speed traffic pipe tower
In figure: 1, pipe tower tower body; 2, communication antenna pole; 3, Foundation of steel frame; 4, support bar; 5, concrete balancing weight; 6, the first support bar junction plate; 7, the second support bar junction plate; 8, lightning rod; 9, safety rope; 10, safety rope fixed head; 11, communication antenna.
The specific embodiment
Below in conjunction with drawings and Examples, the utility model will be further described.
Shown in seeing figures.1.and.2, the high-speed traffic pipe tower that the utility model discloses, it comprises pipe tower tower body 1, communication antenna pole 2, Foundation of steel frame 3, support bar 4 and concrete balancing weight 5, pipe tower tower body 1 comprises lightning rod 8, safety rope 9 and safety rope fixed head 10, lightning rod 8 is arranged on the top of pipe tower tower body 1, safety rope fixed head 10 is arranged on the bottom of pipe tower tower body 1, safety rope 9 one end are arranged on the top of pipe tower tower body 1, the other end is arranged on safety rope fixed head 10, in staff's climbing, play a protective role, prevent that staff from falling, communication antenna pole 2 welds with pipe tower tower body 1, communication antenna pole 2 communicates signal transmitting for hanging communication antenna 11, Foundation of steel frame 3 is detachable package assembly, Foundation of steel frame 3 upper end center positions are provided with connector, connector is connected with pipe tower tower body 1 bottom by flange, on four angles of Foundation of steel frame 3, be welded with respectively the first support bar junction plate 6, on pipe tower tower body 1, corresponding position is welded with respectively the second support bar junction plate 7, it is hinged with the first support bar junction plate 6 and the second support bar junction plate 7 respectively that support bar 4 two ends have junction plate, form a braced structures, concrete balancing weight 5 is four, be placed on respectively on the four direction of Foundation of steel frame 3, pipe tower tower body 1, Foundation of steel frame 3 and support bar 4 are made by metal material, pipe tower tower body 1 adopts the outer design of climbing, and moulding can design as required, can also on pipe tower tower body 1, beautify, as increase beautifying and decorating, job platform and brightening illuminating lamp etc., concrete balancing weight 5 adopts the grade strength concrete of designing requirement preset in advance in factory, reach preserving period, and by strength test, the scene of being transported to can be installed, do not need cast in situs, the time of foundation construction in early stage and the destruction of reducing on-the-spot soil are reduced, Fast Installation, construction is not subject to the impact in season.
Described above is only preferred embodiment of the present utility model, and above-mentioned specific embodiment is not to restriction of the present utility model.In technological thought category of the present utility model, can there is various distortion and modification, retouching that all those of ordinary skill in the art make according to above description, revise or be equal to replacement, all belong to the scope that the utility model is protected.

Claims (7)

1. a high-speed traffic pipe tower, it is characterized in that: it comprises pipe tower tower body, communication antenna pole, Foundation of steel frame, support bar and concrete balancing weight, described communication antenna pole is fixedly connected with described pipe tower tower body, described pipe tower tower body and described Foundation of steel frame removably connect, described support bar is rotatably connected with pipe tower tower body and Foundation of steel frame respectively, and described concrete balancing weight is placed on Foundation of steel frame.
2. high-speed traffic pipe tower according to claim 1, it is characterized in that: on four angles of described Foundation of steel frame, be respectively equipped with the first support bar junction plate, on described pipe tower tower body, corresponding position is respectively equipped with the second support bar junction plate, and described support bar two ends have junction plate and are rotatably connected with described the first support bar junction plate and described the second support bar junction plate respectively.
3. high-speed traffic pipe tower according to claim 1, it is characterized in that: described pipe tower tower body comprises lightning rod, safety rope and safety rope fixed head, described lightning rod is arranged on the top of pipe tower tower body, described safety rope fixed head is arranged on the bottom of pipe tower tower body, described safety rope one end is arranged on the top of pipe tower tower body, and the other end is arranged on safety rope fixed head.
4. high-speed traffic pipe tower according to claim 1, is characterized in that: described concrete balancing weight is four, is placed on respectively on the four direction of Foundation of steel frame.
5. high-speed traffic pipe tower according to claim 1, is characterized in that: described Foundation of steel frame is provided with connector, and described connector is connected with described pipe tower tower body bottom by flange.
6. high-speed traffic pipe tower according to claim 2, is characterized in that: described junction plate is hinged with described the first support bar junction plate and described the second support bar junction plate respectively.
7. high-speed traffic pipe tower according to claim 1, is characterized in that: described communication antenna pole and the welding of described pipe tower tower body.
CN201320782767.5U 2013-11-29 2013-11-29 Rapid communication pipe tower Expired - Lifetime CN203626356U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320782767.5U CN203626356U (en) 2013-11-29 2013-11-29 Rapid communication pipe tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320782767.5U CN203626356U (en) 2013-11-29 2013-11-29 Rapid communication pipe tower

Publications (1)

Publication Number Publication Date
CN203626356U true CN203626356U (en) 2014-06-04

Family

ID=50812847

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320782767.5U Expired - Lifetime CN203626356U (en) 2013-11-29 2013-11-29 Rapid communication pipe tower

Country Status (1)

Country Link
CN (1) CN203626356U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104141406A (en) * 2014-07-09 2014-11-12 国家电网公司 Electric iron tower mounted with 4G antenna
CN105896022A (en) * 2015-01-26 2016-08-24 泉州市铁通电子设备有限公司 Mine ultra-low-frequency two-way communication antenna

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104141406A (en) * 2014-07-09 2014-11-12 国家电网公司 Electric iron tower mounted with 4G antenna
CN105896022A (en) * 2015-01-26 2016-08-24 泉州市铁通电子设备有限公司 Mine ultra-low-frequency two-way communication antenna

Similar Documents

Publication Publication Date Title
CN103132766B (en) Truss for lifting power transmission line tower connecting leg and erection method
CN204152259U (en) A kind of newly-built multi-functional communications base station of greenbelt
CN204186123U (en) Mast type communication head tower mast
CN206174593U (en) Telegraph pole
CN102828469A (en) Positioning mounting construction method for triangular steel constructed pillar of inclined-leg steel box
CN203626356U (en) Rapid communication pipe tower
CN204920400U (en) Tower room integration communication base station
CN201883746U (en) Base of movable high-voltage wire pole
CN101914999A (en) Communication device for fast integrating integrative machine room
CN204920399U (en) Communication tower convenient to installation
CN208479146U (en) A kind of open caisson of staggered floor cable laying
CN101769089A (en) Own weight rapidly integrated communication device
CN203175134U (en) Truss used for lifting electric transmission line tower connecting legs
CN201778510U (en) Rapid integrated communication device of integral computer room
CN203271221U (en) Self-standing type ground combined derrick with equipment platform
CN202550057U (en) Antenna holding pole device
CN207245313U (en) A kind of Fast Installation communication tower
CN202945831U (en) Rapid construction type integrated assembling communication base station
CN201635472U (en) Quick integrated communication device of self balance weight
CN207686323U (en) Diamond shape installation part and diamond shape mounting operation platform
CN202431029U (en) Integrated beautification base station
CN207177418U (en) Communicate triangle tower
CN203701662U (en) Integrated fast assembling base station
CN205399270U (en) A base for monitoring rod and traffic signal lamp fixed mounting
CN204979710U (en) Frame is put in wallboard exhibition

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140604