CN202945831U - Rapid construction type integrated assembling communication base station - Google Patents

Rapid construction type integrated assembling communication base station Download PDF

Info

Publication number
CN202945831U
CN202945831U CN 201220565553 CN201220565553U CN202945831U CN 202945831 U CN202945831 U CN 202945831U CN 201220565553 CN201220565553 CN 201220565553 CN 201220565553 U CN201220565553 U CN 201220565553U CN 202945831 U CN202945831 U CN 202945831U
Authority
CN
China
Prior art keywords
girder
base station
base
main beams
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN 201220565553
Other languages
Chinese (zh)
Inventor
孙新武
李远忠
陈鄂湘
吴向荣
叶创志
张建仁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUNAN POST TELECOMMUNICATION PLANNING DESIGN INSTITUTE CO LTD
Original Assignee
HUNAN POST TELECOMMUNICATION PLANNING DESIGN INSTITUTE CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN POST TELECOMMUNICATION PLANNING DESIGN INSTITUTE CO LTD filed Critical HUNAN POST TELECOMMUNICATION PLANNING DESIGN INSTITUTE CO LTD
Priority to CN 201220565553 priority Critical patent/CN202945831U/en
Application granted granted Critical
Publication of CN202945831U publication Critical patent/CN202945831U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Images

Landscapes

  • Support Of Aerials (AREA)

Abstract

The utility model discloses a rapid construction type integrated assembling communication base station which comprises a base station base, balancing weight blocks and an outdoor machine cabinet. The base station base comprises two first main beams, four second main beams and six third main beams. Two connecting flanges are both arranged on symmetrical positions of middle portions of the two first main beams. Secondary beams are arranged in a hollow portion of the center of the base station base. Two ends of the secondary beams are fixed on the third main beams through secondary beam connection angles. The outdoor machine cabinet is fixed on the secondary beams. The balancing weight blocks are respectively fixed at the tail ends of the first main beams and the tail ends of the second main beams, wherein the tail ends of the first main beams and the tail ends of the second main beams are located on four directions of the base station base. The rapid construction type integrated assembling communication base station is simple in structure, beautiful in appearance, capable of not connecting with an original roof face, low in requirements of a structure of an original house, capable of solving the problems that renting site selection is difficult and residents obstruct the construction, capable of manufacturing rapidly, processing and installing, short in constructing cycle, low in construction, maintaining and operating cost, flexible in dismount, and low in dismounting difficulty.

Description

The integrated assembling communication base station of a kind of run-up formula
Technical field
The utility model relates to radio communication, civil engineering structure field, is specially the integrated assembling communication base station of a kind of run-up formula.
Background technology
At present, existing roofing communication base station normally is made of roofing communication iron tower, support bar, pole or camouflaged rod and radio communication machine room, and machine room generally can be divided into lease machine room, Simple machinery room or outdoor integrated rack three types.
Mainly there is following problem in existing roofing communication base station in process of construction:
1) structural requirement to former house is high, and Cell Site Placement and lease difficulty are large;
2) scale of construction of roofing communication iron tower, support bar is large, and in the process of construction of base station, resident's Work hindrance phenomenon happens occasionally;
3) to account for the roofing area larger for traditional communication iron tower, and it line modelling is simple and crude, affects the appearance of the city;
4) there is certain destruction on the communication iron tower basis to the established estate mask in work progress, easily causes roof leakage, infiltration phenomenon, causes the owner and is discontented with;
5) the base station construction cycle long, and construction, maintenance and running cost are high;
6) resettlement of roofing communication iron tower, remove long in time limitly, and difficulty is larger.
The utility model content
The technical problem that the utility model solves is to provide a kind of run-up formula integrated assembling communication base station, to solve the problem that proposes in the above-mentioned background technology.
The technical problem that the utility model solves realizes by the following technical solutions:
The integrated assembling communication base station of a kind of run-up formula, comprise base station base, balancing weight, Cabinet, described base station base includes two the first girders, four the second girders, the six roots of sensation the 3rd girder, be equipped with two adpting flanges on the middle part symmetric position of the first girder, two the first girder two ends are connected with the 3rd girder by connecting angle, are connected with the 3rd girder by connecting angle between two the first girders middle parts, four adpting flanges; Wherein two the second girder one ends are connected with the 3rd girder by connecting angle, the other end is fixed on the middle part of first the first girder, other two the second girder one ends are connected with the 3rd girder by connecting angle, and the other end is fixed on the middle part of second the first girder; Be provided with secondary beam in the hollow at base center, described base station, described secondary beam two ends are fixed on the 3rd girder by the secondary beam connecting angle, described Cabinet is fixed on secondary beam, and described balancing weight is separately fixed at the first girder of base station base four direction, the end of the second girder.
One of them fixing microwave antenna pole of two adpting flanges of diagonally opposing corner on the base of base station, another fixed RF far-pulling module (RRU) pole, two other adpting flange of diagonally opposing corner is provided with the embellished antenna pole, and described embellished antenna pole is provided with the embellished antenna crossover flange.
As a kind of optimization of above technology, described the first girder, the second girder, the 3rd girder are channel-section steel, and described secondary beam is angle steel.
As a kind of optimization of above technology, described adpting flange bottom is provided with the first girder stiffening rib that is welded on the first girder.
As a kind of optimization of above technology, described microwave antenna pole, radio frequency remoto module pole, embellished antenna pole one end are equipped with the base flange fixing with adpting flange.
The size of the Cabinet that the utility model proposes according to radio communication specialty, form and the height of embellished antenna, the size of calculative determination base station base and be placed on precast concrete balancing weight on the base of base station; According to the wireless coverage requirement, then in conjunction with the structural configuration situation of former roofing, determine the putting position of base station base.Prepared screw-bolt hole on the girder of base station base connects by bolt between girder; According to the base flange size of embellished antenna pole, microwave antenna pole, RRU pole and the size of equipment, at the edge of a wing of base station base prepared screw-bolt hole, be bolted above-mentioned pole is fixed on the base of base station.
Compared with prior art, the beneficial effects of the utility model are:
1) base area is little, only need be positioned on former roofing right-angled intersection beam or bearing wall, is not connected with former roofing, without any damage, requires lower to former building structure to former roof structure;
2) simple in structure, good looking appearance, environmental protection have solved the problem that the lease addressing is difficult, the resident hinders work;
3) can produce fast, process, install, the construction period is short, and construction, maintenance and running cost are low;
4) can move fast, dismounting is flexible, difficulty is little, the duration is short.
Description of drawings
Fig. 1 is structural representation of the present utility model.
Fig. 2 is base station of the present utility model understructure schematic diagram.
In figure: 1, base station base, 1-1, the first girder, 1-2, the second girder, 1-3, the 3rd girder, 1-4, adpting flange, 1-5, connecting angle, 1-6, the first girder stiffening rib, 1-7, secondary beam, 1-8, secondary beam connecting angle, 2, balancing weight, 3, embellished antenna crossover flange, 4, Cabinet, 5, the microwave antenna pole, 6, radio frequency remoto module pole, 7, the embellished antenna pole.
The specific embodiment
Of the present utility modelly to realize technological means, creation characteristic in order making, to reach purpose and effect is easy to understand, below in conjunction with concrete diagram, further set forth the utility model.
as shown in Fig. 1 ~ 2, the integrated assembling communication base station of a kind of run-up formula, comprise base station base 1, balancing weight 2, Cabinet 4, described base station base 1 includes two the first girder 1-1, four the second girder 1-2, the six roots of sensation the 3rd girder 1-3, be equipped with two adpting flange 1-4 on the middle part symmetric position of the first girder 1-1, two the first girder 1-1 two ends are connected with the 3rd girder 1-3 by connecting angle 1-5, in the middle part of two the first girder 1-1, pass through connecting angle 1-5 between four adpting flange 1-4 and be connected with the 3rd girder 1-3, wherein two the second girder 1-2 one ends are connected with the 3rd girder 1-3 by connecting angle 1-5, the other end is fixed therein the middle part of first a girder 1-1, other two the second girder 1-2 one ends are connected with the 3rd girder 1-3 by connecting angle 1-5, the other end is fixed on the middle part of other first a girder 1-1, be provided with secondary beam 1-7 in the hollow at base 1 center, described base station, described secondary beam 1-7 two ends are fixed on the 3rd girder 1-3 by secondary beam connecting angle 1-8, described Cabinet 4 is fixed on secondary beam 1-7, described balancing weight 2 is separately fixed at the first girder 1-1 of base station base 1 four direction, the end of the second girder 1-2.
Above-mentioned the first girder 1-1, the second girder 1-2, the 3rd girder 1-3 are channel-section steel, and secondary beam 1-7 is angle steel.Described adpting flange 1-4 bottom is provided with the first girder stiffening rib 1-6 that is welded on the first girder 1-1.
One of them fixing microwave antenna pole 5 of two adpting flange 1-4 of diagonally opposing corner on the base 1 of described base station, another fixed RF far-pulling module pole 6, two other adpting flange of diagonally opposing corner 1-4 is provided with embellished antenna pole 7, and described embellished antenna pole 7 is provided with embellished antenna crossover flange 3.Described microwave antenna pole 5, radio frequency remoto module pole 6, embellished antenna pole one end 7 are equipped with the base flange fixing with adpting flange 1-4.
When the utility model is installed, first flooring is carried out levelling, install be delivered for use 1 year after, tackle that its verticality is adjusted and comprehensively fastening.The utility model is applicable to wind reference pressure 0.7kN/m 2, seismic fortification intensity is six degree; The concrete of described balancing weight adopts C20, and all members all adopt the galvanizing preservative treatment; Galvanizing surface is smooth, has not allowed jagged, droplet knurl and unnecessary caking in the junction, without peeling, without the solvent slag that leaks zinc, noresidue, and the defectives such as overpickling or leakage iron must not be arranged.
Above demonstration and described basic principle of the present utility model and principal character and advantage of the present utility model.The technician of the industry should understand; the utility model is not restricted to the described embodiments; that describes in above-described embodiment and manual just illustrates principle of the present utility model; under the prerequisite that does not break away from the utility model spirit and scope; the utility model also has various changes and modifications, and these changes and improvements all fall in claimed the utility model scope.Claimed scope of the present utility model is defined by appending claims and equivalent thereof.

Claims (5)

1. integrated assembling communication base station of run-up formula, comprise base station base, balancing weight, Cabinet, it is characterized in that: described base station base includes two the first girders, four the second girders, the six roots of sensation the 3rd girder, be equipped with two adpting flanges on the middle part symmetric position of the first girder, two the first girder two ends are connected with the 3rd girder by connecting angle, are connected with the 3rd girder by connecting angle between two the first girders middle parts, four adpting flanges; Wherein two the second girder one ends are connected with the 3rd girder by connecting angle, the other end is fixed on the middle part of first the first girder, other two the second girder one ends are connected with the 3rd girder by connecting angle, and the other end is fixed on the middle part of second the first girder; Be provided with secondary beam in the hollow at base center, described base station, described secondary beam two ends are fixed on the 3rd girder by the secondary beam connecting angle, described Cabinet is fixed on secondary beam, and described balancing weight is separately fixed at the first girder of base station base four direction, the end of the second girder.
2. the integrated assembling communication base station of a kind of run-up formula according to claim 1, it is characterized in that: one of them fixing microwave antenna pole of two adpting flanges of diagonally opposing corner on the base of base station, another fixed RF far-pulling module pole, on the base of base station, two other adpting flange of diagonally opposing corner is provided with the embellished antenna pole, and described embellished antenna pole is provided with the embellished antenna crossover flange.
3. the integrated assembling communication base station of a kind of run-up formula according to claim 1, it is characterized in that: described the first girder, the second girder, the 3rd girder are channel-section steel, and described secondary beam is angle steel.
4. the integrated assembling communication base station of a kind of run-up formula according to claim 1, is characterized in that: be provided with the first girder stiffening rib that is welded on the first girder bottom described adpting flange.
5. the integrated assembling communication base station of a kind of run-up formula according to claim 1 and 2 is characterized in that: described microwave antenna pole, radio frequency remoto module pole, embellished antenna pole one end are equipped with the base flange fixing with adpting flange.
CN 201220565553 2012-10-31 2012-10-31 Rapid construction type integrated assembling communication base station Withdrawn - After Issue CN202945831U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220565553 CN202945831U (en) 2012-10-31 2012-10-31 Rapid construction type integrated assembling communication base station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220565553 CN202945831U (en) 2012-10-31 2012-10-31 Rapid construction type integrated assembling communication base station

Publications (1)

Publication Number Publication Date
CN202945831U true CN202945831U (en) 2013-05-22

Family

ID=48421538

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220565553 Withdrawn - After Issue CN202945831U (en) 2012-10-31 2012-10-31 Rapid construction type integrated assembling communication base station

Country Status (1)

Country Link
CN (1) CN202945831U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102900252A (en) * 2012-10-31 2013-01-30 湖南省邮电规划设计院有限公司 Quick building type integrated assembly communication base station and assembly method thereof
CN111585001A (en) * 2020-04-03 2020-08-25 国网浙江省电力有限公司湖州供电公司 Sharing iron tower type base station antenna support

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102900252A (en) * 2012-10-31 2013-01-30 湖南省邮电规划设计院有限公司 Quick building type integrated assembly communication base station and assembly method thereof
CN102900252B (en) * 2012-10-31 2014-11-26 湖南省邮电规划设计院有限公司 Quick building type integrated assembly communication base station and assembly method thereof
CN111585001A (en) * 2020-04-03 2020-08-25 国网浙江省电力有限公司湖州供电公司 Sharing iron tower type base station antenna support

Similar Documents

Publication Publication Date Title
CN206737563U (en) A kind of construction guard fender quickly assembled
CN202945831U (en) Rapid construction type integrated assembling communication base station
CN108049666A (en) A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction
CN203247868U (en) Large-span steel structure construction temporary supporting frame
CN105480002B (en) A kind of single-layer steel structure decoration tree and its installation method
CN204920400U (en) Tower room integration communication base station
CN204960456U (en) Roofing counter weight communication tower structure
CN203034777U (en) Rail-mounted mobile tall operation platform
CN111794524A (en) Bolt ball steel pipe net rack segmented hoisting and high-altitude scattered splicing combined installation construction process
CN102900252B (en) Quick building type integrated assembly communication base station and assembly method thereof
CN101769081A (en) Co-construction and sharing type triangle-tube tower communication base station and setting method thereof
CN204125963U (en) A kind of communication tower steel pipe pile foundation
CN204098552U (en) A kind of Joint construction and sharing integration-in-one base station
CN203983929U (en) Assemble type underground cable ditch based on city integrated wiring
CN203795459U (en) Foundation structure of tower crane for high-altitude roofs
CN204899374U (en) Low -cost television tower
CN114033189A (en) Large-area high-altitude grid structure aluminum grid ceiling construction device and construction method
CN203878563U (en) Suspended single-row scaffold
CN204112790U (en) A kind of integral quick-mounting base station
CN203626356U (en) Rapid communication pipe tower
CN203701555U (en) Movable type pipe truss installation platform
CN203440913U (en) Supporting structure for reinforced concrete corridor construction
CN102777703A (en) Assembly type light pipeline hanger
CN207553715U (en) Communication iron tower and computer room combined type base station
CN203175134U (en) Truss used for lifting electric transmission line tower connecting legs

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20130522

Effective date of abandoning: 20141126