CN202001787U - Detachable ground anchor of tower crane - Google Patents

Detachable ground anchor of tower crane Download PDF

Info

Publication number
CN202001787U
CN202001787U CN2011201154920U CN201120115492U CN202001787U CN 202001787 U CN202001787 U CN 202001787U CN 2011201154920 U CN2011201154920 U CN 2011201154920U CN 201120115492 U CN201120115492 U CN 201120115492U CN 202001787 U CN202001787 U CN 202001787U
Authority
CN
China
Prior art keywords
angle steel
main limb
limb angle
base
tower crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011201154920U
Other languages
Chinese (zh)
Inventor
徐克诚
杨志英
娄春媛子
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING ZENHE ENGINEERING EQUIPMENT SERVICE CO., LTD.
Original Assignee
BEIJING ZHONGJIAN ZHENGHE CONSTRUCTION MECHANIZATION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING ZHONGJIAN ZHENGHE CONSTRUCTION MECHANIZATION Co Ltd filed Critical BEIJING ZHONGJIAN ZHENGHE CONSTRUCTION MECHANIZATION Co Ltd
Priority to CN2011201154920U priority Critical patent/CN202001787U/en
Application granted granted Critical
Publication of CN202001787U publication Critical patent/CN202001787U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model discloses a detachable ground anchor of a tower crane, which comprises a base, main limb angle steel, four rib plates and two mounting devices. The main limb angle steel is fixedly arranged on the base; the center of form of the main limb angle steel is coincident with that of the base; the two mounting devices are respectively arranged at the top ends of two sides of the main limb angle steel fixedly and extend out from the top end of the main limb angle steel upwards; the rib plates are fixedly connected with the main limb angle steel and the base and play a role in supporting the main limb angle steel; two of the four rib plates are respectively arranged on two wing plates of the main limb angle steel; and the setting positions of the rest two rib plates ensure that extended lines of longitudinal centerlines of the rest two rib plates pass through the center of form of the main limb angle steel. The base is provided with eight mounting holes, and the mounting holes are uniformly distributed along a circumference using the center of form of the base as a center of a circle. By using the ground anchor, the tower crane can be applicable to various construction places.

Description

The detachable lower margin of tower crane
Technical field
The utility model relates to a kind of tower crane lower margin, particularly a kind of detachable lower margin.
Background technique
Tower crane is widely used in the construction projects such as industrial premises, power station, bridge, civil building; Its mounting type is now mainly based on fixed, as shown in Figure 1, the concrete foundation of promptly making a special use with the tower machine fixedly lower margin 11(be called for short lower margin) be embedded in the basis 14, during use, as shown in Figure 2, the body of the tower 12 with tower crane is connected by erecting device 13 with lower margin 11.But along with the development of Building technology, a lot of construction project can't be made special concrete foundation so that the tower machine to be installed.Especially large-scale steel structure is built, and some project tower crane can only be installed on steel structure girder or the pillar; And most steel structure also do not allow welding.And the means of fixation that tower crane of the prior art was suitable for is and is fixed on the concrete embedded lower margin; And do not consider that tower crane will be installed on the steel structure, so when concrete embedded lower margin can't be used in the job site, tower crane then can't use.
The model utility content
The problem that is run into when tower crane being installed at prior art, the detachable lower margin that the utility model provides a kind of novel being used to that tower crane is installed, this detachable lower margin comprises: base, main limb angle steel, four gussets and two erecting devices.Main limb angle steel is fixedly installed on the base, and the centre of form of main limb angle steel overlaps with the centre of form of base; Two erecting devices are fixedly installed on the top on two limits of main limb angle steel respectively, and are protruded upward by the top of main limb angle steel; Gusset is fixedlyed connected with base with main limb angle steel, and main limb angle steel is played a supporting role; In four gussets two are separately positioned on two wing plates of main limb angle steel, two other the elongation line that the position should guarantee its vertical center line is set should be by the centre of form of main limb angle steel.Base is provided with 8 mounting holes, and mounting hole is the circumference uniform distribution in the center of circle along the centre of form with base.
Detachable lower margin in the utility model, can will be arranged on the steel structure by bolt, the installation and removal of tower crane have been made things convenient for, and, four positions that are provided with that position and 8 mounting holes are set of strengthening gusset on the main limb angle steel make lower margin each several part more reasonable stress, improve the installation stability of tower crane, prolonged the working life of lower margin.
Description of drawings
Fig. 1 is a concrete embedded lower margin schematic representation in the prior art;
Fig. 2 is a tower crane scheme of installation in the prior art;
Fig. 3 is removably leg structure schematic representation figure of the utility model tower crane;
Fig. 4 is a removably leg structure plan view of the utility model tower crane;
Fig. 5 is a removably leg structure mounting structure schematic representation of the utility model tower crane.
Embodiment
As shown in Figure 3, the detachable lower margin 1 in the utility model comprises: base 2, main limb angle steel 3, gusset 4 and erecting device 5.Main limb angle steel 3 is fixedly installed on the base 2, and main limb angle steel 3 is the angle steel of certain specification, and its centre of form overlaps with the centre of form of base 2.Two erecting devices 5 are fixedly installed on the top on two limits of main limb angle steel 3 respectively, and are protruded upward by the top of main limb angle steel 3.Gusset 4 is fixedlyed connected with base 2 with main limb angle steel 3, and main limb angle steel 3 is played a supporting role.The quantity of gusset 4 is generally 4, from four direction, main limb angle steel 3 is played a supporting role, it should be noted that, in four gussets 4 two are separately positioned on two wing plates of main limb angle steel 3, two other the elongation line that the position should guarantee its vertical center line is set should be by the centre of form of main limb angle steel 3.Make the more reasonable stress of gusset 4 like this, firm more, stable to the support of main limb angle steel 3.As shown in Figure 4, also be provided with 8 mounting holes 6 on the base 2, mounting hole 6 is the circumference uniform distribution in the center of circle along the centre of form with base 2.
As shown in Figure 5, during use, at first, use bolt, detachable lower margin 1 is fixedly installed on the steel structure 7, by erecting device 5 stacker crane body 12 is connected with detachable lower margin 1 then by the mounting hole on the base 26.Because mounting hole 6 is to be provided with along the circumference uniform distribution that is the center of circle with the centre of form of base 2, so each is bolt strained evenly rationally.
Disclosed detachable lower margin in the utility model can either be arranged on the steel structure frame of building by bolt, also can equally be embedded in the concrete foundation with fixedly lower margin of the prior art.So this lower margin is applicable to various building site.Made things convenient for the layout of tower crane.And the main limb angle steel centre of form of this lower margin overlaps with the base centre of form, and the position that is provided with of four gussets has guaranteed that also each gusset is stressed evenly, and it is the circumference in the center of circle that the mounting hole that is used for being connected with steel structure that is provided with on the base is distributed on the base centre of form.Detachable lower margin and steel structure or other basic connection stability have further been guaranteed.In detachable lower margin with said structure characteristics and the prior art fixedly lower margin compare that it is highly low, so have than advantages of higher stability and rigidity.

Claims (1)

1. the detachable lower margin of tower crane is characterized by, and described detachable lower margin comprises: base, main limb angle steel, four gussets and two erecting devices; Main limb angle steel is fixedly installed on the base, and the centre of form of main limb angle steel overlaps with the centre of form of base; Two erecting devices are fixedly installed on the top on two limits of main limb angle steel respectively, and are protruded upward by the top of main limb angle steel; Gusset is fixedlyed connected with base with main limb angle steel, and main limb angle steel is played a supporting role; In four gussets two are separately positioned on two wing plates of main limb angle steel, two other the elongation line that the position should guarantee its vertical center line is set should be by the centre of form of main limb angle steel; Base is provided with 8 mounting holes, and mounting hole is the circumference uniform distribution in the center of circle along the centre of form with base.
CN2011201154920U 2011-04-19 2011-04-19 Detachable ground anchor of tower crane Expired - Lifetime CN202001787U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201154920U CN202001787U (en) 2011-04-19 2011-04-19 Detachable ground anchor of tower crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201154920U CN202001787U (en) 2011-04-19 2011-04-19 Detachable ground anchor of tower crane

Publications (1)

Publication Number Publication Date
CN202001787U true CN202001787U (en) 2011-10-05

Family

ID=44704528

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201154920U Expired - Lifetime CN202001787U (en) 2011-04-19 2011-04-19 Detachable ground anchor of tower crane

Country Status (1)

Country Link
CN (1) CN202001787U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102922241A (en) * 2012-11-23 2013-02-13 南通太平洋海洋工程有限公司 Rotary table lightering method for ocean engineering crane
CN103276742A (en) * 2013-05-28 2013-09-04 中国能源建设集团广东省电力设计研究院 Insert angle iron

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102922241A (en) * 2012-11-23 2013-02-13 南通太平洋海洋工程有限公司 Rotary table lightering method for ocean engineering crane
CN103276742A (en) * 2013-05-28 2013-09-04 中国能源建设集团广东省电力设计研究院 Insert angle iron
CN103276742B (en) * 2013-05-28 2016-02-24 中国能源建设集团广东省电力设计研究院有限公司 Inserted angle steel

Similar Documents

Publication Publication Date Title
CN203640309U (en) Adjustable pipe carrier used on large-span steel structure roof primary truss general assembly jig frame
CN203903834U (en) Internal-climbing tower crane
CN203255892U (en) Heightened gantry type crane
CN202001787U (en) Detachable ground anchor of tower crane
CN202108245U (en) Adjustable double-layer jack
CN202596242U (en) Concrete tower
CN205134966U (en) Superaltitude conversion truss hoisting device
CN205187695U (en) Steel construction has hoisted gallows
CN205314539U (en) Large -scale cantilever type combination steel form
CN203175134U (en) Truss used for lifting electric transmission line tower connecting legs
CN103397638A (en) Tie bar for supporting system in high-rigidity integral prestressed fabricated foundation pit support
CN203383563U (en) Fast assembled communication iron tower
CN202925883U (en) Large size wooden formwork surrounding purlin device
CN207795460U (en) Muscle and anchor bolt levelling device are worn with prestressing force in a kind of concrete tower high-altitude
CN203066043U (en) Diversion tunnel top arch concrete lining steel formwork support
CN202388183U (en) Lifting equipment for H-shaped steel numerical control cutting machine
CN202144673U (en) Integrated base station fixing structure
CN204023603U (en) A kind of shearing resistance screw communication base station basis
CN204000639U (en) A kind of large-scale pier stud concrete reinforcement integral hoisting mechanical splice device
CN204780985U (en) Special double -deck hi -Fix crown plate of large -scale rag bolt
CN205402659U (en) Tower foundation structure who puts power boiler furnace roof in a position
CN204703185U (en) A kind of precast reinforced concrete structure
CN109505304A (en) A kind of permafrost soil area assembled type base for power transmission line iron tower prefab-form
CN203334290U (en) Supporting rod
CN103437365B (en) The steel strand support component of pattern foundation pit supporting structure inner support system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: BEIJING ZENHE ENGINEERING EQUIPMENT SERVICES CO.,

Free format text: FORMER OWNER: BEIJING ZHONGJIAN ZHENGHE CONSTRUCTION MACHINERY CONSTRUCTION CO., LTD.

Effective date: 20121017

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20121017

Address after: 100102, Beijing, Chaoyang District, Tong Tung Street, No. 6 Fang Heng International B block, room 1207

Patentee after: BEIJING ZENHE ENGINEERING EQUIPMENT SERVICE CO., LTD.

Address before: 100102, Beijing, Chaoyang District, Tong Tung Street, No. 6 Fang Heng International B block, room 1207

Patentee before: Beijing Zhongjian Zhenghe Construction Mechanization Co., Ltd.

CX01 Expiry of patent term

Granted publication date: 20111005

CX01 Expiry of patent term