CN202954577U - Reinforced structure for bearing beam of wall-attached embedded part of large-tonnage self-climbing tower crane - Google Patents

Reinforced structure for bearing beam of wall-attached embedded part of large-tonnage self-climbing tower crane Download PDF

Info

Publication number
CN202954577U
CN202954577U CN 201220683522 CN201220683522U CN202954577U CN 202954577 U CN202954577 U CN 202954577U CN 201220683522 CN201220683522 CN 201220683522 CN 201220683522 U CN201220683522 U CN 201220683522U CN 202954577 U CN202954577 U CN 202954577U
Authority
CN
China
Prior art keywords
coupling beam
layer coupling
fitting
lower floor
tower crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220683522
Other languages
Chinese (zh)
Inventor
刘勇
贾春
林冰
钟燕
高立为
曹林
高铁成
田卫国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN 201220683522 priority Critical patent/CN202954577U/en
Application granted granted Critical
Publication of CN202954577U publication Critical patent/CN202954577U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a reinforced structure for a bearing beam of a wall-attached embedded part of a large-tonnage self-climbing tower crane. The reinforced structure comprises an upper-layer coupling beam and a lower-layer coupling beam which are arranged in a core tube and between two lateral shear walls at two sides of the core tube, wherein longitudinal bars and stirrups are arranged in both the upper-layer coupling beam and the lower-layer coupling beam, and the wall-attached embedded part is further arranged in the lower-layer coupling beam; vertical inter-beam tie bars with two ends provided with hooks are symmetrically arranged at four corners of the wall-attached embedded part between the upper-layer coupling beam and the lower-layer coupling beam, the hooks are parallel to the coupling beams and point to the center of the wall-attached embedded part, the hooks at the two ends of the inter-beam tie bars are respectively buried into the upper-layer coupling beam and the lower-layer coupling beam, and reinforced bend bars are further arranged in two ends of upper-layer coupling beam and the lower-layer coupling beam. According to the reinforced structure, the disadvantages that the site operation is complex, the mounting and dismounting are inconvenient, a large amount of steel is wasted, the reinforcing cost is relatively high and the like when a concrete beam structure is processed by utilizing external structure reinforcing methods such as external encasing of structural steel and external bonding of steel plates are solved.

Description

Large-tonnage is from the spandrel girder ruggedized construction of the tower crane attached wall built-in fitting that climbs
Technical field
The utility model relates to a kind of building reinforce structure, the ruggedized construction of particularly using on a kind of spandrel girder for large-tonnage tower crane attached wall built-in fitting when climbing.
Background technology
Along with the design height of city high building engineering is more and more higher, in order to satisfy construction requirement, generally can arrange in the inboard of high building Core Walls Structure from climbing tower crane.Tower crane generally need to arrange attached wall spandrel girder in order to climb from great in work progress, and pre-buried attached wall built-in fitting on shear wall satisfies large-tonnage from the requirement for bearing capacity of the tower crane that climbs.When the spandrel girder of attached wall built-in fitting can not bear the built-in fitting load of tower crane under the most unfavorable processing condition, just need to reinforce spandrel girder.
The reinforcing means of the concrete beam structure of China present stage generally adopt the shaped steel outsourcing, steel plate is the method for the structure external reinforcement such as sticking outward, and there are the shortcomings such as site operation is complicated, installing/dismounting is inconvenient, expend great deal of steel, the reinforcing expense is higher in the method for this structure external reinforcement.
The utility model content
The purpose of this utility model is to provide a kind of large-tonnage from the spandrel girder ruggedized construction of the tower crane attached wall built-in fitting that climbs, solve the concrete beam structure and adopt the shaped steel outsourcing, the shortcoming such as the site operation that steel plate exists during the method for the structure external reinforcement such as sticking outward is complicated, installing/dismounting is inconvenient, expend great deal of steel, the reinforcing expense is higher.
For achieving the above object, the utility model adopts following technical scheme:
a kind of large-tonnage is from the spandrel girder ruggedized construction of the tower crane attached wall built-in fitting that climbs, comprise and being arranged in Core Walls Structure, upper strata coupling beam between the shear wall of both sides and lower floor's coupling beam, be equipped with vertical muscle and stirrup in beam, also be provided with the attached wall built-in fitting in lower floor's coupling beam, between described upper strata coupling beam and lower floor's coupling beam, the Si Jiaochu of attached wall built-in fitting is arranged with steel tie between the beam of vertical two ends band crotch, described crotch is parallel with coupling beam and point to the center of attached wall built-in fitting, between beam, the crotch at steel tie two ends is imbedded respectively among upper strata coupling beam and lower floor's coupling beam, in the beam of described upper strata coupling beam and lower floor's coupling beam, two ends also are provided with the reinforcing bent-up bar.
Between described beam, steel tie divides two sections, and segmentation place is positioned at the upper surface of lower floor's coupling beam and uses reinforced bar sleeve to connect.
Described reinforcing bent-up bar is two grade reinforcing steels that are not less than diameter 28mm, and the length of its horizontal anchoring section equals original vertical muscle length in coupling beam.
Compared with prior art the utlity model has following characteristics and beneficial effect:
The utility model is to satisfy large-tonnage from the requirement for bearing capacity of the tower crane that climbs, and adopts to increase in spandrel girder and joins beam-ends reinforcing bent-up bar, and main structure body is not exerted an influence, and saves the dismounting operation, saves manpower; Between the two-layer spandrel girder in up and down, steel tie between beam is set, engineering is cut off after finishing, and the reinforcing bar that cuts off is also recycling.The advantages such as the utility model only adopts steel reinforcing to be convenient to draw materials, and has constructing operation simple, and is safe and reliable efficient, economical and practical.
Description of drawings
The utility model is described in more detail below in conjunction with accompanying drawing.
Fig. 1 is that the utility model is installed the position schematic top plan view.
Fig. 2 is the schematic side view of the direction of arrow in Fig. 1.
Fig. 3 is that the utility model increases the plan structure schematic diagram of joining reinforcing bar in lower floor's beam.
Fig. 4 is the reinforcement bar arrangement schematic diagram of the utility model first bent-up bar and rear bent-up bar in lower floor's beam.
Reference numeral: between 1-upper strata coupling beam, 2-lower floor coupling beam, 3-beam, steel tie, 4-reinforce bent-up bar after bent-up bar, the first bent-up bar of 4.1-, 4.2-, 5-attached wall built-in fitting, 6-reinforced bar sleeve, 7-shear wall, the vertical muscle of 8-, 9-spandrel girder, 10-tower crane.
The specific embodiment
Embodiment is a high building engineering, in order to satisfy the requirement of lifting construction, be provided with one from climbing tower crane 10,400 tons of tower crane 10 deadweights in the Core Walls Structure inboard, this tower crane need rely on attached wall spandrel girder 9 upwards to climb at work progress, and attached wall spandrel girder 9 need arrange 11 roads.In the present embodiment, the built-in fitting of attached wall spandrel girder is all imbedded in two coupling beams between shear wall, this coupling beam can not be born the load of tower crane attached wall built-in fitting under the most unfavorable processing condition, the size of coupling beam is 600mm * 700mm, is equipped with embedded bar in beam: comprise vertical muscle and stirrup.The reinforcement measure of this coupling beam is take the reinforcing between any two-layer coupling beam in centre as example, and is specific as follows:
Shown in Fig. 1-3, a kind of large-tonnage is from the spandrel girder ruggedized construction of the tower crane attached wall built-in fitting that climbs, comprise the upper strata coupling beam 1 and the lower floor's coupling beam 2 that are arranged in Core Walls Structure, between both sides shear wall 7, be equipped with vertical muscle 8 and stirrup in beam, also be provided with attached wall built-in fitting 5 in lower floor's coupling beam 2.
Between described upper strata coupling beam 1 and lower floor's coupling beam 2, the Si Jiaochu of attached wall built-in fitting 5 is arranged with steel tie 3 between the beam of vertical two ends band crotch, steel tie is located at four jiaos of the attached wall built-in fitting, near the position on coupling beam limit, its objective is the construction for the ease of upper strata coupling beam template.Described referring to Fig. 3, two grade reinforcing steels that the present embodiment can pre-buried 4 diameters is 40mm are as steel tie 3, upper strata coupling beam 1 and lower floor coupling beam 2 drawknots are in the same place, making the tower crane load be divided into the up and down two-layerly together bears, the crotch at two ends is imbedded respectively among upper strata coupling beam 1 and lower floor's coupling beam 2, crotch is symmetrical arranged, crotch is parallel with coupling beam and point to the center of attached wall built-in fitting 5,3 minutes two sections of steel tie between beam: lower semisection is first done pre-buried, and the soffit formwork of upper strata coupling beam 1 is held the template hole successfully and refilled upper semisection.Segmentation place is positioned at the upper surface of lower floor's coupling beam 2 and uses reinforced bar sleeve 6 to connect.
Referring to Fig. 2, shown in Figure 4, in the beam of described upper strata coupling beam 1 and lower floor's coupling beam 2, two ends also have additional and reinforce bent-up bar 4, be generally two grade reinforcing steels that are not less than diameter 28mm, reinforcing bent-up bar 4 in the present embodiment is that 6 diameters are the grade reinforcing steel of 28mm, the first bent-up bar 4.1 of the bearing of opposite end is two, rear bent-up bar 4.2 is four, and the length of its horizontal anchoring section equals original vertical muscle length in coupling beam.
In the present embodiment, the attached wall spandrel girder need arrange 11 roads, is connected by attached wall built-in fitting 5 with the coupling beam of each story shear wall of high building, the utility model is repeated construction can complete whole reinforcings.

Claims (3)

1. a large-tonnage is from the spandrel girder ruggedized construction of the tower crane attached wall built-in fitting that climbs, comprise and being arranged in Core Walls Structure, upper strata coupling beam (1) between both sides shear wall (7) and lower floor's coupling beam (2), be equipped with vertical muscle (8) and stirrup in beam, also be provided with attached wall built-in fitting (5) in lower floor's coupling beam (2), it is characterized in that: between described upper strata coupling beam (1) and lower floor's coupling beam (2), the Si Jiaochu of attached wall built-in fitting (5) is arranged with steel tie (3) between the beam of vertical two ends band crotch, described crotch is parallel with coupling beam and point to the center of attached wall built-in fitting (5), the crotch at steel tie between beam (3) two ends is imbedded respectively among upper strata coupling beam (1) and lower floor's coupling beam (2), in the beam of described upper strata coupling beam (1) and lower floor's coupling beam (2), two ends also are provided with and reinforce bent-up bar (4).
2. large-tonnage according to claim 1 is from the spandrel girder ruggedized construction of the tower crane attached wall built-in fitting that climbs, it is characterized in that: steel tie between described beam (3) minute two sections, segmentation place are positioned at the upper surface of lower floor's coupling beam (2) and use reinforced bar sleeve (6) to connect.
3. large-tonnage according to claim 1 is from the spandrel girder ruggedized construction of the tower crane attached wall built-in fitting that climbs, it is characterized in that: described reinforcing bent-up bar (4) is for being not less than two grade reinforcing steels of diameter 28mm, and the length of its horizontal anchoring section equals original vertical muscle length in coupling beam.
CN 201220683522 2012-12-12 2012-12-12 Reinforced structure for bearing beam of wall-attached embedded part of large-tonnage self-climbing tower crane Expired - Fee Related CN202954577U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220683522 CN202954577U (en) 2012-12-12 2012-12-12 Reinforced structure for bearing beam of wall-attached embedded part of large-tonnage self-climbing tower crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220683522 CN202954577U (en) 2012-12-12 2012-12-12 Reinforced structure for bearing beam of wall-attached embedded part of large-tonnage self-climbing tower crane

Publications (1)

Publication Number Publication Date
CN202954577U true CN202954577U (en) 2013-05-29

Family

ID=48460156

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220683522 Expired - Fee Related CN202954577U (en) 2012-12-12 2012-12-12 Reinforced structure for bearing beam of wall-attached embedded part of large-tonnage self-climbing tower crane

Country Status (1)

Country Link
CN (1) CN202954577U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018196453A1 (en) * 2017-04-28 2018-11-01 中国建筑股份有限公司 Tower crane climbing frame and structural support beam integrated mechanical device and using method thereof
CN110255403A (en) * 2019-06-17 2019-09-20 广西建工集团第五建筑工程有限责任公司 A kind of steel building can turnover type tower crane attached wall anchor and its installation method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018196453A1 (en) * 2017-04-28 2018-11-01 中国建筑股份有限公司 Tower crane climbing frame and structural support beam integrated mechanical device and using method thereof
CN110255403A (en) * 2019-06-17 2019-09-20 广西建工集团第五建筑工程有限责任公司 A kind of steel building can turnover type tower crane attached wall anchor and its installation method

Similar Documents

Publication Publication Date Title
CN101781878B (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
CN106337555A (en) Method for constructing triangular steel support for cantilever structure of outer wall of building
CN103215894B (en) Portable interim prestressed stretch-draw anchor block
CN203729193U (en) Low tower stay cable reinforced T-type rigid framework system with suspension beams
CN203834373U (en) Lifting movement mold carriage trolley for box culvert side wall formwork
CN105239510A (en) Dismounting beam support used for high pier small-radius curve cast-in-situ box beam and construction method
CN103821359A (en) Large-cross-section concrete beam layered casting construction method
CN102926504A (en) Connecting steel construction member for steel and concrete overlapped beam combined part and construction method thereof
CN106978909A (en) A kind of method that beams of concrete is connected with profile steel concrete column joint reinforcing bar
CN102134832B (en) Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane
CN103938871B (en) A kind of construction method adopting the steel core concrete column bonded prestress frame beam structure of reinforced concrete ring beam joint
CN205501843U (en) Consolidate rigid framed arch bridge
CN202954577U (en) Reinforced structure for bearing beam of wall-attached embedded part of large-tonnage self-climbing tower crane
CN103993739B (en) The construction method of granulation tower spraying layer stiff beam
CN203795311U (en) Multi-leg high pier and slip form construction device
CN103696567B (en) The construction method of assembling concrete in mass beam is built with Special supporting device
CN103552911B (en) A kind of movable boom hoisting and the construction installation method of use thereof
CN203034799U (en) Tower hoist standard knot bearing overhead support formwork steel platform structure
CN201567784U (en) City elevated collision-preventing wall formwork and scaffold combination device
CN103046743A (en) High-rise conversion layer type steel concrete girder hanging type template supporting system and construction method
CN102605945B (en) Manufacturing method of big wood formwork
CN201588172U (en) Integral single-tower non-dorsal-cord cable-stayed-bridge king tower lifting template
CN205296821U (en) Oblique roofing formwork system of heavy grade cast in situ concrete
CN210530314U (en) Formwork frame is pour to steel concrete combination shear wall T type node
CN209397926U (en) A kind of elevator fence operation platform structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130529

Termination date: 20131212