CN202954577U - Reinforced structure for bearing beam of wall-attached embedded part of large-tonnage self-climbing tower crane - Google Patents
Reinforced structure for bearing beam of wall-attached embedded part of large-tonnage self-climbing tower crane Download PDFInfo
- Publication number
- CN202954577U CN202954577U CN 201220683522 CN201220683522U CN202954577U CN 202954577 U CN202954577 U CN 202954577U CN 201220683522 CN201220683522 CN 201220683522 CN 201220683522 U CN201220683522 U CN 201220683522U CN 202954577 U CN202954577 U CN 202954577U
- Authority
- CN
- China
- Prior art keywords
- coupling beam
- layer coupling
- fitting
- lower floor
- tower crane
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model relates to a reinforced structure for a bearing beam of a wall-attached embedded part of a large-tonnage self-climbing tower crane. The reinforced structure comprises an upper-layer coupling beam and a lower-layer coupling beam which are arranged in a core tube and between two lateral shear walls at two sides of the core tube, wherein longitudinal bars and stirrups are arranged in both the upper-layer coupling beam and the lower-layer coupling beam, and the wall-attached embedded part is further arranged in the lower-layer coupling beam; vertical inter-beam tie bars with two ends provided with hooks are symmetrically arranged at four corners of the wall-attached embedded part between the upper-layer coupling beam and the lower-layer coupling beam, the hooks are parallel to the coupling beams and point to the center of the wall-attached embedded part, the hooks at the two ends of the inter-beam tie bars are respectively buried into the upper-layer coupling beam and the lower-layer coupling beam, and reinforced bend bars are further arranged in two ends of upper-layer coupling beam and the lower-layer coupling beam. According to the reinforced structure, the disadvantages that the site operation is complex, the mounting and dismounting are inconvenient, a large amount of steel is wasted, the reinforcing cost is relatively high and the like when a concrete beam structure is processed by utilizing external structure reinforcing methods such as external encasing of structural steel and external bonding of steel plates are solved.
Description
Technical field
The utility model relates to a kind of building reinforce structure, the ruggedized construction of particularly using on a kind of spandrel girder for large-tonnage tower crane attached wall built-in fitting when climbing.
Background technology
Along with the design height of city high building engineering is more and more higher, in order to satisfy construction requirement, generally can arrange in the inboard of high building Core Walls Structure from climbing tower crane.Tower crane generally need to arrange attached wall spandrel girder in order to climb from great in work progress, and pre-buried attached wall built-in fitting on shear wall satisfies large-tonnage from the requirement for bearing capacity of the tower crane that climbs.When the spandrel girder of attached wall built-in fitting can not bear the built-in fitting load of tower crane under the most unfavorable processing condition, just need to reinforce spandrel girder.
The reinforcing means of the concrete beam structure of China present stage generally adopt the shaped steel outsourcing, steel plate is the method for the structure external reinforcement such as sticking outward, and there are the shortcomings such as site operation is complicated, installing/dismounting is inconvenient, expend great deal of steel, the reinforcing expense is higher in the method for this structure external reinforcement.
The utility model content
The purpose of this utility model is to provide a kind of large-tonnage from the spandrel girder ruggedized construction of the tower crane attached wall built-in fitting that climbs, solve the concrete beam structure and adopt the shaped steel outsourcing, the shortcoming such as the site operation that steel plate exists during the method for the structure external reinforcement such as sticking outward is complicated, installing/dismounting is inconvenient, expend great deal of steel, the reinforcing expense is higher.
For achieving the above object, the utility model adopts following technical scheme:
a kind of large-tonnage is from the spandrel girder ruggedized construction of the tower crane attached wall built-in fitting that climbs, comprise and being arranged in Core Walls Structure, upper strata coupling beam between the shear wall of both sides and lower floor's coupling beam, be equipped with vertical muscle and stirrup in beam, also be provided with the attached wall built-in fitting in lower floor's coupling beam, between described upper strata coupling beam and lower floor's coupling beam, the Si Jiaochu of attached wall built-in fitting is arranged with steel tie between the beam of vertical two ends band crotch, described crotch is parallel with coupling beam and point to the center of attached wall built-in fitting, between beam, the crotch at steel tie two ends is imbedded respectively among upper strata coupling beam and lower floor's coupling beam, in the beam of described upper strata coupling beam and lower floor's coupling beam, two ends also are provided with the reinforcing bent-up bar.
Between described beam, steel tie divides two sections, and segmentation place is positioned at the upper surface of lower floor's coupling beam and uses reinforced bar sleeve to connect.
Described reinforcing bent-up bar is two grade reinforcing steels that are not less than diameter 28mm, and the length of its horizontal anchoring section equals original vertical muscle length in coupling beam.
Compared with prior art the utlity model has following characteristics and beneficial effect:
The utility model is to satisfy large-tonnage from the requirement for bearing capacity of the tower crane that climbs, and adopts to increase in spandrel girder and joins beam-ends reinforcing bent-up bar, and main structure body is not exerted an influence, and saves the dismounting operation, saves manpower; Between the two-layer spandrel girder in up and down, steel tie between beam is set, engineering is cut off after finishing, and the reinforcing bar that cuts off is also recycling.The advantages such as the utility model only adopts steel reinforcing to be convenient to draw materials, and has constructing operation simple, and is safe and reliable efficient, economical and practical.
Description of drawings
The utility model is described in more detail below in conjunction with accompanying drawing.
Fig. 1 is that the utility model is installed the position schematic top plan view.
Fig. 2 is the schematic side view of the direction of arrow in Fig. 1.
Fig. 3 is that the utility model increases the plan structure schematic diagram of joining reinforcing bar in lower floor's beam.
Fig. 4 is the reinforcement bar arrangement schematic diagram of the utility model first bent-up bar and rear bent-up bar in lower floor's beam.
Reference numeral: between 1-upper strata coupling beam, 2-lower floor coupling beam, 3-beam, steel tie, 4-reinforce bent-up bar after bent-up bar, the first bent-up bar of 4.1-, 4.2-, 5-attached wall built-in fitting, 6-reinforced bar sleeve, 7-shear wall, the vertical muscle of 8-, 9-spandrel girder, 10-tower crane.
The specific embodiment
Embodiment is a high building engineering, in order to satisfy the requirement of lifting construction, be provided with one from climbing tower crane 10,400 tons of tower crane 10 deadweights in the Core Walls Structure inboard, this tower crane need rely on attached wall spandrel girder 9 upwards to climb at work progress, and attached wall spandrel girder 9 need arrange 11 roads.In the present embodiment, the built-in fitting of attached wall spandrel girder is all imbedded in two coupling beams between shear wall, this coupling beam can not be born the load of tower crane attached wall built-in fitting under the most unfavorable processing condition, the size of coupling beam is 600mm * 700mm, is equipped with embedded bar in beam: comprise vertical muscle and stirrup.The reinforcement measure of this coupling beam is take the reinforcing between any two-layer coupling beam in centre as example, and is specific as follows:
Shown in Fig. 1-3, a kind of large-tonnage is from the spandrel girder ruggedized construction of the tower crane attached wall built-in fitting that climbs, comprise the upper strata coupling beam 1 and the lower floor's coupling beam 2 that are arranged in Core Walls Structure, between both sides shear wall 7, be equipped with vertical muscle 8 and stirrup in beam, also be provided with attached wall built-in fitting 5 in lower floor's coupling beam 2.
Between described upper strata coupling beam 1 and lower floor's coupling beam 2, the Si Jiaochu of attached wall built-in fitting 5 is arranged with steel tie 3 between the beam of vertical two ends band crotch, steel tie is located at four jiaos of the attached wall built-in fitting, near the position on coupling beam limit, its objective is the construction for the ease of upper strata coupling beam template.Described referring to Fig. 3, two grade reinforcing steels that the present embodiment can pre-buried 4 diameters is 40mm are as steel tie 3, upper strata coupling beam 1 and lower floor coupling beam 2 drawknots are in the same place, making the tower crane load be divided into the up and down two-layerly together bears, the crotch at two ends is imbedded respectively among upper strata coupling beam 1 and lower floor's coupling beam 2, crotch is symmetrical arranged, crotch is parallel with coupling beam and point to the center of attached wall built-in fitting 5,3 minutes two sections of steel tie between beam: lower semisection is first done pre-buried, and the soffit formwork of upper strata coupling beam 1 is held the template hole successfully and refilled upper semisection.Segmentation place is positioned at the upper surface of lower floor's coupling beam 2 and uses reinforced bar sleeve 6 to connect.
Referring to Fig. 2, shown in Figure 4, in the beam of described upper strata coupling beam 1 and lower floor's coupling beam 2, two ends also have additional and reinforce bent-up bar 4, be generally two grade reinforcing steels that are not less than diameter 28mm, reinforcing bent-up bar 4 in the present embodiment is that 6 diameters are the grade reinforcing steel of 28mm, the first bent-up bar 4.1 of the bearing of opposite end is two, rear bent-up bar 4.2 is four, and the length of its horizontal anchoring section equals original vertical muscle length in coupling beam.
In the present embodiment, the attached wall spandrel girder need arrange 11 roads, is connected by attached wall built-in fitting 5 with the coupling beam of each story shear wall of high building, the utility model is repeated construction can complete whole reinforcings.
Claims (3)
1. a large-tonnage is from the spandrel girder ruggedized construction of the tower crane attached wall built-in fitting that climbs, comprise and being arranged in Core Walls Structure, upper strata coupling beam (1) between both sides shear wall (7) and lower floor's coupling beam (2), be equipped with vertical muscle (8) and stirrup in beam, also be provided with attached wall built-in fitting (5) in lower floor's coupling beam (2), it is characterized in that: between described upper strata coupling beam (1) and lower floor's coupling beam (2), the Si Jiaochu of attached wall built-in fitting (5) is arranged with steel tie (3) between the beam of vertical two ends band crotch, described crotch is parallel with coupling beam and point to the center of attached wall built-in fitting (5), the crotch at steel tie between beam (3) two ends is imbedded respectively among upper strata coupling beam (1) and lower floor's coupling beam (2), in the beam of described upper strata coupling beam (1) and lower floor's coupling beam (2), two ends also are provided with and reinforce bent-up bar (4).
2. large-tonnage according to claim 1 is from the spandrel girder ruggedized construction of the tower crane attached wall built-in fitting that climbs, it is characterized in that: steel tie between described beam (3) minute two sections, segmentation place are positioned at the upper surface of lower floor's coupling beam (2) and use reinforced bar sleeve (6) to connect.
3. large-tonnage according to claim 1 is from the spandrel girder ruggedized construction of the tower crane attached wall built-in fitting that climbs, it is characterized in that: described reinforcing bent-up bar (4) is for being not less than two grade reinforcing steels of diameter 28mm, and the length of its horizontal anchoring section equals original vertical muscle length in coupling beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220683522 CN202954577U (en) | 2012-12-12 | 2012-12-12 | Reinforced structure for bearing beam of wall-attached embedded part of large-tonnage self-climbing tower crane |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220683522 CN202954577U (en) | 2012-12-12 | 2012-12-12 | Reinforced structure for bearing beam of wall-attached embedded part of large-tonnage self-climbing tower crane |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202954577U true CN202954577U (en) | 2013-05-29 |
Family
ID=48460156
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220683522 Expired - Fee Related CN202954577U (en) | 2012-12-12 | 2012-12-12 | Reinforced structure for bearing beam of wall-attached embedded part of large-tonnage self-climbing tower crane |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202954577U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2018196453A1 (en) * | 2017-04-28 | 2018-11-01 | 中国建筑股份有限公司 | Tower crane climbing frame and structural support beam integrated mechanical device and using method thereof |
CN110255403A (en) * | 2019-06-17 | 2019-09-20 | 广西建工集团第五建筑工程有限责任公司 | A kind of steel building can turnover type tower crane attached wall anchor and its installation method |
-
2012
- 2012-12-12 CN CN 201220683522 patent/CN202954577U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2018196453A1 (en) * | 2017-04-28 | 2018-11-01 | 中国建筑股份有限公司 | Tower crane climbing frame and structural support beam integrated mechanical device and using method thereof |
CN110255403A (en) * | 2019-06-17 | 2019-09-20 | 广西建工集团第五建筑工程有限责任公司 | A kind of steel building can turnover type tower crane attached wall anchor and its installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101781878B (en) | Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof | |
CN106337555A (en) | Method for constructing triangular steel support for cantilever structure of outer wall of building | |
CN103215894B (en) | Portable interim prestressed stretch-draw anchor block | |
CN203729193U (en) | Low tower stay cable reinforced T-type rigid framework system with suspension beams | |
CN203834373U (en) | Lifting movement mold carriage trolley for box culvert side wall formwork | |
CN105239510A (en) | Dismounting beam support used for high pier small-radius curve cast-in-situ box beam and construction method | |
CN103821359A (en) | Large-cross-section concrete beam layered casting construction method | |
CN102926504A (en) | Connecting steel construction member for steel and concrete overlapped beam combined part and construction method thereof | |
CN106978909A (en) | A kind of method that beams of concrete is connected with profile steel concrete column joint reinforcing bar | |
CN102134832B (en) | Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane | |
CN103938871B (en) | A kind of construction method adopting the steel core concrete column bonded prestress frame beam structure of reinforced concrete ring beam joint | |
CN205501843U (en) | Consolidate rigid framed arch bridge | |
CN202954577U (en) | Reinforced structure for bearing beam of wall-attached embedded part of large-tonnage self-climbing tower crane | |
CN103993739B (en) | The construction method of granulation tower spraying layer stiff beam | |
CN203795311U (en) | Multi-leg high pier and slip form construction device | |
CN103696567B (en) | The construction method of assembling concrete in mass beam is built with Special supporting device | |
CN103552911B (en) | A kind of movable boom hoisting and the construction installation method of use thereof | |
CN203034799U (en) | Tower hoist standard knot bearing overhead support formwork steel platform structure | |
CN201567784U (en) | City elevated collision-preventing wall formwork and scaffold combination device | |
CN103046743A (en) | High-rise conversion layer type steel concrete girder hanging type template supporting system and construction method | |
CN102605945B (en) | Manufacturing method of big wood formwork | |
CN201588172U (en) | Integral single-tower non-dorsal-cord cable-stayed-bridge king tower lifting template | |
CN205296821U (en) | Oblique roofing formwork system of heavy grade cast in situ concrete | |
CN210530314U (en) | Formwork frame is pour to steel concrete combination shear wall T type node | |
CN209397926U (en) | A kind of elevator fence operation platform structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |