CN202936805U - Foundation for treating deep collapsible loess - Google Patents

Foundation for treating deep collapsible loess Download PDF

Info

Publication number
CN202936805U
CN202936805U CN 201220596935 CN201220596935U CN202936805U CN 202936805 U CN202936805 U CN 202936805U CN 201220596935 CN201220596935 CN 201220596935 CN 201220596935 U CN201220596935 U CN 201220596935U CN 202936805 U CN202936805 U CN 202936805U
Authority
CN
China
Prior art keywords
header
collapsible loess
french drain
cushion layer
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220596935
Other languages
Chinese (zh)
Inventor
彭亦亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hennan Electric Power Survey and Design Institute
Original Assignee
Hennan Electric Power Survey and Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hennan Electric Power Survey and Design Institute filed Critical Hennan Electric Power Survey and Design Institute
Priority to CN 201220596935 priority Critical patent/CN202936805U/en
Application granted granted Critical
Publication of CN202936805U publication Critical patent/CN202936805U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model provides a foundation for treating deep collapsible loess, wherein two-eight ash-soil cushion layer is paved on the treated region dynamically compacted previously; a blind ditch is formed on the two-eight ash-soil cushion layer; a water collecting pipe is laid in the blind ditch and a round hole is formed on the water collecting pipe; and the water collecting pipe is communicated with a water catchment pipe. The foundation with the technical scheme is characterized in that the collapsible loess of the top layer is excavated and then dynamic compaction is performed in the foundation pit, the two-eight ash-soil cushion layer which is 3 m thick is then formed on the dynamic compaction surface after the completion of dynamic compaction, and finally, the blind ditch is formed on the cushion layer. The dynamically compacted soil is obviously improved in bearing capacity; the two-eight ash-soil cushion layer is capable of functioning as a short-term water isolation layer, and the blind ditch formed on the cushion layer is capable of draining surface water penetrating on the cushion layer in time, so that the water is prevented from penetrating into the soil of the lower part to cause collapse; and therefore, the safety of the structure is guaranteed.

Description

A kind of ground of processing deep layer collapsible loess
Technical field
The utility model relates to a kind of brand-new deep layer collapsible loess foundation and processes means.
Background technology
Collapsible loess is wider in China's distribution, and saturated yielding grade and soil thickness differ, and need adopt pile foundation to penetrate yellow soil horizon of collapsibility or adopt method for processing foundation to process the following whole yellow soil horizon of collapsibility of foundation bed when building the Class A building on the self weight collapse loess place.If adopt the pile foundation expense higher when deep layer collapsible loess carries out the basic engineering of Class A building, adopt strong rammer or change method for processing foundation such as filling out bed course when deep layer collapsible loess processed thicker because of yellow soil horizon of collapsibility, be difficult to all eliminate the settlement by soakings of soil layers.
Summary of the invention
For overcoming above-mentioned deficiency, the utility model proposes a kind of brand-new deep layer collapsible loess processing method, can effectively prevent deep layer collapsible loess generation saturated yielding, and significantly improve soil body supporting capacity, save investment.
For achieving the above object, the utility model is by the following technical solutions:
A kind of ground of processing deep layer collapsible loess, it is included in lays sixteen cushion limes on processing region after strong rammer, lay french drain on sixteen cushion limes, lays header in described french drain, have circular hole on header, and header communicates with collection pipe.
Bottom of trench at french drain arranges sand-gravel cushion, and every limit of sand-gravel cushion all is wider than french drain.
Bottom of trench and sidewall at french drain are laid geotextiles, lay the cobble loaded filter between header and geotextiles, at geotextiles outside laying medium sand loaded filter.
Axially at interval of 40m, a manhole is set along described header.
Header in described french drain adopts pvc pipe, and makes a call to 12 along all equally distributed circular holes of pipe, circular hole aperture 12mm interlacing interlaced arrangement on header along header longitudinal separation 150mm.
Adopt the utility model of technique scheme, first the collapsible loess on upper strata excavated, carry out afterwards strong rammer in foundation ditch, do sixteen thick cushion limes of 3m after strong rammer is completed on the strong rammer face, french drain is set on bed course at last.Soil body supporting capacity after strong rammer significantly improves, and sixteen cushion limes can play the effect of short-term water barrier, and the french drain that is arranged on a bed course can in time be drained the surface water that infiltrates on bed course, and anti-sealing infiltrates and causes saturated yielding to guarantee structural safety in the soil body of bottom.
Fig. 1 is layout plan of the present utility model.
Fig. 2 is french drain profile in the utility model.
The specific embodiment
As shown in Figure 1 and Figure 2, a kind of ground of processing deep layer collapsible loess, strong rammer after excavating on full wafer processing region 9, and sixteen cushion limes after strong rammer face upper berth 3m, along processing region periphery french drain 1, and look for the slope by arrow direction indication in Fig. 1, provide safeguard for natural drainage is unobstructed.At the interior laying header 2 of french drain 1, have circular hole on header 2, and header 2 communicates with collection pipe 4.
The specific practice of french drain 1 is as follows:
(1) header in french drain 12 adopts pvc pipe, and the caliber of header 2 is selected according to amount of precipitation, and makes a call to 12 along all equally distributed circular holes of pipe, circular hole aperture 12mm interlacing interlaced arrangement on pipe along pipe longitudinal separation 150mm.
(2) at 1 end of ditch, the thick sand-gravel cushion of 100mm 8 is set, every hem width of sand-gravel cushion 8 goes out french drain 100mm.
(3) lay geotextiles 6 at bottom of trench and the sidewall of french drain 1, to cut apart cobble loaded filter 5 and medium sand loaded filter 7, geotextiles 6 is not less than 100mm in french drain lap length suitable for reading, and along underflow direction overlap joint.
(4) in the french drain of completing geotextiles 6, be between geotextiles 6 and header 2, cobble loaded filter 5 to be set, the cobble loaded filter is selected the clean cobble of 5~10mm, and the boulder bed of header 2 bottoms part should be looked for the slope by the gradient of header 2 when laying the cobble loaded filter, is strictly on guard against refluence.
(5) side of french drain 1 and end face setting are not less than the thick medium sand loaded filter 7 of 200mm.
Need to prove, above-mentioned cobble loaded filter 5 and medium sand loaded filter 7 can prevent effectively in Precipitation Process that foreign material from entering or stopping up header.
Due to the existence of french drain 1 and the reasonability of structure, make the enough filtrations by loaded filter of the surface water that infiltrates on sixteen cushion limes successfully enter in header 2.Axially at interval of about 40m, a manhole 3 can be set along header 2, with the silt in water in the sedimentation and drawing process, guarantee the unobstructed of header.By the precipitation of manhole 3 and enter in collection pipe 4 along drainage grade, finally pour in drainage pipeline networks, realized the function of draining, anti-sealing enters lower floor's soil body and produces saturated yielding.

Claims (5)

1. ground of processing deep layer collapsible loess, it is characterized in that: it is included in upper sixteen cushion limes of laying of processing region (9) after strong rammer, lay french drain (1) on sixteen cushion limes, lay header (2) in described french drain (1), header has circular hole on (2), and header (2) communicates with collection pipe (4).
2. the ground of the deep layer of processing according to claim 1 collapsible loess, it is characterized in that: the bottom of trench at described french drain (1) arranges sand-gravel cushion (8), and every limit of sand-gravel cushion (8) all is wider than french drain (1).
3. the ground of the deep layer of processing according to claim 1 collapsible loess, it is characterized in that: bottom of trench and sidewall at described french drain (1) are laid geotextiles (6), lay cobble loaded filter (5) between header (2) and geotextiles (6), at geotextiles (6) outside laying medium sand loaded filter (7).
4. the ground of the deep layer of processing according to claim 1 collapsible loess, is characterized in that: axially at interval of 40m, a manhole (3) is set along described header (2).
5. the ground of the deep layer of processing according to claim 1 collapsible loess, it is characterized in that: the header (2) in described french drain (1) adopts pvc pipe, and upward make a call to 12 along all equally distributed circular holes of pipe, circular hole aperture 12mm interlacing interlaced arrangement along header (2) longitudinal separation 150mm at header (2).
CN 201220596935 2012-11-14 2012-11-14 Foundation for treating deep collapsible loess Expired - Fee Related CN202936805U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220596935 CN202936805U (en) 2012-11-14 2012-11-14 Foundation for treating deep collapsible loess

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220596935 CN202936805U (en) 2012-11-14 2012-11-14 Foundation for treating deep collapsible loess

Publications (1)

Publication Number Publication Date
CN202936805U true CN202936805U (en) 2013-05-15

Family

ID=48321051

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220596935 Expired - Fee Related CN202936805U (en) 2012-11-14 2012-11-14 Foundation for treating deep collapsible loess

Country Status (1)

Country Link
CN (1) CN202936805U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106337422A (en) * 2016-08-31 2017-01-18 西安长庆科技工程有限责任公司 Method for treating fill foundation of collapsible loess area
CN107268580A (en) * 2016-04-09 2017-10-20 河南城建学院 Collapsible loess composite foundation water proof ponding system and its application method
CN108547281A (en) * 2018-06-25 2018-09-18 中国电建集团中南勘测设计研究院有限公司 Accelerate the discharge structure and its construction method of dyke strengthening by warping engineering silt back of the body body consolidation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107268580A (en) * 2016-04-09 2017-10-20 河南城建学院 Collapsible loess composite foundation water proof ponding system and its application method
CN106337422A (en) * 2016-08-31 2017-01-18 西安长庆科技工程有限责任公司 Method for treating fill foundation of collapsible loess area
CN106337422B (en) * 2016-08-31 2018-09-04 西安长庆科技工程有限责任公司 A method of processing Collapsible Loess District fill foundation
CN108547281A (en) * 2018-06-25 2018-09-18 中国电建集团中南勘测设计研究院有限公司 Accelerate the discharge structure and its construction method of dyke strengthening by warping engineering silt back of the body body consolidation

Similar Documents

Publication Publication Date Title
CN105201002B (en) A kind of underground structure oozes drainage system and its construction method
CN201896316U (en) System for reducing and draining confined water in deep foundation pit of rock foundation
CN109797769B (en) Collapsible loess area underground comprehensive pipe gallery foundation structure and construction method thereof
CN102296572B (en) Earth and rockfill dam body seepage monitoring structure provided with abandoned dreg site behind dam and construction method thereof
CN205152889U (en) Reservoir falling zone stable structure
CN103046565A (en) Draining method for ultra-deep batholith deep foundation pit
CN106087953B (en) A kind of drainage and construction method for preventing and treating mountain area large size spoil ground mud-rock flow
CN205152970U (en) Underground structure oozes drainage system
CN101220589B (en) Soil engineering bag and method for dynamically squeezing and synthetically reinforcing soft groundwork
CN105179011A (en) Tunnel plugging facility and tunnel plugging method
CN110847199A (en) Construction method for drainage of underground water of deep foundation pit
CN202936805U (en) Foundation for treating deep collapsible loess
CN110306565A (en) A kind of Road ecology slope protection system and construction method
CN109940033B (en) Foreign soil restoration method for farmland heavy metal pollution
KR101127810B1 (en) Method and structure for getting underground water
CN202627002U (en) Tailing dam for water-inrush section of river-cut tailing pond
CN105672242A (en) Consolidating and water draining system and method for coal cinder yard of coal-fired power plant
CN107724405B (en) Dewatering of foundation construction method in a kind of underground pipe construction
CN202181539U (en) Dam body seepage monitoring structure used for earth-rock dam with abandoned dreg site arranged behind
CN209816896U (en) Collapsible loess area utility tunnel foundation structure
CN115045311A (en) Method for combining foundation pit drainage and structure anti-floating
CN113882491A (en) Method for reducing infiltration line of tailing pond or phosphogypsum pond
CN211228563U (en) Assembled groundwater drainage blind ditch drainage system that oozes
CN210086317U (en) Leachate leakage detection collection structure
CN203977434U (en) The foundation pit enclosure structure of deep In Soft Muddy Soil Region

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130515

Termination date: 20161114