CN202895412U CN 201220622060 CN201220622060U CN202895412U CN 202895412 U CN202895412 U CN 202895412U CN 201220622060 CN201220622060 CN 201220622060 CN 201220622060 U CN201220622060 U CN 201220622060U CN 202895412 U CN202895412 U CN 202895412U
Authority
CN
China
Prior art keywords
mixer
discharging opening
injection molding
frame
crane rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220622060
Other languages
Chinese (zh)
Inventor
许迪茗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Ouk Building Materials Science & Technology Co Ltd
Original Assignee
Sichuan Ouk Building Materials Science & Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Ouk Building Materials Science & Technology Co Ltd filed Critical Sichuan Ouk Building Materials Science & Technology Co Ltd
Priority to CN 201220622060 priority Critical patent/CN202895412U/en
Application granted granted Critical
Publication of CN202895412U publication Critical patent/CN202895412U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to production equipment of a wallboard, in particular to a double-line automatic production line of the building wallboard. In order to solve the problem that the cost of a production line in the prior art is high, the double-line automatic production line of the building wallboard which comprises a rack, a material conveying device, a casting mould continuous operation device, a pouring funnel and a blender is provided. The material conveying device is arranged beside the rack, the casting mould continuous operation device is arranged on the rack, the pouring funnel and the blender are arranged on the rack and placed above the casting mould continuous operation device. The blender is provided with a side material outlet and a bottom material outlet. The side material outlet is placed in the side face of the blender, the bottom outlet is placed in the bottom of the blender and above the rack, and the material conveying device is arranged between a casting body and the side material outlet of the blender. The double-line automatic production line is used, cheap casting equipment is used, so that the production cost of the production line is lowered, and blending process and casting process can be completed automatically so that labor intensity is lowered.

Description

Building wall board two-wire automatic assembly line
Technical field
The utility model relates to wallboard manufacture equipment, especially a kind of building wall board two-wire automatic assembly line.
Background technology
At present, the production of wallboard is the production of mainly adopting the hand process separate type, and laying the operations such as fiber cloth, cast slurry, cut-out all is to be undertaken by manual.Production process is all finished at production platform, the workman is according to the ingredient composition of slurry, give again mixer after material is assorted and stir, with the good slurry of barreled, manually the length of fiber cloth is cut and is deposited in according to the length of watering injection molding and width with width after stirring is finished.The workman will shear good fiber cloth and be laid on and water on the injection molding, then manually the slurry in the bucket will be poured into to complete the watering on the injection molding of bottom fiber cloth, and sandwich or sandwich mould are installed behind the casting complete, and hand dropping upper strata slurry is laid top fiber cloth again.After slurry solidifies, if the centre is the sandwich mould of extraction of the sandwich mould installed, finish like this production of wallboard.So artificial productive labor intensity is high, and production efficiency is also slow, so the manual production of wallboard is made into streamline production.Need to pour into a mould bottom and cast upper strata two procedures in the production process of streamline wallboard, so a production line is poured into a mould with regard to two mixers of needs, and every all needs workman's deallocation material.Because adopted two mixers, and the cost of mixer is higher, so the cost of this production line is very high, and workman's labour intensity is higher.
The utility model content
Technical problem to be solved in the utility model provides a kind of lower-cost building wall board two-wire automatic assembly line.
The technical scheme that its technical problem that solves the utility model adopts is: building wall board two-wire automatic assembly line, comprise frame, at the other conveying device that arranges of frame, the rack-mounted injection molding continuous operation device that waters, be installed on the frame and the interval is arranged in depositing funnel and the mixer that waters injection molding continuous operation device top, mixer has side discharging opening and end discharging opening, the side discharging opening is positioned at the side of mixer, end discharging opening is positioned at the bottom of mixer and above frame, conveying device is arranged between the side discharging opening of depositing funnel and mixer.
The described injection molding continuous operation device that waters comprises rack-mounted motor, belt, roller, and motor and roller are in transmission connection, and belt and roller are in transmission connection.
The next door of described mixer is provided with material conveyer belt and material tower, and mixer links to each other with the material tower by material conveyer belt.
Described conveying device comprises dumper and Crane Rail, and dumper is installed on the Crane Rail.
Described Crane Rail is parallel with frame.
Described depositing funnel is consistent with the length of Crane Rail to the distance between the side discharging opening, and the two ends of Crane Rail are provided with stopping means.
The beneficial effects of the utility model are: adopt two-wire automatic assembly line of the present utility model, owing to having adopted more cheap casting equipment, so reduced the production cost of production line, and blending process and casting process can finish automatically, reduce like this labour intensity.
Description of drawings
Fig. 1 is structured flowchart of the present utility model;
Fig. 2 is structural representation of the present utility model;
Fig. 3 is the bottom surface structure schematic diagram of mixer.
Shown in the figure: 1-mixer, 2-depositing funnel, 3-conveying device, the 4-Crane Rail, 5-stopping means, discharging opening at the bottom of the 6-, the 7-dumper, 8-frame, 9-material conveyer belt, 10-expects tower, and 11-waters injection molding, 12-side discharging opening, 13-waters injection molding continuous operation device, the 14-motor, 15-belt, 16-roller.
The specific embodiment
Below in conjunction with drawings and Examples the utility model is further specified.
Such as Fig. 1, Fig. 2, shown in Figure 3, building wall board two-wire automatic assembly line of the present utility model, comprise frame 8, at the frame 8 other conveying devices 3 that arrange, be installed in and water injection molding continuous operation device 13 on the frame 8, be installed on the frame 8 and the interval is arranged in depositing funnel 2 and the mixer 1 that waters injection molding continuous operation device 13 tops, mixer 1 has side discharging opening 12 and end discharging opening 6, side discharging opening 12 is positioned at the side of mixer 1, end discharging opening 6 is positioned at the bottom of mixer 1 and above frame 8, conveying device 3 is arranged between the side discharging opening 12 of depositing funnel 2 and mixer 1.Because in the production process of wallboard, watering injection molding 11 is watering on the injection molding continuous apparatus 13, the workman sets a layer fiber cloth watering injection molding 11 upper berths, water injection molding 11 through mixer 1, the end discharging opening 6 of mixer 1 is cast in slurry on lower floor's fiber cloth, the workman installs sandwich at slurry, water injection molding 11 and pass through again mixer 1, mixer 1 is cast in slurry on the sandwich, water injection molding 11 and continue to finish the operations such as top fiber cloth laying watering injection molding continuous operation device 13, then need two mixers 1 pour into a mould and the cost of mixer 1 more expensive, depositing funnel 2 simple in structure, cost is lower, select depositing funnel 2 to replace wherein mixer 1, saved cost.Will finish the operation that sandwich is installed because water injection molding 11 between through mixer 1 and depositing funnel 2, so need that the interval is arranged between mixer 1 and the depositing funnel 2, then mixer 1 has the interval with depositing funnel 2 in frame 8.Because depositing funnel 2 can't stir slurry, then depositing funnel 2 need to be from mixer 1 transportation slurry, so being set between the side discharging opening 12 of mixer 1 and the depositing funnel 2, the slurry that conveying device 3 just can finish mixer 1 is transported to depositing funnel 2, it is other that conveying device 3 is arranged on frame 8, and conveying device 3 just can not have influence on the casting process of depositing funnel 2 and mixer 1 like this.Because mixer 1 can be cast in slurry on lower floor's fiber cloth or with slurry and be cast on the sandwich, depositing funnel 2 also can be cast in slurry on lower floor's fiber cloth or with slurry and be cast on the sandwich, then water injection molding 11 after watering injection molding continuous operation device 13 to pass through first mixer 1 during through depositing funnel 2, production process is: mixer 1 stirs slurry, slurry is transported in the depositing funnel 2 by conveying device 3, and haul is to repeat continuously, start and water injection molding continuous apparatus 13, watering injection molding 11 is watering on the injection molding continuous apparatus 13, the workman sets a layer fiber cloth watering injection molding 11 upper berths, through mixer 1, the end discharging opening 6 of mixer 1 is cast in slurry on lower floor's fiber cloth, the workman installs sandwich at slurry, water injection molding 11 and pass through again depositing funnel 2, depositing funnel 2 is cast in slurry on the sandwich, waters injection molding 11 and continues to finish the operations such as top fiber cloth laying watering injection molding continuous operation device 13, finishes at last the production of whole wallboard.During through mixer 1, the whole production process of wallboard is exactly that depositing funnel 2 is cast in slurry on lower floor's fiber cloth after watering injection molding 11 to pass through first depositing funnel 2, and mixer 1 is cast in slurry on the sandwich, and remaining operation is all consistent with above-mentioned whole production process.Conveying arrangement 3 is transported to supply line of depositing funnel 2 interior formations with slurry from mixer 1 like this, water injection molding 11 and finish to produce and consist of a production line watering on the injection molding continuous operation device 13 continuous operation, namely these two lines consist of a wallboard two-wire automatic assembly line.
The described injection molding continuous operation device 13 that waters can be the driven by motor sprocket rotation, and sprocket wheel drives chain movement or driven by motor roller turn, and roller drives the belt strip motion.The cost of sprocket wheel and chain is greater than the cost of roller and belt strip.Therefore, as preferred embodiment, the described injection molding continuous operation device 13 that waters comprises motor 14, belt 15, the roller 16 that is installed on the frame 8, and motor 14 is in transmission connection with roller 16, and belt 15 is in transmission connection with roller 16.Motor 14 drives roller 16 and rotates, and belt 15 owing to the effect campaign of frictional force, consists of the cycle of rotation of belt 15 like this on roller 16.Water injection molding 11 and be installed on the belt 15, because the effect of frictional force, water injection molding 11 and follow belt 15 and move, water injection molding 11 and in moving process, finish each operation through each device, finish like this production of wallboard.
Because mixer 1 needs the workman first stirring in the deployed mixer 1 that reinjects of material ratio as required, has increased like this workman's labour intensity.Therefore, as preferential embodiment, the next door of described mixer 1 is provided with material conveyer belt 9 and material tower 10, and mixer 1 links to each other with material tower 10 by material conveyer belt 9.Material tower 10 can be automatically good materials allocating as required, be directly injected in the mixer 1 by material conveyer belt 9, mixer 1 stirs, go allotment and charging without the workman like this, reduced workman's labour intensity, and batching and convey materials are all finished automatically, have increased like this production efficiency.
Described conveying device 3 can be material conveying trolley or slurry conveyer belt etc.The slurry conveyer belt need to set up independent frame, the cost of slurry conveyer belt is higher than material conveying trolley like this, again the slurry conveyer belt in course of conveying, need motor always driving conveying belt move, the energy consumption of slurry conveyer belt is greater than material conveying trolley, it is to need the regular hour that the slurry of depositing funnel 2 the insides is poured, and be enough to during this period of time allow material conveying trolley that slurry is transported to depositing funnel 2 from mixer 1, material conveying trolley can be finished the haul task.Therefore, as preferred embodiment, described conveying device 3 comprises dumper 7 and Crane Rail 4, and dumper 7 is installed on the Crane Rail 4.Dumper 12 is in Crane Rail 13 operation, and dumper has just had fixing conveying track, and easy operation has reduced labour intensity.
Because the more short cost of more saving of the length of Crane Rail 4.Therefore, as preferred embodiment, described Crane Rail 4 is parallel with frame 8.The length that is shorter in length than Crane Rail 4 oblique frames 8 of Crane Rail 4 has been saved cost like this.
Whether because dumper 7 moves at Crane Rail 4, but needing the workman to remove to observe dumper 7 aligns with side discharging opening 12, and whether dumper 7 aligns with depositing funnel 2, has increased like this workman's labour intensity.Therefore, as preferred embodiment, described depositing funnel 2 is consistent with the length of Crane Rail 4 to the distance between the side discharging opening 12, and the two ends of Crane Rail 4 are provided with stopping means 5.Depositing funnel 2 is consistent with the length of Crane Rail 4 to the distance between the side discharging opening 12, the position at dumper 7 two ends on Crane Rail 4 just has been side discharging opening 12, depositing funnel 2 alignment like this, thereby the length of having saved Crane Rail is saved cost, stopping means 5 be arranged on Crane Rail 4 two ends so that dumper 7 be obstructed at the two ends of Crane Rail 4 and can't move out Crane Rail 4, easy operation, reduced labour intensity
Embodiment
As shown in Figures 2 and 3, motor 14, belt 15, roller 16 all is installed on the frame 8, motor 14 is in transmission connection with roller 16, belt 15 is in transmission connection with roller 16, mixer 1 is installed on the frame 8 with depositing funnel 2 intervals, mixer 1 has side discharging opening 12 and end discharging opening 6, discharging opening 12 is positioned at the side of mixer 1, end discharging opening 6 is positioned at the bottom of mixer 1 and above frame 8, the next door of mixer 1 is provided with material conveyer belt 9 and material tower 10, mixer 1 links to each other with material tower 10 by material conveyer belt 9, dumper 7 and Crane Rail 4 are arranged between depositing funnel 2 and the side discharging opening 2, and dumper 7 is installed on the Crane Rail 4, and the length of Crane Rail 4 is consistent to the distance between the side discharging opening 12 with depositing funnel 2, the two ends of Crane Rail 4 are provided with stopping means 5, and Crane Rail 4 is parallel with frame 8.
Production process: mixer 1 stirs slurry according to need of production, the slurry that the stirs side discharging opening 12 from mixer 1 is injected in the dumpers 7, dumper 7 is mobile at Crane Rail 4, move to stopping means 5 places and stop mobile, be injected into depositing funnel 2 with the slurry in the dumper 7 this moment, and haul is that repetition is continuous.After watering injection molding 11 to pass through first mixer 1 during through depositing funnel 2, actuating motor 14, motor 14 drives roller 16 and rotates, roller 16 drives belt 15 motions, water injection molding 11 on belt 15, lay lower floor's fiber cloth, through mixer 1, the end discharging opening 6 of mixer 1 is cast in slurry on lower floor's fiber cloth, the workman installs sandwich at slurry, waters injection molding 11 and passes through depositing funnel 2 again, and depositing funnel 2 is cast in slurry on the sandwich, water injection molding 11 and continue to finish the operations such as top fiber cloth laying watering injection molding continuous operation device 13, finish at last the production of whole wallboard.During through mixer 1, the whole production process of wallboard is exactly that depositing funnel 2 is cast in slurry on lower floor's fiber cloth after watering injection molding 11 to pass through first depositing funnel 2, and mixer 1 is cast in slurry on the sandwich, and remaining operation is all consistent with above-mentioned whole production process.

Claims (6)

1. building wall board two-wire automatic assembly line, it is characterized in that: comprise frame (8), at the other conveying device (3) that arranges of frame (8), be installed in and water injection molding continuous operation device (13) on the frame (8), be installed in the upper also interval of frame (8) and be arranged in depositing funnel (2) and the mixer (1) that waters injection molding continuous operation device (13) top, mixer (1) has side discharging opening (12) and end discharging opening (6), side discharging opening (12) is positioned at the side of mixer (1), end discharging opening (6) is positioned at the bottom of mixer (1) and in the top of frame (8), conveying device (3) is arranged between the side discharging opening (12) of depositing funnel (2) and mixer (1).
2. building wall board two-wire automatic assembly line as claimed in claim 1, it is characterized in that: the described injection molding continuous operation device (13) that waters comprises rack-mounted motor (14), belt (15), roller (16), motor (14) is in transmission connection with roller (16), and belt (15) is in transmission connection with roller (16).
3. building wall board two-wire automatic assembly line as claimed in claim 1 is characterized in that: the next door of described mixer (1) is provided with material conveyer belt (9) and material tower (10), and mixer (1) links to each other with expecting tower (10) by material conveyer belt (9).
4. such as claim 1,2 or 3 described building wall board two-wire automatic assembly lines, it is characterized in that: described conveying device (3) comprises dumper (7) and Crane Rail (4), and dumper (7) is installed on the Crane Rail (4).
5. building wall board two-wire automatic assembly line as claimed in claim 4, it is characterized in that: described Crane Rail (4) is parallel with frame (8).
6. building wall board two-wire automatic assembly line as claimed in claim 5, it is characterized in that: described depositing funnel (2) is consistent with the length of Crane Rail (4) to the distance between the side discharging opening (12), and the two ends of Crane Rail (4) are provided with stopping means (5).
CN 201220622060 2012-11-22 2012-11-22 Double-line automatic production line of building wallboard Expired - Fee Related CN202895412U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220622060 CN202895412U (en) 2012-11-22 2012-11-22 Double-line automatic production line of building wallboard

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220622060 CN202895412U (en) 2012-11-22 2012-11-22 Double-line automatic production line of building wallboard

Publications (1)

Publication Number Publication Date
CN202895412U true CN202895412U (en) 2013-04-24

Family

ID=48116122

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220622060 Expired - Fee Related CN202895412U (en) 2012-11-22 2012-11-22 Double-line automatic production line of building wallboard

Country Status (1)

Country Link
CN (1) CN202895412U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104816379A (en) * 2015-05-14 2015-08-05 王旭广 Full-automatic production line for light wallboard

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104816379A (en) * 2015-05-14 2015-08-05 王旭广 Full-automatic production line for light wallboard

Similar Documents

Publication Publication Date Title
CN101795836B (en) Equipment for producing slabs on same production line
CN103144187B (en) Flat die and stand die combined product line for producing wallboard
CN102320079B (en) Demoulding hook push ferrying vehicle
CN108527635A (en) A kind of concrete foamed bricks machining production line
CN102941621B (en) Automatic production line of building wallboards
CN202895412U (en) Double-line automatic production line of building wallboard
CN202753283U (en) Movable concrete mixing device
CN203331210U (en) Flat die and erect die combination production line for producing wallboards
CN205000978U (en) Open type overlength tunnel concrete placement device
CN202784874U (en) Building block decoding layering conveyor used for foam slurry core filling building block production line
CN202370255U (en) Mixed blanking construction device for block type waste concrete
CN208203296U (en) One kind being used for underground coal mine large-section underground continuous concrete device
CN208468690U (en) A kind of concrete foamed bricks machining production line
CN104118035B (en) Material distributing device for gypsum block production device
CN215486063U (en) Movable type guniting device for roadway support
CN209453849U (en) A kind of full-automatic concrete platemaking machine
CN109049311A (en) A kind of promotion charging equipment and the cloth system with the promotion charging equipment
CN105573280A (en) Adhesive polystyrene granule heat preservation plate automatic production apparatus and method
CN216075123U (en) Large-warehouse-surface concrete integrated conveying device
CN103182734A (en) Automatic mortar distributor for prefabricating interlocking blocks
CN204094934U (en) A kind of distribution device for gypsum block production equipment
CN209579983U (en) A kind of promotion charging equipment and the cloth system with the promotion charging equipment
CN210795049U (en) Divide material transportation sports car system that applies to silo upper portion
CN208775696U (en) A kind of prefabricated components concrete transportation system
CN203033464U (en) Bridge-type side scrapper material taking machine and system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130424