CN202731279U - 爬锥埋件系统 - Google Patents

爬锥埋件系统 Download PDF

Info

Publication number
CN202731279U
CN202731279U CN201220430182.2U CN201220430182U CN202731279U CN 202731279 U CN202731279 U CN 202731279U CN 201220430182 U CN201220430182 U CN 201220430182U CN 202731279 U CN202731279 U CN 202731279U
Authority
CN
China
Prior art keywords
cone
climbing
climb
brake component
embedded part
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201220430182.2U
Other languages
English (en)
Inventor
张文光
刘莉莉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CSCEC Strait Construction and Development Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd filed Critical Third Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority to CN201220430182.2U priority Critical patent/CN202731279U/zh
Application granted granted Critical
Publication of CN202731279U publication Critical patent/CN202731279U/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

本实用新型涉及一种爬锥埋件系统,其特征在于:它包括爬锥、套设于爬锥外的保护套筒、位于爬锥外端且与爬锥配合连接的紧固件、位于爬锥内旁侧的制动件以及内端与制动件固定连接且与爬锥可拆装连接配合的定位连接件;所述爬锥外端部露置于保护套筒外。本实用新型的目的在于提供一种工艺简单,施工操作方便,预埋精度高的爬锥埋件系统。

Description

爬锥埋件系统
技术领域
本实用新型涉及爬锥埋件系统。
背景技术
目前,在一般超高层建筑施工中,核心筒剪力墙液压爬模体系的附墙装置与墙体的连接基本上都是先预埋套管,再用穿墙螺栓固定的方法。这样的预埋方法,其预埋精度不高,套管容易受到钢筋安装、模板安装、混凝土浇筑的扰动,而产生变形、损坏、堵管、偏位等影响,且一旦预埋失误,处理难度较大,将耗费大量人力、财力,并影响施工进度。而且预埋套管孔在后期封堵工作量大,且两头都需封堵,操作困难、封堵质量难以保证。
发明内容
本实用新型的目的在于提供一种工艺简单,施工操作方便,预埋精度高的爬锥埋件系统。
本实用新型的目的通过如下技术方案实现:一种爬锥埋件系统,其特征在于:它包括爬锥、套设于爬锥外的保护套筒、位于爬锥外端且与爬锥配合连接的紧固件、位于爬锥内旁侧的制动件以及内端与制动件固定连接且与爬锥可拆装连接配合的定位连接件;所述爬锥外端部露置于保护套筒外。
本实用新型的预埋方法如下:在爬模模板的相应位置开设通孔,通过后期连接悬挂靴和爬锥的紧固件穿过爬模模板与位于爬模模板内侧的爬锥连接,从而将爬锥固定在爬模模板上;定位连接件穿过保护套筒预设的通孔与爬锥连接,通过调节定位连接件使制动件与爬锥的距离与设计距离相符。
较之现有技术而言,本实用新型的优点在于:
将本实用新型固定在爬模模板上,随爬模模板的合模而预埋,因爬模系统为整体爬升,爬模模板位置固定不变,故只要在爬模模板上固定准确,合模后爬锥埋件系统的位置精确度高,且在第一次预埋成功后,后续预埋操作简单,极大缩小预埋工作量;
设计科学合理,不仅不受钢筋安装、模板安装以及混凝土浇筑的扰动,不产生变形、损坏、堵管、偏位等影响,而且受力均匀,抗拔力符合设计要求;
由于保护套筒的保护,爬锥为可方便拆卸的部件,后期只需拆卸下爬锥,封堵爬锥孔即可。
附图说明
图1是本实用新型一种爬锥埋件系统实施例的结构示意图。
图2是图1中爬锥埋件系统的装配示意图。
标号说明:1、爬锥,2、保护套筒,3、紧固件,4、制动件,4-1、固定孔,5、定位连接件,6、垫块,7、爬锥模板。
具体实施方式
下面结合说明书附图和实施例对本实用新型内容进行详细说明:
如图1和图2所示为本实用新型提供的一种爬锥埋件系统的实施例示意图。
一种爬锥埋件系统,其特征在于:它包括爬锥1、套设于爬锥1外的保护套筒2、位于爬锥1外端且与爬锥1配合连接的紧固件3、位于爬锥1内旁侧的制动件4以及内端与制动件4固定连接且与爬锥1可拆装连接配合的定位连接件5;所述爬锥1外端部露置于保护套筒2外。
所述爬锥1外形呈截头圆锥体。
所述定位连接件5为与爬锥1螺纹连接的调节螺杆。
所述制动件4为与定位连接件5垂直固定连接的制动板,所述制动件4设有一对与定位连接件5轴向平行的固定孔4-1。制动件4与爬锥1定位好后,用两根铁丝分别穿过两固定孔4-1,然后将铁丝两端穿过爬锥模板7上已经钻好的穿铁丝眼,固定于爬锥模板7外侧的木工字梁上。
所述紧固件3为与爬锥1螺纹连接的固定螺栓。
所述紧固件3上套设有位于紧固件3与爬锥1之间的垫块6。所述垫块6可以是大小合适的胶合板,其固定在爬锥模板7外侧,位置根据施工图爬锥1位置确定。

Claims (6)

1.一种爬锥埋件系统,其特征在于:它包括爬锥(1)、套设于爬锥(1)外的保护套筒(2)、位于爬锥(1)外端且与爬锥(1)配合连接的紧固件(3)、位于爬锥(1)内旁侧的制动件(4)以及内端与制动件(4)固定连接且与爬锥(1)可拆装连接配合的定位连接件(5);所述爬锥(1)外端部露置于保护套筒(2)外。
2.根据权利要求1所述的爬锥埋件系统,其特征在于:所述爬锥(1)外形呈截头圆锥体。
3.根据权利要求1所述的爬锥埋件系统,其特征在于:所述定位连接件(5)为与爬锥(1)螺纹连接的调节螺杆。
4.根据权利要求3所述的爬锥埋件系统,其特征在于:所述制动件(4)为与定位连接件(5)垂直固定连接的制动板,所述制动件(4)设有一对与定位连接件(5)轴向平行的固定孔(4-1)。
5.根据权利要求1所述的爬锥埋件系统,其特征在于:所述紧固件(3)为与爬锥(1)螺纹连接的固定螺栓。
6.根据权利要求1-5任意一项所述的爬锥埋件系统,其特征在于:所述紧固件(3)上套设有位于紧固件(3)与爬锥(1)之间的垫块(6)。
CN201220430182.2U 2012-08-27 2012-08-27 爬锥埋件系统 Expired - Lifetime CN202731279U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201220430182.2U CN202731279U (zh) 2012-08-27 2012-08-27 爬锥埋件系统

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201220430182.2U CN202731279U (zh) 2012-08-27 2012-08-27 爬锥埋件系统

Publications (1)

Publication Number Publication Date
CN202731279U true CN202731279U (zh) 2013-02-13

Family

ID=47656991

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201220430182.2U Expired - Lifetime CN202731279U (zh) 2012-08-27 2012-08-27 爬锥埋件系统

Country Status (1)

Country Link
CN (1) CN202731279U (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107461029A (zh) * 2017-08-25 2017-12-12 中建五局华东建设有限公司 一种基于液压爬模系统设置的下挂梁浇筑成型装置
CN110748162A (zh) * 2019-10-30 2020-02-04 中国铁建重工集团股份有限公司 翻模设备和翻模设备的翻升方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107461029A (zh) * 2017-08-25 2017-12-12 中建五局华东建设有限公司 一种基于液压爬模系统设置的下挂梁浇筑成型装置
CN110748162A (zh) * 2019-10-30 2020-02-04 中国铁建重工集团股份有限公司 翻模设备和翻模设备的翻升方法
CN110748162B (zh) * 2019-10-30 2021-12-07 中国铁建重工集团股份有限公司 翻模设备和翻模设备的翻升方法

Similar Documents

Publication Publication Date Title
CN103437459B (zh) 穿墙对拉螺杆套管连墙件
CN203821867U (zh) 剪力墙墙体组装调直装置
CN203799586U (zh) 输电线路钢管塔标识牌安装支架
CN104847122B (zh) 一种用于张拉叉耳式拉索或钢拉棒的装置组件及其张拉施工方法
CN105332516A (zh) 一种悬挑承力架组合定位装置安装方法
CN202731279U (zh) 爬锥埋件系统
CN202787926U (zh) 一种简便拆装式悬挑脚手架
CN205153515U (zh) 一种悬挑承力架组合定位装置
CN209244225U (zh) 一种可调节长度的斜撑杆
CN204455823U (zh) 一种悬索桥刚性拉杆锚固系统
CN103882840B (zh) 一种调压井现浇砼可装配式模板支架及其安装方法
CN202031309U (zh) 一种结构混凝土施工用悬空作业平台
CN205501827U (zh) 一种用于猫道制振系统的水平拉索转向架
CN201924532U (zh) 可重复使用的标准楼梯防护栏杆
CN201265214Y (zh) 用于体外预应力加固结构的钢板锚固块
CN204163073U (zh) 桩基钢筋笼套筒钢筋接头结构
CN204081085U (zh) 箱形钢柱连接结构
CN204343647U (zh) 一种型钢悬挑脚手架用支撑架
CN104164968A (zh) 新型的可移位穿墙(或预埋)式双点附着装置
CN203285057U (zh) 一种模板混凝土剪力键
CN204299142U (zh) 一种悬挑脚手架的卸荷结构
CN103556813B (zh) 钢管脚手架连墙件
CN203006799U (zh) 塔式起重机标准节联接套止动装置
CN102433961A (zh) 一种预制梁结构施工构件
CN202627472U (zh) 钢管脚手架可调底座

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CSCEC STRAIT CONSTRUCTION AND DEVELOPMENT CO., LTD

Free format text: FORMER NAME: THE THIRD COMPANY OF CHINA SEVENTH ENGINEERING BUREAU CO., LTD.

CP03 Change of name, title or address

Address after: 98-1 No. 350003 Fujian province Fuzhou Mawei District Jiangbin East Avenue

Patentee after: CSCEC STRAIT CONSTRUCTION AND DEVELOPMENT Co.,Ltd.

Address before: Fuzhou City, Fujian Province, 350000 North Road, No. 148 in the construction of the third construction company seven

Patentee before: THE THIRD COMPANY OF CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION. CORP.,LTD.

CX01 Expiry of patent term

Granted publication date: 20130213

CX01 Expiry of patent term